PAINTING FOR STRUCTURAL STEEL

PART 1 GENERAL

1.1SECTION INCLUDES

A.Prepare and paint all surfaces except where indicated otherwise.

1.2RELATED SECTIONS Not Used

1.3REFERENCES

A.ASTM D 4285: Indicating Oil or Water in Compressed Air
B.ASTM D 4417: Field Measurement of Surface Profile of Blast Cleaned

Steel

C.ASTM E 11: Wire Cloth and Sieves for Testing Purposes
D.American Institute of Steel Construction (AISC)
E.Federal Standards
F.Mine Safety and Health Administration (MSHA) Standards
G.National Institute for Occupational Safety and Health (NIOSH) Standards
H.Northeast Protective Coating Committee (NEPCOAT)
I.The Society for Protective Coatings (SSPC)

1.4DEFINITIONS Not Used

1.5SUBMITTALS

A.Materials
1.Source and gradation of the blast abrasive.
2.Type and source of solvent if required.
3.Manufacturer’s information regarding the specified coating

materials, including:

a.Required wet and dry film thickness
b.Project safety data

Painting For Structural Steel

c.Thinning recommendations
d.Temperature requirements
e.Profile recommendations
f.Mixing and application procedures
g.Required equipment
h.Method of application
4.Test samples. Refer to this Section, article 1.6.
B.Qualifications, methods, and documentation.
1.Certifications before the preconstruction meeting. Refer to this

Section, article 1.7.

2.Detailed plan of protection methods that includes Environmental

Protection for approval.

3.Quality Control Plan that contains at a minimum procedures and

verification of the following:

a.Compression air check
b.Dry film thickness – Refer to SSPC-PA 2
c.Air temperature
d.Humidity and dew point
e.Surface temperature
f.Abrasive cleanliness check – Refer to SSPC-AB 2
g.Degree of cleanliness achieved
h.Surface profile – Refer to ASTM D 4417 method C
i.Batch number and amount of thinner used
j.Batch number of paint used
k.Mixing procedures
l.Paint repair procedures for scratches, gouges, holidays, mud

cracking, runs, and sags

4.Daily reports upon request.
a.Submit no later than 24 hours following the completion of

work.

1.6TEST SAMPLES

A.Department tests paint samples from each batch or lot before use.
1.Submit samples for verification.
2.Paints must match the spectrum samples on file with the

Department

Painting For Structural Steel

1.7PAINTER AND SANDBLASTER QUALIFICATIONS

A.Contractors and subcontractors performing surface preparation or

coatings applications in the field.

1.Must have SSPC-QP 1 certification before the preconstruction

meeting.

2.Remain certified for the duration of the project.
B.Contractors, subcontractors, and fabricators performing shop surface

preparation or coatings applications.

1.AISC-420-10/SSPC-QP 3 enclosed shop certification before the

preconstruction meeting.

2.Remain certified for the duration of the project.
a.Do not perform work if certification has expired.
3.Notify the Department of any change in certification status.

PART 2 PRODUCTS

2.1MATERIALS

A.Select a complete three-part coating system consisting of a zinc primer,

epoxy or urethane intermediate coat, and aliphatic urethane top coat from the NEPCOAT Qualified Products List. Refer to http://www.udot.utah.gov/go/standardsreferences.

B.Use paint color No. 26293 for the first field coat and No. 26306 for the top

coat following Federal Standard 595.

PART 3 EXECUTION

3.1GENERAL

A.Use manufacturer’s information regarding the specified coating materials

including required wet and dry film thickness, project safety data, thinning recommendations, temperature requirements, profile recommendations, mixing and application procedures, and required equipment.

3.2INSPECTION

A.Engineer examines surfaces before surface preparation and before

application of each succeeding coating. Correct any condition that is determined by the Engineer to negatively affect a proper coating application.

Painting For Structural Steel

B.Provide safe access to permit inspection of the steel before and after

painting. Use rubber rollers or other approved protective devices for scaffold fastenings. Do not mar or damage freshly coated surfaces.

3.3PREPARE SURFACES

A.Painted steel – Clean surfaces with clean petroleum solvents and then

blast clean to a near-white condition following SSPC-SP 10. Use clean oil-free air.

1.Grind off all fins, tears, slivers, and burred or sharp edges present

on any steel member or those that result from the blasting operation.

a.Reblast where needed.
b.Remove all mill scale.
c.Do not scar metal.
d.Grind the edges of all flame cut steel until the hardened

edge accepts the blast profile. Refer to ASTM D 4417 method A.

e.Produce a 0.5 - 3 mils uniform profile not to exceed

manufacturer’s recommendation.

2.Remove all abrasive and paint residue using either a commercial

vacuum cleaner or by double blowing.

a.Equip commercial vacuum cleaner with a brush-type

cleaning tool.

b.Double blowing – Vacuum the top surfaces of all structural

steel, including items such as top and bottom flanges, longitudinal stiffeners, splice plates, and hangers after the double-blowing operations are completed.

3.Keep the steel dust free and prime within 8 hours after cleaning.

Reblast to a near-white condition if any rust is visible before priming.

4.Protect freshly coated surfaces from subsequent blast-cleaning

operations.

a.Repair surface if damaged.
b.Mask all areas requiring field welding before shop painting.
5.Have the surfaces inspected and approved by Engineer or

Construction and Materials Division representative of Department before applying shop coat.

