01150.40 1033 Section 01150 - Potable Water Valves Description
01150.00 Scope - This Work consists of furnishing and installing valves in potable water systems at
the locations shown or at other locations as directed. Materials
01150.10 Materials - Furnish Material s meeting the following requirements:
Backflow Prevention Devices ................................................................ 02480.70 Butterfly Valves ..................................................................................... 02480.22 Combination Air Release/Air Vacuum Valves ....................................... 02480.60 Commercial Grade Concrete in Precast Concrete Blocks .......................... 00440 Commercial Grade C oncrete in Thrust Blocking ........................................ 00440 Gate Valves ........................................................................................... 02480.20 Spring -Loaded Plug or Disc Check Valves ....................................... 02480.40(b) Swing Check Valves ......................................................................... 02480.40(a) Tapping Sleeve and Valve Assemblies ................................................. 02480.30 Valve Boxes .......................................................................................... 02480.25 Valve Stem Extensions ......................................................................... 02480.26
01150.11 Handling - Handle valves so as to prevent damage to the valve, lining or coating. Load
and unload valves using hoists and slings so as to avoid shock or damage, and under no circumstances allow them to be dropped or skidded. Damaged valves will be rejected. If damage is confined to the coating or lining, it may be repaired in a manner satisfactory to the Engineer . Immediately place all damaged valves apart from the undamaged and remove the damaged valves from the site as soon as possible.
01150.12 Connecting Ends - Furnish valves with connecting ends as shown and as required for
connection to pipe and fittings furnished. Construction
01150.40 General - Install valves , back flow devices, and tapping sleeves according to the Plans and
the manufacturer's recommendations. Join to the pipe according to Section 01140 and AWWA Standards for the type of connecting ends furnished. Thoroughly clean and repair joints prior to installation.
01150.50 Field Testing - After installation, operate valves from full open to full closed to make sure
valves do not bind during operation. Correct all deficiencies in the operation of the valves. Verify the number of turns from full open to full closed and provide to the Engineer for the Agency's records.
01150.51 Hydrostatic Testing - Subject valves to hydrostatic testing according to 01140.51.
Correct all defects to the satisfaction of the Engineer.
01150.52 Disinfecting - Disinfect valves according to 01140.52.
Measurement
01150.80 Measurement - The quantities of valves will be measured on the unit basis.
Payment
01150.90 Payment - The accepted quantities of Work performed under this Section will be paid for
at the Contract unit price, per unit of measurement, for the following items: Pay Item Unit of Measurement
Get an email when 01150 changes
Oregon revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.