619.1Description.
This work consists of providing, constructing, reconstructing, or repairing stone or brick masonry.
619.2Materials.
1040. Provide stone free of iron content significant enough to cause rust-staining of the stone or materials below the stone.
stone types, colors, sizes, shapes, and patterns.
and patterns as closely as possible.
stainless steel in accordance with AASHTO M163.
619.3Construction.
projects within the last 5-years. Include a brief description of each project and the owner's contact person's name and current phone number for each project listed.
water. Do not re-temper mortar.
Fill all joints with mortar and finish as work progresses. Make mortar joints 1-inch to 1 1/2- inches thick.
or plastered joints. Arrange all brick headers and stretchers in order to bond the mass with alternate courses breaking joints. Fill all joints with mortar and finish as the work progresses. Make 1/4-inch to 1/2-inch thick joints. Do not use spalls or bats, except for shaping irregular openings or when unavoidable to finish out a course. If the engineer approves the use of spalls or bats, place full bricks at the corners and place bats in the interior of the course.
to present a natural color. Clean the area with water. Treat with a solution of 1 percent hydrochloric acid and then wash again with water a final time. When cleaning stone masonry with
the solution, take care to notice any deteriorating reaction. If a reaction is noticed, stop using the solution, wash the treated area immediately and clean the stone masonry to present the natural color.
joints with water under high pressure. Remove excess water from the cavity with air under high pressure. Wet joints before applying the mortar. Mix and place mortar in accordance with Section 619.3.B. Use only mortar that matches the color of the existing mortar. In hot or dry weather, shield pointing work from the sun and keep wet for a period of 3-days after completion.
breaking or scarring the stones. Reuse exposed surfaces of existing stone in the reconstructed structure, except as directed by the engineer. Ensure that the reconstruction results in a structure that resembles the original and adjacent structures in overall appearance.
619.4Method of Measurement.
masonry reconstructed and accepted.
reconstructed and accepted.
619.5Basis of Payment.
materials and pointing the joints as described in this specification.
removing and stockpiling existing stone or brick, disposing of unsuitable materials, and providing, placing, and cleaning stone or brick masonry.
ITEM DESCRIPTION UNIT
619000 STONE MASONRY SF 619001 BRICK MASONRY SF 619002 POINTING EXISTING MASONRY LF 619020 RECONSTRUCTING STONE MASONRY SF 619021 RECONSTRUCTING STONE MASONRY CF 619030 RECONSTRUCTING BRICK MASONRY SF 619031 RECONSTRUCTING BRICK MASONRY CF
Get an email when 619 changes
Delaware revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.