503.1Description.
This work consists of patching existing PCC pavement with high early strength concrete.
503.2Materials.
503.3Construction.
pre-approved by the Department to supervise all finishing. Provide the flatwork certification to the engineer before placing concrete. 503.3.1 Patching Limits.
patching limits on the existing pavement.
less in length. A Type B patch is greater than 15-feet and less than 100-feet in length and contains load transfer assemblies consisting of dowel support baskets and dowel bars spaced at a maximum of 15-feet.
existing concrete pavement joints, any cracks, or patch ends in the immediate adjacent lanes.
locations at least 5-days before removal. The engineer will determine all patching limits
503.3.2 Saw Cutting.
and parallel to the roadway centerline. Minimize and seal over-cuts into the remaining slabs as directed by the engineer. Cut existing steel across the patch perimeter. Cut concrete no more than 2-days before removals. Remove and dispose of concrete slurry from saw cutting in accordance
with Section 106.8. Clean all travel lanes to the satisfaction of the engineer before opening to traffic following the saw cutting operation. 503.3.3 Patch Removal.
technique without damaging the remaining concrete slabs or disturbing the base and subgrade. The lift-out technique entails drilling holes into the patch to insert lifting hooks, pins, or chains. Repair damage to the remaining concrete slabs or the base and subgrade caused by improper patch removal using methods approved by the engineer.
an approved mechanical pavement breaker or jackhammer. Remove the existing patch material with minimal disturbance to the remaining concrete or foundation.
shoulder edge, the engineer may allow the contractor to use the shoulder edge as the form for the new concrete. If the shoulder is not designated for replacement, repair all areas of the shoulder pavement structure removed or disturbed by the patching operation. If the bituminous shoulder is damaged during concrete removal, place a side form to provide a vertical edge for the concrete patch. 503.3.4 Patch Preparation.
unsuitable material to a maximum depth of 6-inches, or less as directed by the engineer. Fill the excavated area with concrete when placing the patch. Clean out the repair area with hand tools and protect the patch subgrade from water intrusion. Excessive moisture remaining after excavation may require construction of a pipe underdrain system as directed by the engineer or as shown in the contract.
contractor may pour the concrete patch flush with existing bituminous concrete pavement to eliminate grade differential. Place the additional concrete depth, not to exceed 6-inches, as directed by the engineer.
cracked away from the plumb line during patch removal. Clean all vertical faces before placing concrete.
longitudinal and transverse vertical faces of existing concrete pavement adjacent to the patch. 503.3.5 Dowel and Tie Bar Installation.
contract for internal crack control joints at Type B patches. Cut the shipping or tie wires on the dowel bar support basket after placement within the proposed pavement box.
Use a drill support system to maintain proper hole alignment. Use gang drills on contracts requiring multiple patches. Saw out all damaged pavement adjacent to the patch if damaged by the drilling operation and replace the damaged sections.
provided and installed for Type B patches that are placed adjacent to concrete. Do not install tie bars on Type A patches.
or tie bar length. Align the dowel bars and tie bars to not exceed the tolerances indicated in the contract. Drill holes 1/8-inch greater than the dowel bar or tie bar diameter or as recommended by the manufacturer. Use a wire brush of appropriate size to clean the hole and then blow the hole with compressed air that is dry and oil free at a continuous pressure of at least 100 pounds per square inch, measured at the source. Place concrete adhesive using a nozzle or wand that will deposit the material to the back of the hole. Do not push or pour the anchoring materials into the holes. Install the dowel bar or tie bar using a twisting motion to completely coat the dowel or tie bar surface. Place a grout retainer ring at the interface of the concrete and dowel bar or tie bar. Support the dowel bars and tie bars in proper alignment until the concrete adhesive has cured. 503.3.6 Placing Concrete.
pooling on the grade.
the entire patch area. Place the concrete in each patch area in a continuous operation. Consolidate the concrete using a standard spud-type vibrator capable of visibly affecting the concrete a distance of 1-foot from the vibrator head. Insert the vibrator vertically into the concrete without dragging it through the mix.
otherwise allowed by the engineer.
by the engineer.
opening along the edges of the existing concrete using duct tape, caulk, or other approved material to prevent stones or grout from entering the saw cut. 503.3.7 Concrete Strength Requirements.
weights and proportion of admixtures as required due to field conditions, ambient temperature, humidity, and wind conditions. If unfavorable weather conditions prevent the concrete from reaching the desired strength in 6 hours, reschedule the patching work subject to approval by the engineer. The Department may consider the concrete defective if it fails to meet the compressive strength within 6-hours.
