605.1Description.

This work consists of providing, installing and dynamically testing foundation piles.

605.2Materials.

A.Reinforcing Steel Section 611 and 1037
B.PCC, Class A Section 1022
C.Steel Shell Piles Section 1032.3.1
D.Precast, Prestressed Concrete Piles Section 1032.5
E.Steel H Piles Section 1032.4
F.Timber Piles Section 1032.2
G.Metal Sheets Section 1039.9
H.Epoxy Grout Section 1047.4

605.3Construction.

605.3.1 Submittals.

A.Submit working drawings showing:
1.Details of the proposed pile;
2.splice details if proposing an alternate to the contract details;
3.procedures for lifting, transporting, and handling piles; and
4.for precast concrete piles, include details of the reinforcement and prestressing strands; and
5.for cast-in-place piles, include the proposed method of securing the reinforcement bar in

position during concrete placement.

B.Pile Installation Equipment.
1.At least 30 calendar days before driving piles, submit technical specifications for the proposed

pile driving system to the engineer for approval. Use Figure 605.3C-1 DelDOT Pile and Driving Equipment Data Form.

2.Provide the engineer with a chart from the hammer manufacturer, equating stroke and blows

per minute for the hammer in use.

C.Pile Testing Firm.
1.Employ a pile testing firm experienced in high-strain dynamic monitoring of driven piles to

conduct load tests, record all data, and provide test result reports to the engineer.

2.Use a pile testing firm with at least 5-years of documented experience in performing and

interpreting dynamic pile testing.

3.Ensure that the testing firm's field engineer or technician operating the instrumentation and

collecting the data has documented experience on at least 10 previous projects with similar pile

requirements and possesses a valid certificate of proficiency issued by the Pile Driving Contractors Association (PDCA).

4.Ensure that the field engineer or technician is capable of understanding and interpreting the

collected data during pile driving.

5.Submit the pile testing firm qualifications for dynamic testing to the engineer for approval with

the wave equation analysis submittal. The engineer will review the firm's qualifications and applicable previous experience on other projects.

D.Wave Equation Analysis Requirements.
1.Use the wave equation analysis to verify the adequacy of each proposed pile driving system. A

registered Delaware professional engineer will sign and seal each analysis. Submit the wave equation analysis to the engineer 30 calendar days before driving test piles.

2.Include a static soil analysis with the wave equation analysis. If the contractor's static analysis

predicts a need for alternate test pile lengths, clearly indicate the lengths of test piles in the submittal.

3.Use the wave equation analysis to establish the necessary blow counts, stroke heights, pile

cushions, and any other applicable information for use in driving initial test piles to the required bearing resistance and tip elevation.

4.Include computer input and output sheets, and suitable data plots displaying the wave equation

analysis for the pile driving throughout the various subsurface conditions of the site. Show resistance versus blow count, as well as maximum tension and compression stresses versus resistance on the plots.

5.Perform a wave equation analysis for each test pile. Evaluate drivability of the pile to various

depths of penetration using the proposed driving system. At a minimum, evaluate the driving conditions for 5 percent penetration, 70 percent penetration, 90 percent penetration, 100 percent penetration, and 110 percent penetration of the pile during initial driving and after set- up condition. Perform additional analysis at depths where the possibility exists of difficult driving or significant changes in drivability. A value of 100 percent penetration refers to penetration to the plan estimated tip elevation to achieve the designated ultimate resistance. Use the wave equation analysis estimate of tip elevation for the ultimate resistance, if it differs from the plan estimate by more than 10 percent at 100 percent penetration. Show the driving conditions for plan estimated depth in the analysis, if the chosen wave equation analysis estimate is used for 100 percent penetration.

6.Use the estimated friction and end bearing values obtained by the static soil analysis, along with

soil layer specific quake and damping values and friction parameters for each level of penetration in the drivability analysis. At a minimum, include ultimate resistances, blow counts, compressive and tensile stresses, and transferred energy plotted as a function of depth of penetration in the analysis output.

7.If the driving equipment consists of a varying energy or varying stroke type hammer, perform an

additional analysis that plots blow count versus stroke and energy for a fixed resistance equal to the ultimate resistance.

8.Select a hammer that drives the pile to its required penetration to achieve required bearing or

minimum tip elevation with a driving resistance not exceeding 120-blows per 12-inches. Driving resistance cannot exceed 20-blows per 1-inch in the last 6-inches of penetration.

