606.01 558 SECTION 606 – PILING
606.01 Description ................................ ................................ ................... 558
606.02 Classification ................................ ................................ ................ 559
606.03 Materials ................................ ................................ ...................... 559
606.04 Equipment ................................ ................................ .................... 559
606.05 Preliminary Work ................................ ................................ ......... 562
606.06 Precast Concrete Piles ................................ ................................ .. 562
606.07 Cast -in-Place Concrete Piles ................................ ........................ 564
606.08 Test Piles ................................ ................................ ...................... 565
606.09 Calibration Tests ................................ ................................ .......... 568
606.10 Order Lists for Piles ................................ ................................ ..... 568
606.11 Storage and Handling ................................ ................................ ... 569
606.12 Driving Piles ................................ ................................ ................ 569
606.13 Bearing Value and Penetration ................................ ..................... 571
606.14 Determination of Bearing Value ................................ .................. 571
606.15 Inspection of Shells for Cast -in-Place Piling ............................... 573
606.16 Extensions and Splices ................................ ................................ . 573
606.17 Cutoffs and Treatment of Pile Heads ................................ ........... 574
606.18 Conditioning of Treated Timber Piles after Driving .................... 574
606.19 Painting Steel Piles and Steel Shells ................................ ............ 574
606.20 Final Cleanup ................................ ................................ ............... 574
606.21 Method of Measurement ................................ .............................. 575
606.22 Basis of Payment ................................ ................................ .......... 577
DESCRIPTION
606.01 Description
This work consists of furnishing and driving or placing piling. This w ork also includes the furnishing and driving of test piling and production piling and conducting load tests, when shown on the Plans or included in the Contract. 606.02 559 606.02 Classification The Department will classify piling accordi ng to the following designations:
606.03 Materials
Provide materials as specified in: Materials for Concrete ................................ ........................... 604.02 Reinforcement for Concrete Piles ................................ .......... 907.01 Pre-Stressing Reinforcement Steel and Anchorages .............. 907.04 Steel Piles ................................ ................................ .............. 908.15 Steel Shells ................................ ................................ ............ 908.16 Steel Pipes ................................ ................................ .............. 908.17 Paint ................................ ................................ ....................... 910.03 Timber Piles ................................ ................................ ........... 911.03 EQUIPMENT
606.04 Equipment
Have all equipme nt required for handling and driving steel piling, timber piling, precast concrete piling, steel shells or steel pipe on the Project and approved by the Engineer before beginning work. Use pile driver leads that are straight and allow fr eedom of movement of the hammer. Hold the leads in position with guys or braces to support the pile during driving. Except where driving piles through water, use leads of 606.04 560 sufficient length to make the use of a follower unnecessary, unless otherwise approved by the Engineer. Provide equipment and tools to manufacture concrete for piles, whether precast or cast -in-place, which meet 604.04 and the Engineer’s approval. Provide forms for precast concrete piles that meet the applicabl e requirements of 604.05. The plant and equipment furnished for steam and air driven hammers shall have sufficient capacity to maintain, under working conditions, the pressure at the hammer specified by the manufacturer. Equip t he boiler or tank with an accurate pressure gauge. Also install a gauge that will accurately measure the pressure at the hammer intake, unless another approved method is provided to furnish the data necessary to determine the energy delivered by the hamme r. Operate diesel hammers with a wide open throttle when blows are being counted to determine the average penetration to use in the safe load formula, except that in the case of diesel hammers with enclosed rams, the throttle settings shall be just short of the settings that would cause non -striking parts of the hammer to rise off the piles as the ram piston travels upward. Equip diesel hammers that have an enclosed ram with an accurate gauge and charts that will evaluate the equivalent energy being produced under any driving condi tion. If the Engineer finds the size or type of hammer used to be unsatisfactory, replace it with another size or type of hammer, or use other corrective measures as required to produce satisfactory results.
606.05 Preliminary Work
Perform Clearing and Grubbing, Removal of Structures and Obstructions, Excavation and Undercutting, Structure Excavation, Foundation Preparation and Backfill, and Embankment Construction as specified in 201, 202, 203, 204, and 205, respectively. In areas where piles are to be driven and excavation or embankment construction is to be performed, complete the excavation or embankment before driving piles.
