EROSION CONTROL MAT 228.04
228.01 Description
This work consists of providing and installing erosion control mat for lining ditches and protecting slopes.
228.02 Materials
Provide materials in accordance with the following subsections: Material: Subsection: Erosion Control Mat 735.04.F Seed 735.03 Mat Fasteners 735.05.B
228.03 Equipment – Vacant
228.04 Construction Methods
228.06 Erosion Control Mat
228.05 Method of Measuremen T
The Resident Engineer will meas ure the area covered by the erosion control mat installed in place, not including overlaps between adjacent pieces of mat.
228.06 Basis of Payment
The Department will pay for each pay item at the contract unit price per the specified pay unit as follows: Pay Item: Pay Unit: EROSION CONTROL MAT Square Yard [Square Meter] Include the cost of mat fasteners and seeding in the contract unit price for Erosion Control Mat . DITCH LINER PROTECTION 229.05 SECTION 229 DITCH LINER PROTECTION
229.01 Description
This work consists of providing and installing excelsior mat or solid slab sod to protect ditch liners.
229.02 Materials
Provide materials in accordance with the following subsections: Material: Subsection: Excelsior Mat 735.04. B Solid Slab Sod 735.01 Mat Fasteners 735.05.B
229.03 Equipment — Vacant
229.04 Construction Methods
229.05 Method of Measuremen T
The Resident Engineer will measure Ditch Liner Protection along the centerline of the dit ch. (The linear measurement includes the ditch liner protection for both sides of the ditch to the width indicated.)