LIQUIDATED DAMAGES; TERMINATION
108.1Contract Subletting.
organization, excluding designated specialty items. The Department will allow the contractor to perform specialty items by subcontract. The Department may deduct the amount of specialty items, performed by subcontractors, from the total original contract price before calculating the amount of work the contractor plans to perform using the contractor’s own organization. The contract price that the Department will use as a basis to calculate the 50 percent requirement includes the cost of material and manufactured products that the contractor plans to purchase or produce. The Department will not require an adjustment of the calculated percentage due to adjustments in quantities or added or extra work.
the Contractor’s employees, will not be included in the 50 percent subcontracting limit.
deliver and deposit, but do not incorporate, material; suppliers or services that transport material; and work performed that does not physically advance the completion of the contract and is not considered as an item of work.
contractor and equipment owned or rented by the contractor with or without operators. The term does not include subcontractor employees or equipment, agents of the contractor, or any other assignees. The term may include payments for the costs of hiring leased employees from an employee leasing firm if the contractor:
compliance statements, and all other federal regulatory requirements.
engineer’s written consent. Consent, when given, does not relieve the contractor its responsibility to fulfill the contract requirements. Do not provide work or materials from an organization other than the contractor’s own, or otherwise dispose of the contract or contracts or any portion thereof, or of its right, title or interest therein, without written consent from the engineer. The engineer will only provide written consent after assurance that each subcontract is in writing and that it contains the pertinent provisions and requirements of the contract.
engineer, detail the cost of the materials included in the subcontractor’s work. Include the cost of subcontractor materials in the value of the subcontracted work. Obtain the engineer’s written permission before allowing a subcontractor to subcontract a portion of subcontracted work. In granting such permission, the engineer will require that the subcontractor seeking to subcontract
TIME EXTENSIONS; LIQUIDATED DAMAGES; TERMINATION
a portion of its subcontract to perform no less than 50 percent of its subcontract with the subcontractor using its own organization.
contractor's own organization and a single subcontractor unless approved by the engineer.
will apply the subcontractor payment to fulfill the Disadvantaged Business Enterprise (DBE) contract requirements if the subcontractor is a DBE. The cost of the portion of the contract or bid item performed by a DBE will be included in the total amount of work subcontracted by the contractor in determining whether the contractor is performing at least 50 percent of the total contract bid price, as required by this section.
business licenses as a prerequisite to payment for work performed by a subcontractor, or on a subcontractor's behalf. Submit the information before a subcontractor performs work on the project. Submit contracts with suppliers or any other person, firm, or organization that will perform work on the project for review and approval by the engineer. Ensure that each subcontract clearly states that all provisions and requirements of the contract are included in the subcontract.
prospective subcontractor or supplier. This information may include any required by the contract, by the Department, by the FHWA, or by other governmental agencies. This information may include:
work.
to labor performed on all work encompassed by the contract.
subcontractors or suppliers;
subcontract agreements; and
agreement.
specifications as approval of the work a subcontractor performs or of material provided by a supplier. Such reviews, permissions, or approvals by the Department do not relieve the contractor of the sole responsibility for satisfactory completion of the contract. Contracts, subcontracts, supplier agreements, sales, transfers, leases, assignments, or any other agreements applicable to this contract will in any case release the contractor of its sole responsibility and liability under the contract and bonds.
subcontractor or materials supplier the contractor failed to submit to the Department for
TIME EXTENSIONS; LIQUIDATED DAMAGES; TERMINATION
approval or by a subcontractor or material supplier that the contractor did submit that the Department did not approve.
108.2Preconstruction Meeting; Submitting a Schedule; Notice to Proceed.
Following contract execution, the engineer may schedule a preconstruction meeting. Before the preconstruction meeting, submit the progress schedule in accordance with Section 108.4, Progress Schedule. After the preconstruction meeting, the engineer will issue the contractor a notice to proceed that will stipulate the contract start date. The Department will set the contract start date at least 10 calendar days after the date the Department issues the notice to proceed. The contractor may begin work upon receipt of the notice to proceed. The Department will not require the contractor to wait 10 days to begin work. Contract time will begin on the day that work starts or on the date stipulated in the notice to proceed, whichever is earlier.
108.3Commencement of Work; Counting Contract Time.
contract time using either calendar days or working days in accordance with the bid proposal.