606.06 Precast Concrete Piles
Construct precast concrete piles as shown on the Plans and according to these Specifications. Construct precast concrete piles of either air -entrained or non-air-entrained Class P concrete that is proportioned and mixed as 606.06 563 specified in 615.09. Submit to the Department for approval a concrete design, indicating the proportions, the source or brand of all materials, and the type of cement to be used. Prepare and place the concrete as specified in 604 with the revisions and additions stipulated herein. Assemble and place the reinforcement as shown on the Plans. Stress cables for precast prestressed concrete piles as specified in 615.07 and 615.08. Cast piles in a horizontal position. Do not cast in tiers. Place the concrete continuously in each pile and con solidate by mechanically vibrating and spading. Take care to avoid horizontal or diagonal cleavage planes, and to ensure that the reinforcement is properly embedded in the concrete and not displaced. Overfill the forms, screed off the surplus concrete, a nd finish the top surface to a uniform, even texture similar to that produced by the forms. Side forms may be removed as soon as their removal will not cause distortion to the hardened concrete. As soon as the forms are removed, repair surface irregularit ies, and unless otherwise specified, give the piles a Class I finish as specified in 604.21.A. Cure the precast concrete piles by the water method as specified in 604.23.B, or by steam curing as specified in 615.11.C.2 Do not move piles from the bottom supporting forms, or release the stressing force on prestressed piles, until the concrete has attained a compressive strength of at lea st 3,500 pounds per square inch, as evidenced by test specimens made and cured in the same manner as the piles. Ensure that the concrete in precast and precast prestressed piles have developed a compressive strength of at least 5,000 pounds per square inch and have reached a minimum age of 7 days before driving the piles. Make, cure, and perform testing of test specimens as specified in 615.09. When handling or hauling precast concrete piles, support them at the points shown on th e Plans, or, if not so shown, support the piles at the quarter points. The Engineer will make a final inspection as to condition after delivery to the site. 606.07 564 606.07 Cast-in-Place Concrete Piles
606.08 Test Piles
When called for in the Bid Schedule, furnish and drive test piles of the dimensions, at the locations, and to the minimum tip elevations, shown on the Plans or as designated by the Engineer. When approved by the Engineer, the Contractor may drive test piles to be load tested through the existing overburden, without excavating to the bottom of the footing elevation and by predrilling when required by the Engineer, provided that the additional length of test pile necessary to obt ain the requirements specified below is furnished at no additional cost to the Department. Before driving any other test or foundation piles, excavate the ground at each test pile to the elevation of the bottom of the footing. Drive t est piles to be load t ested full length or to the specified bearing indicated on the Plans as determined by the applicable specification equation in 606.14 , whichever occurs first. Drive a ll other test piles full length or to 1.5 times the specified bearing indicated on the Plans, whichever occurs first. However, the tip elevation for all piles shall be either a minimum of 10 feet below ground elevation or the minimum tip elevation when sp ecified on the Plans. If the test pile has been driven to 1.5 times the specified bearing but has not reached the minimum tip elevation, continue to drive the test pile until the required penetration is obtained or practical refusal occurs, whichever occu rs first. When the required pile penetration cannot be achieved by driving without exceeding practical pile refusal, use other penetration aids such as jetting or preformed pile holes. Practical refusal shall be defined as 15 blows per in ch for 2 consecu tive i nches of driving or when 2 times the minimum required bearing is achieved based on the last 6 in ches of driving. Use p ile driving equipment capable of driving to 1.5 times the specified bearings indicated on the Plans at a driving rate not to exceed 15 blows per inch. Perform a load test on one or more of the test piles as shown on the Plans or as designated by the Engineer. From driving logs for test piles and hold - 606.08 566 down piles, load tests , and other available subsoil information, the Engineer will determine the number and length of piles to be used and the minimum required bearing. The Engineer may require a test pile to be left in place for use, cut off, spliced, or removed. Load tests shall consist of a test load accomplished by loading weights o n a platform or by jacking against hold -down piles with a suitable apparatus for accurately measuring the test load and the pile settlement under each increment of load. The pile load test apparatus for applying loads and measuring movement shall meet the requirements of ASTM D1143. Apply the load to not exert any undue bending stresses or damage to the pile. The loading and calibration system shall be capable of applying and recording loads up to 200% of the pile bearing values shown on the Plans. Mate rials used in performing load tests shall remain the property of the Contractor. Unless otherwise shown on the Plans, wait a minimum of 3 days between installing the load test pile and starting the test. The Engineer may direct that load tests be added, d eleted, or repeated, and will make payment for such testing in accordance with 606.22. The Department based the number of load tests and test piles shown on the Plans on the assumption that the Contractor will drive all tests p iles with the same pile driver as was used for the load test pile. If choosing to drive some test piles with a different pile driver, furnish the necessary additional load tests at no additional cost to the Department. After the Engineer establishes the n umber and length of piles to be used, the Contractor may drive regular piles with a different pile driver from that used for driving test piles, provided it notifies the Structures Division before pile lengths are established and uses a pile driver that co nforms to the specified requirements. Before driving a pile to be load tested, submit to the Engineer written details outlining the method of applying, measuring, and recording test loads along with sufficient sketches to fully illustrate the method, proce dure, and arrangements proposed. For the jacks to be used in the tests, submit to the Engineer calibration certificates from a laboratory approved by the Engineer. Ensure that the certificates are no more than 6 months old. The following are the two meth ods for performing pile load tests. Perform the quick load test unless directed otherwise on the Plans. 606.08 567 A. Quick Load Test The full test load shall be 200% of the pile load shown on the Plans. Apply the load in approximately equal increments of 10 to 20% of the pile load as shown on the Plans, and at intervals of 5 minutes throughout the load test. Take and record readings of time, load, and movement immediately before and after applying each load. Apply the load until either a plunging failure occurs, or t he full test load is reached. Plunging failure occurs when continuous jacking is required to maintain the test load. After the final holding time, or immediately after plunging failure occurs, remove the applied load in five approximately equal decrement s with intervals of 5 minutes between decrements. Take readings after removing each decrement and 5 minutes after the complete removal of the test load.
