602.1Description.
This work consists of constructing, providing, replacing, adjusting, and repairing drainage inlets, drainage inlet frames and grates, manholes, manhole frames and covers, and junction boxes.
602.2Materials.
602.3Construction.
For precast elements, adhere to the General Manufacturing Requirements of Section 612.3.2.
Standard Construction Details before fabrication for:
proposed structure can handle all loads including the HS-20 live load.
determine the exact sizes of the drainage inlet frames and grates, and manhole frames and covers before placing the order.
determine the exact sizes of the top cover slab and hinge. Also include all parts and fittings for installation.
and structure requirements.
firm, even surface, to the acceptance of the engineer.
unless otherwise specified in the contract. The contractor may request use of precast structures subject to the engineer’s approval. Use precast structures for new construction unless otherwise specified in the contract.
accordance with AASHTO M199.
deeper when measured from the top of grate or cover to the invert of the lowest pipe, install steps at an accessible location. Ensure that the steps have a minimum embedment of 3-inches into the wall and protrude out 6-inches from the wall. Begin steps within 24-inches of the top of grate or lid and place the last step no more than 12-inches above the lowest invert except where a pipe is in the backwall. Place steps vertically 12-inches apart.
contract and that pipes extend through, and are flush with, the inside of the wall. When cutting off the end of a reinforced concrete pipe, finish with mortar so that no reinforcement steel remains exposed. Fill any space between the pipe and the walls of the drainage inlet with non- shrink grout conforming to the requirements of Section 1047, with a minimum strength of 5,000-PSI. Ensure that the pipe opening in the drainage inlet is no more than 4-inches larger than the pipe diameter measured from the outside wall of the pipe.
Section 610.3.6.
accordance with Section 1022.6 except water curing will not be permitted.
accordance with Section 207.
surface exposed concrete with silane sealer meeting the requirements of Section 1045.3 in accordance with Section 613.3.D.
manholes and junction boxes.
recommendation.
accordance with the Standard Construction Details. ii. Excavate materials from the perimeter in accordance with Section 207.3. Dispose of waste materials in accordance with Section 106.8. iii. Remove existing castings. Clean and set castings aside for reuse or replacement in accordance with the contract. If the engineer determines that the casting is damaged and not suitable for reuse, provide a new casting in accordance with Section 602.3.B iv. Place forms for the top unit to accommodate the replacement frame.
vi. Place required steel reinforcement and encase in PCC, Class B. Cure in accordance with Sections 501.3 or 503.3. vii. Prepare surface exposed concrete ahead of sealing in accordance with Section 613.3.B. Seal surface exposed concrete with a silane sealer meeting the requirements of Section 1045.3 in accordance with Section 613.3.D viii. Take removed drainage inlet frames, grates, manhole frames, and covers, to the Department's District Maintenance Yard or to a location specified in the contract. ix. Seal joints in accordance with Section 504.
Section 602.3.D.
engineer.
accordance with Section 207.
301.
with Section 602.3.B.8.
602.3.B.9 and as directed by the engineer.
602.4Method of Measurement.
number of each installed and accepted. The Department will measure inlet and outlet pipes with the adjoining pipe. The Department will not measure frames and grates and will consider these items as included in the drainage inlet, manhole, or junction box items.
frames as the number of each placed and accepted.
manholes, and junction boxes as the number of each adjusted or repaired and accepted.
special manholes placed as the number of each.
and special manholes placed and accepted measured as lump sum.
inlets, manholes, and junction boxes.
602.5Basis of Payment.
junction boxes at the contract unit price. Price and payment will constitute full compensation for:
and junction boxes.
and payment will constitute full compensation for supply, replacement, and disposal of the existing materials.
and junction boxes at the contract unit price of each. Price and payment will constitute full compensation for:
the frame.
below the frame to 4 1/2-feet below the frame.
payment adjustments.
Section 109. ITEM DESCRIPTION UNIT 602000 DRAINAGE INLET, 17.625” X 11.625” EA 602001 DRAINAGE INLET, 24” X 24” EA 602002 DRAINAGE INLET, 34” X 18” EA 602003 DRAINAGE INLET, 34” X 24” EA 602004 DRAINAGE INLET, 48” X 30” EA 602005 DRAINAGE INLET, 48” X 48” EA 602006 DRAINAGE INLET, 66” X 30” EA
602007 DRAINAGE INLET, 66” X 48” EA 602008 DRAINAGE INLET, 66” X 66” EA 602009 DRAINAGE INLET, 72” X 24” EA 602014 DRAINAGE INLET, 72” X 36” EA 602010 DRAINAGE INLET, 72” X 48” EA 602011 DRAINAGE INLET, 72” X 72” EA 602012 DRAINAGE INLET, SPECIAL EA 602013 DRAINAGE INLET, SPECIAL LS 602030 MANHOLE, 48” X 30” EA 602031 MANHOLE, 48” X 48” EA 602032 MANHOLE, 66” X 30” EA 602033 MANHOLE, 66” X 48” EA 602034 MANHOLE, 66” X 66” EA 602035 MANHOLE, ROUND EA 602036 MANHOLE, SPECIAL EA 602037 MANHOLE, SPECIAL LS 602060 JUNCTION BOX, 48” X 30” EA 602061 JUNCTION BOX, 48” X 48” EA 602062 JUNCTION BOX, 66” X 30” EA 602063 JUNCTION BOX, 66” X 48” EA 602064 JUNCTION BOX, 66” X 66” EA 602065 JUNCTION BOX, SPECIAL EA 602066 JUNCTION BOX, SPECIAL LS 602100 DRAINAGE INLET GRATE(S) EA 602101 DRAINAGE INLET FRAME(S) EA 602102 MANHOLE GRATE(S) EA 602103 MANHOLE FRAME(S) EA 602130 ADJUSTING AND REPAIRING EXISTING DRAINAGE INLET EA 602131 ADJUSTING AND REPAIRING EXISTING DOUBLE DRAINAGE EA 602132 ADJUSTING AND REPAIRING EXISTING MANHOLE EA 602133 ADJUSTING AND REPAIRING EXISTING JUNCTION BOX EA