M 41-10 Page 2-72-03 Roadway Excavation and Embankment
2-03.1 Description
The Work described in this section, regardless of the nature or type of the materials encountered, includes excavating and grading the Roadway, excavating in borrow pits, excavating below grade, excavating channels and ditches, removing slide material, and disposing of all excavated material. These activities may be performed in making cuts, embankments, slopes, Roadway ditches, approaches, parking areas, Highway-driveway intersections, and in completing related Work. The Work includes the removal of pavement, sidewalks, curbs and gutters as described in Section 2-02 when these items lie within an excavation area. The Work excludes these items if they are designated as pay items in the Contract:
2-03.2 Vacant
2-03.3 Construction Requirements
2-03.3(1) Widening of Cuts
If routine cuts do not supply enough material to form the embankment, the Contractor shall obtain more material from areas inside or outside the Right of Way and/or from widening one or both sides of existing cuts as determined by the Engineer. The Contractor shall dress the sides of the cuts to any slopes the Engineer may require. If the Contractor has dressed a cut before the Engineer determines to widen it, the Contracting Agency will pay for the resloping as provided in Section 1-04.4 . In addition, material obtained from areas beyond the cuts shown in the Plans that result in additional haul will be paid by the Contracting Agency as provided in Section 1-04.4 .
2-03.3(2) Rock Cuts
2-03.3(3) Normally cuts will be made from the top, lift by lift, to protect the rock
bench that will remain. The Contractor shall be responsible for methods used and for any damage caused to the Roadbed, regardless of any previous approvals by the Engineer.
2-03 Roadway Excavation and Embankment
M 41-10 Page 2-9e. Controlled blast holes shall extend a minimum of 30 feet beyond the limits of the production holes to be detonated, or to the end of the cut as applicable.
2-03.3(4) Sluicing
The Contractor shall not excavate by sluicing unless the Special Provisions specifically call for it.
2-03.3(5) Slope Treatment
The tops of all Roadway cut slopes, except solid rock cuts, shall be rounded in accordance with the Standard Plan s. Unless otherwise noted in the Plans or Special Provisions, Class A slope treatment shall be utilized. If a layer of earth covers a rock cut, the slope shall be rounded above the rock as if it were an earth slope. When the Contractor removes stumps or any embedded material from the rounded area, the void shall be backfilled and stabilized to prevent erosion. All Work required to complete slope treatment, including excavation, haul, and slope rounding, shall be included in the unit Bid price for Roadway excavation.
2-03.3(6) Deposit of Rock for the Contracting Agency’s Use
At the Engineer’s direction, the Contractor shall deposit excavated rock at the roadside or elsewhere. If this requires the Contractor to use material that would otherwise have gone into an embankment, the Contracting Agency will pay for the extra cubic yards of excavation needed to complete the embankment. Any such rock deposit shall be Contracting Agency property. The Contractor shall be responsible for safekeeping the deposit until the Contracting Agency has removed it or until the Contract is completed.
2-03 Roadway Excavation and Embankment
M 41-10 Page 2-112-03.3(7) Disposal of Surplus Material
2-03.3(7)A General
The Contractor shall haul all excavation to the nearest embankment unless the Engineer declares the hauling distance to be too great. If excavation yields more material than needed for nearby embankments, the Contractor shall dispose of the excess in keeping with the Special Provisions or as the Engineer directs.