108.2, Preconstruction Meeting; Submitting a Schedule; Notice to Proceed, and continue counting every day shown on the calendar until substantial completion as determined by the engineer. The Department will not allow work on Sundays or holidays unless the engineer determines that working on Sundays or holidays is in the best interest of the Department. Submit a written request to the engineer to work on a Sunday or holiday, if there is a reason to work those days. Submit the request to work at least 3 business days before the Sunday or holiday planned for work. Provide notice to the engineer no later than 12:00 PM on a Friday if the contractor plans to work the following day.
108.2, Preconstruction Meeting; Submitting a Schedule; Notice to Proceed, and continue as defined in Section 101.3, Definitions, until substantial completion of the work as determined by the engineer. The Department will not allow work on Sundays or holidays unless the engineer determines that such work is in the best interest of the Department. Submit a written request to the engineer to work on a Sunday or holiday, if there is a reason to work those days. Submit the request to work at least 3 business days before the Sunday or holiday planned for work. Provide notice to the engineer no later than 12:00 PM on a Friday if the contractor plans to work the following day.
108.4Progress Schedule.
date, furthers the work progress, and is used to plan, schedule, and monitor the project.
the critical path.
TIME EXTENSIONS; LIQUIDATED DAMAGES; TERMINATION
After the contractor achieves substantial completion, the critical path is the longest work path that forecasts the project acceptance date as that date is defined in Section 105.16, Project Acceptance; Partial Acceptance. Milestones also have critical paths defined as the longest work path that forecasts the completion of the milestone.
activity.
completion date prior to the substantial completion date established by the contract.
substantial completion date. After the contractor achieves substantial completion, float is the amount of time an activity or work path can be delayed and not delay the project acceptance date as that date is defined in Section 105.16, Partial Acceptance; Project Acceptance; Final Acceptance; and Project Closeout.
restrictive logic.
dates.
or finishes and the date when its successor activity can start or finish.
of the project or its interim stages.
successor. Only the first and last activities are allowed to have open ends. The first activity will have no predecessor and the last activity will have no successor.
predecessor may control the start or finish date of its successor.
its predecessors and successors.
plan to complete the entire project.
to complete the entire project.
schedule or the previous bi-weekly look ahead barchart schedule that depicts the work that is expected to occur during the following 2-weeks.
TIME EXTENSIONS; LIQUIDATED DAMAGES; TERMINATION
calendar days of project duration.
progress on a monthly basis into the baseline schedule, the previous monthly update schedule, or revised schedule.
lookahead barchart schedule, a revised barchart schedule, an initial baseline schedule, a baseline schedule, a monthly schedule update, or a revised schedule.
significant modification to the schedule logic or durations. aa. Schedule, Revised Barchart. A barchart schedule prepared and submitted by the contractor that includes a significant modification to the schedule logic or durations. bb. Schedule, Final. The last schedule update containing actual start and finish dates for every activity. cc. Successor. An activity that is defined by schedule logic to succeed another activity.
108.4.C.2, Type 1 CPM Schedules, or 108.4.D.2, Type 2 CPM.
utilities, railroads, government agencies or authorities, and other parties involved with the project.
submittal does not constitute approval of the entire schedule.
such approval in writing.
ii. constitute the Department’s endorsement or validation of the contractor’s schedule logic, activity durations, or assumptions; iii. transfer the contractor’s responsibilities to the Department; the contractor alone shall remain responsible for adjusting forces, equipment, and work schedules to ensure completion of the work within the contract time; iv. guaranty that the contractor can perform the work as scheduled; or
Notification of Contract Changes.
correct the error in the next schedule submission.
TIME EXTENSIONS; LIQUIDATED DAMAGES; TERMINATION
schedule or initial baseline schedule is approved.
providing weather days in the schedule calendar or by increasing activity durations. The Department will not allow the contractor to include time for weather in the form of a weather activity at the end of the scheduled work or by distributing weather activities throughout the schedule.
may approve an early completion schedule, but the Department cannot guaranty it will have the resources available to support the contractor’s early completion schedule. The Department will consider delays to the contractor’s early completion schedule resulting from the Department’s inability to support the schedule as non-excusable and non-compensable.
between the scheduled early substantial completion date and the contract substantial completion date as float.
scheduled substantial completion date to a date later than the contract substantial completion date, the contractor is not entitled to a time extension for such delays.
scheduled substantial completion date to a date later than the contract substantial completion date, the contractor is not entitled to a time extension or compensation for the delay.
