ITEM 607 FENCE
607.01 Description. This work consists of furnishing and erecting fence and gates of the types
designated. Construct fence in a manner that provides a rigid, taut fence closely conforming to the surface of the ground. Fence is designated by the following types:
607.02 Materials. Furnish materials conforming to:
Concrete, QC Misc or QC 1 or QC 2 .......... ............................................. 499 and 511 Reinforcing steel .............................. 509.02 Barbed wire ...................................... 710.01 Woven steel wire fence ................... 710.02 Chain-link fence ............................... 710.03 Fence posts, braces, and dimension lumber ........................................... 710.11 Steel line posts and ties, Type 47 fence ............................................. 710.11 Expansion shield anchors, self drilling ................................... 712.01 Ground Rods..………….…………..725.16 Seeding and Mulching .......................... 659
607.03 Clearing, Grading and Seeding. Perform clearing and grading as necessary to construct
the fence to the required alignment, and provide a reasonably smooth ground profile at the fence line. Perform fenceline seeding and mulching according to Item 659 Seeding and Mulching on all areas disturbed by the clearing and grading for the fence within 8 months of the activity. The Department will deduct the area paid for under Item 607 Fenceline Seeding and Mulching from Item 659 Seeding and Mulching quantities as described in the plan, if applicable.
607.04 Post Assemblies. Securely brace end, corner, gate, and pull or intermediate anchor posts
in position during the curing period of the concrete encasement. The Engineer will not require forms for post encasement. For Type 47 and Type CLT fence, ensure that the maximum spacing between intermediate anchor post assemblies, or between end post assemblies and intermediate anchor post assemblies, are 660 feet.
607.05 Horizontal Deflection. At points of horizontal deflection, construct the fence as follows:
607.06 Line Posts. Set line posts according to the following:
607.07 Fabric. If setting posts in concrete, do not erect the fabric until after 5 days from the time
of setting the posts when using regular concrete, or until after 3 days when using concrete with high early strength cement, Stretch and securely fasten Type 47 fabric to line posts using galvanized ties. At a minimum, use one tie each for the top and bottom horizontal wires and one tie for each alternate horizontal wire below the top horizontal wire. Fasten chain-link fabric to the line posts using clips or bands spaced approximately 14 inches apart, and to the top rail or top tension wire using bands or tie wires at approximately 24 inch intervals or less. Join successive rolls of fabric by weaving a single picket into the ends of the rolls to form a continuous mesh.
607.08 Barbed Wire. If barbed wire is specified, stretch and fasten it in the same manner as
woven wire fabric.
607.09 Method of Measurement. The Department will measure Fence, Type ___ by the number
of feet, complete in place. The Department will measure along the top of the fence from outside to outside of end posts, exclusive of gates and other openings. The Department will count Gate, Type ___ by the number of complete units of the size and type specified. The Department will measure Fenceline Seeding and Mulching by the number of feet of fence. The Department will measure along the top of the fence from outside to outside of end posts, exclusive of gates and other openings.
607.10 Basis of Payment. The Department will pay for accepted quantities at the contract prices
as follows: Seeding and Mulching shall be paid under Item 607 Seeding and Mulching Item Unit Description 607 Foot Fence, Type___ 607 Each Gate, Type___ 607 Foot Fenceline Seeding and Mulching