2-03.3(7)B Haul
When the Contract includes a payment item for haul, the Contracting Agency will pay as follows for hauling excess excavation to a disposal site:
2-03.3(7)C Contractor-Provided Disposal Site
If the Contracting Agency provides no waste site, but requires disposal of excess excavation or other materials, the Contractor shall arrange for disposal at no expense to the Contracting Agency, except as provided in Section 2-03.3(7)B , item 2 . The Contractor shall acquire all permits and approvals required for the use of the disposal sites before any waste is hauled off the project. The Contractor shall submit a Type 1 Working Drawing consisting of copies of the permits and approvals for any disposal sites to be used. The cost of any such permits and approvals shall be included in the Bid prices for other Work. Disposal of excess material within a wetland area will not be allowed without a Section 404 permit issued by the U.S. Corps of Engineers and approval by the local agency with jurisdiction over the wetlands. The Contractor shall protect, indemnify, and save harmless the Contracting Agency from any damages that may arise from the Contractor’s activities in making these arrangements. Such indemnity shall be in accordance with RCW 4.24.115 as amended by CH. 305, Laws of 1986. Any action required to satisfy any permit and/or any approval requirements in a Contractor-provided disposal site shall be performed by the Contractor at no additional expense to the Contracting Agency. Reclamation of a Contractor-supplied waste site must conform to the requirements of Section 3-03 .
2-03.3(8) Wasting Material
If, against the Engineer’s orders, the Contractor wastes material needed for the embankment, it shall be replaced at no expense to the Contracting Agency with material the Engineer approves.
2-03.3(9) Roadway Ditches
At each transition from cut to fill, the Contractor shall divert any Roadway ditch away from the embankment in natural ground. Ditches shall never permit water to flow into or upon embankment material. Roadway Excavation and Embankment 2-03 Page 2-12 M 41-102-03.3(10) Selected Material When the Contract or the Engineer calls for it, selected material shall be used for finishing the top part of the Subgrade, for structural or other backfill, or for other purposes. Unless the Special Provisions specify otherwise, the Engineer may identify as “selected” any material excavated within the right-of-way, including the excavation of local borrow. Direct Hauling – If it is practical, the Contractor shall haul selected material immediately from excavation to its final place on the Roadbed. The Contracting Agency will pay for such Work at the unit Contract prices for excavating, hauling, watering, and compacting. Delayed Excavation – If it is impractical to haul selected material to its final place at once, the Contractor shall delay excavation until the placement will be workable. The Contracting Agency will not pay extra for delayed excavation. Stockpiling – The Engineer may allow the Contractor to stockpile selected materials if delaying the excavation will hamper grading or force impractical movements of equipment. In this case, the Engineer will direct where and when the Contractor shall excavate, stockpile, haul, and place the selected materials. Sections 2-03.4 and 2-03.5 describe how the Contracting Agency will measure and pay for excavating and hauling these stockpiled selected materials. The neat line volume of material removed will provide the basis for measuring material taken from the stockpile.
2-03.3(11) Slides
If a slide occurs on a finished slope before final acceptance of the Work, the Contractor shall remove or replace the slide material. The Contractor shall also refinish the slope to the condition and with the materials required by the Engineer. The Contracting Agency will pay for the excavation at the unit Contract price and for resloping on a force account basis. The Engineer may authorize payment for the excavation by agreed price or force account if:
2-03.3(12) Overbreak
Overbreak includes that part of any material excavated, displaced, or loosened outside the staked or reestablished slope or grade. Such material is considered overbreak whether its movement resulted from blasting, from the character of the material itself, or from any other cause. Overbreak, however, does not include material from slides as described in If the Engineer does not approve use of the overbreak, the Contractor shall remove, haul, and dispose of it at no expense to the Contracting Agency. In this case, the Contractor shall follow the procedure for handling surplus described in Section 2-03.3(7) . If the Engineer approves, the Contractor may use overbreak:
2-03 Roadway Excavation and Embankment
M 41-10 Page 2-13borrow excavation, whichever costs less. The Engineer will include haul to be paid as in the original Proposal in comparing the costs under the two payment methods.
