662
6-237SECTION 662 – RAILROAD TRACK CONSTRUCTION
662.01DESCRIPTION . This work shall consist of constructing new ballasted track with jointed or
continuous welded rail (CWR); removing and replacing rail; removing and resetting track; removing and replacing ties; raising, aligning, and surfacing track; removing track; instal ling other track material ( OTM ) such as tie plates, anchors, and spikes as required; and de -stressing rail as required in accordance with the CWR program of the Operating Railroad.
662.02MATERIALS . Materials shall meet the requirements of the followings ubsections:
Aggregate for Railroad Ballast ................................ ................................ .................. 704.03 Railroad Ties ................................ ................................ ................................ .............. 709.04 Rail ................................ ................................ ................................ ............................. 715.0 6 Other Track Material (OTM) ................................ ................................ ..................... 715.0 8
662.03SUBMITTALS
review and approval by the Engineer . Submittals shall meet the requirements of Subsection 105.0 6.
the source of the material. Information to be provided on rail shall include the rail weight, rail section, rail wear, drilling pattern, typical rail length, date rolled, and the name of the mill where the rail was rolled.
Section 3.12 .
are incorporated into the work.
vibration and the type of mechanical vibratory equipment to be used.
662 6-238 (9) Thermite Weld Submittals .
thermite weld kit, and the method and detailed procedure for making field welds. If there are different types of welds in the Contract (e.g. different sizes or types of rail, compromise joints), a procedure shall be provided for each. Installation procedures submitted shall comply with these provisions and those of the weld kit manufacturer.
welding have been trained by the welding kit manufacturer. The documentation shall include the name of the trainee, the location of the tr aining, name of the instructor, and date of the training.
work under the Contract. Weld supervisors and welders shall be required, when requested by the Engineer, to submi t their qualification certificates throughout the duration of the project.
laboratory and the persons who will perform ultrasonic testing of field welds have previously tested a minimum of 250 welds.
equipment, including calibration blocks, that will be used in the t esting process.
include, but not be limited to, identification of test equipment used, calibration, weld number and location, members of the test crew, date and time of test, descr iption of defects, and a recommendation to accept or reject weld.
each rail.
662 6-239 (b) Post-Construction Submittals . No more than 2 working days following the completion of the work related to the submittal, the following information shall be prepared and submitted for review and approval by the Engineer . The following submittals by the Contractor shall meet the requirements of Subsection 105.0 6.
or exceed the requirements specified herein.
on the approved Contractor created form and shall include, but not be limited to, the following information for each weld:
the weld wa s made. Rail identification including section, rail strength and chemistry, heat number, and date rolled.
string number, the weight of the rail, the manufacturer, the year, the temperature at which the rail was laid, the mileage location, and whether the string was the north or south r ail (for east/west rail lines) or the east or west rail (for north/south rail lines).
be submitted within 48 hours of the completion of work or upon the request of the Operating Railroad or Agency. Records shall be filled out on forms in accordance with the Operating Railroad ’s CWR plan.
662 6-240 662.04 REMOVAL OF TRACK . Existing rail, anchors, spikes, or other rail fastening devices, bolts, nuts, washers, joint bars, tie plates, concrete ties, wood cross ties, and wood switch ties shall be removed within the limits shown on the Plans.
deemed to be fit for reuse and shall be stockpiled and protected from damage due to construction operations. The rail shall be reused at the locations indicated on the Plans. When necessary, cutting of rai l shall be performed as specified in Subsection
662.07(c)(10)
rail holding devices in a manner that does not damage any existing materials. Flame cutting of bol ts to be removed will be permitted providing the joint bars and rails are not damaged. Existing hardware shall include but not be limited to track spikes, rail anchors, joint bars, tie plates, and shim plates. The Engineer will determine which track hardw are is fit for reuse.
ties.
spaced along the l ength of the rail.
amount of wear.
mid-height of the stack. These markings shall be painted neatly near one end of the rail. The Contactor shall mark rail ends in yellow designating fit relay rail. The Contractor shall also mark the centerline of each rail length on the rail head in yellow.
662 6-241 (2) Stacking of Joint Bars, Gage Rods, and Tie Plates for Reuse on the Project .
condition.
other approved containers.
determined by the Engineer, as well as any waste material, including ties, shall become the property of the Contractor and shall be removed from the site and disposed of properly at the Contractor’s expense.
662.05BALLAST HANDLING . The Contractor shall handle ballast in accordance with the requirements
of AREMA Chapter 1, Section 2.5 and the following. Processed ballast shall be handled at the producing plant in such a manner that it does not segregate. Ballast shall be washed prior to loading. Ballast shall be loaded into rail cars or vehicles that are in good order and tight enough to prevent leak age and waste of material, and that are clean and free from rubbish, sand, dirt, or any substance that would foul or damage the ballast. Broken stone for ballast shall be delivered from the screens directly to the rail car (or other vehicle) or to clean bi ns provided for the storage of the output of the crusher.
662.06BOTTOM BALLAST INSTALLATION . The depth of ballast required shall be as shown on the
Plans.
surface upon which the track will be constructed. The Contractor shall remediate and correct any deficiencies as directed by the Engineer.
Bottom ballast shall be installed to the underside of the ties to the depths shown in the Contract.
662
6-242To the extent practicable, ballast shall be unloaded for use with minimum redistribution and
dressing. Care shall be taken when unloading ballast cars to ensure that they are completely unloaded. Railroad ballast shall be distributed so that ample clearance below top of rail is provided for rolling equipment, switches are not fouled, and guard rails are unobstructed. Care shall be taken when unloading and dressing ba llast near open deck bridge approaches.
TRACK CONSTRUCTION . Ballasted track shall be constructed in accordance with the
applicable sections of AREMA Chapter 5, Part 4 ; AREMA Chapter 5, Part 5; and as specified herein. Ballasted track includes the rail, ties, fastenings, OTM, and ballast. The Contractor shall connect new rail to existing rail sections as indicated on the Plans by the use of standard or compromise joint bars, or by the use of standard or compromise welds whe n connecting to existing CWR.