party.
ii. Overly restrictive relationships between activities. iii. Activities with excessively long durations.
schedule.
ii. procurement, including submittals that require engineer review time;
TIME EXTENSIONS; LIQUIDATED DAMAGES; TERMINATION
iii. third party activities related to the contract; iv. all work completing within the contract time; and
schedule is based on judgment and not on computer analysis.
schedule to the engineer.
by either approving the schedule, rejecting the submission and identifying the reasons for rejection, or asking for more information.
notice-to-proceed date is not known, then use an assumed date until the actual notice-to- proceed date is known.
barchart schedule addressing all of the Engineer’s comments within 7 calendar days of receiving the comments.
barchart schedule by approving the baseline barchart schedule, rejecting the baseline barchart schedule and identifying the reason(s) for rejection, or asking for more information.
week period. The engineer will identify the day of the week for submission of the bi-weekly look ahead barchart schedule.
sequence of work activities, along with the planned hours of work for the next 2-week period.
or the approved revised barchart schedule.
occur:
ii. the actual sequence of work is different from that in the approved baseline barchart or revised schedules; iii. the scheduled substantial completion date is delayed to a date more than 10 calendar days later than the contract substantial completion date; or
TIME EXTENSIONS; LIQUIDATED DAMAGES; TERMINATION
iv. the engineer extends the contract time.
ii. modifications to the sequence or durations of remaining activities; and iii. approved time extensions.
barchart schedule.
from the engineer.
rejecting the schedule and identifying the reasons for rejection, or asking for more information.
in the bid proposal.
that complies with each of the following requirements:
completely and accurately into the Oracle Primavera Unifier Software used by the Department. Provide native files in the XML format. ii. Use the following schedule settings:
iii. Do not use user-defined fields. iv. Ensure that each activity:
engineer; and
TIME EXTENSIONS; LIQUIDATED DAMAGES; TERMINATION
vi. At a minimum, include CPM schedule activities that show:
vii. Use project-specific activity codes in place of WBS. viii. Assign each activity to one of the project-specific calendars as identified in the following Table. Table 108.4-1. Acceptable CPM Schedule Activity Calendars. Calendar Name Non-workdays Standard 5-day workweek Weekends and holidays 7-day workweek None ix. Obtain the engineer’s written authorization before using activity calendars other than those listed in Table 108.4-1.
schedule submission is not approved, name the resubmitted files as shown in the table. The ####-### indicates a placeholder for the State Project Number. Table 108.4-2. CPM Schedule Filename Convention. Schedules 1st Version 2nd Version 3rd Version Baseline Schedule (All Schedules until it is Accepted as Baseline) ####-###-BASE-1 ####-###-BASE-2 ####-###-BASE-3 1st schedule update ####-###-UP01 2nd schedule update, etc. ####-###-UP02 1st revised schedule ####-###-RS01-1 ####-###-RS01-2 ####-###-RS01-3 1st Update to revised schedule, etc. ####-###-RUP01
schedule to the engineer.
respond by either approving the schedule, rejecting the submission and identifying the reasons for rejection, or asking for more information.
TIME EXTENSIONS; LIQUIDATED DAMAGES; TERMINATION
notice-to-proceed date is not known, then use an assumed date until the actual notice-to- proceed date is known.
Type 1 CPM schedule addressing all of the Engineer’s comments within 7 calendar days of receiving the comments.
CPM schedule by approving the baseline Type 1 CPM schedule, rejecting the baseline Type 1 CPM schedule and identifying the reason(s) for rejection, or asking for more information.
provided in the bid proposal.
that complies with good scheduling practice as described in the most current edition of the AGC’s Construction Planning & Scheduling Manual and each of the following requirements. If the AGC’s manual conflicts with the contract, the contract takes precedence:
completely and accurately into the Oracle Primavera Unifier Software used by the Department. Provide native files in the XML format. ii. Use the following schedule settings:
iii. Do not use user-defined fields. iv. Ensure that each activity:
writing by the engineer;
engineer; and
TIME EXTENSIONS; LIQUIDATED DAMAGES; TERMINATION
vi. Include no more than 20 percent critical activities and no more than 30 percent near-critical activities, unless otherwise authorized in writing by the Engineer. vii. At a minimum, ensure that the CPM schedule includes activities for the following items:
contract and availability dates specified in the contract;
approval activities using approval durations in accordance with the contract;
equipment;
viii. Use only “Finish on or Before” activity constraints and apply only to contract-required milestones or completion dates, unless otherwise authorized in writing by the engineer. ix. Use project-specific activity codes in place of WBS.