2-03.3(13) Borrow
Borrow is the excavation of material outside the Roadway prism or outside the limits of any other excavation area required by the Contract. Before any borrow site can be used, it must be measured and approved by the Engineer. Any material excavated from a borrow site before the site is measured will not be paid for. The widening of Roadway cuts and ditches will be considered Roadway excavation, not borrow. If the Contract documents designate borrow sources, the Contractor may utilize those sources or may obtain borrow from other sites. If borrow is obtained from a Contractor- provided site, there will be no additional cost to the Contracting Agency beyond the Contract unit price for the excavated borrow material. There will be no payment for aeration of the borrowed material from a Contractor-provided site, even if the Contract contains an item for aeration and even if the Contract documents designate borrow sources. If neither the Plans nor the Special Provisions name a source for borrow, the Contractor shall provide a source at no expense to the Contracting Agency. The Contractor shall reclaim all borrow sites, Contracting Agency-owned, Contracting Agency-supplied, or obtained by the Contractor, in keeping with Section 3-03 .
2-03.3(14) Embankment Construction
The Contracting Agency classifies embankment construction as:
2-03.3(14)B Earth Embankment Construction
The Contractor shall place earth embankments in horizontal layers of uniform thickness. These layers shall run full width from the top to the bottom of the embankment. Slopes shall be compacted to the required density as part of embankment compaction. During grading operations, the Contractor shall shape the surfaces of embankments and excavations to uniform cross-sections and eliminate all ruts and low places that could hold water. The Contractor shall raise the center of an embankment above the sides. When the surface of an embankment intersects a side hill, the surface shall be sloped away at a rate not to exceed 20:1.
2-03 Roadway Excavation and Embankment
M 41-10 Page 2-152-03.3(14)C Compacting Earth Embankments This section describes three methods (A, B, and C) for building earth embankments. The Contractor shall use Method B unless the Special Provisions require another method. Method A – Each embankment shall be made of layers no more than 2 feet thick. The Contractor shall compact each layer by routing loaded haul equipment over its entire width. If the Engineer approves, the Contractor may use end dumping to begin placing a side hill fill too narrow for hauling equipment. When the fill is wide enough, the remaining layers shall be compacted by the loaded hauling equipment. Method B – The top 2 feet of each embankment shall be compacted to 95 percent of the maximum density as determined by the compaction control tests described in Section
2-03.3(14)D All material below the 2-foot level shall be compacted to 90 percent of the
same maximum density. In the top 2 feet, horizontal layers shall not exceed 4 inches in depth before compaction. No layer below the top 2 feet shall exceed 8 inches in depth before compaction. The Contractor shall use compacting equipment approved by the Engineer. Method C – Each layer of the entire embankment shall be compacted to 95 percent of the maximum density as determined by the compaction control tests described in Section
2-03.3(14)D .
In the top 2 feet, horizontal layers shall not exceed 4 inches in depth before compaction. No layer below the top 2 feet shall exceed 8 inches in depth before compaction. The Contractor shall use compacting equipment approved by the Engineer. Under Methods B or C, the Engineer may permit the Contractor to increase layer thickness up to 18 inches before compaction, provided:
2-03.3(14)D Compaction and Moisture Control Tests
Maximum density and optimum moisture content shall be determined by one of the following methods:
2-03.3(14)E Unsuitable Foundation Excavation
When the Contract or the Engineer requires it, the Contractor shall excavate unstable natural ground before building any embankment over it. This unstable material may include peat, muck, swampland, buried logs and stumps, or other material not fit for an embankment base. The Contractor shall excavate such material to the boundaries set by the Engineer. The Work will not be considered unsuitable foundation excavation if the materials:
2-03.3(14)F Vacant
2-03.3(14)G Backfilling
When water fills an area after the removal of soft or unstable materials, the Contractor shall, if possible, drain the site so that any backfill may be compacted. If drainage is not possible, the Contractor shall use granular material for backfilling in water, including areas where blasting has displaced the soft material. The Special Provisions may require other backfilling methods. The costs of pumping or digging temporary drainage ditches shall be incidental to and included in other items of Work that apply.