Chapter 30, Section 3.5.11 .
the ties with the outside (field) end of the tie used as a reference line to align the ties.
as a reference line unless otherwise designated by the Engineer.
tie tongs. The use of picks will not be permitted.
ties to avoid damage to the ties.
not skewed and approximately centered about the centerline of track. Ties shall be spaced
in accordance with the Contract.
662
ties. Tie plates shall not be placed directly under thermite welds.
the shoulders bearing firmly against the sides of the rail base. Under no circumstances shall
the tie plate shoulder be allowed under any portion of the rail base. Care shall be taken to
ensure that the tie plates are well seated on the ties and the rail properly seated on the tie
plates. Canted tie plates shall be placed so as to cant the rail inward towards the gage side
of the rail. Tie plates with different amounts of cant or flat plates shall not be intermixed
except as directed by the Engineer. This requirement shall also apply to any surfacing
within the limits of the project.
extraneous material shall be removed by blowing or brushing off the surface of the tie and
tie plate to prevent damage and to ensure proper seating of the rail.
completed track gage is correct and within the specified limits in Subsection 662.07(c).
and replacement of rail shall be installed in accordance with the following requirements. When
laying CWR strings or welding lengths of rail into CWR, bolted joints may be used for temporary
works where applicable and as indicated in the Operating Railroad’s CWR plan.
subject to inspection and acceptance by the Engineer.
shall be placed so that it can be laid with as little handling as possible.
tie shall be gaged on tangents and every third tie shall be gaged on curves. The gage shall
be 56-1/2 inches between points 5/8 inch below the top of the rail on the two inside edges
of the rail.
the rail in existing track abutting the new rail is not at or within those limits, gaging shall
be performed within existing track for a sufficient length to meet the limits specified in
Table 662.07B for rate of change of track gage. The limits of gaging will be determined by
the Engineer.
662
When correcting gage, all spike pulling and driving shall be done on the rail opposite the
rail used for lining. Where spikes are pulled, the holes in the ties shall be plugged with tie
plugging material meeting the requirements of Subsection 709.04(e). New spikes shall be
driven as specified in Subsection 662.07(g).
TABLE 662.07A – EXISTING TRACK GAGE LIMITS
Minimum
Gage (in.)
Maximum
Gage (in.)
56-1/4 56-1/2
TABLE 662.07B – EXISTING TRACK GAGE RATE OF CHANGE LIMITS
Track Gage Parameter Class of Track
1 2 3 4
The rate of change within
31 feet shall not exceed 1 in. 1 in. 3/4 in. 1/2 in.
bolt threads shall be lubricated with an approved corrosion-resistant lubricant in
accordance with the manufacturer’s instructions before they are applied. When joint bars
are used in temporary works prior to welding, they shall not be lubricated.
use of a hammer, maul, or other similar tools to drive the rail into position will not be
permitted.
chamfered. All chips and burrs shall be removed. Holes shall not be burned with a torch.
in AREMA Chapter 4, Section 3.3. Rail ends shall be drilled with three holes.
662
bars being utilized. If a rail end which is currently drilled requires drilling for
another pattern, the Contractor shall not double drill the new pattern on the existing
rail end. The Contractor shall crop off the rail end and then drill the new pattern.
shall be in accordance with the Operating Railroad’s CWR plan.
Joint bars shall be properly seated in the rail.
middle of the bar and working towards the ends. The Contractor shall strike both bars with
a sledgehammer during the tightening process to help seat the bars properly. The
Contractor shall then perform a final re-tightening of the two middle bolts. The Contractor
shall torque the bolts as required by AREMA for the respective bolt size. All bolts shall be
torqued with a mechanical bolt machine and set to apply the required torque. The
Contractor shall not use this method to of striking the bars when installing insulated joint
bars.
with a mechanical tamper as specified in Subsection 662.07(i). Ties shall be tamped after
rail is bolted and laid in tie plates and prior to gauging and spiking.
the rail end of the lighter of the two rail sections being joined. Hardwood ties meeting the
requirements of 49 C.F.R. § 213.109 for non-defective crossties shall be used under
compromise joints. When using temporary compromise joints as part of rail change-out or
turnout change-out programs, it is permissible to use track shims to support the joint until
the shims and compromise joints are removed the next day. The ties shall be tamped to
support any permanent compromise joints left in the track. Shims to support permanent
compromise joints will not be permitted.
unless otherwise indicated on the Plans.
shall not be installed on bridges, nor shall they be installed on roadbed approaches within
300 feet of the ballast walls at either end of the bridge.
662
or horizontally on the gage side of the rail head shall be corrected. The rail end mismatch
shall be measured after the standard or compromise joints have been applied and tightened.
If mismatched rail ends already contain rail end batter (due to the larger rail having been
struck by wheels), the amount of rail end batter shall be taken into account when calculating
the mismatch. Mismatches shall be corrected by changing joint bars and bolts, by being
built-up with weld material on the offending rail, or by substituting a different piece of rail.
The length of ramp required for this procedure will be calculated as the ramp slope, which
shall be the rail end mismatch measurement (in thousandths of an inch) divided by 0.012.
(d) and Subsection 662.07(e)
temperature (PRLT) range in accordance with the requirements of the Operating Railroad’s CWR
plan.
Laying and adjustment procedures for CWR will be dependent on the maximum and minimum rail
temperatures expected.
If CWR is laid at rail temperatures above the maximum preferred rail laying temperature, the CWR
shall be adjusted within 48 hours after being installed.
If CWR is laid at rail temperatures below the minimum preferred rail laying temperature, rail
heaters shall be used to bring the rail temperature within the PRLT range.