codes. Examples of acceptable activity code values for each of the activity codes are listed below each mandatory activity code:
• Phase 1 • Phase 2 • Phase 3
• Stage 1 • Stage 2 • Stage 3
• Name of general contractor
TIME EXTENSIONS; LIQUIDATED DAMAGES; TERMINATION
• Department • Names of Subcontractors
• Station 100+00 to 110+00 • Station 110+00 to 120+00 • East Abutment • West Abutment
• Concrete • Drainage • Earthwork
• Electrical subcontractor • Earthwork Crew 1 • Earthwork Crew 2 xi. Assign each activity to one of the project-specific calendars as identified in the following Table 108.4-3. Table 108.4-3. Acceptable CPM Schedule Activity Calendars Calendar Name Non-workdays Standard 5-day workweek Weekends and holidays 7-day workweek None xii. Obtain the engineer’s written authorization before using activity calendars other than those listed in Table 108.4-3. xiii. Use the schedule file naming convention depicted in the following Table 108.4-4. If the schedule submission is not approved, name the resubmitted files as shown in the table. The ####-### indicates a placeholder for the State Project Number. Table 108.4-4. CPM Schedule Filename Convention Schedules 1st Version 2nd Version 3rd Version Baseline Schedule (All Schedules until it is Accepted as Baseline) ####-###-BASE-1 ####-###-BASE-2 ####-###-BASE-3 1st schedule update ####-###-UP01 2nd schedule update, etc. ####-###-UP02 1st revised schedule ####-###-RS01-1 ####-###-RS01-2 ####-###-RS01-3 1st Update to revised schedule, etc. ####-###-RUP01
TIME EXTENSIONS; LIQUIDATED DAMAGES; TERMINATION
xiv. Eliminate instances of out-of-sequence progress on the critical path and near-critical paths in monthly schedule updates and revised schedules.
and maintaining CPM project schedules on contracts of similar size and complexity.
accept the baseline schedule.
ii. the contractor’s representative in all matters that concern the schedule; iii. the contractor’s designated attendee to schedule-related meetings; and iv. the scheduling representative shall know the status of work throughout the project’s duration.
approves the baseline schedule.
schedule and provide the baseline schedule instead. Submit the baseline schedule in accordance with the time limits of the initial baseline schedule. The engineer will review the baseline schedule in accordance with the time limits for the baseline schedule.
the baseline schedule, but only for the first 60-days of the project.
depicting the work after the first 60-days.
proceed date.
schedule to the engineer for review.
rejecting the schedule and identifying the reason for rejection, or asking for more information.
TIME EXTENSIONS; LIQUIDATED DAMAGES; TERMINATION
60-days of work depicted in the initial baseline schedule.
engineer for review. The engineer will respond within 21 calendar days of receipt of the baseline schedule by approving the baseline schedule, rejecting the baseline schedule and identifying the reasons for rejection, or asking for more information.
schedule addressing the engineer’s comments within 7 calendar days of receiving the engineer’s comments.
schedule by approving the baseline schedule, rejecting the baseline schedule and identifying the reasons for rejection, or asking for more information.
date coordinated with the date of the pay estimate.
and agree on the progress achieved in the previous month. Show the progress agreed upon in the meeting in the monthly schedule update. Include actual start dates, actual finish dates, and the new remaining durations for activities that show as started and continuing.
schedule update. Describe the reason for changes to the schedule in the written narrative submitted with the monthly update schedule.
approving the monthly schedule update, rejecting the monthly schedule update and identifying the reason for rejection, or asking for more information.
previous monthly schedule update.
same as for the baseline schedule.
durations depicted on the approved baseline schedule or monthly schedule updates.
TIME EXTENSIONS; LIQUIDATED DAMAGES; TERMINATION
work in the current monthly schedule update;
delayed more than 14 calendar days from the dates established by the contract time;
actual duration of the work, and the work as depicted in the monthly schedule update;
manner of its performance;
directive to accelerate the work.
of the request.
the revised schedule, rejecting the revised schedule and identifying the reasons for rejection, or asking for more information.
baseline schedule.
begin and how work and crews will flow through the project; ii. the working days per week, number of shifts per day, number of hours per shift, the holidays anticipated by the contractor, and how the schedule anticipates weather days; iii. a statement describing the status of required permits; iv. a description of the number of crews and planned production rates for critical activities and near-critical activities;
utilities; vi. a statement identifying constraints and an explanation of the purpose of each constraint; vii. a statement describing the reason for the use of each lag; and viii. a list of the key limited equipment or labor resources.
