B
HomeLibrariesCode AISearchProjectsBookmarksAddress
FeedbackHelp Desk
Libraries
Estimate & calculate
CalculatorsChecklists
PricingLog in
Part 800 — Bridge Structures

804Driven Piles

RI · 2022 (Aug 2025 compilation) Standard Specifications✓ Full text on BuildSpecBook pages 379–399 Save this section

Ask about Section 804

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

SECTION 804 — DRIVEN PILES — DRIVEN PILES

804.01 Description.

This work includes furnishing and installing foundation piles at the required locations. Ensure that the work also conforms to the applicable requirements of Section 4, Driven Foundation Piles of the AASHTO LRFD Bridge Construction Specifications. This work also includes wave equation analysis, static pile load and dynamic pile testing, and vibration monitoring as required. Pile Types Included. Driven piles include timber, steel H -section, open- end and closed- end steel pipe, micropiles, drilled shafts, mandrel-driven or self -supporting driven steel casings, precast -prestressed concrete piles, and composite piles consisting of two or more sections of differing materials. See SECTION 844 for micropiles and SECTION 845 for drilled shafts. Furnish and install piles driven for soldier-pile retaining walls according to SECTION 805. Wave Equation Analyses and Pile Load Testing. Submit a wave equation analysis for each pile type and capacity to be installed and for each driving hammer and system proposed for use. See Subsection 804.03.8. Pile Load Testing. As required, perform pile load tests according to ASTM D1143, “ Piles Under Static Axial Compressive Load.” Perform dynamic pile tests as required. See Subsection 804.03.08. Pile Lengths. Provide production piles in sufficient lengths to be driven to the required minimum tip elevations that meet the required driving criteria established by the wave equation analysis and to the design cut-off elevation. Production pile lengths shown on the Contractor’s order list generally includes only those lengths anticipated for use in the final structure. In addition to pile lengths shown or ordered, furnish increased lengths of production or preliminary test piles to provide for fresh heading and the additional pile lengths as needed to fit the method of operation. When preliminary test piles are required, production pile lengths shown on the Plans are for estimating purposes only. Provide the actual pile lengths for production piles as required to reach the minimum tip elevations and to develop the required capacit ies, subject to the Engineer ’s written approval after driving preliminary piles. Furnish preliminary piles in lengths greater than the estimated production pile lengths. The Engineer will approve the increased pile lengths before the Contractor orders the preliminary piles. Drive preliminary test piles at the required locations to the minimum tip elevations and based on the driving criteria established for production piles. Preliminary piles may be incorporated into the work as permanent piles, if approved by the Engineer.

Part 800 — Bridge Structures August 2025

SECTION 804 — DRIVEN PILES 800-11 Defective Piles. Repair or remove and replace all unsatisfactory piles.

804.02 Materials.

Use materials that conform to the following. Material Standard Specification Reference Timber Piles Subsections M07.05/M.07.06 Steel H-Piles Subsection M07.09 Open-end and Closed-end Steel Pipe Piles Subsection M07.10 Concrete-Filled Steel Casing Piles Subsection M07.08 Precast-Prestressed Concrete Piles Subsection M07.07 Portland Cement Concrete SECTION 601/Subsection M02 Steel Reinforcement and Prestressing Steel Subsections M05.01/M05.03 Steel Closure Plates, Driving Shoes, and Points, Lugs, and Splicers Subsections M07.11/M07.12 Protective Coatings SECTION M06 Wood Preservatives and Treatment SECTION M07 and AASHTO M133, “Preservatives and Pressure Treatment Process for Timber”

804.03 Construction Methods.

Ensure compliance with all requirements in Subsection 104.15. Pile Lengths and Order Lists. When preliminary test piles are not specified, furnish production piles of sufficient length to be driven to the minimum tip elevation, to meet the approved driving criteria determined from the wave equation analysis, and to provide the required cut-off elevation. In determining the lengths of production piles to be ordered, ensure that the lengths in the order list are based upon the lengths that are assumed to remain in the completed structure. Calculate these pile lengths from the design cut -off elevation to the estimated tip elevation. Increase the lengths to provide for fresh heading and for such additional length as necessary to accommodate the method of operation. For preliminary test piles, drive piles of lengths and at the required locations. The lengths of production piles indicated on the Plans are for estimating purposes only. For actual production pile lengths, ensure that these are as required to reach minimum tip elevations and deeper, if necessary to develop required capacities, subject to the approval of the Engineer in writing, after test piles have been driven. Provide test piles that are in lengths, subject to the Engineer ’s approval, greater than the estimated lengths of production piles, and drive at least to the minimum

Part 800 — Bridge Structures August 2025

800-12 SECTION 804 — DRIVEN PILES tip elevations and deeper, if necessary, to develop required capacities established for production piling. Timber Piles. • General. Do not use cant hooks, dogs, or pike poles. Ensure that the butt ends of timber piles are sawn square to the longitudinal axis of the pile before driving. • C ollars, Bands, or Strapping. Ensure that collars, bands, or strapping are affixed at the butt, intermittently along the length, and near the tip of each pile. • Tr imming and Drive Points . Ensure that the tips of timber piles are sawn square or tapered to a diameter of not less than 4 in . If required, provide timber piles with metal boots or steel point attachments. Trim pile tips to fit the type of boot or point attachment specified. Precast-Prestressed Concrete Piles.

a.Manufacture. Use concrete for precast/prestressed piles that conforms to SECTION 601. Provide precast/prestressed piles that are manufactured and prestressed according to both the AASHTO LRFD Construction Specifications , Section 10, “ Prestressing,” and SECTION 809.
b.P restressing. Submit Shop Drawings for the Engineer ’s written approval according to Para. b of Subsection 809.03.3. In addition, ensure that the Shop Drawings identify the pile dimensions, materials, prestressing methods, tendon arrangement, and prestressing forces proposed for use, and any addition or positioning of reinforcing steel differing from that shown on the Plans. Do not initiate the manufacture of the piles until the S hop Drawings have been approved by the Engineer in writing.
c.C uring, Storage, and Handling. Ensure that the removal of forms, storage, transport, and handling of precast/prestressed concrete piles prevent any excessive bending stresses, cracking, spalling, or other injurious results. Submit a curing plan as specified in Subsection 809.03.8. When lifted or moved, support the precast/prestressed concrete piles at the quarter points or other designated pick-up points. Do not drive piles until the specified curing period is completed and the concrete has attained the specified 28-day compressive strength.
d.E xtensions . When required, make extensions for precast/prestressed concrete piles by removing concrete at the end of the pile end to clear 40 diameters of reinforcement steel and to produce a face perpendicular to the axis of the pile. Fasten the reinforcement of the same size as that used in the pile to the projecting steel. Place the necessary formwork to prevent leakage along the pile. Immediately before placing concrete, clean and wet the tops of piles and cover with a thin coating of approved suitable bonding material. Use concrete of the same mix design and quality as that used in the pile. Ensure that forms remain in place for not less than seven days. Cure and finish extensions according to SECTION 809. Do not drive extended precast/prestressed piles.