The rail temperature of any CWR string laid shall be measured with an accurate and reliable rail
thermometer placed on the base of the rail near the web. The thermometer shall be designed for
measurement of rail temperature and shall be placed away from the wind and out of direct sunlight.
the minimum preferred rail laying temperature, the rail shall be heated to the preferred laying
temperature with a propane rail heater. The rail shall be heated directly following it being laid or
vibrated. The temperature of the rail will determine the amount of heat required.
On the base of the rail next to a tie plate which has been set to proper gage and spiked, the exact
distance the rail will need to expand based on the difference between the current rail temperature
and the PRLT shall be marked. The rail string shall be marked at each quarter point and at the end.
662
The rail shall be vibrated by a mechanical vibrator to ensure proper rail movement in accordance
with the approved rail vibration plan. In no case will the Contractor be permitted to simultaneously
apply mechanical vibrations and heat to perform rail expansion.
Under no circumstances shall the rail be vibrated by using spike mauls, sledgehammers, or other
types of hammers or tools to strike the rail.
Equipment such as hydraulic rail pullers may be used to expand the rail to the proper PRLT
equivalent length.
Adjustment of CWR shall occur after all work specified in Subsection 662.07(i) has been
completed.
track electric flash-butt welding.
Electric flash-butt welding shall be performed in accordance with the requirements of AREMA
Chapter 4, Section 3.10 and AREMA Chapter 4, Section 3.11.
Thermite welding shall meet the requirements of AREMA Chapter 4, Section 3.13 and Subsection
662.14
Field welds shall be completed using in-track electric flash-butt welding to connect continuous
welded rail strings, connect turnouts to adjacent rail strings, weld shop-fabricated rails containing
bonded insulated joints into track, and weld shop-fabricated transition/compromise rails into track.
Thermite welding shall be used within turnouts, for compromise welds, and at other locations
noted on the Plans or designated by the Engineer.
Excessive rail grinding of the weld that causes a depression on the head and or gage face of the
rail after a weld is completed will not be accepted. The weld shall be cut out beyond the heat
affected zone and replaced.
The Engineer will visually inspect welds for visible defects, such as any incomplete portion or
inclusions. The weld will be rejected and shall be replaced if it contains these defects.
otherwise specified.
opposite rail by more than 100 feet.
662
vertically and square with the rail and driven so as to allow 1/8 inch to 3/16 inch in the
space between the underside of the head of the spike and the top of the base of the rail.
Opposite holes on the gage and field side of the rail shall be used for rail holding spikes.
The rail holding spiking arrangement shall be in accordance with Table 662.07C unless
otherwise specified in the Contract.
vertically so the head has full bearing against the tie plate. Plate holding spiking
arrangements shall be in accordance with Table 662.07C unless otherwise specified in the
Contract.
TABLE 662.07C – TIE SPIKING TABLE
Degree of Curve Tie Spiking Arrangement
Main and Siding Track Yard and Industrial Track
0°-00' to 2°-00' 0°-00' to 2°-00' 2 rail holding and 0 plate holding
2°-01' to 6°-00' 2°-01' to 13°-00' 2 rail holding and 1 plate holding –
1 field side
6°-01' and greater 13°-01' and greater 2 rail holding and 2 plate holding -
1 field side and 1 gage side
other and spikes on the field side of the running rail shall be placed across from each other.
Spikes on the field side shall be placed in the hole on the north or west side of the plate.
The spiking pattern shall be held consistent through the limits of work.
against the rail. Spikes which are bent while being driven shall be discarded and replaced.
No spikes shall be driven against the end of joint bars. No spikes shall be driven in a slot
in a rail joint.
662
If spikes are pulled, the ties shall be plugged with synthetic tie plugging material meeting
the requirements of Subsection 709.04(e). Track spikes may be driven through tie plugging
material. The Contractor shall remove and replace any tie where the tie plugging material
is not completely and tightly filling the track spike hole or where the tie plugging material
is not properly holding a driven track spike.
5.4.
The rail anchor pattern shall be spaced approximately uniformly along the rail length. To avoid tie
skewing, the anchors shall be applied against the same tie on opposite rails.
Rail anchors shall have full bearing against a sound tie.
New rail anchors shall firmly grip the bottom of the rail to which they are applied to provide
longitudinal rail restraint. Rail anchors shall not be installed at ties which support rail joints, where
they will interfere with bond wire, boot legs, insulated joints, and other signal or track appliances.
Rail anchors shall be installed manually or with standard anchor machines.
For track constructed with jointed rail, rail anchors shall be installed immediately after rail is laid.
All rail laid in a given day shall be fully anchored on that same day.
Unless otherwise specified, the Contractor shall anchor CWR in accordance with the following
and the CWR program of the Operating Railroad:
rail anchors shall be applied and boxed at every tie in both directions, including where
joints are to be field welded. For the remainder of the string, rail anchors shall be applied
and boxed at every second tie for restraint in both directions.
shall be box anchored for 200 feet in each direction.
on every second tie.
662
lengths at every third tie in both directions.
in accordance with the following:
when anchors are applied to one rail, anchors are also required on the opposite rail
of the same side). Rail anchors shall be applied on the gage side of the rail except
where insufficient clearance restricts the use of the anchor or application tool, in
which case anchors may be applied from the field side of the rail where clearance
permits.
distance to prevent rail movement from disturbing the switch point and frog.
200 feet past the frog on each track on each side of the turnout.
at either end of a bridge.
shall be as shown on the Plans. Track shoulders shall be a minimum of 12 inches. Work shall be
performed so that the track alignment, surface, and elevation will be maintained after tamping.
shall be distributed in advance of the track surfacing in sufficient quantity to properly
surface, align, tamp, and dress the track to the required ballast cross section.
redistribution and dressing. Care shall be taken when unloading ballast cars to
ensure that they are completely unloaded.
provided for rolling equipment.
approaches.