606.09 Calibration Tests
When diesel or other types of hammers requiring calibration are to be used, calibrate the hammers by performing load tests, as directed by the Engineer, even if no load tests are called for in the Bid Schedule. The Department will not require such calibra tions if the hammer is to be used only for driving piles to rock or a fixed tip elevation, or when the hammer is of a type and model that has previously been calibrated by sources acceptable to the Engineer, for similar type, size, and length of pile, and foundation material.
606.10 Order Lists for Piles
The Engineer will furnish the Contractor with an itemized list showing the number and length, as determined by tests, of all required piles, complete in place. The Engineer will not prepare the list of piling for any portion of the foundation area until t he required test data representative of that portion has been determined. The Engineer will base the lengths given in the order list on the lengths that are assumed to remain in the completed structure. Furnish the piles in accordance with the itemized list, except, at no additional cost to the Department, increase the lengths to provide for fresh heading and 606.11 569 for such additional length as may be necessary to suit the Contractor’s method of operation. If during pile driving, the conditions encountered req uire a change in lengths, make such changes by cutting off piling if it is too long, by furnishing new piling, or by splicing as specified in 606.16 if the piling is too short. The Department will make no allowance for delays cau sed by the procedure of determining pile lengths.
606.11 Storage and Handling
Store and handle piles to avoid damaging them and as follows:
606.12 Driving Piles
Drive piles at the locations shown on the Plans or as directed in writing by the Engineer, and to within an allowed variation as to direction of pile of n ot more than ¼ inch per foot of pile length, with a maximum variation at the head of the pile from the position shown on the Plans of not more than 3 inches. To ensure proper positioning of each pile, use templates constructed of heavy timbers or steel, w hich are accurately positioned, securely held in place, and approved by the Engineer. When using water jets, ensure that the number of jets and the nozzle volume and pressure is sufficient to erode the material adjacent to the piling freely. The pump sha ll always have sufficient capacity to deliver a pressure of at least 100 pounds per square inch at two ¾-inch jet nozzles. Before the required penetration is reached, shut off the jets and drive the piles by hammer to final penetration. When preformed pil e holes are used, construct them by drilling or driving and withdrawing a suitable punch or chisel at or near the locations of the piles. If preformed pile holes are so oversized that the sides of a round pile or the corners of a square pile are not in co ntact with the soil, restore lateral stability by filling the space between the pile and the sides of the hole with 606.12 570 approved clean sand , at no cost to the Department . Terminate p reformed holes before the required penetration is reached and drive the pile by hammer to the final tip elevation to seat the pile and secure the minimum required bearing. Except when the pile head is fitted into a steel head block, provide every timber pile with a metal collar or wire wrapping. Protect the heads of all concrete p iles, and the heads of all other piles when the nature of the driving is such that piles may be unduly damaged, with caps of approved design, having a plywood cushion next to the pile head and fitting into a casting, which, in turn, supports a hammer cushi on made from durable, manufactured material. Do not use wire rope and other materials of limited durability. Use an approved pile cushion of sufficient thickness to prevent damage to the pile during driving. Use a minimum initial dimension of 4 -inch thick plywood pile cushion for concrete piles. Replace the pile cushion before excessive compression (more than ½ the original thickness), burning, or charring takes place. During hard driving, several pile cushions may be necessary for a single pile. Use a new pile cushion for each pile. For special types of piling, provide driving heads, mandrels, or other devices in accordance with the manufacturer’s recommendations so that the pile may be driven without damage. For steel piling, squarely cut the heads a nd provide a driving cap to align the axis of the pile with the axis of the hammer. When shown on the Plans, cap steel piles with steel plates or other devices. Use full length piles where practicable. In exceptional circumstances, the Engineer may allow splicing of piles. Splice as specified in 606.16. Install production piles full length, except terminate driving when practical refusal as defined in 606.08 has been reached. If production piles do not achieve the minimum required bearing when driven full length, the Engineer will determine if additional piles are required. The tip elevation for all production piles shall be equal to or below the minimum pil e tip elevation shown on the Plans. When the required pile penetration cannot be achieved by driving without exceeding practical refusal, use other penetration aids such as jetting or preformed pile holes. If piles are raised during driving of other piles , or by any other cause, drive them down again at no cost to the Department . 