9.Select a hammer that drives the pile without exceeding the following permissible stress limits:
a.For steel piles, the maximum permissible compressive or tensile driving stress is 90 percent of

the minimum yield strength of the pile material.

b.For prestressed concrete piles, the environmental exposure level will be as shown in the

contract.

i.For normal exposure, the maximum permissible tensile stress is 3 multiplied by the square

root of the concrete compressive strength, f c ′, plus the effective prestress value, fpe, or 3√fc ′ + fpe, with all units expressed in PSI. ii. For severe exposure, the maximum permissible tensile stress is fpe. iii. For all exposure conditions, the maximum permissible compressive stress is 85 percent of the compressive strength minus the effective prestress value, or 0.85 fc ′ - fpe.

c.For timber piles, the maximum permissible compressive driving stress is 3 times the

permissible static design strength listed in the contract.

E.The engineer will complete the conformance review and comment on the driving system within 14

calendar days of receiving the contractor's Pile and Driving Equipment Data Form and wave equation analysis. Modify or replace the proposed methods or equipment for nonconforming analysis. The engineer will complete the conformance review of the revised driving system within calendar days of receipt of a revised Pile and Driving Equipment Data Form and wave equation analysis.

F.If there is a change to the pile driving system, submit the necessary wave equation analysis, drive

additional test piles, and perform dynamic pile testing, as directed by the engineer, before driving any production piles.

G.Post-driving Reporting.
1.Prepare and submit a written report with the results of the test pile program, within 3 working

days of the completion of each dynamic test. Include the following:

a.Meet the requirements of ASTM D4945;
b.summary of the pile driving system used during dynamic testing;
c.summary of dynamic testing instrumentation and methods utilized;
d.performance of the hammer and driving system including:
i.Maximum transferred energy,

ii. blows per minute, and iii. ram stroke;

e.pile integrity:
i.indicate instances of pile overstressing during driving and

ii. indicate instances of pile damage or broken piles;

f.provide the following data for the full length of driving at intervals of no more than 10

hammer blows:

i.bearing resistance from the case method and 1 additional recognized method,

ii. pile penetration depth and corresponding blow sequence, and iii. maximum compressive and tensile driving stresses;

g.detailed results of the signal matching analyses; and
h.driving logs recorded in the field.
2.Perform signal matching analyses for the initial drive and each re-strike of dynamically tested

piles as follows:

a.One for a representative blow near the end of each initial drive.
b.Two representative blows towards the beginning of each re-strike.
c.One additional signal matching analysis at the request of the engineer.

605.3.2 Pile Installation Equipment.

A.Pile Hammers.
1.Use air, steam, diesel, or hydraulic hammers for driving piles.
a.Air and Steam Hammers:

Equip the plant and equipment with easily accessible pressure gauges. Ensure that the weight of the striking parts of air and steam hammers are at least 1/3 the weight of the helmet and pile being driven, but in no case less than 2,750-pounds.

b.Diesel Hammers

Equip open-end, single-acting diesel hammers with a device to allow the engineer to visually determine hammer stroke at all times during pile driving.

c.Hydraulic Hammers

Equip the power plant and equipment with easily accessible pressure gauges.

B.Hammer Cushion.
1.Provide hammer cushions made of durable manufactured materials, provided in accordance

with the hammer manufacturer's guidelines. Do not use wood, wire rope, or asbestos hammer cushions. Place a striker plate, as recommended by the hammer manufacturer, on the hammer cushion to ensure uniform compression of the cushion material. Remove the hammer cushion from the helmet and inspect in the presence of the engineer when beginning pile driving at each structure, or after each 100-hours of pile driving, whichever is less. Replace hammer cushions compressed to less than 75 percent of the original thickness before resuming pile driving.

C.Helmet.
1.Piles driven with impact hammers require an adequate helmet or drive head to distribute the

hammer blow to the pile head. Use leads to guide the helmet and prevent it from swinging freely. Use the correct helmet or drive head size to appropriately fit the pile head, to hold the axis of the pile in line with the axis of the hammer, and to prevent eccentric impacts on the pile head.

D.Pile Cushion
1.Protect the heads of precast concrete piles with a pile cushion made of plywood, hardwood,

or composite plywood and hardwood materials. Ensure the pile cushion dimensions prevent movement within the helmet during driving. Provide pile cushion of the thickness specified in the wave equation submittal or as determined from the results of dynamic testing. The engineer will evaluate the use of manufactured pile cushion materials instead of a wood pile cushion on a case-by-case basis.

E.Leads.
1.Use leads to support piles in line and position while driving. Construct pile driver leads to

allow the hammer to move freely while maintaining alignment with the pile to ensure concentric impact for each blow. The contractor may use either fixed or swinging-type leads. When using swinging-type leads, fit a pile gate at the bottom of the leads and, in the case of battered piles, fit a horizontal brace between the crane and the leads, as necessary. Provide leads of sufficient length to raise the hammer into a clear position while placing the pile in the leads and with the leads embedded.