Department will allow concrete determined to be structurally adequate by the engineer, but not meeting 2,000 pounds per square inch in 6-hours, to remain in place at a prorated payment in accordance with Section 503.5.1. If the contractor does not want to accept the prorated payment, the contractor may remove and replace the concrete in an attempt to achieve full compensation.
503.3.8 Finishing Concrete.
place the screed parallel to the centerline of the roadway. For longer patches, the contractor may place the screed perpendicular to the centerline of the roadway.
to the traffic flow when a bituminous concrete overly will cover the patch surface. Match the adjacent pavement surface cross slope and profile. The Department will consider the patch unacceptable if the profile in the finished patch area contains excessive surface deviations. The maximum allowable longitudinal and transverse deviation is 1/4-inch in 10-feet. Provide a 10-foot straight edge for testing. When the concrete patch is the final roadway surface, match the texture of the adjacent pavement. Match the patch surface cross section with the preceding and following pavement surfaces. The Department will not allow use of steel trowels for finishing surfaces. The engineer may test for excessive surface deviations with a straightedge, a profilometer, or other surface measuring device.
503.3.9 Curing.
following concrete texturing.
Place polyethylene sheeting over the concrete and beyond the slab edges a distance that equals double the pavement thickness. Add weight to secure the material against wind and weather.
Secure edges and seams of insulating blankets to prevent dislodging due to wind, rain, or adjoining traffic. Use insulating blankets in accordance with Section 610.3.5.C.6. 503.3.10 Joints.
achieved, if no overlay is planned in accordance with Section 504.
Type B patches matching existing within the patch area in accordance with Section 501.3.9. Clean and seal the joints around the entire patch perimeter, and all transverse joints in larger patches, with hot-poured sealant material within 5 days after concrete placement, if no overlay is planned. Refer to and comply with all Section 504 requirements.
of the patch. The Department will not require a sealant reservoir in this case. Widen and seal the sawed transverse joints for crack control within Type B patches for both finished surface and overlay conditions.
503.3.11 Performance Measures. Repair or remove and replace uncontrolled random cracks before Final Acceptance and payment. Submit repair or replacement procedures to the engineer for approval.
503.4Method of Measurement.
feet to 100 feet, Type B.
Department will measure the width from outside of the completed patches as constructed and will measure parallel to the transverse saw cuts. The Department will measure parallel to the centerline of the pavement, along the center of the patch. The Department will not measure additional patch areas made necessary due to improper concrete removal or saw cutting.
pavement the contractor patched by the cubic yard. Refer to Section 202.3.7.
original pavement requiring the patch, or additional thickness above in order to eliminate grade differential in finished pavements by the square yard-inch.
each. The Department will not measure dowel bars and dowel support baskets (load transfer assemblies) installed at internal crack control joints in Type B patches. The Department will consider dowel bars and dowel support baskets installed at internal crack control joints in Type B patches as incidental to the contract unit price per square yard for item 503002 – Patching PCC Pavement, Greater Than 15 feet to 100 feet, Type B.
503.5Basis of Payment.
using the applicable bituminous concrete pay item.
adjoining pours from entering the saw cut before placing adjoining pavement;
patch area at the time of removal;
the new concrete; and
and the following:
baskets at all transverse joint locations except at either end of the patch;
6-inches resulting from the undercut excavation, patching item, or to eliminate the grade differential of finished pavements.
separate payment for this work:
noted in the contract;
503.5.1 Price Adjustment for Low Strength Concrete. The Department will calculate the prorated payment for concrete, as referenced in Section 503.3.7, as shown in the following equation:
ITEM DESCRIPTION UNIT 503001 PATCHING PCC PAVEMENT, 6’ TO 15’, TYPE A SY 503002 PATCHING PCC PAVEMENT, 15’ TO 100’, TYPE B SY 503004 PATCHING PCC PAVEMENT (UNDERCUTTING) SY-IN 503006 DOWEL BARS EA
PATCHING PORTLAND CEMENT CONCRETE PAVEMENT in other states
Get an email when 503 changes
Delaware revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.