Home / Calculators / Building Permit Fee Calculator

Maricopa County, Arizona Building Permit Cost Calculator

Estimates permit cost in Maricopa County from the city's own published fee schedule — not a national average. Every figure is computed from a rule quoted verbatim from that document, and rules that cannot be computed honestly are shown as the published text instead of a number.

217 jurisdictions with fee schedules on file

Total cost of work, labor and materials

Used by cities that price per square foot

Fences and retaining walls

Electrical permits priced by the ampere

Building Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

○Valuation $1 to $500
Flat fee $23.50
$23.50
Valuation $2,001 to $25,000
$69.25 for the first $2,000 plus $14.00 per additional $1,000
see rule
Valuation $100,001 to $500,000
$993.75 for the first $100,000 plus $5.60 per additional $1,000
see rule
Valuation $1,000,001 and up
$5,608.75 for the first $1,000,000 plus $3.65 per additional $1,000
see rule
Plan review (all permit types) · add-on
65% of the calculated permit fee, includes three submissions — select the permit fee line above to calculate
see rule
How this jurisdiction calculates the fee

Maricopa County prices a building permit from declared or county-assigned construction valuation run through TABLE 1-A of the Summary of the Fee Schedule (June 2024 edition). The table is graduated: a flat amount covers the first dollar band and a per-$1,000 (or per-$100 at the low end) increment applies above it, so the marginal rate falls as valuation rises. Plan review is charged on top at 65 percent of the calculated permit fee and that charge buys three plan submissions; further resubmittals are billed separately. Valuation for many project types is not the owner's number but a county-published unit value (for example non-habitable accessory buildings are valued as a private garage, wood-frame or masonry patio covers are valued as open carports, and metal patio covers and covered pipe-rail horse corrals are valued at 50 percent). An investigation fee equal to the permit or application fee is added when a violation is resolved administratively, effectively doubling the cost of permitting after the fact. Arizona has no statewide building-permit surcharge, so there is no state add-on line.

Source: published fee schedule · Verified 9/15/2026

Deck Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

Valuation $501 to $2,000
$23.50 for the first $500 plus $3.05 per additional $100
see rule
Valuation $2,001 to $25,000
$69.25 for the first $2,000 plus $14.00 per additional $1,000
see rule
Plan review · add-on
65% of the calculated permit fee — select the permit fee line above to calculate
see rule
How this jurisdiction calculates the fee

There is no flat deck or patio-cover fee. Maricopa County assigns the structure a construction valuation using its published unit values (patio covers valued as open carports, metal covers at 50 percent of that), then runs that valuation through TABLE 1-A of the June 2024 Summary of the Fee Schedule and adds plan review at 65 percent of the resulting permit fee. Because deck valuations are typically low, most residential decks land in the $2,001-to-$25,000 valuation band, where the permit fee is $69.25 for the first $2,000 plus $14.00 per additional $1,000. The exact dollar outcome depends on the county-assigned per-square-foot carport unit value in effect at application; confirm the current unit value with Planning & Development, so the exact dollar outcome depends on the county-assigned unit value in effect at application.

Source: published fee schedule · Verified 9/15/2026

Electrical Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

○Electrical service, residential, 1 to 200 amps
Flat fee $50.00
$50.00
○Electrical service, residential or commercial, 201 to 400 amps
Flat fee $75.00
$75.00
○Electrical service over 400 amps
Flat fee $120.00
$120.00
○Air conditioner
Flat fee $50.00
$50.00
How this jurisdiction calculates the fee

Unlike the valuation-driven building permit, common residential and light-commercial electrical work in Maricopa County is flat-rated in the June 2024 Summary of the Fee Schedule, priced by service amperage rather than by job cost. Larger or more complex electrical scopes that are part of a building project are instead folded into the building permit valuation and picked up by TABLE 1-A, with plan review at 65 percent of the permit fee. Arizona levies no state electrical surcharge. Note that Arizona ROC contractor licensing is required for most work; the flat fees below are the permit charge only.

Source: published fee schedule · Verified 9/15/2026

Fence Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

○Chain link (including mesh), valuation per lineal foot
Flat fee $6.00
$6.00
○Wood fence, valuation per lineal foot
Flat fee $11.00
$11.00
○CMU 4-inch wide block, 6 ft height or less, valuation per lineal foot
Flat fee $14.00
$14.00
○Three-strand barbed wire, valuation per lineal foot
Flat fee $3.00
$3.00
○Rail fence, valuation per lineal foot
Flat fee $6.00
$6.00
○Minimum permit fee (valuation $1 to $500)
Flat fee $23.50
$23.50
How this jurisdiction calculates the fee

Fences are not flat-rated. Maricopa County assigns a construction valuation using published per-lineal-foot unit values by fence material and height, then runs that valuation through TABLE 1-A of the June 2024 Summary of the Fee Schedule and adds plan review at 65 percent of the permit fee. Because the unit values are low, most residential fence permits fall in the first two TABLE 1-A bands, where the minimum permit fee is $23.50. The county also publishes a dedicated online fencing fee estimator on its Fee Schedule and Estimators page. An investigation fee equal to the permit fee applies to fences built without a permit.

