407.03 Fog Seal and Tack Coat
406.05 Method of Measuremen T
The Resident Engineer will measure the weight of Open -Graded Friction Surface Course not exceeding the calculated we ight obtained by multiplying the unit weight from the job mix formula by the completed length of OGFSC and the area of the typical cross section shown on the Plans.
406.06 Basis of Payment
The Department will pay for each pay item at the contract unit pric e per the specified pay unit as follows: Pay Item: Pay Unit OPEN -GRADED FRICTION SURFACE COURSE Ton [Metric Ton] The Department will pay for tack in accordance with Section 407, “Fog Seal and Tack Coat.” The Department will adjust payment for asphalt binder in accordance with Subsection 411.06.B, “Price Adjustments for Asphalt Binder.”
407.01 Description
This work consists of preparing and treating an existing bituminous or concrete surface with bituminous material. Original Emulsion. A mixture of asphalt, water, and a small amount of emulsifying agent to maintain a uniform blend. Diluted Emulsion. An original emulsion diluted with additional water to reduce the viscosity and to allow easier spraying, typically used for fog seals. Residual Asphalt Content. The amount of asphalt remaining on the pavement surface after all of the water, b oth in the original emulsion and any additional water, has evaporated.
407.02 Materials
Provide materials in accordance with Subsection 708.03, “Asphalt Materials. ”
407.03 Equipment
Provide distributors, heating equipme nt, and supply tanks in accordance with Subsection 401.03, “Equipment.” FOG SEAL AND TACK COAT 407.04
407.04 Construction Methods
408.03 Prime Coat
Re-apply tack at a rate that ensures proper bonding if the tack loses its adhesive properties or is damaged by traffic before being covered by the next surfacing layer, as directed by the Resident Engineer, at no additional cost to the Department.
407.05 Method of Measurement
The Resident Engineer will measure the volume of Emulsion for Fog Sea l, Tack Coat , and NT Tack Material as delivered, before dilution. The Resident Engineer will measure bituminous material by the gallon [liter] or ton [metric ton].
407.06 Basis of Payment
The Department will pay for each pay item at the contract unit price per the specified pay unit as follows: Pay Item: Pay Unit:
408.01 Description
This work consists of preparing and treating a surface with bituminous and blotter material. Cutback. A mixture of asphalt and petroleum solvent. Residual Asphalt Content. The amount of asphalt remaining on the pavement surface after the petroleum solvent evaporates. MC-30 and MC -70. Cutbacks with resi dual asphalt contents of at least 50 percent and 55 percent, respectively.
408.02 Materials
Provide materials in accordance with Subsection 708.03, “Asphalt Materials,” for MC -30 and MC -70. In ODEQ designated non -attain ment air quality counties, an emulsion may be used at the same percent residual application rate.
408.03 Equipment
Provide distributors, heating equipment, and supply tanks in accordance with Subsection 401.03, “Equipment.”