662
the track structure or shoulders for the purpose of tamping or dressing the ballast
sections. Any sod, vegetation or foreign matter inadvertently pulled in shall be
removed by the Contractor prior to tamping.
as are needed to bring the track into the tolerances specified in Table 662.07D while
meeting the following requirements. The Contractor shall consider overhead clearances
where present.
of the rail, straining of the joints, and damaging or loosening the fastenings. The
amount of track lift in a single operation shall neither exceed 4 inches nor endanger
the horizontal or vertical stability of the track. The track shall be raised such that
the lift required to reach the final surface shall not be less than 1 inch nor more than
3 inches. The final raising and aligning operations shall fill cribs to the top of tie
and the shoulders with ballast. A minimum of 2 inches of clearance shall be
provided between metallic portions (non-rail) of the track structure and ballast.
Particular attention shall be given to the tamping of ties not attached to the rails, to
ensure that they maintain firm bearing against the base of the rail, without admitting
ballast between the rail and tie. No portion of the tie plate shoulder, or stone, or any
foreign material shall be permitted under the base of rail.
be thoroughly cleaned of ballast in the rail seat area, the tie raised to firm bearing
against the rail, and re-tamped until the tie plate is bearing firmly against the rail
base.
shall comply with the construction tolerances specified in Table 662.07D.
tamping machine having at least sixteen tools, on traversing work heads, per tie. The work
heads shall be capable of penetrating cemented or fouled ballast in the event that providing
a smooth transition requires tamping existing track. A uniform squeeze shall be applied to
all tools and the tools shall remain perpendicular to the tie during the entire tamping cycle.
The tamping tools shall have sufficient length and head and face area, based on the
manufacturer’s specifications, to compact the ballast under the tie. The tamper shall be
capable of tamping both ballasted open track and ballasted special trackwork. The tamper
shall be capable of automatic lift, level, and alignment of tangent and curved track, as well
as turnouts.
662
insertions of the vibratory tamper. Tamping tools shall be inserted simultaneously
inside and outside of both running rails on opposite sides of the same tie. The ballast
under the tie shall be completely and uniformly tamped from 15 inches inside of
the rail to the end of the tie. The tamping tools and limit switches shall be set to
avoid damage to the track structure directly beneath the ballast layer.
When the tamping operation is completed, all cribs shall be filled in.
dressed by utilizing a ballast regulator to provide the ballast section shown on the Plans.
Following dressing, the ballast shall be flush with the top of tie and cribs shall be full.
There shall be no ballast material left on the base of the rails, tie plates, or top of the ties.
spikes become damaged, loose, or are otherwise not functioning as intended, the Contractor
shall remove damaged spikes, fill the resulting holes with synthetic tie plugging material
specified in Subsection 709.04(e), and drive a new spike in accordance with Subsection
damaged such that the ties are defective as defined in 49 C.F.R. § 213.109, the damaged
ties shall be removed and replaced with new ties and fastenings at no additional expense to
the Agency.
Plans and meet the alignment of the existing tracks to which it will be connected. The final track
alignment shall be continuous throughout and within the tolerances specified in this Subsection.
The actual centerline of track shall be within ± 1/4 inch of the locations indicated on the Plans.
The top of rail elevation shall be within ± 1/4 inch of the elevations indicated on the Plans.
The Contractor shall perform a conventional survey to measure the horizontal and vertical
alignment, track geometry, superelevation, and gage of the as-built track. The as-built alignment
shall be compared to the design alignment indicated on the Plans. The track shall be within the
tolerances shown in Table 662.07D. Any deviations above the allowable specified shall be
corrected at no cost to the Agency.
662
TABLE 662.07D – TRACK SURFACE AND ALIGNMENT CONSTRUCTION TOLERANCES
Track Surface and Alignment Parameter Maximum Allowable
Construction Tolerance
Deviation from uniform profile on either
rail at the mid-ordinate of a 62-foot
chord shall not exceed
1/4 in.
Deviation from zero cross level at any
point on tangents or the specified
elevation on curves shall not exceed
1/8 in.
The difference in cross level between
any two points less than 62 feet apart on
tangents or curves shall not exceed
1/4 in.
Deviation from uniform alignment at the
mid-ordinate of a 62-foot chord on
tangent and curved track shall not exceed
1/4 in.
specified in Table 662.07D, the Contractor shall perform an additional conventional survey after
corrective action has been performed to bring the track to within tolerances for final surface,
alignment, gage, cross level, and superelevation.
Track inspections shall be performed in the presence of the Engineer. The Contractor shall notify
the Engineer 7 calendar days in advance of requesting any track inspection.
Track deviations, as disclosed by the inspection described above, which exceed tolerances
specified herein shall be corrected by the Contractor at no additional cost to the Agency. Additional
inspections are required to ensure the corrections have been made.
Traffic shall not be permitted upon the newly installed track section until the track has been
accepted by the Engineer.
662.08REMOVE AND REPLACE RAIL. The Contractor shall remove existing jointed rail and furnish
and install replacement jointed rail or CWR at locations shown in the Plans. The Contractor shall supply
and install new joint bar bolts, washers, nuts, track spikes, and as many new joint bars, tie plates, rail
anchors and welds as necessary to complete this work.
Relay rail shall be subject to inspection and acceptance by the Engineer prior to installation. Relay rail
shall meet the requirements of Subsection 715.06(b).
662
Existing rail and track hardware shall be removed within the limits shown on the Plans. Existing rail and
track hardware shall be removed and disposed of as specified in Subsection 662.04.
Any material damaged or lost due directly to the Contractor’s operations shall be replaced at the
Contractor’s expense.
Sufficient ballast shall be removed from the cribs for adzing and anchor application. On ties that require
adzing, the ties shall be adzed to get a full and even bearing for new tie plates. Excessive adzing shall be
avoided. The adzed surface shall be parallel to the top of the ties.
All spike holes shall be plugged in accordance with Subsection 662.07(g)(6). All newly adzed surfaces
shall be coated with a preservative meeting the requirements of AWPA Standard M4 in accordance with
Subsection 726.01.
The replacement rail and joint bar assemblies shall be installed in accordance with Subsection 662.07(c).