Part 800 — Bridge Structures August 2025

SECTION 804 — DRIVEN PILES 800-13 Concrete-Filled Steel Casing Piles.

a.General. Construct concrete-filled steel casing piles by driving the casings, with or without a mandrel, placing reinforcement steel, and filling the driven casings with concrete.
b.S teel Casings . Provide steel casings that comply with Subsection M07.08.1 and that have a sufficient thickness and strength to hold the original form and demonstrate no harmful distortion after driving adjacent casings or after withdrawal of the driving core. Casing designs other than that shown on the Plans will be approved by the Engineer before use. Ensure that t he thickness of steel casings driven without a mandrel are a minimum No. 9 gauge for fluted casings and 3/16 in. for pipe casings. Ensure that casings driven with a mandrel have a thickness not less than No. 18 gauge.
c.C leanout and Dewatering. Remove accumulated soil cuttings and water from driven casing piles before placement of any concrete. C leanout and dewater the casing and ensure that this work does not result in damage to the steel casing. Provide equipment and facilities for containment, temporary storage, and separation of soil cuttings, and properly dispose of debris/sediment/soils and water accumulations.
d.I nspection of Driven Casings. Inspect each driven casing pile, which must be approved by the Engineer before any concrete is placed. P rovide access to the pile and furnish a suitable illuminating device for inspection of the casing interior throughout its length.
e.P lacement of Reinforcement and Concrete. Remove accumulated soils and water from driven casings before concrete is placed. Use concrete that complies with Subsection M07.08.2. Fabricate and secure the reinforcing steel cages, and lower the casing pile to ensure proper placement throughout the length of the pile and to provide the required pile cap connections. Place and consolidate the concrete in steel-reinforced casing piles by vibration throughout the length of the pile interior. Do not place concrete until all other casing pile driving within a radius of 20 ft of the driven pile has been completed. Alternatively, if approved by the Engineer or where allowed, discontinue all driving within the specified limits until concrete in the last casing driven has set for at least five days. Steel Pipe Piles.
a.General. Where practical, furnish steel piles in full length.
b.Protective Coating. When specified, before being driven or placed, apply a protective coating in the shop to steel pipe piles, closure plates, and splices with zinc-silicate primer. When specified, after piles are driven and all bracing members, concrete caps, and encasements are in place, apply one complete field coating to all exposed steel.
c.D rive Points, Drive Shoes , and Closure Plates. When specified, fit steel pipe piles with closure plates and/or drive points. Furnish c losed-end steel pipe piles with flat closure plates of the required thickness and weight of steel. When specified, provide end closure

Part 800 — Bridge Structures August 2025

800-14 SECTION 804 — DRIVEN PILES plates that are single-piece cast steel , 60-degree conical points (ASTM A27), with an external flange. When specified, furnish open-end or closed-end steel pipe piles with one-piece, cast steel (ASTM A27) drive shoes, provided with a thickened ridge along the bearing surface between the pile tip and the shoe. Ensure that s hoe flanges are external and are of the required dimensions and weight of steel. Ensure that plates, drive points, and shoes provide full bearing with pile tips and are affixed to the piles using 5/16-in. continuous fillet welds along the flange or ridge contact with the pile tips.

d.Cleanout and Dewatering. Clean out steel pipe piles that are driven open- ended to remove accumulated soil materials and then dewater the pile. U se methods to remove the soil materials from the interior of the pile that do not result in damage to the driven pipe pile. Contain and separate soil cuttings and accumulated water. Properly dispose of water and accumulated soil cuttings.
e.Inspection of Driven Pipe Piles. Provide access and facilities for the Engineer to inspect the interior of each driven pipe pile. The Engineer will not accept any driven steel pipe pile unless inspected and approved by the Engineer as described in Subsection 804.03.4(d). Correct or replace improperly driven, damaged, or defective piles at no additional cost to the Department.
f.P lacement of Concrete and Steel Reinforcement . Where driven steel pipe piles are concrete-filled and no interior steel reinforcement will be installed except within 5 ft of the cut-off elevation, place the concrete in one continuous operation with the concrete installed from the lowest point of the pile by tremie. Do not allow the concrete to free fall. Use vibration or rodding only to a depth of 5 ft below the design cut-off elevation. Use the class of concrete as specified in Subsection M07.10.2. For all steel pipe piles at each structure footing or within the required radius, drive, clean out, and inspect before placement of concrete. Alternatively, if approved by the Engineer, discontinue all driving within the specified limits until concrete in the last pile driven has attained its 28-day compressive strength.
g.Holes in Piling. Pile segments with one drilled hole with a diameter of ⅞ in. or less in any cross section may be incorporated into the finished structure. Cut off pile segments with more than one hole in the cross section, flame cut hole(s), or a hole greater than ⅞ in. to remove the hole(s). This requirement does not apply to holes drilled for attaching dynamic testing equipment, holes shown in the C ontract, or holes within 12 in . of the cutoff elevation. Steel H-Section Piles.
a.Dimensions and Section Thicknesses. Where practical, furnish steel H -sections in full lengths.