F.Followers.
1.Only use followers when approved in writing by the engineer, or when specifically stated in

the contract. In cases of follower allowance, drive the first pile in each bent, and every tenth pile driven thereafter, full-length without a follower, to determine adequate pile penetration attainment in order to develop the ultimate pile resistance.

2.Hold and maintain the follower and pile in equal and proper alignment during driving. Use a

follower of the material and dimensions that allows driving the piles to the penetration depth as determined necessary from the driving of the full-length piles. Verify the final position and alignment of the first 2 piles installed with followers in each substructure unit, according to the location tolerances specified in Section 605.3.6.A before installing additional piles. 605.3.3 Preparation and Driving of Test Piles.

A.Preparation.
1.Provide equipment and perform testing and reporting procedures in strict accordance with

ASTM D4945 - Standard Test Method for High-Strain Dynamic Testing of Piles.

2.Perform the wave equation analysis based on the procedure outlined in Section 605.3.1.D. Do

not drive test piles prior to approval of the wave equation analysis.

3.Provide test piles in 1 length as indicated in the contract to allow for uninterrupted driving

during dynamic testing, unless otherwise approved by the engineer.

4.Prepare all test piles for instrumentation attachment.
5.Ensure that test piles are the initial piles driven and are the same material and dimensions as

the production piles. Install test piles at the locations indicated in the contract.

B.Driving with Dynamic Load Tests.
1.Drive test piles in accordance with Section 605.3.4 with the following additional procedures.
2.Before installing the dynamic monitoring instrumentation on the pile, including all gauges and

cables, lift the pile and align in the leads, and set the hammer and helmet. Once the pile set and the pile driving system is in place, attach dynamic monitoring instrumentation.

3.Perform dynamic testing during the entire initial drive and re-strike of all test piles so designated

in the contract, or as otherwise directed by the engineer. Continuously monitor the tensile and compressive stresses during driving to prevent exceeding permissible stress limits during driving. Immediately reduce the hammer stroke or stop the driving operation if stresses in the pile approach, or exceed, the permissible limits. If non-axial driving appears by dynamic test measurements, stop pile driving immediately and realign the driving system, or take other corrective action, before resuming driving.

4.If the top of the pile becomes damaged or deformed at any time during the dynamic pile testing,

stop pile driving and cut off the damaged area in accordance with Section 605.3.4.B. Prepare the remaining pile section for gauge installation. After the engineer inspects and approves, continue driving.

5.Drive all dynamically tested piles deep enough to achieve the minimum tip elevation and the

minimum initial driving resistance. Do not exceed the permissible stress limits.

6.Maintain a minimum distance of 1-foot between the pile monitoring gauges and the ground

surface, water surface, or pile template. If driving and dynamic testing are complete, remove the gauges.

7.If additional ground penetration becomes necessary, stop driving the pile, remove the gauges,

and splice the pile before proceeding. Before splicing, properly prepare the pile splice segment for gauge installation, in accordance with ASTM D4945, and make it accessible to the engineer for inspection. After splicing the pile and resetting the hammer and leads, reattach the gauges to the new pile segment and continue the drive.

8.If some length of test pile remains above the cut-off elevation after completing dynamic testing,

do not drive the remainder of the pile without the approval of the engineer.

C.Post-Driving.
1.Following the driving of the test pile or series of initial test piles, as agreed in the approved

sequence of driving, the engineer will review the driving records and make 1 or more of the following requirements:

a.Establish the driving criteria of required blow count, stroke height, and minimum tip elevation

for the driving of production piles based on satisfactory test pile results. The engineer reserves the right to establish or modify the minimum tip elevation for all the piles, depending on the actual conditions encountered.

b.When shown in the contract, issue a list of production pile lengths for fabrication of those

piles governed by the test pile, or group of test piles, within 5 working days after completing test pile driving.

c.Order a test pile re-strike, in accordance with Section 605.3.5, within 2 working days after

completing the initial driving.

d.Order a driving splice on the test pile within 2 working days after unsatisfactory results of the

re-strike. Make the driving splice in accordance with the driving splice details shown in the contract. Upon completion of driving the spliced pile, the engineer will review the new driving records and make 1 of the above recommendations.

e.Based on satisfactory test pile results, the engineer will accept the test pile for use as a

production pile.

f.Approve the driven test pile for load testing when requiring static load testing. The engineer

may select 1 of the above requirements before authorizing performance of a load test, or if a load test is unsatisfactory.

g.If the data and information obtained from driving any original test pile is conflicting,

inconclusive, or unsatisfactory in any way, the engineer will order another test pile driven for additional information within 2 working days after receipt of the post-driving report.