Additional requirements for laying and adjusting CWR are specified in Subsections 662.07(d) and
Subsection 662.07(e). Rail shall be laid on tie plates as specified in Subsection 662.07(b). Rail shall be
spiked as specified in Subsection 662.07(g) and anchored as specified in Subsection 662.07(h). CWR shall
be welded in accordance with Subsection 662.07(f) and Subsection 662.14.
After rail installation is completed, the ballast shall be dressed in accordance with Subsection 662.07(i)(4).
662.09REMOVE AND RESET RAILROAD TRACKS. The Contractor shall remove and reset existing
jointed rail track as shown in the Contract or as directed by the Engineer. The Contractor shall furnish
new joint bars, joint bar bolts, washers, nuts, track spikes, and rail anchors.
Existing rail, ties, and track hardware shall be removed and stockpiled for reuse within the limits shown
on the Plans in accordance with Subsection 662.04.
New ballast shall be installed as required in accordance with Subsection 662.05, Subsection 662.06, and
Subsection 662.07. Track shall be reconstructed to the alignment and profile shown on the Plans using
existing rail, ties, and new track hardware in accordance with Subsection 662.07. The Contractor shall
surface, align, tamp, and dress the track as specified in Subsection 662.07(i).
662.10REMOVE AND REPLACE CROSS TIES. The Contractor shall remove existing cross ties,
properly dispose of all removed cross ties, and install new cross ties, including tie plates and tie attachment
hardware, as detailed in the Contract and as directed by the Engineer. The size of the replacement ties
shall be as indicated on the Plans.
The Contractor shall clean the tie surfaces sufficiently to permit the identification of defective cross ties.
The Contractor shall remove only those cross ties designated by the Engineer as being defective.
Cross ties shall be removed in such a manner that the existing line and surface of the rails is not disturbed.
The crib shall be excavated sufficiently to allow for the installation of the new cross tie without jacking
or otherwise disturbing the rails.
662
New cross ties shall be installed in accordance with Subsection 662.07(a), except ties shall be spaced in
accordance with the existing spacing, unless otherwise noted in the Contract.
Ties shall be plated as specified in Subsection 662.07(b). Existing rail anchors which affect the installation
of a new tie plate shall be removed and reinstalled.
Ties shall be spiked as specified in Subsection 662.07(g) with the following additional requirements:
within, the limits specified in Table 662.07A.
The Contractor shall be responsible for gaging if the existing track gage is not within the above
limits. Limits of gaging shall extend to the limits of tie replacement in the Contract.
installed on an existing joint:
fully tightened.
After the installation of the cross ties, tie plates, track spikes, and rail anchors, the
Contractor shall replace the ballast that was removed for this operation. The Contractor
shall tamp the ballast as specified in Subsection 662.07(i).
If the existing rail is CWR, the rail shall be thermally adjusted in accordance with Subsection 662.07(d)
and Subsection 662.07(e).
662.11REMOVE AND REPLACE BRIDGE TIES. The Contractor shall remove all existing bridge ties,
properly dispose of all removed existing bridge ties, and install new timber bridge ties, including tie plates
and tie attachment hardware, as detailed in the Plans and as directed by the Engineer.
Installation of new timber bridge ties required to complete the work shall be performed in accordance with
AREMA Chapter 7, Section 1.7.8; AREMA Chapter 7, Part 4; and AREMA Chapter 15, Section 8.3.
Holes for bolts connecting bridge ties to stringer top flanges shall be drilled the same diameter as the bolt.
Bridge tie to stringer top flange connectors shall be installed in accordance with the manufacturer’s
instructions.
662
All field cut ends and connection holes in timber members shall be treated with a field-applied preservative
treatment meeting the requirements of AWPA Standard M4 in accordance with Subsection 726.01.
Tie plates shall be installed on all new ties in accordance with Subsection 662.07(b).
662.12RAISE, ALIGN, AND SURFACE TRACK. The Contractor shall raise, align, and surface track
at the locations indicated in the Contract, or as directed by the Engineer.
The completed track section shall conform with Table 662.12A for the FRA class of track as defined in
the Contract.
The track shall be raised in 2-inch maximum nominal lifts unless otherwise approved by the Engineer.
TABLE 662.12A – ALLOWABLE TRACK SURFACE AND ALIGNMENT MAINT. DEVIATIONS
Track Surface and Alignment Parameter Class of Track
1 2 3 4
The runoff in any 31 feet at the end of a
raise shall not exceed 2-5/8 in. 2-1/4 in. 1-1/2 in. 1-1/8 in.
Deviation from uniform profile on either
rail at the mid-ordinate of a 62-foot
chord shall not exceed
2-1/4 in. 2 in. 1-5/8 in. 1-1/2 in.
Deviation from zero cross level at any
point on tangents or the specified
elevation on curves shall not exceed
2-1/4 in. 1-1/2 in. 1-1/4 in. 1 in.
The difference in cross level between any
two points less than 62 feet apart on
tangents or curves shall not exceed
2-1/4 in. 1-5/8 in. 1-1/2 in. 1-1/4 in.
Deviation from uniform alignment at the
mid-ordinate of a 62-foot chord on
tangent and curved track shall not exceed
3-3/4 in. 2-1/4 in. 1-1/4 in. 1 in.
662
accordance with Subsection 622.07(i) with the following modifications:
the Contractor shall tamp the tie up tight so that it is in full contact with the base of the rail.
No portion of the tie plate shoulder, stone, or any foreign material shall be permitted under
the base of rail at these locations.
the track surface to the geometric parameters in Table 662.12A for the designated FRA
class as indicated in the Contract.
comply with surface and superelevation tolerances specified in Table 662.12A for the
designated class of track.
in a situation where there is greater than allowable deviations in the runoff of the top of rail
elevations due to meeting the existing grade at a highway grade crossing, bridge, or turnout,
the Contractor shall surface out of face consistent with designated FRA class of track
requirements and tolerances or as directed by the Engineer. Such work shall be incidental
to the Contract.
with Subsection 662.07(d) and Subsection 662.07(e).