Part 800 — Bridge Structures August 2025

SECTION 804 — DRIVEN PILES 800-15

b.Drive Points . Fit H -section piles with drive points that are cast in one- piece steel conforming to ASTM A27 Grade 65-35. Ensure that the drive points have sufficient flange and continuous web vertical backups to provide proper alignment and a secure fit with the pile. Flange surfaces to bear on rock or in soil may be horizontal or sloped (minimum 15 degrees to maximum 30 degrees) and may be provided with individual or continuous cutting teeth.
c.P rotective Coating. Where specified, provide steel H -section piles with a shop application of one coat of zinc -oxide primer. Additionally, apply one or more field-applied surface coats to exposed sections of piles as driven. Do not apply field coats to lengths of pile to be concrete encased.
d.C oncrete Encasement. Where specified, encase exposed lengths of driven steel H - section piles in concrete. Furnish and place concrete encasements according to SECTIONS 601 and 808.
e.Ho les in Piling . Pile segments with one drilled hole with a diameter of ⅞ in. or less in any cross section may be incorporated into the finished structure. Cut off pile segments with more than one hole in the cross section, flame cut hole(s), or a hole greater than ⅞ in. to remove the hole(s). This requirement does not apply to holes drilled for attaching dynamic testing equipment, holes shown in the Contract, or holes within 12 in. of the cutoff elevation. Splices and Splicing Piles.
a.General. Where splicing is permitted, ensure that the splice develops the full strength of the unspliced pile. Only one splice may be used throughout the pile length unless specifically approved by the Engineer. Ensure that splices are fabricated and installed as shown on the Plans. Ensure that any alternative method of splicing or commercial splice proposed for use provides equal results and has been approved by the Engineer before use.
b.S teel Pipe, Steel Casing, and H -Section Piles. Where practical, use full length piles. Use full penetration electric arc welding for splices. Use proprietary or other fabricated steel splicers that match the grade of the piles being spliced and that develop the full strength of the unspliced pile. The Engineer will approve the splices before use. Chamfer the flanges of fabricated splicers to enable effective welding. Before splicing, cut off the top of any pile that is bent, deformed, or twisted by driving or trueing up to normal with the axis of the pile before placing the next pile section. Ensure that the end surfaces of piles provide full bearing with the next pile section or splicers. Ensure that axes of all spliced sections are in a straight alignment. Provide flanges of H-section piles that are either spliced by butt welding or with plates that are welded or bolted. Prefabricated splicers may be used if the splice can develop the net section of the pile in compression, tension, shear , and bending. Splice pipe piles either by butt welding or using welded sleeves.

Part 800 — Bridge Structures August 2025

800-16 SECTION 804 — DRIVEN PILES Ensure that the surfaces to be welded are smooth, uniform, and free from loose scale, slag, grease, or other material that could prevent proper welding. Steel may be oxygen cut. Carbon-arc gouging, chipping, or grinding may be used for joint preparation. Welding is permitted for splicing steel casings . Use welding for splicing steel piles, attaching pile points, and attaching bracing or other steel members to steel piles. Ensure that all welding and qualifications for welders conforms to Subsection 824.03.6.

c.Precast/Prestressed Concrete Piles . Do not splice p recast/prestressed concrete piles except to produce short extensions as permitted herein. Dowels or other mechanical splices must be approved by the Engineer before incorporat ion into the work. Design splices to develop the full axial and moment capacity of the unspliced cross section. Determination of Bearing Capacity.
a.General. Drive piles to the required bearing capacity.
b.Wave Equation Analysis. For design loads less than or equal to 50 tons, a Rhode Island Registered Professional Engineer shall prepare a wave equation analysis to determine the ultimate bearing capacity of the piles. The Contractor shall be responsible for retaining a Professional Engineer registered in the State of Rhode Island to perform the wave equation analysis. Submit the results of the analysis, driving system specifications and data, and the proposed driving criteria to the Engineer for written approval. Perform a separate wave equation analysis for each design pile type, load, and length, and for each driving system proposed for use. Ensure that the analysis accounts for the proposed hammer assembly, pile cap, blocks, cushion characteristics, pile properties and estimated lengths, and anticipated soil properties. Use the pile driving equipment properties as recommended or provided by the manufacturer. Ensure that t he design bearing capacity of a pile is 0.364 of the calculated ultimate bearing capacity as determined by a wave equation analysis alone. The analysis may, at the discretion of the Engineer, be used to establish design capacities of greater than 50 tons if similar piles have been installed in similar soil conditions in close proximity to the site.
c.Wave Equation Analysis Calibrated with Dynamic Pile Tests. S ubmit for review and approval by the Engineer a wave equation analysis (WEAP) for each pile that will be installed. Ensure that the analysis demonstrates that the driving forces developed by the pile hammer equipment and driving methods will not overstress the pile section and any splices. The Contractor’s Engineer or testing consultant shall supply all equipment, including the Pile Driving Analyzer (PDA), and perform the dynamic pile analyses during the driving of the indicator piles. Within three days of completion of the dynamic testing, submit the results of the field data for review and approval by the Engineer. Furnish the electrical power required for dynamic testing of the piles. Equip f ield generators with functioning meters for monitoring voltage and frequency. P rovide a temporary shelter of adequate size to protect the dynamic test equipment from the elements.

Part 800 — Bridge Structures August 2025

SECTION 804 — DRIVEN PILES 800-17 ● General Procedures. ○ Before Driving. P rovide equipment, personnel, or labor as required to perforate the pile and attach and remove the PDA transducers to and from the pile as directed by the Engineer. P rovide a man-lift or other suitable equipment for the Engineer to access the PDA instrumentation during driving. Attach a minimum of four strain and acceleration transducers (two each minimum) to the pile at the locations specified or directed by the Engineer. The Contractor’s Engineer will provide the transducers. Locate the t ransducers at equal radial or cross- sectional distances on diametrically opposite sides of the piles. L ocate the transducers at the same axial distance from the top of the pile, and attach them at least 1½ pile diameters below the top of the pile but no closer than 2 ft below the lowest point of the pile hammer and sleeve. R elocate the transducers satisfying these conditions before driving each new pile section. Ensure that the transducers remain above water level during installation and driving. A lign and protect the transmission cables to suit the Contractor’s method of operation but maintain the operation of the equipment during driving. Position and align t he pile so that t he hammer impact is applied axially and concentrically with the pile. ○ Driving. D rive the piles to the tip elevation or deeper to a driving resistance determined by the WEAP analysis and as confirmed by PDA measurements on the indicator piles. Within each substructure unit, drive the indicator piles first. Drive and restrike all indicator piles within a given substructure unit shown on the Contract Drawings with monitoring by PDA before the Engineer establishes the final tip elevations for friction piles or driving resistance for end-bearing piles for the remaining non-indicator piles within the substructure unit. In the Contractor’s schedule, allow time for a two-day evaluation at each substructure unit by the Engineer following the end of restrikes on the indicator piles at each substructure unit so that the Engineer can establish final criteria for the remaining production piles. While waiting for restrike of the indicator piles, the Contractor may begin installation of other non-indicator piles; do not drive to completion any non-indicator piles before the Engineer establishes the final tip elevation or driving resistance. Where friction piles are used, drive the indicator piles to the required design tip elevation and to the required resistance as measured by dynamic monitoring. Drive t he indicator piles deeper than the design tip elevations to meet the required resistance, if necessary. The Engineer will determine the final tip elevations for the remaining non-indicator piles at each substructure unit following the indicator pile installation and restrike and analysis of the PDA results performed on the indicator piles. At the substructure unit s supported by end-bearing piles, initially drive the indicator piles to a penetration resistance expressed as a minimum number of blows per inch for six successive inches as determined by WEAP or other