2.When shown in the contract, perform static load tests on selected test piles. Perform static load

tests in accordance with the procedures specified in ASTM D1143. Upon completion, the engineer will review the load test records and make 1 or more of the requirements in Section 605.3.3.C.1. 605.3.4 Preparation and Driving of Production Piles.

A.Preparation.
1.Clearly mark the pile in 12-inch increments with markings visible from a safe inspection distance.
2.Provide the engineer with reasonable inspection access along the full length and perimeter of all

piles. Prior to installation, repair or replace piles with damage incurred during shipping, handling, or storage. Piles with any of these defects will cause rejection by the engineer:

a.Visible cracks or spalls in a concrete pile;
b.a bent, kinked, or distorted steel pile; or
c.damaged timber pile treatment of a timber pile or compromised integrity as outlined in

Section 605.3.4.B.10 below.

3.Pile Driving Sequence.
a.Provide the engineer with schedules of the proposed driving sequence. Do not begin driving

test or production piles at any location until the engineer approves the schedule for that location. Do not depart from these schedules without the prior approval of the engineer.

b.Place individual piles in pile groups either starting from the center of the group and

proceeding outwards in both directions, or starting at the outside row and proceeding progressively across the group.

B.Driving.
1.Drive the production piles using the same pile driving system used to drive the test piles. For

changes to the pile driving system, see Section 605.3.1.F.

2.Conduct the pile driving operations in close cooperation with the engineer and in a manner that

allows the engineer to obtain essential measurements and data. The engineer will observe the progress of all pile driving work. The engineer will record a complete driving log for each pile driven. The driving log will list all data essential for the determination of correct bearing resistance.

3.Embed the leads in the ground or constrain the pile in a structural frame, such as a template, to

maintain alignment of the pile during driving. Do not apply side pressure to move piles into the correct position for driving.

4.Place the tip of each pile in the correct plan location before attaching the helmet. Ensure the

heads of all piles are in a true plane and perpendicular to the longitudinal axis of the pile before attaching the helmet.

5.Protect the heads of concrete piles with a pile cushion in accordance with Section 605.3.2.D.

Secure the pile cushion within the helmet prior to attaching the helmet to the pile. Provide a new pile cushion for each pile. During the driving of a single pile, replace the pile cushion if the cushion is compressed more than 1/2 the original thickness or it begins to burn.

6.Drive each production pile continuously from the start until reaching the driving criteria from

the test piles as established in Section 605.3.3.C, except as required for splicing the pile or replacement of the pile cushion.

7.Stop pile driving if the blow count exceeds 240-blows per 12-inches, or 20-blows per 1-inch of

driving for 3 consecutive inches. Immediately inform the engineer if blow counts exceed these limits at a tip elevation above the minimum tip elevation specified.

8.Stop pile driving if the top of a pile is damaged or becomes deformed. Cut off piles

perpendicular to the length to remove damage or deformations detrimental to the performance of the pile driving system or to the integrity of the pile. Allow steel piles to cool before continuing.

9.Drive piles within an allowed variation of 1/8-inch per 12-inches of pile length from the vertical

or batter shown in the contract. The maximum allowable variation at the top of the pile is 3- inches in any direction from the location shown in the contract.

10.Construct driving splices in accordance with the contract or submit alternate details to the

engineer for review and approval. After completing the splice, drive the spliced pile to meet the driving criteria. If it becomes necessary to splice timber piles, submit the method for splicing and driving to the engineer for written approval.

11.Survey the location, alignment, and top elevation of the piles after driving of each pile group.

Provide the survey results to the engineer.

12.The engineer will reject piles damaged by improper driving or driven outside of the allowable

tolerance specified.

a.Remove and replace rejected piles. Alternately, drive a replacement pile or piles adjacent to

the damaged pile, if driving of additional piles can occur without detriment to the structure, and if approved by the engineer.

b.In addition, modify the footing or pile cap, as required by the engineer, to accommodate the

out of tolerance or added piles.

13.Check piles for heave during driving of adjacent piles or by any other cause. Re-drive all piles

heaved more than 1/4-inch to the nominal bearing resistance and at least to the original tip elevation, or as directed by the engineer. Remove any material forced up between the piles during driving to the correct elevation before placement of foundation concrete.

