GENERAL PROVISIONS

106MATERIAL QUALITY AND TESTING REQUIREMENTS

DE · 2026 Standard Specifications✓ Full text on BuildSpecBook pages 61–0 Save this section

Ask about Section 106

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

106.1Source of Supply and Quality Requirements.

A.Use materials that meet the contract requirements.
B.Use only new materials unless otherwise specified in the contract.
C.Submit documentation requesting approval of material sources before delivery to the project.

Submission requirements and instructions for source information are listed on DelDOT’s website: https://deldot.gov/Business/prodlists/index.shtml.

1.If material requirements are not provided in the Standard Specifications or a Special Provision,

submit all Plan sheets that contain relevant material requirements as documentation with the source of supply submission.

D.The Department will only allow one source of material to be used. An alternate source may be

submitted. Sources cannot be combined.

E.Material approval varies based on the type and use of material. The Department approves

materials based on:

1.Supply source verified by sample testing and analysis
2.Certification
3.Approved products lists
F.Obtain Department approval for all materials before use. Using unapproved materials is at the

contractor’s risk as the engineer may deem the unapproved materials unacceptable.

G.The Department’s acceptance of a source, certification, or approved product does not constitute

final acceptance. If materials do not meet the contract requirements at the jobsite before or after use, remove or correct the materials to comply with the contract.

106.2Samples, Tests, and Referenced Specifications.

A.The engineer may inspect and test materials at any time before, during, or after use in the work.

Tests performed by the engineer are for quality assurance and acceptance of the work. Material quality control is the contractor’s responsibility as stated in Division 1000 of these specifications.

B.The Department will perform material tests in accordance with the Department of Highway

(DOH), AASHTO, or ASTM test methods current on the date of the advertisement. When a specification or test is identified in the form of an AASHTO or ASTM number indicated as "modified," it refers to an AASHTO or ASTM specification or test modified by the Department's Materials Manual in effect on the date of advertisement. If there is a procedural difference in the DOH, AASHTO, or ASTM test methods, the Department will follow this order of precedence:

1.Materials Manual
2.AASHTO
3.ASTM
C.The engineer will set forth minimum requirements for material quality assurance sampling and

testing on each contract. Ensure that the engineer has the access and time needed to perform the

sampling and testing. The engineer reserves the right to perform more than the minimum number of tests. The Department will make copies of any or all test results available to the contractor upon request.

D.When, in the engineer’s judgment, the contract requires inconsequential quantities and use of

materials, the Department may make a field inspection report of materials instead of following the minimum requirements for sampling materials.

106.3Compliance Certification.

A.Use materials for the work designated in the contract or designated by the Department's

Materials and Testing Schedule accompanied by manufacturer certificates of compliance. Provide certificates of compliance signed by the manufacturer stating that the materials or assemblies provided fully comply with the contract. Ensure that each lot of certified materials or assemblies has a certificate of compliance clearly identifying the materials delivered and the specification requirement satisfied.

B.The Department may sample and test materials or assemblies provided on the basis of

certification of compliance. The Department will reject materials not in conformance with the contract in accordance with Section 105.11, Removal of Defective and Unauthorized Work.

C.Distribute the compliance certificates in accordance with the contract or the Department’s

Materials Manual.

106.4Manufacturing Plant Inspection.

A.The Department may inspect manufacturing plants for compliance with specified manufacturing

methods. The contractor and the material producer shall cooperate and assist the engineer. Provide the engineer with full access at any time to all parts of the plant manufacturing or producing the project materials.

B.The Department will take material samples to test for compliance with material quality

requirements. Provide a laboratory conforming to the requirements of Section 106.5, Field Laboratory, located near the plant for the Department’s use.

C.The Department may retest materials, previously tested at the supply source, when delivered to

the project.

D.The material producer shall establish plant safety protocols that the contractor and the

Department will follow.

E.Manufacturing plants shall comply with OSHA workplace requirements.

106.5Field Laboratory.

Provide field laboratories in accordance with Section 612, Precast Concrete, for precast concrete items and Section 1014, Asphalt Materials Production, for bituminous asphalt.

106.6Storage and Handling.

A.Store and handle materials to ensure fitness for the work and in a manner that facilitates

inspection. The Department may inspect or test stored materials before use.

B.The contractor may use an approved portion of the right-of-way for material storage, to locate a

contractor's plant, or to store equipment. Do not use private property for storage without written

permission of the property owner or lessee. The engineer may request copies of written permission to use private property for storage.

1.Do not store materials or equipment under or adjacent to DelDOT maintained bridges or

retaining walls without an executed agreement.

C.Restore storage and plant sites to their original condition.

106.7Unacceptable Materials.

The Department will reject materials not conforming to the contract requirements. Either remove rejected materials from the project or correct the material defects using methods approved by the engineer in accordance with Section 106.8, Disposal of Unacceptable Materials.

106.8Disposal of Unacceptable Materials.

A.Waste materials from the work become the contractor’s property. Remove the waste materials

from the project.

1.The contract may provide disposal sites for the contractor’s use. If the contract-provided

disposal sites are not large enough to handle all contract waste materials, procure additional disposal sites as necessary.

2.Submit proposed disposal sites for the engineer’s approval before using the sites.
a.Provide a plan of the disposal area that includes:
i.Includes sediment and erosion control devices.

ii. Shows the existing contours and proposed final contours. iii. Contains a list of materials the contractor plans to place in the disposal area. iv. Details proposed security measures.

b.When preparing and using off-site disposal areas, comply with all stormwater and

environmental rules, regulations, or applicable permits issued by DNREC, USACOE, and all other applicable government agencies. Obtain permits, if necessary, in accordance with Section 107.2, Permits, Licenses, and Taxes.

c.Costs for preparing these plans are incidental to the pay item that generates the waste.
d.For disposal sites designated in the contract documents, the Department will pay for erosion

and sediment controls, seeding, and mulching under applicable pay items.

e.The Department will consider costs for erosion and sediment controls, seeding, and mulching

for contractor-procured disposal sites as incidental to the pay items that generate the waste.

106.9Department-Provided Material.

A.The Department will deliver, or make available, to the contractor Department-provided material

at locations specified in the contract.

B.Include the cost of handling and placing Department-provided materials in the pay items the

materials are used for. The Department will make deductions from monies due the contractor for damage that occurs to the material after delivery due to contractor negligence. The Department

will deduct money due the contractor should the Department incur unanticipated delivery costs because of contractor delays in accepting and unloading the materials.

Get an email when 106 changes

Delaware revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Delaware Standard Specifications for Road and Bridge Construction, 2026 Edition. Pages 61–0 of 786. View official source ↗