Part 800 — Bridge Structures August 2025

800-18 SECTION 804 — DRIVEN PILES alternatives. Ensure that the f inal driving of the indicator piles satisfies one of the two following criteria: + The final required penetration resistance determined by dynamic monitoring (PDA) + To refusal (defined as > 20 blows with less than 1 in. of penetration) Drive the remaining end-bearing production piles to the minimum tip elevation and to whichever of the following criteria is satisfied first: + The required penetration resistance as determined by the Engineer after driving the indicator piles and analyses of the PDA results of the indicator piles + The pile has refused (defined as > 20 blows with less than 1 in. of penetration) Adjust the driving energy to maintain acceptable stresses in the pile, and realign the driving system if the testing equipment indicates that the hammer impact is not delivered axially to the pile. Monitor and record: + Ram travel length + Bounce chamber pressure and/or steam or air pressure at the inlet to the hammer as appropriate for the driving system used + Blow counts for specific intervals of penetration during driving of piles + Complete the restrike driving of the indicator piles. During restrike operations, the Engineer will perform PDA monitoring. During restrike, the Engineer may direct the Contractor to apply individual hammer blows to the pile to provide for dynamic records and analyses. Before restriking, wait a minimum of three days after the end of the initial driving. The Engineer will determine the amount of penetration during restrike not to exceed 1 ft.

d.Static Pile Load Tests. When the design capacity of piles is greater than 50 tons, establish the driving criteria and ultimate load capacity for each pile type and capacity following the procedures in ASTM D1143, “Piles Under Static Axial Compressive Load,” using 1) the quick load compression test, except take the test to failure as described below, or 2) three times the design load, or 3) 1000 tons, whichever first occurs. Use testing equipment and measuring systems that conform to ASTM D1143. Install telltales and/or elastic s train gauges, appropriately sheathed, in or along piles at the intervals specified, and monitor vertical movements or incremental strain measurements. Use calibrated dial gauges capable of reading increments of 0.001 in. to monitor relative movements or strains at the pile tip, head, or specified interval along the pile length. Submit for the Engineer’s approval a wave equation analysis for each type and capacity of pile to be tested and detailed plans of the proposed pile load test apparatus, including: ● Load frame and reference members ● Load cell or jacking apparatus

Part 800 — Bridge Structures August 2025

SECTION 804 — DRIVEN PILES 800-19 ● Reaction system ● Proposed method and intervals for telltale installation and protection A Rhode Island Registered Professional Engineer, retained or employed by the Contractor, shall prepare the wave equation analysis and pile load test plans. Design and construct t he load test apparatus to allow the various load increments to be placed gradually without causing vibration to the pile. Ensure that t he wave equation analys is demonstrates that the piles will not be damaged during driving, and determine the blow count necessary to achieve the required ultimate static capacities. The Engineer will review and approve in writing the proposed driving criteria. The design bearing capacity is defined as 50 percent of the failure load. The failure load of a pile under axial compressive load is that load that produces a settlement of the pile head at failure equal to: Sf = S + (0.15 + 0.008D) Where: Sf = Settlement at failure, inches D = Pile diameter or width, inches S = Elastic deformation of total unsupported pile length, inches Furnish piles to be used for load tests with telltales and protective sleeves incorporated into or along the length of the pile. S ubmit the proposed telltale design and method of installation to the Engineer for written approval before the manufacture or furnishing of piles. Ensure that the telltales are sleeved and protected during driving and are functional throughout the pile load test. Secure the sleeves and cast them in the interior of precast or cast-in-place concrete piles, secured to the interior walls of steel pipe piles, or affixed to the faces of steel pipe, timber , and precast piles or the web of H -section piles as required. For the telltales, provide solid, flush-joint sections of steel rods that extend to and screw into threaded steel mounts affixed to or cast into the pile at the specified points along the pile length. For the t elltale sleeves, use plastic or steel tubing as specified, which are properly aligned, installed, and affixed to the screw mounts so that the telltale rods can be lowered into the sleeves entirely under their own weight. Where permitted by the dimensions of the test pile, the Contractor may choose to protect the tubes by installing them inside steel or PVC pipe. Provide sleeves and rods with end caps that provide protection during pile driving. Before installation of the telltale rods, fill the sleeves with a sufficient quantity of oil or grease to fully occupy the annular space between the sleeve and the rod. Install telltale rods into sleeves under the inspection of the Engineer. For any telltale rod installed without the Engineer’s inspection, remove, measure, and re-insert the rod under the inspection of the Engineer. Drive load test piles to the minimum tip elevations and at the driving criteria determined based upon the wave equation analysis. Determine the elevation of the top of the test pile immediately after driving, after driving anchor piles, and just before load testing to