C.Post-driving.
1.The engineer will review the driving records and may provide 1 or more of the following

responses depending on the what the driving records show:

a.No further action needed.
b.Re-strike selected production piles. Perform the production pile re-strikes in accordance with

the requirements of Section 605.3.5.

c.Dynamically test production pile re-strikes or subsequent production pile initial drives in

accordance with the requirements of Section 605.3.3. 605.3.5 Pile Re-strike.

A.Preparation.
1.Within 2 working days after initial driving, the engineer may order a pile re-strike of test pile as a

result of Section 605.3.3.C or of production piles as a result of Section 605.3.4.C when the contractor does not meet the driving criteria.

2.Perform the re-strike at least 48-hours, but no more than 7 calendar days, after initial driving

unless otherwise noted in the contract. If pile installation continues adjacent to a pile requiring a re-strike, the engineer reserves the right to delay the re- strike until at least 48 hours after the contractor completes all adjacent pile driving.

3.Dynamically test all re-strikes of test piles. The engineer may require the contractor to

dynamically test production pile re-strikes.

4.Perform re-strikes using the same pile driving system used to install the piles during initial

driving.

5.Mark the pile in 1-inch increments for at least 12-inches for measurement of the pile movement

during re-strike.

6.Establish the elevation of the top of pile using a survey level before performing the re- strike.
B.Driving.
1.Warm up the hammer and verify proper operation of the driving system by striking another pile

or pile cut-off at least 20 blows at full stroke.

2.Lower and position the hammer on the pile. If necessary, connect dynamic monitoring

instrumentation. Strike the pile 20 blows at the required stroke height.

3.If any component of the pile driving system does not function properly during the pile re- strike,

perform additional re-strikes until the pile driving system operates properly through a complete continuous re-strike procedure in accordance with this Section.

C.Post-driving.
1.Use a survey level to establish the new top of pile elevation.
2.Following the pile re-strike, the engineer will review the driving records and, within 2 working

days, make 1 or more of the following decisions:

a.Accept a test pile for use as a production pile, based on satisfactory re-strike results.
b.Establish the required re-strike blow count, stroke height, and acceptable top of pile elevation

change for production piles re-strikes, based on satisfactory test pile re-strike results.

c.Accept a production pile, or representative group of piles, if the pile re-strike results are

satisfactory.

d.Require additional ground penetration based on unsatisfactory pile re-strike results. The

engineer may order:

i.An additional re-strike with a longer wait time;

ii. additional driving until the driving criteria is met or the full length of pile is driven, in cases where the top of pile remains above existing grade; or iii. a driving splice, in cases where the top of pile reaches existing grade. 605.3.6 Additional Installation Requirements.

A.Non-Driving Pile Build-ups.
1.Construct all non-driving pile build-ups as shown in the contract or approved alternate.
B.Pile Cut-Offs.
1.Upon completion of pile driving, cut off all test and production piles to final elevation, in

accordance with the contract. Dispose of cut-off material in accordance with Section 106.8.

a.Cut off steel shells or steel H-piles square to the pile, using an acetylene or electric torch.
b.Cut off precast concrete piles square to the pile. If insufficient length of inserts for dowel bars

remains, deepen the remaining hole or drill a new hole of adequate length.

c.Saw timber piles that support a timber superstructure to conform to the plane of the bottom

of the superimposed structure:

i.Treat all exposed sawed surfaces of timber piles in accordance with Section 1041.4.E.

ii. Install 2 layers of metal sheet covering of either 13-gauge zinc or 20-gauge copper a minimum of 4-inches greater than the diameter of the pile on top of the treatment.

(1)Bend excess metal down over the sides of the pile, trim, and nail.
(2)Fasten zinc sheets with 1-inch long galvanized, large-headed nails.
(3)Fasten copper sheets with 1-inch long copper nails.
2.Cover the tops of pre-stressed concrete piles or steel shell piles with plastic to prevent dirt and

water from entering the pile until placement of grout or concrete. Remove dirt or water from holes or sleeves of pre-stressed concrete piles before grouting in bar reinforcement.

3.Cut off test piles driven outside permanent foundation locations at a point at least 24-inches

below finished grade or final stream bed elevation, upon satisfactory completion of test driving,

C.Cast-in-place Concrete Piles.
1.Placement of Reinforcement Bar.
a.Assemble the longitudinal reinforcement bar and circular ties as a complete unit. Securely

fasten the bars and ties together at all bar intersections, in accordance with the details shown in the contract.

b.Keep the interior of the reinforcement cage open to allow for the free flow of concrete into

the pile shell. Do not use interior bracing or spacers.

c.Place the completed assembly in the driven steel shell and prevent displacement during

concrete placement.

