510.01 Description.
509.04 Method of M easurement.
The quantity to be measured shall be the number of thousand feet board measure {cubic meters} of lumber and timber, complete in place and accepted. Measurements of lumber and timber will be computed using the nominal width and thickness, and the actual length of each piece shown on the plans, unless changes in such dimensions have been authorized in writing. The nominal size dimensions shall be used in the computations even though the actual size be scant in the amount provided above. The measur ements of timber will include only such timber as is a part of the completed and accepted work, and will not include timber used for erection purposes, such as falsework, bracing, sheeting, etc.
509.05 Basis of Payment.
510.01 Description.
The work under this Section shall cover the construction of bridges, or parts thereof , including members designated as mass concrete . When widening or modification of an existing facility is required, the work under this Section shall include the cutting or breaking away of portions of the existing structural material and the preparation of th e exposed structural materials for joining of new materials to the lines and grades shown on the plans or as directed. The requirements for concrete temperature monitoring, maximum allowable concrete temperatures, and the Thermal Control Plan (ThCP) are co vered in this section. The requirements of this Section shall apply to any concrete element that is designated as mass concrete in the Contract Documents. A ThCP to control and monitor concrete temperatures is required for all mass concrete elements.
510.02 Materials.
510.02 Materials.
510.03 Construction Requirements.
510.03 Construction Requirements.
510.03 Construction Requirements.
transverse slab construction joints will be requ ired. Where slab construction joints are used on simple composite spans, construction joints shall be placed at approximately the quarter points of the span; after pouring the center portion of the span and when the concrete has reached a compressive stren gth of 2 800 psi {19 MPa} by cylinder tests, or after four days, the end slab portions of the span may be poured. Consideration will be given to reducing the number of construction joints specified above where transverse screeding is to be employed; however , all requests for changes to pouring sequences must be submitted in writing to the Construction Engineer for approval. If the number of construction joints is reduced, a minimum pour rate of 30 cubic yards {23 m³} per hour may be required, and an approved retarder may be required in the deck concrete. During the placing operation, the concrete shall be placed in strips just ahead of the screed for the entire length or width of the pour, whichever applicable. A small roll of grout shall be kept on the leadi ng edge of the screed so that all depressions ahead of the screed will be filled.
510.03 Construction Requirements.
finish or burlap drag. Brooms for broom finishing shall have medium to stiff nylon bristles. The final texture shall be obtained by the cutting of transverse grooves in the cured concrete. The bridge decks shall be grooved perpendicular to the centerline. The grooving operation shall not be started until the bridge deck has been cured in accordance with the requirements given in Section 501 . The grooves shall be cut into the hardened concrete using a mechanical saw device which will leave grooves approximately 1/8 inches {3 mm} wide and 1/8 inches {3 mm} deep. The grooves shall be unevenly spaced and randomly varying between 5/8 inches {15 mm} and 1.125 inches {30 mm}. The grooved finish shall be at right angles to the centerline of the b ridge deck, regardless of skew, and shall extend across the roadway from 2 feet {600 mm} inside the face of the curb or barrier rail to 2 feet {600 mm} inside the face of the opposite curb or barrier rail. Each pass of the grooving machine shall be adjacen t to the previous pass without overlapping. All residue, slurry and other waste resulting from the grooving operation shall be continuously removed from the bridge deck so that there is never a build- up of these waste materials. Upon approval by the Engin eer, these waste materials may be disposed in earthwork when earthwork is a part of the bridge construction project. The waste materials may be tilled into the earthwork so that water run -off will not transport these materials from the construction site. I f the Engineer does not approve of the disposal of the waste material on the construction site, the Contractor shall remove the waste material from the project and dispose of it in accordance with all applicable laws and ordinances for disposal.
510.03 Construction Requirements.
for fixed forms. The forming po rtion of the extrusion machine shall be readily adjustable vertically during the forward motion of the machine so that the top of the barrier can be maintained at the required grade. Open joints shall be located as required on Standard Drawing No. I -131. Longitudinal bars shall be cut at joint locations to provide for 2 inch {50 mm} end cover. The Contractor shall be responsible for marking these locations in advance of placement of concrete so that sawed joints will be properly located. The joints shall b e sawed as soon as the concrete has hardened to the degree that tearing and raveling is not excessive, and before uncontrolled shrinkage cracking begins. This time may be as short as four hours or even less in extremely warm weather, but not over 12 hours unless authorized by the Engineer. If extreme conditions exist which make it impractical to prevent uncontrolled cracking by early sawing, the procedure shall be revised immediately to adjust the sequence of sawing. A minimum saw cut width of 5/16 of an in ch {8 mm} shall be maintained. On the inside of the barrier, the saw cut shall extend from the top to the bottom of the rail to the point of intersection with the bridge deck. On the outside of the barrier, the saw cut shall extend from the top to within 11 inches {280 mm} of the bottom of the rail.
510.03 Construction Requirements.
conductor with provisions for not less than 12 inches {300 mm} horizontal movement of the structure at point of conne ction. Reference is made to Article 836.09 for additional material requirements.