Part 800 — Bridge Structures August 2025

800-20 SECTION 804 — DRIVEN PILES determine heave. Redrive or jack any test pile that has heaved more than ¼ in. to the original tip elevation before load testing. Observe a minimum three- day waiting period between the driving of any anchor piles or the load test pile and the initiation of the pile load test. Prevent eccentric loading of the pile. If the test fails due to eccentric loading, no payment will be made for the test and no future test will be performed on the eccentrically loaded pile. When the approved test method requires the use of tension (anchor) piles that will later be used as permanent piles in the work, use the tension piles that are the same type and diameter as the production piles and are driven in the location of the permanent piles. Test piles must successfully test (i.e., did not fail during testing) to be used as permanent piles. Do not incorporate test anchor piles into the permanent work should a failure of the test occur. Perform the Boot Strap method by jacking down on the test pile or piles with a calibrated hydraulic jack placed beneath a girder. Anchor the girder to tension piles located at least 6 ft from the test pile or piles. Do not allow piles to be closer than 6 ft from the test pile or allow piles to be used to assist in anchoring the girder. Ensure that c onnections of the girder to the anchors and hydraulic jack are tight when the test is initiated, and ensure that the jack can move the test pile or piles a vertical distance of at least 5 in. during the test. If the load is applied to the test pile or piles by jacking against a dead load, do not provide supports to this dead load that are closer than 6 ft from the test pile or piles. Ensure that the jack can move the test pile or piles a vertical distance of 5 in. Always provide a qualified employee to be present during the performance of the test to maintain the required load. If the test is stopped before completion and the load is entirely or partially removed from the pile or piles due to defects in the jack, yield of connections, insufficient load or travel capacity of the jack, or for other mechanical reasons, the Engineer will order that the load test be abandoned and replaced by a new test to be conducted on another pile or piles at an adjacent location. Pile Driving Equipment.

a.Submittals. Submit a description of the proposed equipment, including hammers and appurtenances, according to Subsection 105.02 before starting work. When the bearing capacity of piles will be determined by a wave equation analysis, submit calculations based on the wave equation analysis (WEAP or other equivalent analysis) that demonstrate that the piles can be driven to the required length with a driving energy without damage to the piles. The required number of hammer blows to achieve pile capacity shall be between 4 and 10 blows per inch for the equipment to be considered acceptable for the pile installation. The required number of hammer blows indicated by the calculations for the required bearing capacity shall be between 4 and 10 blows per inch for the equipment to be considered acceptable. In addition, acceptable driving equipment requires that calculated pile stresses corresponding to the driving criteria and required pile capacity are less than the stress

Part 800 — Bridge Structures August 2025

SECTION 804 — DRIVEN PILES 800-21 level that will result in damage to the pile. For steel piles, compressive driving stresses must not exceed 90 percent of the yield point (0.9 Fy) of the pile. For concrete piles, tensile stresses must not exceed three times the square root of the concrete compressive strength, f ′c, of the pile plus the effective prestress value; i.e., [3 x (f ′c)½ + prestress]. Compressive stresses in concrete piles cannot exceed 85 percent of the concrete compressive strength minus the effective prestress (0.85 f′c – prestress). For timber piles, compressive stresses must not exceed three times the allowable static design strength. In-water or near-water pile driving locations, comply with the most recent soft-start State and Federal programmatic and consultation requirements. Before any change in the driving system or equipment will be considered, submit the revised pile driving equipment data and calculations for corresponding driving criteria and pile stresses. The Engineer ’s written approval of the pile driving equipment does not relieve the Contractor of its responsibility to drive piles, free of damage, to the required bearing and tip elevations.

b.Hammers. Piles may be driven with drop hammers, single-, double- or differential-action compressed air or steam operated hammers, or diesel or hydraulic hammers. ● Gravity or Drop Hammers. Gravity or drop hammers may be used for driving timber piles, but do use gravity hammers for precast concrete piles or for piles with design capacities greater than 30 tons. When gravity hammers are allowed, ensure that the ram weight is at least equivalent to the combined weight of the drive cap and the pile. Ensure that the ram weight is less than 3000 lb and that the fall height does not exceed 12 ft. Equip all drop hammers with hammer guides to ensure concentric impact on the drive head or pile cushion. ● Hydraulic Hammers. Use a power plant having sufficient capacity to maintain, under working conditions, the volume and pressure specified by the manufacturer. Equip the power plant and equipment with accurate pressure gauges that are easily accessible to the Engineer. ● Diesel Hammers. Equip open- end (single-acting), diesel hammers with a device to permit the Engineer to determine hammer stroke at all times during pile driving operations. Submit a copy of the manufacturer ’s chart that equates the stroke and blows per minute. Equip closed- end (double-acting), diesel hammers with a bounce chamber pressure gauge that is easily read from ground level. Provide a correlation chart of bounce chamber pressure and delivered hammer energy. ● Vibratory Pile Drivers. Vibratory pile drivers may be used, subject to the Engineer ’s approval, provided that sufficient correlated data is developed and furnished to permit a satisfactory evaluation of pile load- carrying capacity and performance. Establish these characteristics by direct comparison to the penetration and performance of the same type(s) of pile, driven with conventional impact hammers under similar conditions and in corresponding locations.

Part 800 — Bridge Structures August 2025

800-22 SECTION 804 — DRIVEN PILES If a vibratory hammer is used, redrive each pile for a minimum of two pile diameters with an impact hammer that has the energy to verify the required bearing resistance during driving. Delays and additional costs resulting from load tests or other extra work required to verify approval of the vibratory hammer or driving aids are at no additional cost to the Department. Drive a number of length- determination piles as ordered by the Engineer using a conventional hammer to determine with reasonable accuracy the depth of acceptable penetration throughout the area of each foundation or trestle bent. Drive the subsequent piles using the accepted alternative method to the corresponding depths of penetration with minor adjustments if driving conditions change. Load test a representative number of such piles as designated by the Engineer and indicated on the Project Plans to the required capacity, plus a corresponding number of those piles driven using the alternative method and equipment. Record and correlate load test data. Perform a sufficient number of load tests on piles driven using the alternative method as required to verify the results and ensure design capacity. No payments will be made to the Contractor for pile load tests in excess of those that would be required for piles driven by conventional methods, unless field conditions are such that the alternative methods must be used to advance piles. In these cases, the additional load tests will be measured for payment if the Engineer has ordered the tests in writing, and the tests are completed. Driving Appurtenances.

