380Calcium chloride and sodium chloride will be measured in tons and will be paid for at the contract unit price per ton. This price shall include preparing and shaping the subgrade or subbase and shoulders, adding moisture, removing and replacing unstable subgrade or subbase and constructing the base course thereon, and filling test holes. Payment will be made under: ————————————————————————————Pay Item Pay Unit———————————————————————————— Aggregate base material (Type/no.) Cubic yard or ton Aggregate material (No.) Cubic yard or ton Calcium chloride Ton Sodium chloride Ton———————————————————————————— SECTION 310—TACK COAT
310.01 Description
This work shall consist of preparing and treating an existing asphalt or concrete surface with asphalt in accordance with these specifications and in conformity with the lines shown on the plans or as established by the Engineer.
310.02 Materials
310.03 Procedures
The existing surface shall be patched, cleaned, and rendered free from irregularities to the extent neces - sary to provide a reasonably smooth and uniform surface. The Contractor shall remove unstable corru - gated areas, and replace with suitable patching materials when required by the Contract. The Contractor shall clean the edges of existing pavements that are to be adjacent to new pavement to permit adhesion of tack. The Contractor shall uniformly apply tack coat or non-tracking tack coat material with a pressure distrib - utor conforming to Section 314.04(b). Hand spray equipment shall not be used except in areas inacces - sible by a pressure distributor. The distributor shall be calibrated by the Contractor in the presence of the Engineer prior to initial asphalt plant mix placement to demonstrate an even and accurate spray application. Calibration will be consid - ered acceptable when the spray rate is uniform and within 0.02 gal/yd ² of the design application rate.309.06 381All tack coat and non-tracking tact coat materials stored longer than 30 days from the shipping date on the Bill of Lading shall be retested in accordance with Section 210.06 to verify the material still meets product specifications. Tack at joints, adjacent to curbs, gutters, or other appurtenances shall be applied with a hand wand or with a spray bar at the rate of 0.2 gal/yd ². At joints, the tack applied by the hand wand or a spray bar shall be 2 feet in width with 4 to 6 inches protruding beyond the joint for the first pass. Tack for the adjacent pass shall completely cover the vertical face of the pavement mat edge so that slight puddling of asphalt occurs at the joint, and extend a minimum of 1 foot into the lane to be paved. Care shall be taken to prevent spattering adjacent items during the application of tack coat. The distributor shall not be cleaned or discharged into ditches or borrow pits, onto shoulders, or along the right of way. When not in use, the Contractor shall ensure equipment is parked so that the spray bar or mechanism will not drip asphalt on the surface of the traveled way. The tack coat or non-tracking tack coat shall be applied to the pavement surface in such a manner that it will bond the overlay and the underlying surfaces together. The Contractor shall apply tack coat and non-tracking tack coat in accordance with the weather limita - tions that apply to the course being placed as well as the manufacturer’ s recommendations. The Engineer will verify, and reserves the right to alter, the quantity, rate of application, temperature, and areas to be treated prior to application. The tack coat or non-tracking tack coat shall be applied in a manner to offer the least inconvenience to traf - fic and to permit one-way traffic without pick up or tracking of the asphalt onto adjacent non-treated areas. All traffic, including construction traffic, shall be excluded from tacked sections until the tack has cured. Tack will not be required atop asphalt stabilized open-graded material drainage layers. The Contractor shall measure and report the rate of tack material applied on a daily basis in accordance with VTM-137 Method B (Tack Yield Method), on forms provided by the Engineer. On a daily basis, the Contractor shall provide the Engineer readings taken from the calibrated distributor establishing the quantity of gallons placed for that day. The Engineer will verify the desired tack application rate is achieved in accordance with VTM-137 Method A (Tack Plate Method). This test shall be performed , at a minimum frequency of once per each roadway, within the first 500 tons of asphalt mix placed, unless otherwise approved by the Engineer. The Engineer reserves the right to perform the tack plate method testing at a higher frequency, as deter - mined necessary, to ensure adherence to specifications.
310.04 Measurement and Payment
Tack coat , whether standard Tack Coat or Non-Tracking Tack Coat, when a pay item, will be measured in gallons and paid for at the Contract gallon price. The volume will be based on daily volume with temperature corrections in accordance with Section 109. When not a pay item, the Contractor shall include the cost in the contract unit price for other appropriate items. Payment will be made under: ——————————————————— Pay Item Pay Unit——————————————————— Tack coat Gallon Nontracking tack coat Gallon——————————————————— SECTION 311—PRIME COAT
311.01 Description
This work shall consist of preparing and treating an existing surface with asphalt, and cover material if required, in accordance with these Specifications and in conformity with the lines shown on the plans or as established by the Engineer.