Source: published fee schedule · Verified 9/15/2026

Reroof Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

Like-for-like re-roof, same material type
No permit required, no fee
see rule
Non-exempt roof work, valuation $2,001 to $25,000
$69.25 for the first $2,000 plus $14.00 per additional $1,000
see rule
Plan review on non-exempt roof work · add-on
65% of the calculated permit fee — select the permit fee line above to calculate
see rule
How this jurisdiction calculates the fee

Because a like-for-like re-roof is exempt, Maricopa County publishes no re-roof permit fee and there is no flat roofing line item in the Summary of the Fee Schedule. If the work loses the exemption — a change of roofing material type, structural sheathing or framing replacement, or a change to a fire-resistive assembly — it becomes an ordinary building permit priced from construction valuation through TABLE 1-A (June 2024 schedule), with plan review at 65 percent of the permit fee. An investigation fee equal to the permit fee applies if non-exempt roof work was already done without a permit.

Source: published fee schedule · Verified 9/15/2026

Retaining Wall Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

○Retaining wall 0 to 2 ft, valuation per lineal foot
Flat fee $15.00
$15.00
○Retaining wall 2 to 4 ft, valuation per lineal foot
Flat fee $25.00
$25.00
○Retaining wall greater than 4 ft to 6 ft, valuation per lineal foot
Flat fee $42.00
$42.00
○Minimum permit fee (valuation $1 to $500)
Flat fee $23.50
$23.50
Plan review · add-on
65% of the calculated permit fee — select the permit fee line above to calculate
see rule
How this jurisdiction calculates the fee

Retaining walls are valued per lineal foot by wall height, and that valuation is then run through TABLE 1-A of the June 2024 Summary of the Fee Schedule to compute the permit fee, with plan review added at 65 percent of the permit fee. Engineering is generally required as wall height increases, and the valuation tiers step up sharply with height. A 100-foot wall in the 2-to-4-foot tier, for example, values at $2,500 and therefore falls in the $2,001-to-$25,000 TABLE 1-A band. Floodplain and drainage reviews by the Flood Control District are billed separately under the District's own fee schedule.

Source: published fee schedule · Verified 9/15/2026

Shed Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

Valuation $501 to $2,000
$23.50 for the first $500 plus $3.05 per additional $100
see rule
Valuation $2,001 to $25,000
$69.25 for the first $2,000 plus $14.00 per additional $1,000
see rule
Plan review · add-on
65% of the calculated permit fee — select the permit fee line above to calculate
see rule
How this jurisdiction calculates the fee

There is no flat shed fee. A non-exempt shed is permitted as an ordinary building: the Summary of the Fee Schedule directs that non-habitable accessory buildings, other than covered pipe-rail horse corrals, 'shall be valued as a private garage,' and that county-assigned valuation is then run through TABLE 1-A (June 2024 schedule) to produce the permit fee, with plan review added at 65 percent of the permit fee. Small sheds typically land in the $2,001-to-$25,000 valuation band. Using the county's Standard Plans program (DD-5008-01) can shorten review. The final dollar amount depends on the county's current published private-garage unit valuation; confirm the current figure with Planning & Development, so the final dollar amount depends on the current published valuation table.

Source: published fee schedule · Verified 11/4/2026

Water Heater Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

In-kind storage tank water heater replacement, 1-2 family dwelling
No permit required, no fee
see rule
○Plumbing permit, install or replace equipment/fixture/device
Flat fee $50.00
$50.00
○Gas line (connect or clearance)
Flat fee $50.00
$50.00
How this jurisdiction calculates the fee

No fee applies to an exempt in-kind storage-tank water heater replacement in a one- or two-family dwelling. If the work falls outside the exemption — tankless conversion, fuel change, relocation, new gas piping or venting, or multifamily/commercial — it is permitted under the flat plumbing line in the June 2024 Summary of the Fee Schedule, which charges a single amount to install or replace plumbing equipment, fixtures or devices. Related gas-line connection or clearance work is separately flat-rated. Arizona imposes no state plumbing surcharge.

Source: published fee schedule · Verified 9/15/2026

See the full write-up: Maricopa County building permit cost

Estimate only.Fee schedules change, and building departments set the final valuation and decide which fees apply to your scope. Confirm with the jurisdiction before budgeting. Lines marked “see rule” could not be computed from the published wording and are shown verbatim rather than guessed.