TIME EXTENSIONS; LIQUIDATED DAMAGES; TERMINATION
compared to the dates forecast in the previous schedule submission; ii. a statement explaining why the contract completion dates are forecast to occur before or after the dates established based on the contract time; iii. a description of the reasons for the schedule revisions; iv. a statement describing the status of permits;
parties, such as utilities; vi. a description of unusual labor, shift, equipment, or material conditions or restrictions encountered or anticipated since the previous schedule submission; vii. a statement identifying new or revised constraints and an explanation of the reasons for the revisions; and viii. a statement describing the reason for the use of new or revised lags.
submission:
the critical path activities shown in red; ii. a “Critical Path Printout” showing the critical path to substantial completion; iii. a “Near-Critical Printout” showing all near-critical activities grouped by total float values; and iv. any other CPM schedule printouts requested by the engineer.
ii. activity Name; iii. original duration (OD); iv. remaining duration (RD);
vi. finish; and vii. total float.
ii. run date; and iii. CPM schedule name.
TIME EXTENSIONS; LIQUIDATED DAMAGES; TERMINATION
the contract.
the engineer approves the initial baseline and baseline schedules. The Department will pay the lump sum amount in the proposal.
schedule incorporating a time impact analysis as required by Section 108.7, Extensions of Contract Time, as complete and ready for payment when the engineer approves the schedule. The Department will pay the lump sum amount in the proposal for schedule updates, for revised schedules, and schedules incorporating a time impact analysis as required by Section 108.7, Extensions of Contract Time, after the engineer’s approval.
ITEM DESCRIPTION UNIT 763001 Baseline Schedule (Type 1) LS 763002 Monthly Update Schedule (Type 1)
Each 763003 Baseline Schedule (Type 2)
LS 763004 Monthly Update Schedule (Type 2) Each
108.5Traffic Requirements and Contractor's Operations; Completing Work.
Schedule and conduct work to ensure the least interference with traffic. Do not open up work to the prejudice or detriment of work already started. The engineer may require the contractor to finish a section work in progress before starting work on any additional sections.
108.6Preference for Delaware Labor; Character of Workers and Equipment; Specified Construction
Methods.
persons contracting with the State or any political subdivision thereof, give preference in employment of laborers, workers, or mechanics to bona fide legal citizens of the State who have established citizenship by residence of at least 90-days. Each public works contract for the construction of public works for the State or any political subdivision thereof will contain a stipulation that any person, company, or corporation who violates the provisions of this section shall pay a penalty to the Treasurer of the State of Delaware equal to the amount of compensation paid to any person in violation. The requirement to give preference to Delaware laborers, workers, or mechanics will not apply to federally funded contracts.
work, discharge the employee upon the engineer’s request. Do not employ that person on the contract or any other DelDOT contract, without the engineer’s written consent.
contract specifies that the contractor use certain methods and equipment, use alternatives only after providing the engineer with a written request and obtaining the engineer’s approval. If the
TIME EXTENSIONS; LIQUIDATED DAMAGES; TERMINATION
engineer approves the request to use alternative methods, the contractor still retains the responsibility to produce work in accordance with the contract. If, after trial use of the alternate methods and equipment, the engineer determines that the work does not meet the contract requirements, complete the remaining construction with the originally specified methods and equipment.
108.7Extensions of Contract Time.
all the work within the contract time.
Excusable, Non-Compensable Delays, or 108.7.C, Excusable, Compensable Delays, submit a written request to the engineer for a contract time extension in accordance with Section 104.3, Notification of Contract Changes.
