517.05 Basis of Payment.
BRIDGE AND SIDEWALK HANDRAIL
517.01 Description.
This Section shall cover the work of fabricating, furnishing, and installing handrail on structures in accordance with details and at the location shown on the plans, all in conformity with the requirements noted herein or shown on the plans.
517.02 Materials.
Materials used in fabrication and installation shall conform to the applicable Section of the Specifications that the structure to which the railing is to be attached was constructed, the details shown on the plans, and the following: Galvanized Steel Pipe Handrail. Galvanized steel pipe shall meet the requirements of ASTM A 53, Grade B; this grade of pipe to include rail elements and post. Steel shapes, plates, and accessories shall be structural or alloy st eel galvanized in accordance with AASHTO M 111. Bolts, nuts, washers, and other fasteners shall be galvanized in accordance with AASHTO M 232, Class C, with nuts tapped after galvanization in accordance with ASTM A 563 {A 563M}. Galvanized Steel Handrail. Galvanized steel shall be structural or alloy steel, hot dipped galvanized after fabrication in accordance with AASHTO M 111. Bolts, nuts, washers, and other fasteners shall be galvanized in accordance with AASHTO M 232, Class C, with nuts tapped after gal vanization in accordance with ASTM A 563 {A 563M}. Beam Type Handrail. Beam type handrail shall meet the requirements for beam guardrail as provided in Sections 630 and 864. Ornamental Handrail shall meet the requirements shown on the plans. Aluminum or Ga lvanized Steel Sidewalk Handrail. Material for use in aluminum or galvanized steel sidewalk handrail shall meet the requirements specified on the plans. Concrete Handrail. Concrete handrail shall be cast -in-place type conforming to the appropriate requirem ents of Section 501 and the details shown on the plans. Posts for Beam Type Handrail. Steel posts shall meet the requirements of Sections 836 and 864. Timber posts shall be treated in accordance with Section 833.
517.03 Construction Requirements.
Rail shal l be erected in accordance with the best construction practices and in conformity with lines, elevations, and other details indicated on the plans. The plans will show construction details and will specify the type or alternate types of handrail to be used . Where the Contractor is permitted to choose the type rail he wishes to use, he shall indicate in the proposal his choice. One type, once selected, shall be used throughout the project.
517.04 Method of Measurement.
The accepted bridge and sidewalk handra il will be measured in linear feet {meters}, to the nearest 0.1 of a foot {0.1 m}, along the axis of the top rail between extreme limits of the handrail without deductions for laps, posts, or joints. All stair railing, posts, and appurtenances for one stai r tower, including pipe railing on the superstructure but not a part of the bridge or sidewalk handrail, installed and accepted complete in place will be measured as one set of stair railing. No measurement or separate payment will be made for post or misc ellaneous hardware required for installation of handrail and stair railing, such being considered incidental to the installation of the rail.
517.05 Basis of Payment.
520.01 Description.
520.01 Description.
This Section shall cover the work of furnishing all materials, tools, equipment, labor, falsework, or cribbing and all incidental items necessary to repair members or portions of an existing bridge or change the elevation of an existing bridge as may be required by the detailed plans. The work shall also include the removal and satisfactory disposal of all waste material, damaged portions replaced, and all falsework and/or temporary bracing, etc.
520.02 Materials.
Since the majority of the work required under this Section is primarily a work item, materials not to be incorporated into the completed struc ture shall be of such quality as to serve the needs adequately. However, any material which is to become a part of the completed structure shall meet the requirements of Division 800, Materials, for the respective type of member or part involved.
520.03 Construction Requirements.
520.04 Method of Measurement.
Each existing bridge to be repaired, raised, or bridge having a portion or portions of same to be repaired or raised will be shown on t he plans and in the proposal by its station number, and for the purpose of measurement and payment will be considered a complete and separate unit.