2-03.3(14)H Prefabricated Vertical Drains
The Contractor shall furnish all necessary labor, equipment and materials, and perform all operations necessary for the installation of prefabricated vertical drains in accordance with the details shown in the Plans and with the requirements of these Specifications. The prefabricated drain shall consist of a continuous plastic drainage core wrapped in a nonwoven geotextile material as specified in the Contract. The drains shall be free of defects, rips, holes, or flaws. During shipment and storage, the drain shall be wrapped in a heavy-duty protective covering. The storage area shall protect the drain material from sunlight, mud, dirt, dust, debris, and detrimental substances. Manufacturer certification shall be provided for all drain materials delivered to the project. Vertical drains shall be staked by the Contractor and constructed prior to embankment construction. Prior to installation of vertical drains, a sand drainage blanket shall be placed on the ground surface for use as a working platform. This platform shall have a minimum depth of 2 feet and shall consist of uncompacted material meeting the requirements of Section 9-03.13(1) .
2-03 Roadway Excavation and Embankment
M 41-10 Page 2-17Vertical drains shall be installed with equipment that will cause a minimum of subsoil disturbance. A mandrel or sleeve shall be advanced through the subsoil using vibratory, constant load, or constant rate of advance methods. The mandrel shall have a maximum cross-sectional area of 14 square inches, shall protect the prefabricated drain material from tears, cuts, and abrasions during installation, and shall be provided with an “anchor” plate or rod. The “anchor” plate or rod shall provide sufficient strength to prevent the soil from entering the bottom during installation and shall anchor the bottom of the drain at the required depth when the mandrel is removed. Use of falling weight impact hammers or jetting will not be allowed within the compressible subsoil to be drained. The prefabricated drains shall be installed vertically from the working surface to the required elevations and in a sequence that will not require equipment to travel over previously installed drains. The Contractor shall provide the Engineer with a suitable means of verifying the plumbness of the equipment and determining the depth of the drain at any time. The equipment shall not deviate more than 0.25 inches per foot from vertical. Splices or connections in the prefabricated drain material shall be done in a professional manner to ensure continuity of the wick material. The prefabricated drain shall be cut to leave at least 6 inches protruding above the working platform at each drain location. Where obstructions are encountered which cannot be penetrated the Contractor shall abandon the hole. A maximum of two attempts shall be made to install a new drain within 18 inches of the obstructed hole. Drains that otherwise deviate from the Plan location by more than 6 inches, or that are damaged or improperly installed, will be rejected. Installation of the drains should consider and be coordinated with the geotechnical instrumentation shown in the Plans. Special care shall be taken when installing drains near instrumentation already in place. Replacement of instrumentation damaged by the Contractor will be the responsibility of the Contractor. The Contractor shall demonstrate that the equipment, method, and materials produce a satisfactory installation in accordance with these Specifications. For this purpose, the Contractor shall be required to install trial drains at different locations within the Work area. The Contractor shall submit a Type 2 Working Drawing consisting of details of the sequence and method of installation. The submittal shall, at a minimum, contain the dimensions and length of mandrel, a detailed description of the proposed method(s) for overcoming obstructions, and the proposed method(s) for splicing drains. Approval by the Engineer will not relieve the Contractor of the responsibility to install prefabricated vertical drains in accordance with the Plans, Special Provisions, and these Specifications. If, at any time, the Engineer considers the method of installation does not produce a satisfactory drain, the Contractor shall alter the method and equipment as necessary.