a.Hammer Cushions. Equip all impact driving equipment except gravity hammers with a suitable thickness of hammer cushion material to prevent damage to the pile or hammer and to ensure uniform driving behavior. Place a striker plate on the hammer cushion to ensure uniform compression of the cushion material.
b.P ile Drive Head . Fit piles driven with impact hammers with an adequate drive head to distribute the hammer blow to the pile head. Ensure that the drive head is axially aligned with the hammer and pile. Ensure that the drive head is guided by leads, and do not allow the head to be free swinging. Fit the drive head around the pile to prevent the transfer of torsional forces during driving while maintaining proper alignment of hammer and pile.
c.P ile Cushion . Protect concrete piles with a pile cushion that ensures that the hammer energy is uniformly distributed to the pile head.
d.Leads. Use pile driving leads throughout the pile driving operation, and support the pile and hammer in proper positions. Construct leads that affords freedom of movement of the hammer while maintaining alignment of the hammer and pile to ensure concentric impact for each blow. Ensure that the leads have sufficient length to negate the need for a follower, and design the leads to permit proper alignment of batter piles.
e.Fol lowers . Do not use followers.

Part 800 — Bridge Structures August 2025

SECTION 804 — DRIVEN PILES 800-23 Preparation for Driving.

a.Preconstruction Survey and Vibration Monitoring. A Rhode Island Registered Professional Engineer, employed or retained by the Contractor and submitted to the Engineer before beginning work, shall perform a preconstruction survey of any structure within 200 ft of pile driving. Ensure that the survey documents the existing preconstruction condition of structures so that potential impacts due to pile driving can be assessed. Comply with SECTION 841. During pile driving, monitor vibrations at structures within 200 ft of pile driving using a seismograph capable of measuring vibration accelerations, velocities, and amplitudes in three mutually perpendicular directions. A Rhode Island Registered Professional Engineer shall supervise the vibration monitoring. Adjust the pile driving operations to limit construction vibration peak particle velocities to 1 in. per second, unless a lower limit is warranted based on the preconstruction survey. Submit d aily s ummaries of peak particle velocities and vibration records to the Engineer on a weekly basis.
b.Layout and Elevation and Location Control. Perform the layout of all pile locations using offsets from the P roject baselines. Establish ground surface elevations at the proposed driving locations to the nearest 0.1 ft, referenced to the Project elevation datum. Set tide boards as required when driving piles on water. Determine m udline elevations at each pile location on water before initiating driving. Verify the tip elevation of driven piles to the nearest 0.01 ft relative to the Project elevation datum. Where foundation or trestle piles are driven in groups, or where piles will be restruck, check each pile tip elevation before and after restriking as required by the Engineer.
c.Excavations and Sheeting. In general, do not drive piles until after the excavations are completed. Restore any material forced up between or around piles resulting from driving to the correct elevation. Compact the surface before any foundation concrete is placed. Where sheeting or cofferdams will be constructed, and where piles will be driven within sheeting alignments, submit the proposed sequence of operations for the Engineer ’s written approval before beginning any driving of sheeting or piles. Ensure that the sheeting installation does not interfere with, obstruct, damage , or otherwise impact the function of bearing piles.
d.Preboring. When required, prebore holes at pile locations to the required depths. Ensure that prebored holes are generally smaller in diameter than the diameter or diagonal of the cross section of the pile, except where preboring is specified where driving vibrations are not permissible. Ensure that preboring has sufficient depth to allow penetration of the pile to the specified depth. If subsurface obstructions are encountered, the hole diameter may be increased to the least dimension that is adequate for pile installation. Fill a ny void space remaining around the pile after completion of driving or other installation with sand or other approved material. Do not use spuds to make a hole for inserting a pile in lieu of preboring. Drive p iles to be driven through newly constructed embankments in holes drilled or spudded through the embankment when the embankment is more than 5 ft in height.

Part 800 — Bridge Structures August 2025

800-24 SECTION 804 — DRIVEN PILES Ensure that t he hole has a diameter of not less than the greatest dimension of the pile cross section plus 6 in. After driving the pile, fill the space around the pile to the surface of the embankment with dry sand or fine gravel. Properly dispose of material resulting from drilling holes.

e.Templates and Support Spuds. Furnish and fabricate the templates as deemed necessary to align and maintain piles at their proper location, alignment, or batter throughout driving. Securely affix these templates using temporary spud piles or other appropriate bracing. Situate template configurations and support piles to not damage or displace driven piles nor interfere with pile driving or other portions of the work. Maintain templates in place after initial driving and until restriking has been completed. Dismantle and remove templates and temporary supports or piles to not damage or misalign the completed production piling.
f.M easurement and Marking of Piles . Measure the total length of each pile to be driven, and mark each pile in the increments using the required marking material. Notify the Engineer of the total measured length of each pile, and allow the Engineer time to verify the length and to approve the pile marking before placing piles in the leads for driving. During driving, provide markings on the leads or provide a graduated gauge that is clearly marked and situated at ground level to allow verification of the final driving resistance for each pile driven.
g.Jetting. Do not use water jetting unless specifically authorized in writing by the Engineer. Secure any necessary permits before initiating work. When water jetting is used, determine the number of jets and volume and pressure at the jet nozzles that are sufficient to freely erode material adjacent to the pile without affecting the lateral stability of the final in-place pile. Restore or repair all damage to the site resulting from jetting. When jetting is specifically required, ensure that the plant has sufficient capacity to deliver at all times a pressure of 100 lb/sq in. at two, ¾- in. jet nozzles. Cease jetting and remove the jets when the pile tip is at a minimum of 5 ft above the required tip elevation. Drive the pile by impact hammer to the required tip elevation and bearing capacity. C ontrol, treat as necessary, construct, and maintain appropriate settlement basins, and properly dispose of sediments and expended jetting water. See SECTION 208 for specific guidance. Driving Piles.
a.Pile Driving Records . Maintain records for the number of blows required for each pile driven for each foot of penetration for the entire pile and for the penetration under the final series of blows (blows per inch for a minimum of the last 12 in. of driving). Ensure that the records include the type and size of hammer used, rate of hammer operation, and type and dimensions of driving helmet and cushion block. Ensure that the records include the: ● Date ● Starting time ● Total driving time ● Pile location and identification number ● Pile type and size