662.13TEMPORARY RAIL CONNECTIONS. The Contractor shall furnish and install temporary
connections between the new rail and existing rail to allow for the passage of a train (during work periods
of non-exclusive and interruptible access) and at the end of an exclusive occupancy period. The closure
rail shall be connected to the new rail by a compromise joint if the rails are of different sections. The
connection rail shall have a full number of bolts and spikes.
662
THERMITE WELDING
personnel. The training shall include specific training provided by the welding kit manufacturer.
Training shall include classroom and hands-on instruction with the course curriculum set by the
manufacturer.
The Contractor shall provide for a representative of the welding kit manufacturer to be on call with
2 working days’ notice to assist in case any unusual problems arise in the field. The welding kit
manufacturer shall be prepared to provide for laboratory testing needed to solve a problem and
shall have the capability of tracking their kit materials backward through the chain of production.
the weld kit, weld procedure, and each welding crew shall be qualified as specified below.
Welding crews shall prepare, in accordance with the approved method and procedure for
thermite field welding, at least three samples of a thermite weld. Each welding crew shall
perform at least one of each type of sample weld. Sample welds shall join two pieces of
each type of running rail used in the Contract, each a minimum of 30 inches and a
maximum of 36 inches in length.
Sample weld testing and inspection shall be performed by an approved certified
independent testing laboratory. The Engineer may audit operations to ensure that
inspection and tests are being performed in accordance with the specified procedures.
The Contractor shall test three sample welds. A manual ultrasonic test shall be performed
on all sample welds from each type of rail as specified in Subsection 662.14(a)(2). Sample
welds shall be ultrasonically inspected in accordance with ASTM E164. Acceptance criteria
for this test shall be as specified in Subsection 662.14(a)(2)e. and Subsection
(a)(2)g
Approval of the weld kit, welding process, and welding crews will be contingent upon all
sample welds satisfying the specified requirements. Should any sample weld fail to satisfy
the specified requirements, the welding process, the welding crew, or both, will not be
qualified for the work.
A supervisor shall be employed for each welding crew who has been trained and certified
for performing thermite field welding by the manufacturer supplying the weld kits. Should
the supervisor of the welding crew be replaced during the work, the welding crew shall be
re-qualified under the new supervisor.
If the Contractor changes the manufacturer of the welding kits or welders during the work
of the Contract, the sample weld testing shall be completed again.
662
inspected as specified herein. All welds shall be ultrasonically tested by a certified testing
laboratory as specified in this subsection.
Thermite welds shall be visually and dimensionally inspected as soon as the weld has been
completed.
Manual ultrasonic testing of thermite welds in track designated as in-revenue service shall
be completed within 24 hours of weld completion.
Manual ultrasonic testing of thermite welds in track designated as out-of-revenue service
shall be completed within 30 days of the date of welding but in all cases prior to the
resumption of train operations.
The ultrasonic testing calibration process shall be able to permit detection of defects of
size, type, and location described under the acceptance criteria. The test procedure and
equipment shall include, but not be limited to, the following:
least every hour.
probes or cables.
catch configuration.
probes.
probe.
662
pitch-catch configuration.
up and down to cover the entire cross-section of the weld.
from the center of the weld so that the beam is following the path as defined
in the approved test procedure.
probe from side to side.
weld.
form.
accepted in the head, web, or base of the rail.
determine conformance with the alignment and finishing tolerances
specified herein.
662
be checked for obvious failures such as an incomplete weld.
physical inspections shall be made by the Contractor to verify acceptance
criteria.
to be considered acceptable by the Engineer during the physical inspection.
which have been ground.
except to remove notches created by upset conditions. Sharp protrusions
and gouges shall be blended into the rail and weld collar contour to
eliminate possible stress risers.
of 200°F or less, shall not exceed 0.060 inches. No dip camber will be
allowed.
rail head, at a rail temperature of 200°F or less, shall not exceed 0.060
inches.
the parent section of rail head surface will be allowed.
section of new or like relay rail, and welded in place, at no additional cost to the
Agency.
detector car.
662
welds shall be made to join jointed rail or CWR. Thermite welds will be required in
turnouts and in areas of bituminous concrete pavement crossings to eliminate rail joints.
The ends of rails to be welded shall be saw-cut. Torch cutting of rails will not be allowed.
If plug rails are required to meet the requirements, or to replace a defective weld, the
minimum length of the plug rail shall be 19-1/2 feet.
Thermite welds shall not be located within the following areas in standard track work. In
the case of special trackwork, some exceptions will be allowed with the approval of the
Engineer.
staggered a minimum of 4 tie cribs from any thermite or flash butt weld in the
opposite rail.
clearance prior to the welds being made.
feet on curves) or as directed by the Engineer.
require minimum preheating.
Rail ends shall be saw-cut at right angles to the rail. The surface of the rail shall be cleaned
for a length of approximately 6 inches from each end, so that the surface of the rail is free
of all grease, dirt, loose oxide, scale, and moisture. Burrs and lipped metal which would
interfere with the proper fit of molds shall be removed.
662
Rails shall be aligned with respect to alignment prior to welding.
Proper rail end alignment shall be achieved by the use of an alignment device designed and
manufactured for this purpose. In no case will the use of track jacks or track spikes be
allowed for rail end alignment.
Striking of rail with blunt tools, such as a maul, is prohibited with the exception of brass
hammers.
The Contractor shall ensure that rail ends are secured against longitudinal, vertical, lateral,
or twisting movement during and immediately after the welding process. Rail pullers or
expanders shall be used to prevent movement. Rail clips or anchors shall be installed if
there is a chance of longitudinal movement.
At the time of field welding, the rail gap shall be as specified by the manufacturer of the
weld kit. A hydraulic rail puller or expander shall be used to establish the proper rail end
gap at all thermite weld locations.