606.13 571 606.13 Bearing Value and Penetration When the Bid Schedule provides for load tests , the Engineer will determine the minimum number of hammer blows per uni t of pile penetration needed to obtain the specified bearing value based on load tests performed as specified in 606.08 and 606.09. In the absence of load tests, the Engineer will determine the safe bearing value based on test pile data. Each driven pile or shell shall have a minimum bearing value as shown on the Plans or as specified by the Engineer given the results of the load test or test pile data . Drive piles with the same driving system (fuel se tting, hammer cushion, and pile cushion) as the test piles, or the pile that was load tested. Piles used to penetrate a very soft upper stratum overlying a hard stratum shall penetrate the hard material a sufficient distance to fix the pile rigidly.
606.14 Determination of Bearing Value
In the absence of load tests, the Engineer will determine the safe bearing value by one of the following formulas:
606.15 Inspection of Shells for Cast -in-Place Piling
After the shell has been driven, and the core withdrawn, obtain the Engineer’s approval of the shell before placing any concrete. Remove and replace shells that have been improperly driven, do not hold their proper form and dimensions, or are broken or ot herwise defective.
606.16 Extensions and Splices
606.17 Cutoffs and Treatment of Pile Heads
Drive or cut the tops of all piles to a true pla ne at the elevation shown on the Plans or established by the Engineer. Saw timber piles that support timber caps to the plane of the superimposed cap, and ensure they fit snugly. Treat untreated timber pile heads as specified in 601.07 before they are to receive caps . After treatment, place a cover ing of 20-gauge galvanized iron on each timber pile and fold it down neatly over the side and fasten to shed water. No treatment or covering of pile heads will be required if they are to be encased in concrete.
606.18 Conditioning of Treated Timber Piles after Driving
Thoroughly treat all places where the surface of timber piles is broken as specified in 601.07. Treat bored holes and holes caused by withdrawing bolts and spikes as s pecified in 601.06.K .
606.19 Painting Steel Piles and Steel Shells
Unless otherwise specified, paint steel piles or steel pile shells that extend above the ground or water surface. Extend the paint from 2 feet below the low water or ground surface elevation to the top of the exposed steel. Unless otherwise indicated, us e painting System A, as specified in 603.06, except apply the shop coat in the field. Perform painting as specified in 603.
606.20 Final Cleanup
After driving and completing the piling, clean the piles of undue discoloration caused by construction operations. Give those areas of concrete piles that will be exposed the applicable finish, as specified in 604.22. 606.21 575 Perform final cleanup as specified in 104.10. COMPENSATION
606.21 Method of Measurement
607.01 Description ................................ ................................ ................... 578
607.02 Materials ................................ ................................ ...................... 578
607.03 Equipment ................................ ................................ .................... 580
607.04 Preliminary Work ................................ ................................ ......... 581
607.05 Structure Excavation and Foundation Preparation ....................... 581
607.06 Laying Pipe Culverts ................................ ................................ .... 581
607.07 Joining Pipe ................................ ................................ .................. 581
607.08 Field Strutting ................................ ................................ .............. 582
607.09 Backfilling and Post Installation Inspection ................................ . 582
607.10 Disposal of Excess or Unsuitable Material ................................ .. 584
607.11 Final Cleanup ................................ ................................ ............... 584
607.12 Method of Measurement ................................ .............................. 584
607.13 Basis of Payment ................................ ................................ .......... 585
DESCRIPTION
607.01 Description
This work consists of constructing pipe culverts, side drains, slope drains, and storm sewers of the kinds and dimensions shown on the Plans or specified in the Contract. The work also includes all labor, materials, and equi pment as may be necessary to make connections with other drainage structures as shown on the Plans or as directed by the Engineer. MATERIALS