Part 800 — Bridge Structures August 2025

SECTION 804 — DRIVEN PILES 800-25 ● Ground elevation from which the pile is driven ● Final elevation of the pile tip and butt Ensure that the records also indicate the quantity of concrete that is placed in the pile.

b.General. Where underground utilities are located in the immediate vicinity, ensure that the first pile driven is the one nearest the utility. If the Engineer agrees that an obstruction cannot be economically removed, the Contractor has the option of driving an alternative pile (or piles) at a location designated by the Engineer. Remove or cut off the initial pile as directed by the Engineer.
c.Dr iving Test Piles . Drive preliminary test piles and piles designated for dynamic or static load tests at the locations and to the depths directed by the Engineer before other production piles are ordered or driven in the area represented by the test. Drive a ll test piles with equipment identical to that which will be used for production piles. Drive test piles to a hammer blow count determined by the WEAP Analysis and approved by the Engineer at the estimated tip elevation. Allow t est piles that do not attain the specified hammer blow count at a depth of 1 ft above the estimated tip elevation to set up for a period determined by the Engineer before being redriven. If practical , warm up the hammer before redriving begins by applying at least 20 blows to another pile. If the specified hammer blow count is not attained upon redriving, the Engineer may direct the Contractor to drive a portion or all of the remaining pile length and repeat t he set up and redrive procedure. When ordered by the Engine er, drive test piles to plan tip elevation without attaining the required hammer blow count, and splice and drive until the required blow count is attained.
d.Use of Preliminary Test Piles and Loaded Test Piles . Loaded test piles may be used in the permanent structure if the Engineer determines they are satisfactory for this use. Preliminary test piles driven to the required capacities may similarly be used in the permanent structure. Remove loaded test piles or preliminary piles that are determined not suitable for use in the permanent structure, or cut off the piles a minimum of 2 ft below ground and below the base of footing or pile cap elevation.
e.P enetration of Piles . Drive all piles to a penetration so that the minimum pile tip elevation is attained and that the pile bearing value, determined as specified, is not less than that indicated in the Contract. Drive piles located offshore, alongshore, in stream beds , or along stream banks to the penetration as indicated on the Project Plans necessary for scour protection. If, after a test pile or production pile is driven through and below a hard stratum, the bearing value of the pile drops below the required capacity, drive permanent piles through the hard stratum to the required capacity. When production friction piles fail to achieve design bearing capacities after driving the full finished lengths, when approved by the Engineer, wait a minimum of 24 hours and then redrive one representative pile in each pile group to check the gain in bearing upon soil setup. Determine the soil setup bearing based on the number of redriving blows

Part 800 — Bridge Structures August 2025

800-26 SECTION 804 — DRIVEN PILES necessary to drive the pile an additional 3 in. These piles may be accepted without splicing if they exhibit the required bearing capacities upon redriving.

f.Driven Pile Location and Alignment Tolerances . Drive piles to within an axial tolerance not to exceed ¼ in. per ft variation from the vertical or from the design batter orientation. Drive piles for trestle bents so that the bent cap may be constructed in its design location without inducing excessive stresses in the piles. Ensure that the final position of the axial center of driven foundation piles, measured in the plane of the cut-off elevation, does not deviate from the design location by more than 6 in. or ¼ of their diameter, whichever is greater, if all of the following criteria are met: ● The average deviation along a line of piles in any direction within the bent does not exceed 3 in. from the line through the required pile center locations. ● The nearest edge of any pile is not closer than 9 in. from the design position of the edge of footing or pile bent cap. ● The minimum distance between the centers of any two adjacent piles is not less than 24 in. at the cut-off elevation. ● The center of gravity of the pile group at any trestle bent or foundation, as calculated at the cut-off elevation, does not exceed the tolerances specified in the Contract for that pile group. Considering driven pile location and alignment tolerances, if there are complications driving a pile and the pile alignment tolerances are exceeded, immediately stop operations, and contact the Engineer to determine the appropriate course of action. If the location of any pile exceeds these tolerances, then provide appropriate calculations to show the center of gravity of the pile group at the cut off elevation as driven. If the center of gravity of any pile group exceeds the limits specified, or that otherwise presented in the Contract, submit a detailed remedy, including all relevant engineering calculations, for review and approval by the Engineer. P erform the approved corrective action, including replacement of misaligned piles and/or furnishing materials and constructing any required increase in footing dimensions, at no additional cost to the Department. Do not m anipulate piles after driving attempting to force the pile into proper position . Remove or, if space allows and as allowed by the Engineer, cut off misdriven piles and redrive, or replace mislocated piles to the satisfaction of the Engineer.
g.Pile Heave and Restriking. Determine the top elevation of each pile head immediately after driving and again after completion of the driving of all piles within any foundation or trestle pile group. Redrive any pile that heaves more than ¼ in. to the design tip elevation and to the required driving resistance. For concrete -filled piles, restrike heaved casings or steel pipe piles before placing concrete in any pile within that pile group that has not evidenced heave.

Part 800 — Bridge Structures August 2025

SECTION 804 — DRIVEN PILES 800-27 Defective, Damaged, or Broken Piles. Ensure that the driving operations and procedures do not subject piles to excessive or undue damage or stresses that produce: • Spalling and crushing of concrete • Splitting, splintering, or brooming of timber piles • Splitting or excessive deformation of steel piles and casings • Bending, crushing, torsional rotations, etc. (especially for steel H-piles) Correct any pile damaged by reason of internal defects, improper driving, driven out of position, or driven below the required butt elevation by one of the following methods as approved by the Engineer: • Replace the pile with a new and, if necessary, longer pile. • Cut-off the defective or low pile below the base- of-footing elevation, and drive a second pile adjacent to the defective or low pile. • Splice, or otherwise build up, the pile as provided for herein, or extend and reinforce the footing sufficiently to properly embed the pile. Perform all remedial materials and work at no additional expense to the Department. Pile Dewatering, Cleanout, and Spoil/Water Containment and Disposal. Remove soil materials, debris , and/or accumulated water from driven steel pipe piles and steel casing piles to allow inspection of pile interiors and before placement of any concrete. Provide for the control, containment, separation of sediments, and proper disposal of sediments and water volumes removed from the piles. Restore or repair any damage to the site incurred by dewatering and cleanout of piles according to the Contract requirements. Pile Cut-Offs. Do not cut-off piles until: • The driven pile as-builts have been reviewed and approved by the Engineer • All piles within a pile group or within the area specified have been checked for heave • Any required restriking or redriving has been completed Cut-off all piles perpendicular to the longitudinal axis of the pile at the required elevations. For piles that support timber caps or grillages, saw or otherwise cut off the pile to conform to the plane of the bottom of the superimposed structure. Ensure that the amount of cut-off length is sufficient to remove any portion of the pile top that has been trimmed for driving, bruised, or otherwise deformed or damaged during driving. Anchor c ut-off piles to the structure or otherwise protect the pile until incorporated into the remainder of the work. Retain the cut-off portions of all piles, including test piles, and make available for use in splicing or building up piles as required until the pile driving is complete. Upon completion of the work,