6.Apply the shop coat at the fabrication site. Apply coatings at the

fabrication site in an enclosure with a controlled environment to match optimum conditions for application and curing as stated in the manufacturer’s product data sheet.

7.Apply mist coat to the top flange.

Painting For Structural Steel

B.Field Painting
1.Repair all damage to shop coat that occurs during shipping,

handling, and erection.

2.Power wash steel without the field coat to remove contaminants or

other foreign matter from the primed surface.

3.Blast clean bolt heads, fasteners, and any rusted areas to a near-

white finish. Thoroughly clean the coating surrounding the blasted area and re-prime the same day using organic zinc from the same paint manufacturer and the same dry film thickness specified for the shop coat. Follow SSPC-SP 10.

4.Remove all concrete drippings, abrasive, and paint residue.

Vacuum items such as the top and bottom flanges, splice plates, longitudinal stiffeners, and hangers after completing double-blowing operations.

5.Allow the touch-up coat to dry according to manufacturer’s

recommendation as listed on the product data sheet.

3.4PREPARE PAINT MATERIALS

A.Mix and thin paint materials according to manufacturer’s product data

sheets for both shop and field painting.

B.Mix the paint to a lump-free consistency with a high shear mixer such as a

Jiffy mixer according to the manufacturer’s directions.

1.Do not use paddle mixers or paint shakers.
2.Keep paint in the original containers.
3.Mix until all the metallic powder or pigment is suspended and until

all paint solids that may have settled to the bottom of the container are thoroughly dispersed.

C.Strain the paint through a screen having openings no larger than those

specified for a No. 50 sieve according to the material standard. Refer to ASTM E 11.

D.Strain and continuously agitate the mixed material up to and during

application.

3.5APPLY PAINT

A.Apply field coats at the construction site after steel erection work is

completed.

1.Do not apply field coats until Engineer verifies the surface.
2.Dry film thickness of the first field coat must be greater than 4 mils.
3.Keep the dry-film thickness of the top coat greater than 2 mils.

Painting For Structural Steel

B.Use wet and dry film thickness gauges for testing the coating thickness

during and after application.

C.Apply each coat at required consistency and thickness according to the

manufacturer’s recommendations including field coating. Use pressures recommended by the manufacturer of the coating system when using spray nozzles.

D.Produce a uniform, even coating that bonds to the underlying surface.

Refer to SSPC-PA 1.

E.Weather
1.Follow the manufacturer’s recommendations if weather conditions

require paint thinning.

2.Temperature of the air and the steel must be above 40 degrees F,

but not so hot as to cause the paint to blister.

3.Relative humidity must be less than 85 percent or the combination

of temperature and humidity conditions must inhibit surface condensation.

4.Test humidity by applying a thin film of water to a small area.

Surface may be painted if the film evaporates within 15 minutes.

5.The steel temperature must be a minimum of 5 degrees F above

the dew point.

F.Use necessary equipment for the proper application of the specified

coating. Observe safety practices found in SSPC-PA Guide 10, “Guide to Safety and Health Requirements.”

G.Blast clean any shop coat that shows any indication of “mud-cracking” or

adds more than 7 mils to a soundly bonded coating or bare steel. Refer to SSPC-SP 10.

H.Thoroughly clean areas that have deficient primer thickness to remove all

dirt.

I.Apply an intermediate and top coat to any surface at the fabrication site

that will be inaccessible for painting after field erection.

J.Do not load structural steel for shipment until shop paint is dry to the

touch.

K.Protect all paint systems. Place softeners between plates of cross frames

and diaphragms.

Painting For Structural Steel

3.6PROTECTION

A.Stop work if protection is unsatisfactory.
B.Protect pedestrian and vehicular traffic.
C.Protect all portions of the structures that are not to be painted from

splatter, splashes, and overspray including superstructure, substructure, slope, and highway appurtenances. Protect areas during painting and blast cleaning operations where other damage can occur.

D.Use barriers during any blast-cleaning operations to protect pedestrians

and vehicles and to prevent spreading or falling of abrasive materials and debris on the traveled portions of the pavement. Remove any abrasive materials and debris on pavement, shoulders, or slope paving before reopening work areas to traffic.

E.Provide employees performing the blast-cleaning operations air-supplied

blasting hoods approved by the Mine Safety and Health Administration and the National Institute for Occupational Safety and Health.

F.Minimum requirements for the air supply system:
1.Airline filter, pressure-reducing valve with gauge and pressure

release valve.

2.Do not allow the air supply to be contaminated with harmful

materials or elements. Refer to ASTM D 4285.

3.7QUALITY ASSURANCE

A.Minimum Coating Thickness – Apply two or more coats if the required film

thickness cannot be obtained by one coat without producing runs, bubbles, or sags.

B.Refer to SSPC PA 2.

END OF SECTION

Painting For Structural Steel

Get an email when 09972 changes

Utah revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Utah Standard Specifications for Road and Bridge Construction, 2026 Edition. Pages 1189–1195 of 1,331. View official source ↗

Ask about this section

Scoped to Utah Standard Specifications, Section 09972 — Painting For Structural Steel. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.