Contract Changes, constitutes a waiver of the right to a time extension for the delay.
delay to work on the critical path shown on the approved progress schedule that delays the scheduled substantial completion date based on the contract time.
uses to determine an extension of contract time for substantial completion.
use schedules that were not submitted and approved by the Department or schedules the contractor created after the delay occurred.
progress schedule in accordance with the requirements specified in Section 108.4, Progress Schedule, constitutes a waiver of entitlement to a time extension.
caused by the contractor.
schedule submitted to and approved by the Engineer that was in force when the delay was experienced. For example, if the Department determines that extra work is required and the change order for this work is dated June 2, then the contractor would use the last progress schedule submitted and approved by the Department prior to June 2 to show entitlement to a time extension.
occurred. Do not use this method to evaluate delays that have already occurred. In general terms, perform a TIA as follows:
TIME EXTENSIONS; LIQUIDATED DAMAGES; TERMINATION
schedule;
activities in the current accepted schedule;
completion date;
and the schedule calculated with a properly inserted and properly composed fragnet is the delay attributable to the changed work. The engineer will base the time extension due, if any, on this delay. ii. Use a contemporaneous analysis when evaluating delays that have already occurred. In general terms, perform a contemporaneous analysis as follows:
delay being evaluated;
that immediately follows the conclusion of the delay;
schedule immediately following the delay;
extension is due;
delayed. The engineer will base the time extension due, if any, on this delay.
contracts and calendar days for calendar day contracts.
could have foreseen. These delays are not the fault or responsibility of the contractor or the Department.
non-compensable delay.
or epidemics.
subcontractors, and suppliers could not foresee or avoid, and were not responsible for.
TIME EXTENSIONS; LIQUIDATED DAMAGES; TERMINATION
supplier that are beyond the contractor’s, subcontractor’s, and supplier’s power to settle.
the approximate quantity shown in the bid proposal.
unanticipated conflicts between the utility’s facilities and the work.
have been reasonably foreseen by the contractor or the Department.
due to weather in accordance with Section 108.7.F, Weather Delays.
Work.
except delays due to significant changes caused by increases in quantity, which are non- compensable.
Suspensions of Work Ordered by the Engineer.
compensable.
was delayed for reasons of late ordering, or financial considerations.
condition, or failure to provide for immediate emergency repairs.
excusable delay is concurrent with an excusable delay, there is no entitlement to a contract time extension for the time the non-excusable delay is concurrent with the excusable delay. When an excusable, non-compensable delay is concurrent with a compensable delay, there is entitlement
TIME EXTENSIONS; LIQUIDATED DAMAGES; TERMINATION
to a contract time extension, but there is no entitlement to compensation for the period the non-compensable delay is concurrent with the compensable delay.
the contractor’s progress schedule but could not work because of weather or seasonal conditions that prevented critical path work from occurring for more than half of the working day.
engineer’s review. The engineer will respond either by accepting or rejecting the weather days alleged by the contractor. If the engineer rejects the alleged weather days, the engineer will provide a determination of weather days within 7 calendar days of receiving the list of claimed weather days. If there is disagreement with the Engineer’s determination, submit a written justification within 7 calendar days of receiving the engineer’s list of weather days. The engineer will review the written justification and will respond within 7 calendar days. If there is disagreement with the engineer’s response, provide notice as required by Section 104.3, Notification of Contract Changes.
dates and number of weather days. The engineer will provide the determination of weather days in response to a written request.
Section 108.4.A.2.j. Once the Notice to Proceed date has been established, utilize Table 108.7-1 to determine the total number of anticipated weather days for the project. The Department will extend contract time by 1-day for each weather day that exceeds the total number of anticipated weather days for the project. Table 108.7-1. Anticipated Weather Days per Month Month Weather Days Month Weather Days January 20 July 4 February 20 August 4 March 15 September 5 April 10 October 6 May 5 November 10 June 5 December 20
contractor is not entitled to time extensions for weather days or seasonal conditions encountered beyond the contract time, even if the number of weather days exceeds the total number of weather days anticipated for the project.
108.8Failure to Complete on Time.
expired, pay the Department the sum specified in Section 108.9, Schedule of Liquidated Damages.
Liquidated damages are not a penalty.
TIME EXTENSIONS; LIQUIDATED DAMAGES; TERMINATION
completion date, the Department will base the assessment of liquidated damages on the amounts listed under the “Calendar Day” columns of the charts provided in Section 108.9, Schedule of Liquidated Damages. The Department will include every calendar day in the computation of liquidated damages.
assessment of liquidated damages on amounts listed under the “Working Day” column of the chart provided in Section 108.9, Schedule of Liquidated Damages. The Department will calculate liquidated damages by counting each working day after the contract time expires.
complete the work within the contract time. No Department action is required to begin the assessment. Failure of the Department to assess liquidated damages does not constitute a waiver of the Department’s entitlement to recover liquidated damages.