Part 800 — Bridge Structures August 2025

800-28 SECTION 804 — DRIVEN PILES piling cut-off lengths shall become the property of the Contractor and shall be properly disposed of off-site at the Contractor’s expense. Trim cut-off pile heads, cuts for bracing, and exposed abrasions of treated timber piles, and apply the required field coatings of preservatives. Coat predrilled bolt holes with the required field preservative. If treated holes will remain open, install field-treated wood plugs or other approved temporary plugs in the holes. Where specified, after trimming and applying the preservative, bend down over the top of the pile a sheet of three- ply roofing felt, or a sheet of galvanized iron, not lighter than 24 gauge and of sufficient area to project at least 6 in. outside and completely around the pile head to fit tightly around the pile. Trim and fasten t he edges of this cover to the pile face with large -headed galvanized roofing nails or bound with galvanized wire. Clean the tops and faces of precast concrete piles that will be embedded in the structure and remove minor chipping or spalling. Cut off steel pipe piles and steel casings at the design elevation before emplacement of concrete fills. If steel pipe or steel casing piles will remain unfilled, install the required protective caps.

804.04 Method of Measurement.

Piles Furnished. Piles Furnished will be measured to the nearest linear foot of pile, calculated from the tip elevation to the specified cut-off elevation. Measurement for Preliminary Test Piles will be made for that length authorized by the Engineer in writing before delivery of piles based on the Plans and discussions with the Contractor and Construction Manager. The additional footage of production or preliminary piles furnished at the Contractor’s option will not be included in the quantity measured for payment. Piles furnished by the Contractor to replace piles that were previously accepted by the Engineer, but subsequently damaged before completion of the Contract, will not be measured for payment. Piles Driven. Piles Driven will be measured to the nearest linear foot of pile, calculated from the tip elevation to the specified cut-off elevation. Pile Cut-Offs. Pile cut-offs will not be measured separately for payment. Pile Load Tests. Pile Load Tests will be measured by the number of pile load tests performed.

Part 800 — Bridge Structures August 2025

SECTION 804 — DRIVEN PILES 800-29 Protective Coating. Protective Coating will be measured by the linear foot of coated pile. Related Items. • Steel reinforcement for steel casing piles or steel pipe piles and steel reinforcement cages for pipe piles will be measured for payment under the provisions of SECTION 810. Reinforcing steel for pile connections into pile caps is incidental to the Piles Furnished pay item. • Concrete for steel casing piles or steel pipe piles will be measured for payment under the provisions of SECTION 601 and SECTION 808. • Excavations for foundations dug before pile installation will be measured for payment under the provisions of SECTION 203. • Sheeting driven before installation of piles will be measured for payment under the provisions of SECTION 805. • Test piles driven before the installation of production piles and used for pile load tests that pass the testing without damage and are accepted by the Engineer will be measured for payment by the linear foot as production pile under Subsection 804.04.2. • Preconstruction and Post Construction Surveys will be measured for payment under the applicable provisions of SECTION 841.

804.05 Basis of Payment.

The Department will pay for the completed and accepted quantities as follows. Pay Item Pay Unit Timber Piles Furnished LF Precast/Prestressed Concrete Piles Furnished LF Steel Piles Furnished LF Composite Piles Furnished LF Timber Piles Driven LF Precast/Prestressed Concrete Piles Driven LF Steel Piles Driven LF Mobilization & Demobilization of Pile Driving Equipment LF Composite Piles Driven LF Static Pile Load Tests EA Dynamic Pile Load Tests EA Protective Coating LF (of pile coated) The prices constitute full compensation for all labor, materials, tools, equipment, and all incidental items of work necessary to finish the work, complete and accepted.

Part 800 — Bridge Structures August 2025

800-30 SECTION 804 — DRIVEN PILES Remove and replace any broken, improperly driven, or otherwise defective shell pile as directed by the Engineer at no additional cost to the Department. Where a loading test is abandoned because of reasons for which the Contractor is responsible, there will be no payment for the abandoned test. Templates and support piles will remain the property of the Contractor, and no separate payment will be made for furnishing materials or labor to construct templates or for support piles. There will be no payment for the initial pile or for any costs of attempting to remove the obstruction. The Department will pay for the alternative pile or piles (due to an unmovable obstruction) at the Contract unit prices. However, the Contractor shall have no claim for delay if this contingency should arise and no claim for moving his equipment to and from the pile location. Pile dewatering, cleanout, and spoil/water containment and disposal will be considered included in the installation of the pile types. No separate measurement or payment will be made for this work. For Pile Load Tests, anchor, or tension piles installed at the Contractor ’s option for use in conducting pile load tests will not be paid for separately. Metal boots, drive points, drive shoes, and closure plates are incidental to the work and will not be paid for separately. When these items are not specified in the Contract Documents, but ordered by the Engineer, they will be paid for under Subsection 104.05. No payment will be made for splicers or splicing made at the Contractor’s initiative. Preboring is incidental to the work and will not be paid for separately. Reinforcement pile cages for pipe piles will be paid separately under SECTION 810. The Department will only pay once for mobilization and demobilization, regardless of the number of phases.

Get an email when 804 changes

Rhode Island revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Standard Specifications for Road and Bridge Construction (Blue Book), 2022 (Aug 2025 compilation) Edition. Pages 379–399 of 951. View official source ↗

Ask about this section

Scoped to Rhode Island RIDOT Standard Specifications for Road & Bridge Construction, Section 804 — Driven Piles. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.