2.Concrete Placement.
a.Do not place concrete in steel shells until completion and acceptance of all driving within the

same substructure unit. If it is not possible to follow this limitation, do not drive within the same substructure unit until the placed concrete reaches 50 percent of the 28-day strength.

b.Do not place concrete in a steel shell until removal of all water, dirt, and debris and approval

by the engineer.

c.Place the concrete for each steel shell to ensure a dense, homogenous mass throughout the

entire casing to provide a permanent bond with all bar reinforcement embedded in the pile.

d.Place concrete for each steel shell in a continuous operation. If the bar reinforcement caging

or dowels occupy only the upper section of the pile, do not place bar reinforcement in the pile casing or shell until the concrete reaches the elevation of the lowest end of the bar reinforcement. At this point, set the bar reinforcement in the casing, and continue to place the concrete until reaching the cut-off elevation. Concrete must remain plastic throughout placement. When bar reinforcement caging or dowels occupy only the upper section of the pile, the contractor may place reinforcement before placing concrete if the contractor uses a tremie or similar piece of equipment that allows the contractor to deposit concrete in the portion of the pile below the bottom elevation of the reinforcement.

e.Do not disturb piles with freshly placed concrete until the concrete reaches 50 percent of the

28-day strength.

D.After completing all other parts of the structure, clean the exposed part of the piling of

discoloration caused by construction.

605.4Method of Measurement.

A.The Department will measure work acceptably completed in accordance with Section 109.1. The

Department will measure the quantity of:

1.Provided piles by the total length of pile in linear feet.
2.Installed piles by the linear feet of pile in place below the cutoff elevation.
3.Dynamic pile testing for test pile initial drive as 1 each for each test pile driven.
4.Dynamic pile testing for restrike or production pile as 1 each for each re-strike on test or

production pile tested and for each production pile initial drive tested.

5.Pile re-strikes by each re-strike performed.

605.5Basis of Payment.

A.The Department will pay the quantity of provided test piles and production piles at the contract

unit price per linear foot for each type of pile. Price and payment constitute full compensation for:

1.Providing all materials;
2.pile reinforcing tip, driving shoe, or closure plate for the respective pile type;
3.timber pile preservatives;
4.steel pile shells, protective coatings, bar and spiral reinforcement, and PCC for cast-in-place or

steel pipe piles;

5.pre-stressing strands, bar and spiral reinforcement, dowels, and PCC for precast piles; and
6.pile splice and pile build-up materials.
B.The Department will pay for the installed quantity of test piles and production piles at the

contract unit price per linear foot for each type of pile installed. Payment is full compensation for:

1.Driving of all pile types;
2.acceptably performing a pile cut off, and for the disposal of cut-off piles for all pile types;
3.placement of bar, spiral reinforcement, PCC for cast-in-place or steel pipe piles, and placement

of metal sheeting atop timber piles;

4.drilling of holes, epoxy grout, and placement of dowels for precast piles; and
5.pile splices and pile build-ups as additional linear feet of pile installed.
C.The Department will pay for driving additional test piles, as required by the engineer, as an extra

quantity of test piles under this section.

D.The Department will pay for pile re-strikes authorized by the engineer at the contract unit price

per each. Price and payment will constitute full compensation for all work associated with the set up and conducting the pile re-strikes, except for dynamic pile testing of re-strikes.

E.Dynamic pile testing of test pile initial drives authorized and accepted by the engineer at the

contract unit price per each. Payment is full compensation for:

1.Providing a pile testing firm;
2.preparation of the wave equation analysis;
3.providing inspection access to the Department and all materials, equipment and incidental work

required to perform dynamic pile testing during initial driving;

4.completion of the signal matching analysis; and
5.completion of post-driving reports.
F.Dynamic pile testing of re-strikes and production piles authorized and accepted by the engineer at

the contract unit price per each. Payment is full compensation for:

1.Providing inspection access to the Department and all materials, equipment, and incidental

work required to perform dynamic pile testing during re-strikes or production pile driving;

2.completion of the signal matching analysis; and
3.completion of post-driving reports.