2-03.3(14)I Embankments at Bridge and Trestle Ends
This Work consists of filling around the ends of trestles and bridges, the area defined in Section 1-01.3 . The Contractor shall begin and complete this Work as soon as possible after each bridge is completed or when the Engineer requires. The Contractor shall select fill material from the excavation sources elsewhere on the project. Bridge Approach Embankments shall be compacted to at least 95 percent of the maximum density as determined by the tests described in Section 2-03.3(14)D . In any embankment area where piles will be installed, the Contractor shall remove all solid material, rocks, broken concrete, etc., larger than 3 inches across that would interfere with pile driving. Roadway Excavation and Embankment 2-03 Page 2-18 M 41-10To prevent the bridge from being distorted or displaced, the Contractor shall place backfill evenly around all sides and parts of the Structure. The Contractor shall not backfill any abutment prior to placing the Superstructure. After the Superstructure is in place, use of small compactors may be required to compact the backfill around the Structure. Embankments and backfill behind the abutments shall be brought up in layers and compacted concurrently. The difference in backfill height against each abutment shall not exceed 2 feet unless otherwise allowed by the Engineer. The Contractor may request to place the abutment backfill (either full or partial height) prior to placement of the Superstructure by submitting Type 2E Working Drawings consisting of calculations confirming that the abutment is stable, both for overturning and sliding, without the Superstructure in place. The stability calculations shall assume a loading of 30 lbs/ft3 equivalent fluid pressure and include at least a 2-foot surcharge for the backfill placement equipment. If the abutment backfill is allowed to be placed prior to completion of the Superstructure, the Contractor shall bear any added cost that results from the change. The Contractor shall build the embankment under the bridge to the dimensions shown in the Standard Plans or detailed in the Plans. Cost related to all Work described in this section shall be incidental to other Work and included in the unit Contract prices that apply.
2-03.3(14)J Gravel Borrow Including Haul
When required by the Plans or the Engineer, the Contractor shall use gravel borrow meeting the requirements of Section 9-03.14(1) to:
2-03.3(14)K Select or Common Borrow Including Haul
When required by the Plans or the Engineer, the Contractor shall use select borrow meeting the requirements of Section 9-03.14(2) , or common borrow meeting the requirements of Section 9-03.14(3) to:
2-03.3(14)C and 2-03.3(14)D .
2-03.3(14)L Embankment Widening for Guardrail
Embankments widened for the installation of beam guardrail shall be terraced in accordance with the requirements for hillside terraces in Section 2-03.3(14) . Compaction shall be in accordance with Method A, as specified in Section 2-03.3(14)C . Guardrail posts shall not be installed until the embankment widening is completed and compacted.
2-03 Roadway Excavation and Embankment
M 41-10 Page 2-192-03.3(14)M Excavation of Channels and Ditches Channel Excavation includes open excavations 8 feet wide or more at the bottom, but excludes channels that are part of the Roadway. Ditch Excavation includes open excavations less than 8 feet wide at the bottom, but excludes ditches that are part of the Roadway. Before excavating channels or ditches, the Contractor shall clear and grub the area in accordance with Section 2-01 .
2-03.3(15) Aeration
The Contracting Agency may include aeration as a Contract item if material from test holes in excavation or borrow sites is too wet to compact properly. Even if the Contract includes such an item, the Contractor shall make every effort to reduce the need for aeration. The Contractor shall do so by using methods known to be effective in building embankments with wet materials. Such methods include open ditching to drain excavation areas or alternating layers of wet and dry materials. These and similar methods will be incidental to excavation and their costs shall be included in the unit Contract price for Roadway excavation, for borrow excavation (including haul), and for haul. If aeration is not a Contract item, its cost shall be incidental to and included in the excavation and embankment items. Aeration Equipment – The Engineer may direct the Contractor to use aeration equipment in these areas: Roadway excavation, borrow sites, or embankments. The Contracting Agency does not guarantee the moisture-reducing effectiveness of any single type of equipment. The Engineer may, however, require the use of any type that will best aerate a given area. If the Contractor uses any of the following types of equipment, it shall meet these minimum requirements:
2-03.3(16) End Slopes
The Engineer will determine when and where to build end slopes, whether these occur at the beginning or end of a project, at the borders of excavation or embankments, at bridge ends, or elsewhere. The Contractor shall build end slopes not detailed in the Plans to the line and grade designated by the Engineer regardless of centerline limits shown in the Plans. All Work to complete and maintain these end slopes shall be considered as Work to be performed under the Contract. Roadway Excavation and Embankment 2-03 Page 2-20 M 41-102-03.3(17) Snow Removal If snow deep enough to interfere with the Work covers a cut or an embankment, the Contractor shall remove and deposit it outside the slope stakes. Snow removal must be done at least 100 feet ahead of excavation and embankment Work. The Contractor shall remove snow at no expense to the Contracting Agency.
