412Cold-Milling Pavement

OK · 2019 Standard SpecificationsBook pages 268268View official source ↗

412.04 Cold -Milling Pavement

paving grade, as listed under “Midwest/Mid -Continent Markets - MISSOURI/KANSAS/OKLAHOMA - Tulsa, Oklahoma/Southern Kansas .” The publication used to establish each Monthly Aspha lt Binder Price Index will be the Asphalt Weekly Monitor® furnished by Poten & Partners, Inc. The issue of the Asphalt Weekly Monitor® used will be for the last full week in the previous month received by the Department prior to the first day of the index month. If the specified publication ceases to be available for any reason, the Department at its discretion will select and begin using a substitute price source or index to establish the Monthly Asphalt Binder Price Index.

4.Supplemental Items Subject to Adjustment Items included in the contract that are listed in the table above are subject to adjustment in accordance with this provision, regardless of any amount of overrun to the plan quantity. Any new items of work added to th e Contract by supplemental agreement that are listed in the table above, will be subject to the asphalt binder price adjustments in accordance with this provision. The base asphalt binder price, P (b), for any newly added eligible items will be the same P (b) as the eligible items in the Contract and the new unit price established by supplemental agreement will be determined accordingly. COLD -MILLING PAVEMENT

412.01 Description

This work consists of cold -milling and removing pavement surfaces to the specified depth, and removing ridges, ruts, and imperfections.

412.02 Materials — Vacant

412.03 Equipment

Provide a milling machine that:  Can plane at least 1½ in [40 mm] deep in a single pass;  Is self -propelled;  Has the power, traction, and stability to maintain accurate depth of cut and slope;  Automatically establishes profile grades along each side of the milling machine by referring to the existing pavement with a ski or matching shoe, or by an independ ent grade control;  Automatically controls cross slope; and  Has an integral loading mechanism to remove the material cut from the pavement surface and discharge it into a truck in one operation.

412.04 Construction Methods

Mill the existing pavement to the line, grade, and cross section shown on the plans, and provide a milled surface that has a uniform texture and a smooth riding surface for traffic. Ensure no deviations are RUMBLE STRIP 413.03 greater than 3/16 in in a 10 ft [5 mm in a 3 m] section. Make corrections as appr oved by the Construction Engineer. Make passes to remove irregularities and to profile the surface to the depth and cross slope shown on the Plans. Prevent traffic hazards. At the end of the daily milling operation, ensure that milled surface is smooth. Immediately apply fog seal to the milled areas, in accordance with Section 407, "Fog Seal and Tack Coat," unless overlaying the milled area with bituminous material on the same day. Dispose of removed materials in accordance w ith Subsection 104.09, “Removal and Disposal of Salvaged Materials, Structures, and Obstructions.”

412.05 Method of Measuremen T — Vacant

412.06 Basis of Payment

The Department will pay for each pay item at the contract unit price per the specified pay unit as follows: Pay Item: Pay Unit: COLD MILLING PAVEMENT Square Yard [Square Meter] The Department will pay for fog seal in accordance with Section 407, “Fog Seal and Tack Coat.” SECTION 413 RUMBLE STRIP

413.01 Description

This work consists of constructing noise -generating rumble strips in the asphalt or portland cement concrete (PCC) pavement on driving lanes or the roadway shoulders. Rumble strips categ ories are defined as follows: Method HMA -CON. Continuous rumble strips cut in ASPHALT shoulders. Method HMA -CYC. A cyclic pattern of rumble strips cut in ASPHALT shoulders. Method PCC -CYC. A cyclic pattern of rumble strips cut in PCC shoulders. Method P CC-CON. Continuous rumble strips cut in PCC shoulders.

413.02 Materials — Vacant

413.03 Equipment

Provide a machine that produces incised grooves to the specified pattern and dimensional tolerances shown on the Plans.

Source: Oklahoma Standard Specifications for Highway Construction, 2019 Edition. Pages 268268 of 935.