ITEM DESCRIPTION UNIT 605000 PROVIDE TIMBER PILES - TREATED, 12" LF 605001 PROVIDE TIMBER PILES - TREATED, 14" LF 605002 PROVIDE TIMBER PILES - TREATED, 16" LF 605010 PROVIDE CAST-IN-PLACE CONCRETE PILES, 12" LF 605011 PROVIDE CAST-IN-PLACE CONCRETE PILES, 14" LF

ITEM DESCRIPTION UNIT 605012 PROVIDE CAST-IN-PLACE CONCRETE PILES, 16" LF 605013 PROVIDE CAST-IN-PLACE CONCRETE PILES, 18" LF 605020 PROVIDE STEEL H PILES, HP 10 X 42 LF 605021 PROVIDE STEEL H PILES, HP 12 X 53 LF 605022 PROVIDE STEEL H PILES, HP 12 X 63 LF 605023 PROVIDE STEEL H PILES, HP 12 X 74 LF 605024 PROVIDE STEEL H PILES, HP 14 X 73 LF 605025 PROVIDE STEEL H PILES, HP 14 X 89 LF 605026 PROVIDE STEEL H PILES, HP 14 X 102 LF 605030 PROVIDE STEEL PIPE PILES, 24" LF 605031 PROVIDE STEEL PIPE PILES, 30" LF 605032 PROVIDE STEEL PIPE PILES, 36" LF 605033 PROVIDE STEEL PIPE PILES, 48" LF 605034 PROVIDE STEEL PIPE PILES, 12" LF 605040 PROVIDE PRECAST PRESTRESSED CONCRETE PILES, 12" X 12" LF 605041 PROVIDE PRECAST PRESTRESSED CONCRETE PILES, 14" X 14" LF 605042 PROVIDE PRECAST PRESTRESSED CONCRETE PILES, 16" X 16" LF 605043 PROVIDE PRECAST PRESTRESSED CONCRETE PILES, 18" X 18" LF 605044 PROVIDE PRECAST PRESTRESSED CONCRETE PILES, 20" X 20" LF 605045 PROVIDE PRECAST PRESTRESSED CONCRETE PILES, 24" X 24" LF 605046 PROVIDE PRECAST PRESTRESSED CONCRETE PILES, 30" X 30" LF 605050 PROVIDE TIMBER TEST PILES - TREATED, 12" LF 605051 PROVIDE TIMBER TEST PILES - TREATED, 14" LF 605052 PROVIDE TIMBER TEST PILES - TREATED, 16" LF 605060 PROVIDE CAST-IN-PLACE CONCRETE TEST PILES, 12" LF 605061 PROVIDE CAST-IN-PLACE CONCRETE TEST PILES, 14" LF 605062 PROVIDE CAST-IN-PLACE CONCRETE TEST PILES, 16" LF 605063 PROVIDE CAST-IN-PLACE CONCRETE TEST PILES, 18" LF 605070 PROVIDE STEEL H TEST PILES, HP 10 X 42 LF 605071 PROVIDE STEEL H TEST PILES, HP 12 X 53 LF 605072 PROVIDE STEEL H TEST PILES, HP 12 X 63 LF 605073 PROVIDE STEEL H TEST PILES, HP 12 X 74 LF 605074 PROVIDE STEEL H TEST PILES, HP 14 X 73 LF 605075 PROVIDE STEEL H TEST PILES, HP 14 X 89 LF 605076 PROVIDE STEEL H TEST PILES, HP 14 X 102 LF

ITEM DESCRIPTION UNIT 605080 PROVIDE STEEL PIPE TEST PILES, 24" LF 605081 PROVIDE STEEL PIPE TEST PILES, 30" LF 605082 PROVIDE STEEL PIPE TEST PILES, 36" LF 605083 PROVIDE STEEL PIPE TEST PILES, 48" LF 605084 PROVIDE STEEL PIPE TEST PILES, 12" LF 605090 PROVIDE PRECAST PRESTRESSED CONCRETE TEST PILES, 12" X 12" LF 605091 PROVIDE PRECAST PRESTRESSED CONCRETE TEST PILES, 14" X 14" LF 605092 PROVIDE PRECAST PRESTRESSED CONCRETE TEST PILES, 16" X 16" LF 605093 PROVIDE PRECAST PRESTRESSED CONCRETE TEST PILES, 18" X 18" LF 605094 PROVIDE PRECAST PRESTRESSED CONCRETE TEST PILES, 20" X 20" LF 605095 PROVIDE PRECAST PRESTRESSED CONCRETE TEST PILES, 24" X 24" LF 605096 PROVIDE PRECAST PRESTRESSED CONCRETE TEST PILES, 30" X 30" LF 605100 INSTALL TIMBER PILES - TREATED, 12" LF 605101 INSTALL TIMBER PILES - TREATED, 14" LF 605102 INSTALL TIMBER PILES - TREATED, 16" LF 605110 INSTALL CAST-IN-PLACE CONCRETE PILES, 12" LF 605111 INSTALL CAST-IN-PLACE CONCRETE PILES, 14" LF 605112 INSTALL CAST-IN-PLACE CONCRETE PILES, 16" LF 605113 INSTALL CAST-IN-PLACE CONCRETE PILES, 18" LF 605120 INSTALL STEEL H PILES, HP 10 X 42 LF 605121 INSTALL STEEL H PILES, HP 12 X 53 LF 605122 INSTALL STEEL H PILES, HP 12 X 63 LF 605123 INSTALL STEEL H PILES, HP 12 X 74 LF 605124 INSTALL STEEL H PILES, HP 14 X 73 LF 605125 INSTALL STEEL H PILES, HP 14 X 89 LF 605126 INSTALL STEEL H PILES, HP 14 X 102 LF 605130 INSTALL STEEL PIPE PILES, 24" LF 605131 INSTALL STEEL PIPE PILES, 30" LF 605132 INSTALL STEEL PIPE PILES, 36" LF 605133 INSTALL STEEL PIPE PILES, 48" LF 605134 INSTALL STEEL PIPE PILES, 12" LF 605140 INSTALL PRECAST PRESTRESSED CONCRETE PILES, 12" X 12" LF 605141 INSTALL PRECAST PRESTRESSED CONCRETE PILES, 14" X 14" LF 605142 INSTALL PRECAST PRESTRESSED CONCRETE PILES, 16" X 16" LF 605143 INSTALL PRECAST PRESTRESSED CONCRETE PILES, 18" X 18" LF 605144 INSTALL PRECAST PRESTRESSED CONCRETE PILES, 20" X 20" LF 605145 INSTALL PRECAST PRESTRESSED CONCRETE PILES, 24" X 24" LF