510.04 Acceptance of Mass Concrete
• The maximum in -place concrete temperature differential in accordance with Item 510.03(d)3 that shall be used for the project. If an a ge-dependent maximum concrete temperature differential is used, it shall be defined in tabular form, and the CTE shall be reported. • Calculated or measured adiabatic temperature rise of the mass concrete element. • Proposed methods to control concrete tempera ture at time of placement, such as pre -cooling of raw materials or concrete. • Proposed methods to control maximum concrete temperature during curing. A mechanical cooling system may be used to control the internal temperature of mass concrete during curing but shall be designed in conformance with the ThCP. If a mechanical cooling system is used, the plans for the cooling system operation and final grouting after cooling shall be submitted to the State Materials and Tests Engineer for approval. • Maximum concr ete temperature at time of placement used during the development of the Temperature Control Plan. • Calculated maximum concrete temperature during curing based on expected conditions and methods used to control temperature. • Proposed methods to control concrete temperature differentials during curing. • Calculated maximum temperature differential based on expected conditions and methods used to control the temperature difference. Submit the thermal calculation model and/or computational software with the ThCP. • Information on the temperature sensing and recording equipment to be used and drawings of locations of temperature sensors within each placement. • Description of the format and frequency of providing temperature data. • List of corrective measures to be taken to reduce excessive temperatures and temperature differences, if they occur. • Description of curing methods and duration of curing. • Description of formwork removal procedures and method to ensure that the temperature differences at exposed surfaces will no t exceed the maximum concrete temperature differential.
510.04 Acceptance of Mass Concrete
Construction shall not proceed on any mass concrete element until compliance with this specification has been determined and the Contractor has received written notification to continue construction from the State Construction Engineer.
510.06 Basis of Payme nt.
If the Contractor fails to conform to any of the above temperature requirements in any one pour, the construction of any additional mass concrete elements will cease. The State Construction Engineer may, at his sole discretion, direct that the concrete be removed or otherwise mitigated, at no cost to the Department. The contractor shall revise the ThCP to correc t the problem and resubmit the revised ThCP to the State Materials and Tests Engineer for acceptance for completeness. Mass concrete placement shall not begin until the State Materials and Tests Engineer has approved the revised ThCP. No extension of time or compensation will be made for any rejected mass concrete element or revisions of the ThCP.
510.05 Method of Measurement.
Article 503 — 04 or Item 510.05.
510.06 Basis of Payment.
510.06 Basis of Payment.
backfilling, compacting, disposal of surplus material, all falsework piling, falsework, forms, bracing, all materials except as specified below, and for all equipment, tools, labor, an d incidentals necessary to finish and complete the items in accordance with the plans and these specifications. Non -metal expansion joints, scuppers and drains, electrical conduit and equipment, shall be included in the bid price for the concrete, unless o therwise provided on the plans or in the proposal. Steel reinforcement, metal expansion joints, and metal bearings will not be included in the price bid for the concrete but shall be paid for under the appropriate pay item. In case of widening or extension of an existing structure, the breaking away of existing concrete to the approximate lines shown on the plans and disposing of broken concrete and preparing steel reinforcement for splicing as required, will be paid for under Section 206. The accepted mas s concrete, measured as noted above, will be paid for in accordance with the unit price coverage that applies to this element type as defined in either Article 503.05 or Item 510.06. The development of the TCP and all equipment, tools, labor, and incidenta ls necessary to control concrete temperatures shall be included in the bid price for the concrete. All equipment, tools, labor, and incidentals necessary to measure and monitor the in -place concrete temperature as required herein shall be included in the bid price for the concrete. No additional compensation will be allowed for constructing or placing expansion joints, scuppers, drains, weep holes, or for placing service pipes or conduits, anchor bolts, plates, castings, grillages, or metal bearings or appu rtenances, as such are considered incidental to the placing of concrete or other items of the work, unless otherwise noted by the plans or proposal. Payment for grooving concrete bridge decks will be made at the contract unit price bid per square yard {squ are meter} which will be full compensation for furnishing the necessary equipment, tools, and labor to perform the work.
512.01 Description.
510-E Grooving Concrete Bridge Decks - per square yard {square meter} 510-G Mass Bridge Concrete Substructure - per cubic yard {cubic meter} 510-H Mass Bridge Concrete Superstructure, * , **, *** - per lump sum * Station Number, Bridge Identification Number (BIN), Ramp Number, etc. ** Lane, if applicable *** Approximate quantity of superstructure concrete in cubic yards {cubic meters} SECTION 511 ELASTOMERIC BEARINGS
511.01 Description.
This Section shall cover the work of furnishing and installing elastomeric bearings for all types of bridge girders. An elastomeric bearing shall consist of at least a single layer of elastomer and may consist of a possible combination of elastomeric layer(s), internal steel sheet laminate(s), PTFE layer, bearing and/or sole plates, and a stainless steel plate.
511.02 Materials.
Elastomeric bearings shall be fabricated to conform with the material requirements given on the Plans and in Section 837.
511.03 Construction Requirements.
Unless noted otherwise on the plans or in these specifications, Shop Drawings for the elastomeric bearings shall be subm itted to the Bridge Engineer for approval. Shop Drawings will not be required for the elastomeric bearings for precast concrete bridge components furnished under Section 512. The elastomeric bearings will be identified on the plans by Type (Type 1, 2, 3, 4 , or 5) and may be further identified by a Mark (Mark B1, B2, VB1, etc.). Rust that occurs on the portions of bearing plates that are left ungalvanized for welding shall be cleaned to bare metal prior to welding. All exposed surfaces of the sole plate, all uncoated surfaces of the bearing plate and all weld metal shall be coated after welding with galvanizing repair paint that meets the requirements given in SECTION 855.
511.04 Method of Measurement.
The elastomeric bearings will be measured per each for each type of bearing. The bearings measured for payment do not include the randomly selected samples for testing.
511.05 Basis of Payment.
512.01 Description.
This Section shall cover the work of furnishing and installing precast non -prestressed concrete bridge members.