Field welds shall not be made when the ambient temperature is below 40°F or during
inclement weather such as rain, mist, sleet, or snow unless approved by the Engineer and
in compliance with the Operating Railroad’s CWR plan.
The weld shall not be subjected to a sudden strain by releasing hydraulic pressure too
quickly. The rail puller or expander shall be left in place until the rail has cooled to below
500°F. Any movement of the rail before the weld has cooled to at least 500°F may result
in the failure of the weld.
When welding rail in track on lines in service, sufficient time to complete welding shall be
allowed so that the surface finish and temperature of the welded joint will permit safe
operation of scheduled trains without delay to service. The temperature of the welded joint
shall be 200°F or less before rail traffic is allowed to pass over the weld.
When welding rails in track on lines in service, the Contractor shall ensure that rail
fastenings and anchors are properly installed prior to restoration of service.
Thermite field welds shall be made in accordance with and shall not deviate from the
manufacturer’s recommendations and AREMA Chapter 4.
662
otherwise specified by the manufacturer:
remove weld upset. Use of a saw, cutting torch, or other handheld devices
is prohibited.
finish grind the top and sides of the weld. Use of a handheld grinder is
prohibited.
to remove notches created by upset conditions, sharp protrusions, and
gouges. These shall be blended into the rail and weld collar contour to
eliminate possible stress risers. Defects visible to the unaided eye shall be
removed by grinding. If removal by grinding cannot be accomplished
without damaging rail, the weld shall be removed. Precautions shall be
taken to avoid excessive pressure during grinding of a weld in order to
prevent overheating of the rail surface.
than 200°F.
cooled to below 200°F prior to grinding, the temperature rise due to
grinding shall not exceed this temperature.
introduced into the sides of the weld where it will be ground.
to the operation of trains over the weld.
permanent metal marker and the required information shall be recorded in conformance
with these specifications.
records as specified in Subsection 662.03.
662
662.15METHOD OF MEASUREMENT. The quantity of Railroad Ballast to be measured for payment
will be the number of tons placed in the complete and accepted work, as determined based on vehicle
loads. A load ticket shall be furnished to the Engineer for each load delivered to the job site.
The quantity of Remove and Replace Bridge Ties of the size specified in the Contract to be measured for
payment will be the number of existing bridge ties removed and replaced in the complete and accepted
work.
The quantity of Remove and Replace Cross Ties of the size specified in the Contract and as directed by
the Engineer to be measured for payment will be the number of existing cross ties removed and replaced
in the complete and accepted work.
The quantity of Remove and Replace Switch Ties to be measured for payment will be the total linear feet
of existing switch timbers removed and replaced in the complete and accepted work.
The quantity of Remove and Replace Jointed Rail to be measured for payment of the type specified will
be the number of linear feet of rail installed in the complete and accepted work. Individual rails will be
measured separately.
The quantity of Remove and Reset Jointed Railroad Track to be measured for payment will be the number
of linear feet of track removed and reset in the complete and accepted work. Individual rails will not be
measured separately. Measurement will be along the centerline of the track.
The quantity of Remove Railroad Track to be measured for payment will be the number of linear feet of
track removed in the complete and accepted work. Individual rails will not be measured separately.
Measurement will be along the centerline of the track.
The quantity of Ballasted Track Construction with Jointed Rail to be measured for payment will be the
actual number of linear feet of track constructed to final grade in the complete and accepted work.
Individual rails will not be measured separately. Measurement will be along the centerline of the track.
The quantity of Ballasted Track Construction with CWR to be measured for payment will be the actual
number of linear feet of track constructed to final grade in the complete and accepted work. Individual
rails will not be measured separately. Measurement will be along the centerline of the track.
The quantity of Remove Jointed Rail and Install CWR to be measured for payment of the type specified
will be the number of linear feet of track installed in the complete and accepted work. Individual rails will
not be measured separately. Measurement will be along the centerline of the track.
662
The quantity of Raise, Align, and Surface Track to be measured for payment will be the number of linear
feet of track raised, aligned, and surfaced to final grade in the complete and accepted work. Individual
rails will not be measured separately. Measurement will be along the centerline of the track. The
Contractor shall perform as many raising and surfacing passes to achieve final grade or as directed by the
Engineer to bring the track to the designated design standard as indicated in the Contract. Multiple passes
will not be measured separately for payment.
The quantity of Gaging Track to be measured for payment will be the number of linear feet of track gaged.
Measurement will be taken along the centerline of the track.
662.16BASIS OF PAYMENT. The accepted quantity of Railroad Ballast will be paid for at the Contract
unit price per ton. Payment will be full compensation for furnishing, transporting, handling, testing,
placing, and tamping the materials specified, and for furnishing all labor, tools, equipment, and incidentals
necessary to complete the work.
The accepted quantity of Remove and Replace Bridge Ties will be paid for at the Contract unit price per
each. Payment will be full compensation for furnishing, transporting, handling, and placing the material
specified, including removal and disposal of old ties, furnishing and installing tie plates where required,
furnishing new ties, spikes, and tie plugging material as required, and for furnishing all labor, tools,
equipment, and incidentals necessary to complete the work.
The accepted quantity of Remove and Replace Cross Ties will be paid for at the Contract unit price per
each. Payment will be full compensation for furnishing, transporting, handling, and placing the material
specified, including excavation, removal, and disposal of old ties, furnishing and installing tie plates where
required, furnishing new ties, spikes, and tie plugging material as required, and for furnishing all labor,
tools, equipment, and incidentals necessary to complete the work. Railroad Ballast will be paid for
separately.
The accepted quantity of Remove and Replace Switch Ties will be paid for at the Contract unit price per
linear foot. Payment will be full compensation for furnishing, transporting, handling, and placing the
material specified, including excavation, removal, and disposal of old ties, furnishing and installing tie
plates where required, furnishing new ties, spikes and tie plugging material as required, and for furnishing
all labor, tools, equipment, and incidentals necessary to complete the work. Railroad Ballast will be paid
for separately.
