00310.00 258 Section 00310 - Removal of Structures and Obstructions Description
00310.00 Scope - This Work consists of removing and disposing of man- made materials and
cleaning up areas they occupy. See Section 00501 for removal of Bridge s.
00310.01 Areas of Work - Perform removal Work in the same areas as specif ied in 00320.01.
If a building to be removed lies partly within the Right -of-Way, remove the entire building unless otherwise shown or directed.
00310.02 Exclusions - Removal Work does not include removal or disposal of materials that are:
• Designated to remain. • Included in earthwork as given in 00330.41. • Specifically indicated by the Specifications, Plans , or Special Provisions to be removed Incidental to other items of Work under the Contract. • Owned or controlled by third parties. Construction
00310.40 Restrictions on Removal Work:
00310.41 Removal Work :
00310.42 Salvaging Drainag e Structure Fittings - Metal grates, frames, rings, covers, and other
metal fixtures or fittings for drainage Structure s may be salvaged and used on new Structure s if the Engineer determines they are reusable.
00310.43 Disposal of Material - Dispose of materials according to 00290.20(c).
00310.44 Earthwork in Connection with Removal - Excavation required to perform removal of
Structure s and obstructions will be considered Incidental to the removal Work , unless it is within the measurement limits for an excavation Contract Pay Item . Backfill holes according to 00330.45. The backfill will be measured for payment according to 00330.82, w hen there is an embankment measure basis Pay Item for earthwork and that material is used for backfilling, otherwise no separate payment will be made for this Work . Maintenance
00310.60 Repair of Damages - Repair promptly any breakage or damage to materials or items not
intended to be removed. Complete replacement of the affected materials may be required if the Engineer determines it is necessary. Make all repairs and replacements at no additional cost to the Agency. Measurement
00310.80 Measurement - The quantities of removal Work performed under this Section will be
measured according to the following: • Lump Sum Basis - Under this method, no measurement of quantities will be made. • Separate Item Basis - Under this method, the quantities of Work performed on a separate item basis will be measured as follows: • Length and Area - The length or area of the Structure or item actually removed, will be measured along the line and grade of the Structure or item for each continuous Structure or item remove d. Measurement will be on the length or area basis, limited to the Neat Lines shown or directed. The length of a sphalt Pavement cutting will be the length of the actual cut based on a depth of 6 inches. If the depth is greater than 6 inches, the length will be adjusted by converting to an equivalent number of feet on a proportionate-length basis. 00310.90 260 • Each - Items will be measured on the unit basis by count of units removed. No measurement for removal of concrete barrier will be made for barrier that is measured and paid as “Remove and Reinstall Concrete Barrier” under Section 00820. Payment
00310.90 Payment - The accepted quantities of Work performed under this Section will be paid for
at the lump sum basis or separate item basis according to 00310.9 1 or 00310.92 , as applicable. Payment will be payment in full for furnishing all Equipment , labor, and Incidental s necessary to complete the Work as specified. No separate or additional payment will be made for barriers used for temporary protection where guardrail, Median rail, or concrete barriers have been removed. No separate or additional payment will be made for protecting and maintaining milepost markers and reinstall ing them at their original location. No separate or additional payment will be made for removal or disposal Work included in Section 00330 according to 00310.02. When the Contract Schedule of Items does not indicate payment for Work performe d under this Section, no separate or additional payment will be made. Payment will be included in payment made for the appropriate items under which this Work is required.
00310.91 Lump Sum Basis - The accepted quantities of removal Work performed on a lump sum
basis will be paid at the Contract lump sum amount for the following items: Pay Item Unit of Measurement
00310.92 Separate Item Basis - The accepted quantities of removal Work performed on a separate
item basis will be paid for at the Contract uni t price, per unit of measurement, for the following items: Pay Item Unit of Measurement
Removal of Structures and Obstructions in other states
- Alaska 202 · REMOVAL OF STRUCTURES AND OBSTRUCTIONS
- Colorado 202 · Removal of Structures and Obstructions
- Delaware 211 · REMOVAL OF STRUCTURES AND OBSTRUCTIONS
- Indiana 202 · REMOVAL OF STRUCTURES AND OBSTRUCTIONS
- Mississippi 202 · Removal of Structures and Obstructions
- Montana 202 · Removal of Structures and Obstructions
- Nebraska 203 · REMOVAL OF STRUCTURES AND OBSTRUCTIONS
Get an email when 00310 changes
Oregon revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.