01160.00 1036 Section 01160 - Hydrants and Appurtenances Description
01160.00 Scope - This Work consists of furnishing and installing hyd rants and appurtenances in
potable water systems at the locations shown or at other locations as directed. Materials
01160.10 Materials - Furnish Material s meeting the following requirements:
Bollards ...................................................................................................... 00815 Commercial Grade Concrete in Thrust Blocking ........................................ 00440 End Connections ................................................................................... 02485.20 Gate Valves ........................................................................................... 02480.20 Hydrants ................................................................................................ 02485.10 Hydrant Extensions ............................................................................... 02485.40 Tie Rods ................................................................................................ 02485.60 Traffic Flange ........................................................................................ 02485.50 Valve Boxes .......................................................................................... 02480.25 Valve Stem Extensions ......................................................................... 02480.26
01160.11 Handling of Hydrants :
01160.40 Setting Hydrants - Inspect all hydrants upon delivery in the field to ensure proper working
order. Install hydrants as shown or directed.
01160.41 Hydrant Laterals - Install hydrant laterals, consisting of ductile iron pipe, from the auxiliary
gate valve at the main to the hydrant, according to Section 01140 and as shown.
01160.42 Hydrant Restraints - Restrain the thrust created in the hydrant lateral as shown.
01160.43 Gate Valves and Valve Boxes - Install gate valves and valve boxes according to
Section 01150, except that the end connections shall be provided with lugs for tie rods, or the bells shall provide sufficient clearance between the body of the valve and the hub to permit the installation of tie rods. 01160.90
01160.44 Hydrant Bollards - Construct hydrant bollards according to Section 00815 at the locations
shown.
01160.46 Moving Existing Hydrants - Move existing hydrants where shown. As shown, r emove
the existing hydrant lateral tee from the main if the main is to remain active, and insert a new section of pipe into the water main in place of the existing hydrant lateral tee. Where the existing main to which the existing hydrant lateral tee is connecte d is to be abandoned or temporarily activated after the existing hydrant is moved, plug the open end of the hydrant lateral pipeline. Provide temporary thrust restraint if temporarily reactivated.
01160.47 Reconnecting Existing Hydrants - Reconnect exi sting hydrants where shown. Leave the
location and elevation of the existing hydrant unchanged, but change the existing hydrant lateral to connect with a new gate valve and hydrant tee provided in a new main. Install new hydrant lateral according to Sect ion 01140 where the lateral extends to connect to the new main. Where existing hydrants were not restrained, restrain the new connections as shown.
01160.48 Hydrant Extensions - Install hydrant extensions where required.
Field Testing Installations
01160.50 General - After installation, operate hydrants from full open to full closed to ensure that
they do not bind during operation. Correct all malfunctions in the operation of the hydr ants.
01160.51 Hydrostatic Testing - Perform hydrostatic testing of hydrants according to 01140.51.
Correct all defects in Materials or workmanship to the satisfaction of the Engineer.
01160.52 Disinfecting - Disinfect hydrants according to 01140.52.
Measurement
01160.80 Measurement - The quantities of Work performed under this Section will be measured on
the unit basis. New pipe and tees for hydrant connections will be measured according to 01140.80. Gate valves will be measured acc ording to 01150.80. Hydrant bollards will be measured according to 00815.80. Payment
01160.90 Payment - The accepted quantities of Work performed under this Section will be paid for
at the Contract unit price, per unit of measurement, for the followin g items: Pay Item Unit of Measurement