The accepted quantity of Remove and Replace Jointed Rail will be paid for at the Contract unit price per
linear foot of rail. Payment will be full compensation for removing existing rail, tie plates, joint assemblies,
track spikes, and rail anchors; furnishing, transporting, distributing, handling, and installing the materials
specified, including jointed rail, tie plates, spikes, and other miscellaneous materials; and for furnishing
all labor, tools, equipment, and incidental necessary to complete the work.
662
The accepted quantity of Remove and Reset Jointed Railroad Track will be paid for at the Contract unit
price per linear foot of track. Payment will be full compensation for supplying new rail hardware,
removing, handling, and resetting rail, ties, and rail hardware, and for furnishing all labor, tools,
equipment, and incidentals necessary to complete the work.
The accepted quantity of Remove Railroad Track will be paid for at the Contract unit price per linear foot
of track. Payment will be full compensation for furnishing all materials, labor, tools, equipment, and
incidentals necessary to complete the work.
The accepted quantity of Ballasted Track Construction with Jointed Rail will be paid for at the Contract
unit price per linear foot of track. Payment will be full compensation for furnishing, transporting,
distributing, handling, and installing the materials specified, including jointed rail, tie plates, spikes, and
other miscellaneous materials, and for furnishing all labor, tools, equipment, and incidental necessary to
complete the work. Railroad Ballast will be paid for separately.
The accepted quantity of Ballasted Track Construction with CWR will be paid for at the Contract unit
price per linear foot. Payment will be full compensation for furnishing, transporting, distributing,
handling, and installing the materials specified, including CWR, tie plates, spikes, and other miscellaneous
materials, and for furnishing all labor, tools, equipment, and incidental necessary to complete the work.
The costs for thermite welding, all preparation and training activity will not be paid separately but shall
be considered incidental to this item. Railroad ballast will be paid for separately.
The accepted quantity of Remove Jointed Rail and Install CWR will be paid for at the Contract unit price
per linear foot. Payment will be full compensation for removing existing rails; installing new CWR;
installing OTM such as tie plates, anchors, and spikes; scrapping of non-salvaged track materials; de-
stressing rail as required; and for furnishing all labor, tools, equipment, and incidentals necessary to
complete the work. Thermite welding will be considered incidental to this item.
The accepted quantity of Raise, Align, and Surface Track will be paid for at the Contract unit price per
linear foot. Payment will be full compensation for furnishing all materials, labor, tools, equipment, and
incidentals necessary to complete the work. Verification surveys, corrections of track deviations, and re-
inspections shall be considered incidental to this item. Tightening of all loose bolts within the limits of
this item shall be considered incidental to this item. Multiple passes will be considered incidental to the
actual length of track feet raised, aligned, and surfaced to final grade. Railroad Ballast will be paid for
separately.
The accepted quantity of Gaging Track will be paid for at the Contract unit price per linear foot. Payment
will be full compensation for furnishing all materials, labor, tools, equipment, and incidentals necessary
to complete the work. Replacing missing spikes with new track spikes will be considered incidental to this
item.
The cost of temporary rail connections will be considered incidental to the other Contract items of this
section.
662
Payment will be made under:
Pay Item Pay Unit
662.0010 Railroad Ballast.........................................................................................Ton
10 Remove and Replace Bridge Ties .............................................................Each
20 Remove and Replace Cross Ties...............................................................Each
30 Remove and Replace Switch Ties.............................................................Linear Foot
00 Remove and Replace Jointed Rail ............................................................Linear Foot
50 Remove and Reset Jointed Railroad Track ...............................................Linear Foot
00 Remove Railroad Track ............................................................................Linear Foot
50 Ballasted Track Construction with Jointed Rail .......................................Linear Foot
60 Ballasted Track Construction with CWR .................................................Linear Foot
662.0400 Remove Jointed Rail and Install CWR .....................................................Linear Foot
10 Raise, Align, and Surface Track ...............................................................Linear Foot
50 Gaging Track ............................................................................................Linear Foot
663
6-269SECTION 663 – RAILROAD -HIGHWAY GRADE CROSSINGS
663.01DESCRIPTION . This work includes rehabilitation of existing railroad -highway grade crossings
and construction of new full depth bituminous concrete or precast concrete railroad -highway grade crossings, including furnishing all required materials and necessary incidentals in accordance with the Contract and as directed by the Engineer.
663.02MATERIALS . Materials shall meet the requirements of the following subsections:
Aggregate for Railroad Ballast ................................ ................................ .................. 704.03 Cross Ties ................................ ................................ ................................ ................... 709.04( c) Corrugated Polyethylene Pipe (CPEP) ................................ ................................ ......710.03 Polyvinyl Chloride (PVC) Plastic Pipe ................................ ................................ ......710.05 New Rail ................................ ................................ ................................ .................... 715.06(a) Relay Rail ................................ ................................ ................................ ................... 715.06(b) Other Track Material (OTM) ................................ ................................ ..................... 715.0 8 Bituminous Concrete Mixtures ................................ ................................ .................. 716.02 Geotextile under Railroad Ballast ................................ ................................ .............. 720.03 Precast Concrete Grade Crossing Systems ................................ ................................ 781.01 Rubbe r Rail Seal ................................ ................................ ................................ ........ 781.02
663.03SUBMITTALS . The following information shall be prepared and submitted for review and
approval by the Engineer . Submittals shall meet the requirements of Subsection 105.0 6.
staging, any proposed temporary paving or temporary detours, and material storage sites. The work shall comply with the approved traffic control plan.
related sections and production quality control documentation.
operation.
construction affects existing CWR, the Contractor shall submit a plan (CWR Maintenance Plan) for maintenance of the Operating Railroad’s neutral temperature in accordance with their CWR program or submit a plan to adjust the CWR to the Operating Railroad’s neutral temperature.
Get an email when 662 changes
Vermont revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.