Effective with the December 2018 Letting 533 2019 Standard Spec ifications Section 716 QMP Ancillary Concrete
716.1Description
concrete. 716.1.1 Quality Control Program 716.1.1.1 General
III concrete defined as follows: - Class II: ancillary concrete th e department accepts based on field testing during placement. - Class III: ancillary concrete th e department accepts by certi fication. 716.1.1.2 Quality Control Plan
716.2Materials 716.2.1 Class II Concrete
allowed under standard spec 501.3.1.3 , the contractor may use a cla ss I mix design approved under 715.2 . Ancillary concrete placed integrally with mainline pavement is accepted using tests of class I concrete but not eligible for incentive payment under 715.5 . Document the locations and quantities of integral concrete and identify the class I sublot tests used fo r acceptance. Revise 716.2.1(2) to require air and slump testing every 100 CY and cylinders every 200 CY for base patching.
method.
minimum of one set of 2 cylinders per contract for each mix gra de and placement method. Random 28-day compressive strength cylinders ar e not required for HES or SHES concrete.
for 72 hours before transporting the cylinders to a department- qualified laboratory.
results in the least number of tests: - A maximum of one test per day. - A minimum of one test per 400 c ubic yards of cumulative concrete placed. Alternatively the engineer may ac cept aggregate based on docume nted previous testing.
716.2.2 Class III Concrete
compliance at least 3 business days before producing concrete a long with the initial concrete mix documentation as required under 710.4(2) .
certificate of compliance. Conform to 716.2.1 for items not contained within the certificate of compliance.
the QV testing. 716.3 (Vacant) 716.4 (Vacant) 716.5 (Vacant)
Effective with the December 2018 Letting 534 2019 Standard Spec ifications Section 730 QMP Base Aggregate Add section 730 to incorporate STSP 301-010 QMP Base Aggregate.
730.1Description
730.1.1 General
aggregates. Apply to Base Aggregate Open Graded bid items and t o Base Aggregate D ense bid items except reclaimed asphaltic pavem ent placed under the Base Aggre gate Dense bid items.
items.
305, and 310, and to the additional requirements specified here in 730. 730.1.2 Quality Control Program 730.1.2.1 Quality Control Plan
730.1.2.2 Small Quantities
placed under a single bid item.
- An abbreviated quality control plan is allowed under 701.1.2.3. - Contractor QC placement testi ng is modified as specified in 730.3.4.1 . 730.1.2.3 Documentation
day of obtaining the sample.
aggregate size, source or classifi cation, and type. Set the con trol limits and warning limits as follows:
- There are no upper warning limits for sieves requiring or all owing 100 percent passing. - There are no lower warning limits for sieves allowing 0 percent passing. - Dense-graded No. 200 sieve: warning limits are 0.5 percent wi thin the upper and lower control limits. - Dense-graded for all other sie ves: warning limits are 2 perce nt within the upper and lower control limits. - Open-graded 1-inch, 3/8-inch, and No. 4 sieves: warning limits are 2 percent wit hin the upper and lower control limits. - Open-graded No. 10, No. 40, and No. 200 sieves: warning limits are 1 percent wit hin the upper and lower control limits.
type. Set the lower control li mit to the value specified in table 301-2 . Set the lower warning limit 2 percent above the lower control limit. There is no upper warnin g limit.
placement tests in the running average unless a QV test result is out of spec, then include it as specified in 730.3.5(5) . Document corrective action on control charts. Update control charts and submit copies to the engineer daily.
730.2Materials
Stockpile Sampling Coordinated QC/QV sample before beginning placement of aggregate materials.