1119.01RAILS—As shown on the Standard Drawings and as follows:
rails.
rails.
1119.02TERMINAL SECTIONS—As shown on the Standard Drawings and as follows:
1119.03POSTS—As shown on the Standard Drawings and as follows:
is required for projects let after April 14, 2023. Stamping of posts is optional for projects let on or before April 14, 2023.
1119.04OFFSET BRACKETS—Section 1109.04
1119.05MISCELLANEOUS MATERIAL—As shown on the Standard Drawings and as follows:
A153 or ASTM B695 and B696).
Galvanize hardware after fabrication, as specified in Section 1105.02(s) (AASHTO M 111). Do not punch, drill, grind, cut, or weld after galvanizing. Repair minor abrasions of galvanized surfaces with two coats of galvanizing paint.
1119.06GALVANIZING—Galvanize metal parts as specified in Section 1105.02(s) ( ASTM A153 unless
otherwise specified) and conform to the requirements of AASHTO M 180, Section 9.
1119.07GALVANIZING PAINT—ASTM A780 Section 4.2.2
1119.08WELDING MATERIAL—Section 1105.02(t)
1119.09CERTIFICATION—Section 106.03(b)3
INTELLIGENT TRANSPORTATION SYSTEM (ITS) DEVICES
Get an email when 1119 changes
Pennsylvania revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.