707.01 705 SECTION 707 – FENCES
707.01 Description ................................ ................................ ................... 705
707.02 Materials ................................ ................................ ...................... 705
707.03 Reserv ed ................................ ................................ ....................... 706
707.04 Preliminary Work ................................ ................................ ......... 706
707.05 Setting Posts and Backfilling ................................ ....................... 706
707.06 Erecting Fence ................................ ................................ ............. 707
707.07 Final Finishing and Cleanup ................................ ........................ 708
707.08 Method of Measurement ................................ .............................. 708
707.09 Basis of Payment ................................ ................................ .......... 709
DESCRIPTION
707.01 Description
This work consists of constructing fences, gates, and water crossings. MATERIALS
707.02 Materials
Provide materials of the kind, size, and type shown on the Plans, including all necessary posts, fittings, and appurtenances. Provide materials as specified in: Portland Cement Concrete, Class A ................................ ............ 604 Stock Fence ................................ ................................ ............ 909.01 Chain-Link Fence ................................ ................................ .. 909.02 Fence Gates ................................ ................................ ............ 909.03 Water Gates and Water Crossings ................................ ......... 909.04 The Engineer will reject galvanized material that is damaged. With the Engineer’s approval, the Contractor may repair damaged galvanized material as specified in 713.04.B. 707.03 706 707.03 Reserved CONSTRUCTION REQUIREMENTS
707.04 Preliminary Work
Before beginning construction or placing of fences, perform all necessary Clearing and Grubbing a nd Removal of Structures and Obstructions as specified in 201 and 202, respectively. Clearing for fence construction shall not extend beyond the right -of-way line. Do not disturb living trees and shrubs 1 foot or more on each side of the fence line unless otherwise directed by the Engineer. Locate the fence 1 foot inside the right -of-way unless otherwise shown on the Plans. Remove rock, which protrudes above the ground surface and is in the l ine of the fence, to the ground surface. Turn fences in at drainage structures, cattle passes, and bridges where directed by the Engineer so as to abut wingwalls and abutments. Provide two weeks notice to affected property owners before cutting existing fences. Install access control fences before cutting existing fences in areas used by domestic livestock or other areas as directed by the Engineer.
707.05 Setting Posts and Backfilling
Set line posts for stock fence at intervals not to exceed 10 feet. Erect braced line posts at intervals of 330 feet between end or corner posts, and, when necessary due to terrain features, install additional braced line posts at locations designated by the Engineer. Measure the interval between posts parallel to the bottom of the fabric of the proposed fence and in line of fence from center to center of post. Set posts for chain -link fence at intervals not to exceed 10 feet. Measure the intervals between posts as specified above for stock fence. Install posts, shown on the Plans to be set in concrete, in dug or drilled holes of the size and to the depth shown on the Plans or directed by the Engineer. For embedment of posts and for anchors, use Class A concrete meeting the requirements of 604. Construct t he concrete embedment and anchors with a crown at the top to shed water. If ground conditions allow, the Contractor may drive posts that do not require embedment to the required depth using approved methods, or otherwise s hall 707.06 707 install such posts in holes dug or drilled to the specified depth and to a size that will allow sufficient room for proper backfilling. If solid rock is encountered, install posts by drilling the rock to the required depth and grouting the post ther ein with Portland cement grout composed of one part cement to three parts sand. Backfill post holes for posts not requiring concrete embedment with selected earth or other approved material. Place backfill material in layers not exceeding 6 inches, and th oroughly tamp each layer. When backfilling and tamping is completed, secure the posts and anchors in the proper position. Do not apply pull to posts set in concrete until the concrete has cured a minimum of 72 hours.
707.06 Erecting Fence
At certain locations along the right -of-way, the Engineer will direct the Contractor to construct chain -link fence or stock fence prior to the removal of existing fences. When fences are constructed 1 foot inside the right -of-way, landowners may join these fences by setting posts adjacent to them.
707.07 Final Finishing and Cleanup
The Engineer will inspect fences after they have been placed in final position. Dispose of all excess or unsuitable material as directed by the Engineer. Perform final cleanup as specified in 104.10. COMPENSATION
707.08 Method of Measurement
The Department will measure:
707.09 Basis of Pay ment
The Department will pay for accepted quantities, complete in place, at the contract prices as follows: Item Pay Unit Fence (Description) Linear Feet Gate (Description) Each End, Braced Line, and Corner Post Assemblies (Description) Each Water Crossings Linear Feet Water Gates Square Feet Such payment is full compensation for all excavation, backfill, and all other incidentals necessary to complete the work. 708.01 710 SECTION 708 – MONUMENTS AND MARKERS
708.01 Description ................................ ................................ ................... 710
708.02 Materials ................................ ................................ ...................... 710
708.03 Equipm ent ................................ ................................ .................... 711
708.04 Foundation Preparation ................................ ................................ 711
708.05 Manufacture and Erection of Monuments and Markers ............... 711
708.06 Final Finishing and Cleanup ................................ ........................ 712
708.07 Method of Measurement ................................ .............................. 712
708.08 Basis of Payment ................................ ................................ .......... 713
DESCRIPTION
708.01 Description
This work consists of furnishing and erecting monuments or markers composed of Portland cement concrete or other materials approved by the Engineer. Monuments and Markers shall be of the kind, size, dimensions, shapes, and markings as shown on the Plans. MATERIALS
708.02 Materials
Furnish monuments and markers manufactured of Class A concrete, composed of materials including reinforcement meeting 604.02. Provide c oncrete right-of-way markers that have a smooth finish and are fabricated as shown on the Plans. Stone for monuments and markers shall meet 921.07. Metal materials shall conform to the requirements shown on the Plans or specified in the Special Provisions. Provide paint, if required, that meets 910 for the kind and type of paint called for on the Plans.