2-03.3(18) Stepped Slope Construction
When the Plans or the Engineer requires it, the Contractor shall shape slopes cut in soft rock to a stepped pattern conforming closely to the typical cross-section in the Plans. Stepped slopes shall meet these requirements:
2-03.3(19) Removal of Pavement, Sidewalks, Curbs, and Gutters
The requirements of Section 2-02.3(3) shall also apply when pavements, sidewalks, curbs, and gutters lie within an excavation.
2-03.4 Measurement
Roadway excavation, channel excavation, ditch excavation, unsuitable foundation excavation, and common borrow items will be measured by the cubic yard. All excavated material will be measured in the position it occupied before the excavation was performed. An original ground measurement will be taken using cross-section or digital terrain modeling survey techniques. For Roadway excavation, channel excavation, and ditch excavation items, the original ground will be compared with the planned finished section shown in the Plans. Slope/ground intercept points defining the limits of the measurement will be as staked. For unsuitable foundation excavation and common borrow items, the original ground will be compared with a survey of the excavation area taken after the Work is completed. When the Contracting Agency requires excavated material to be stockpiled, re-excavated and moved again, a second measurement will be made, adding quantity for the same item used in the original excavation. The second measurement will be a comparison of the original cross-section of the stockpile with a cross-section of the stockpile area after the second excavation is completed. If the excavation item does not include Haul, then the measurement provisions of Section
2-04 shall apply.
Gravel borrow and select borrow will be measured by the cubic yard or ton. Measurement by cubic yard will be made in the hauling vehicle.
2-03 Roadway Excavation and Embankment
M 41-10 Page 2-21Sand drainage blanket will be measured by the ton with deductions made for the weight of moisture above 8 percent. Embankment compaction (Methods B and C in Section 2-03.3(14)C ) will be measured by the cubic yard. An original ground measurement will be taken using cross-section or digital terrain modeling survey techniques. Quantities will be determined based on a comparison of the original ground measurement with the finished embankment section as staked. No allowance will be made for material that settles. No deduction will be taken for other items constructed within the embankment (bridge abutments, piers, columns, backfill, wall backfill, pipes, etc.). The Contracting Agency will exclude from compaction measurement material that is wasted or placed under water and not compacted in layers as provided by Sections 2-03.3(14)A and 2-03.3(14)C . In cuts, where excavation has been made below the planned Subgrade elevation, and in fills where excavation has been made below original ground, compaction will be measured by the cubic yard in the cross-section of compacted backfill material. When material below grade in cuts or in original ground beneath fills is scarified and recompacted, embankment compaction will be measured by its compacted depth, up to a maximum of 6 inches. There is no specific unit of measure and no measurement will be made for method A compaction as described in Section 2-03.3(14)C . Controlled blasting of rock face will be measured by the linear foot of hole drilled. Holes will be measured from the top of the rock surface to the elevation of the Roadway ditch or to a bench elevation set by the Engineer. Quantities shown in the Plans are based on 30-inch hole spacing. Actual quantities will depend on field conditions and results from test sections. Prefabricated vertical drains will be measured by the linear foot. Trial drains will be measured and included in the payment quantity for the prefabricated vertical drains. The drains will be measured from the top of the working platform to the bottom of each hole.
