MONUMENTS 626.06 595 SECTION 626
626.01 Description
This work consists of constructing concrete monuments or markers.
626.02 Materials
Provide materials in accordance with the following sections: Material: Section: Portland Cement Concrete Class A 701 Reinforcing Steel 723 The Department will provide the bronze plates used for markers or monuments.
626.03 Equipment — Vacant
626.04 Construction Methods
Construct monuments and right -of-way markers using reinforced concrete in accordance with Section 509, “Structural Con crete,” and as shown on the Plans. Provide monuments and right -of-way markers with a carborundum finish. Replace monuments or right -of-way markers, damaged during construction before final acceptance, at no additional cost to the Department. Set and plumb monuments and right -of-way markers to the depth shown on the Plans. Compact select backfill, approved by the Resident Engineer, to stabilize and secure the monuments or right -of-way markers.
626.05 Method of Measuremen T — Vacant
626.06 Basis of Payment
The Department will pay for each pay item at the contract unit price per the specified pay unit as follows: Pay Item: Pay Unit:
627.05 Concrete Longitudinal Barrier
596 SECTION 627 CONCRETE LONGITUDINAL BARRIER
627.01 Description
This work consists of constructing longitudinal concrete barrier with concrete and reinforcing steel. The Department will consider alternative designs that meet exterior dimensions, and test and performance criteria required by the Contract. Submit alternative designs to the Resident Engineer for approval.
627.02 Materials
Provide materials in accordance with the following sections: Material: Section: Portland Cement Concrete Class A 701 Reinforcing Steel 723
627.03 Equipment — Vacant
627.04 Construction Methods
Measure, batch, and mix concrete for the longitudinal concrete barriers in accordance with Subsection 414.04, “Construction Methods.” Build forms for the barriers in accordance with Section 502, “Forms, Falsework & Temporary Works.” Place reinforcing steel for the barriers in accordance with Section 511, “Reinforcing Steel for Structures.” Place the concrete for the barriers in accordance with Section 509, “Structural Concrete.” Ensure exposed concrete surfaces are smooth and dense. Finish concrete surfaces in accordance with Subsection 509.04.G, “Finishing Formed Concrete Surfaces .” Fill rough areas, holes, and porous spots after removing the forms. Cut bolts, wires, or other appliances, used to hold the forms, ¼ in [6 mm] below the surface and fill the depressions with cement mortar. Finish exposed surfaces in accordance with Subsection 509.04.G, “Finishing Formed Concrete Surfaces.”