ITEM DESCRIPTION UNIT 605146 INSTALL PRECAST PRESTRESSED CONCRETE PILES, 30" X 30" LF 605150 INSTALL TIMBER TEST PILES - TREATED, 12" LF 605151 INSTALL TIMBER TEST PILES - TREATED, 14" LF 605152 INSTALL TIMBER TEST PILES - TREATED, 16" LF 605160 INSTALL CAST-IN-PLACE CONCRETE TEST PILES, 12" LF 605161 INSTALL CAST-IN-PLACE CONCRETE TEST PILES, 14" LF 605162 INSTALL CAST-IN-PLACE CONCRETE TEST PILES, 16" LF 605163 INSTALL CAST-IN-PLACE CONCRETE TEST PILES, 18" LF 605170 INSTALL STEEL H TEST PILES, HP 10 X 42 LF 605171 INSTALL STEEL H TEST PILES, HP 12 X 53 LF 605172 INSTALL STEEL H TEST PILES, HP 12 X 63 LF 605173 INSTALL STEEL H TEST PILES, HP 12 X 74 LF 605174 INSTALL STEEL H TEST PILES, HP 14 X 73 LF 605175 INSTALL STEEL H TEST PILES, HP 14 X 89 LF 605176 INSTALL STEEL H TEST PILES, HP 14 X 102 LF 605180 INSTALL STEEL PIPE TEST PILES, 24" LF 605181 INSTALL STEEL PIPE TEST PILES, 30" LF 605182 INSTALL STEEL PIPE TEST PILES, 36" LF 605183 INSTALL STEEL PIPE TEST PILES, 48" LF 605184 INSTALL STEEL PIPE TEST PILES, 12" LF 605190 INSTALL PRECAST PRESTRESSED CONCRETE TEST PILES, 12" X 12" LF 605191 INSTALL PRECAST PRESTRESSED CONCRETE TEST PILES, 14" X 14" LF 605192 INSTALL PRECAST PRESTRESSED CONCRETE TEST PILES, 16" X 16" LF 605193 INSTALL PRECAST PRESTRESSED CONCRETE TEST PILES, 18" X 18" LF 605194 INSTALL PRECAST PRESTRESSED CONCRETE TEST PILES, 20" X 20" LF 605195 INSTALL PRECAST PRESTRESSED CONCRETE TEST PILES, 24" X 24" LF 605196 INSTALL PRECAST PRESTRESSED CONCRETE TEST PILES, 30" X 30" LF 605200 PILE RESTRIKE EACH 605201 DYNAMIC PILE TESTING BY CONTRACTOR FOR TEST PILE INITIAL DRIVE EACH 605202 DYNAMIC PILE TESTING BY CONTRACTOR FOR RE-STRIKE OR PRODUCTION PILE EACH 605210 STATIC LOAD TEST FOR DRIVEN PILES EACH

Get an email when 605 changes

Delaware revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Delaware Standard Specifications for Road and Bridge Construction, 2026 Edition. Pages 197–0 of 786. View official source ↗

Ask about this section

Scoped to Delaware Standard Specifications for Road & Bridge Construction, Section 605 — DRIVEN PILES. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.