2-03.5 Payment
Payment will be made for each of the following Bid items that are included in the Proposal: “Roadway Excavation”, per cubic yard. “Roadway Excavation Incl. Haul”, per cubic yard. “Roadway Excavation – Area ____”, per cubic yard. “Roadway Excavation Incl. Haul – Area ____”, per cubic yard. “Channel Excavation”, per cubic yard. “Channel Excavation Incl. Haul”, per cubic yard. “Ditch Excavation”, per cubic yard. “Ditch Excavation Incl. Haul”, per cubic yard. The unit Contract price per cubic yard for “Roadway Excavation”, “Roadway Excavation Incl. Haul”, “Roadway Excavation – Area __”, “Roadway Excavation Incl. Haul – Area ___”, “Channel Excavation”, “Channel Excavation Incl. Haul”, “Ditch Excavation”, and “Ditch Excavation Incl. Haul” shall be full compensation for all costs incurred for excavating, loading, placing, or otherwise disposing of the material. For “Haul”, the unit Contract price as provided in Section 2-04 shall apply, except when the pay item is shown as including Haul. In that case the unit Contract price per cubic yard shall include “Haul”. When a bid item is not included in the proposal for channel excavation or ditch excavation, all costs shall be included in roadway excavation. When the Engineer orders Work according to Section 2-03.3(3) , unit Contract prices shall apply unless the Work differs materially from the excavation above Subgrade, then payment will be in accordance with Section 1-04.4 . Roadway Excavation and Embankment 2-03 Page 2-22 M 41-10“Unsuitable Foundation Excavation”, per cubic yard. “Unsuitable Foundation Excavation Incl. Haul”, per cubic yard. The unit Contract price per cubic yard for “Unsuitable Foundation Excavation” and “Unsuitable Foundation Excavation Incl. Haul” shall be full payment for all costs incurred for excavating, loading, and disposing of the material. For “Haul”, the unit Contract price as provided in Section 2-04 shall apply, except when the Bid item is shown as including Haul. In that case, the unit Contract price per cubic yard shall include “Haul”. “Common Borrow Incl. Haul”, per cubic yard. The unit Contract price per cubic yard for “Common Borrow Incl. Haul” shall be full compensation for all costs incurred for excavating, loading, hauling, placing, or otherwise disposing of the material. The unit Contract price includes removing, disposing of, wasting, or stockpiling any material in the borrow site that does not meet the Specifications for “Common Borrow”. “Select Borrow Incl. Haul”, per ton. “Select Borrow Incl. Haul”, per cubic yard. “Gravel Borrow Incl. Haul”, per ton. “Gravel Borrow Incl. Haul”, per cubic yard. “Sand Drainage Blanket”, per ton. The unit Contract price per ton or cubic yard for “Select Borrow Incl. Haul”, “Gravel Borrow Incl. Haul” and “Sand Drainage Blanket” shall be full compensation for all costs incurred for excavating, loading, hauling, and placing the material unless otherwise specified in the Proposal. “Embankment Compaction”, per cubic yard. The unit Contract price per cubic yard for “Embankment Compaction” shall be full compensation for all costs incurred for all material, labor, tools, equipment, and incidentals required. When embankments are constructed using Method A compaction, payment for embankment compaction will not be made as a separate item. All costs for embankment compaction shall be included in other Bid items involved. If the Bid item “Embankment Compaction” is not provided in the Proposal, compensation for costs incurred to perform the Work described in Section 2-03.3(14) , Embankment Construction, shall be included in payment for other items of Work in the Contract. “Aeration”, by force account. “Aeration” will be paid for by force account as specified in Section 1-09.6 . The payment for aeration and other related unit Contract prices shall be full compensation for all costs incurred to perform the Work described in Section 2-03.3(15) . Should the Contractor fail to seal an aerated area prior to inclement weather, additional aeration to restore the area to its previous condition shall be at the Contractor’s expense. For the purpose of providing a common Proposal for all Bidders, the Contracting Agency has entered an amount in the Proposal to become a part of the total Bid by the Contractor.
2-03 Roadway Excavation and Embankment
M 41-10 Page 2-23“Controlled Blasting of Rock Face”, per linear foot. The unit Contract price per linear foot for “Controlled Blasting of Rock Face” shall be full compensation for all costs incurred to perform the Work described in Section
2-03.3(2) Measurement and payment for Roadway excavation and haul related to
blasting shall be as provided under those items in this section and shall include the volume of material excavated from the benches or setbacks approved for drilling separate lifts. “Prefabricated Vertical Drain”, per linear foot. The unit Contract price per linear foot shall be full compensation for all costs incurred to perform the Work, including trial drains, as described in Section 2-03.3(14)H . Roadway Excavation and Embankment 2-03