of liquidated damages due within 30 calendar days.
in the Department removing the contractor from the list of qualified bidders until the outstanding balance due is paid in full. In the case of joint ventures, the Department may remove each entity that makes up a part of the joint venture from the list of qualified bidders.
maintenance of traffic (MOT) devices or measures used during days when the Department is assessing liquidated damages. Examples of these costs include MOT devices, flaggers, traffic officers, and any lump sum MOT pay items. The Department will not pay for field office costs or the cost of providing CPM schedule updates during the liquidated damage period.
surety to continue the work after expiration of the contract time.
suspend time charges and the assessment of liquidated damages. Failure to complete all punch list work identified during the initial and primary inspections within the timeframes allotted, will result in the Department restarting liquidated damages in accordance with the chart specified in Section 108.9, Schedule of Liquidated Damages. The assessment of post-substantial-completion liquidated damages will continue until project completion.
108.9Schedule of Liquidated Damages.
additional costs the Department and the traveling public may incur, are as follows:
TIME EXTENSIONS; LIQUIDATED DAMAGES; TERMINATION
Table 108.9-1. Schedule of Liquidated Damages Awarded Contract Value Daily Charge For More Than To and Including Working Day Calendar Day $0 $100,000 $770.00 $550.00 $100,000 $500,000 $1,190.00 $850.00 $500,000 $1,000,000 $1,420.00 $1020.00 $1,000,000 $2,000,000 $2,210.00 $1,580.00 $2,000,000 $5,000,000 $2,520.00 $1,800.00 $5,000,000 $10,000,000 $2,680.00 $1,920.00 $10,000,000 $15,000,000 $3,100.00 $2,220.00 $15,000,000 $20,000,000 $4,670.00 $3,340.00 $20,000,000 $25,000,000 $6,040.00 $4,320.00 $25,000,000 $30,000,000 $7,750.00 $5,540.00 $30,000,000 $35,000,000 $9,730.00 $6,950.00 $35,000,000 $50,000,000 $12,600.00 $9,000.00
awarded contract value exceeding $35,000,000 by Special Provision.
108.10Default of the Contract
default under the following conditions:
prompt completion of the work in accordance with the approved schedule.
correct work the engineer determines is defective or otherwise unacceptable.
stand unsatisfied for a period of 10 days.
after receiving the notice, will result in the engineer declaring the contractor in default of the contract. This action will terminate the contractor's right to proceed with the work and will give full power and authority for the work to the Department without violating the contract. The Department will take ownership of the contractor’s materials at the site suitable for use. The Department may enter into an agreement with another contractor for completion of the contract or use other methods to complete the contract.
charges the Department incurs as a result of the default, including the cost of completing the work
TIME EXTENSIONS; LIQUIDATED DAMAGES; TERMINATION
under contract or remedying defective or otherwise unacceptable work, and applicable liquidated damages or disincentives. If the cost to complete the project exceeds the sum payable under the contract, the Department will hold the contractor and the surety liable for the costs in excess of the contract price.
contractor was not in default, the Department will convert the termination for default to termination for convenience in accordance with Section 108.11, Termination of the Contract for Convenience. The Department will limit the damages the contractor may have entitlement for, resulting from an improper default termination, to amounts in accordance with Section 108.11, Termination of the Contract for Convenience.
108.11Termination of the Contract for Convenience
when termination is in the best interests of the Department. In the event that termination occurs, without fault and for reasons beyond the contractor’s control, the Department will pay for all completed work at the contract price as of the termination date. The Department will pay for partially completed work or costs related to eliminated work in accordance with Section 109.8, Pay Estimates and Retainage.
of the termination. The Department will pay the actual cost of materials delivered to a prescribed location or otherwise dispose of the materials as mutually agreed.
damages or costs not covered by these specifications, within 60 days of the termination date. The request may include the following cost items:
each item claimed.
contractual responsibilities for the completed work or relieve the surety of its obligation for any just claim arising out of the work performed.
108.12Termination of the Contractor's Responsibility
TIME EXTENSIONS; LIQUIDATED DAMAGES; TERMINATION
Termination of the contractor's responsibility for the work occurs upon final acceptance in accordance with Section 105.16, Partial Acceptance; Project Acceptance; Final Acceptance; and Project Closeout, except to the extent provided in Section 107.13, Contractor’s Responsibility for the Work after Final Acceptance; No Waiver of Legal Rights.