609.01 Description.
Required Overlaps Soil Strength (CBR) Unsewn Overlap (inches {mm}) Sewn Overlap (inches {mm}) < 1 - - 9 {225} 1 - 2 38 {950} 8 {200} 2 - 3 30 {750} 3 {75} > 3 24 {600} - - Unless shown otherwise on the plans, the required overlap shall be as shown for a CBR value of 1 - 2. The geotextile may be held in place prior to subbase placement by pins, staples, or piles of fill or rock. Geotextiles may be folded or cut to conform to any curvature of the area. A fold or overlap shall be in the direction of construction and held in place a s prescribed above.
608.05 Seams.
Both factory and field sewn or sealed seams shall conform to the strength requirements of Table 1 as outlined in AASHTO M 288 for Separation Applications. All seams shall be subject to the approval of the Engineer.
608.06 Subbase Placement.
The subbase shall be placed by end dumping onto the geotextile from the edge of the geotextile, or over previously placed subbase aggregate. On subgrades having a CBR of 1, the subbase aggregate shall be spread simultaneously with dumping to minimize the potential of a localized subgrade failure. Direct traffic on the geotextile, along with any sudden stops, starts, or turns on the subbase material by construction equipment, shall be avoided where possible. Using whatever means, the subbase material shall be spread from the back dumped pile. Except in the case of low volume roads (ADT < 200), a minimum thickness of 6 inches {150 mm} shall be maintained. In the case of low volume roads, this thickness shall be 4 inches {100 mm}. A smooth drum roller shall be used to achieve the specified density. Any ruts occurring during construction shall be filled with additional subbase material and compacted to the specified density. The use of vibratory compaction will not be allowed a s it may cause damage to the geotextile.
608.07 Damage Repair.
Damaged geotextiles, as identified by the Engineer, shall be repaired immediately. The damaged area, plus an additional 3 feet {1 m} around the area, shall be cleared of all fill material. This area shall be covered with a geotextile patch extending 3 feet {1 m} beyond the perimeter of the damage. The removed subbase material shall be replaced and compacted to the specified density.
608.08 Method of Measurement.
The geotextile will be measured by the square yard {square meter} from the payment lines shown on the plans, or from the payment lines established in writing by the Engineer. This excludes seam overlaps. Excavation, backfill, bedding, and cover material are separate pay items.
608.09 Basi s of Payment.
609.01 Description.
This Section shall cover the work of furnishing and constructing a slope protection layer of graded aggregat e on slopes as shown on the plans or directed in accordance with these Specifications. This
609.02 Materials.
Section shall also cover the work, if shown on the plans, of furnishing and installing a geotextile filter blanket on slopes which are to receive the aforementioned aggregate protection layer.
609.02 Materials.
Materials furnished for use shall conform to the appropriate requirements of Division 800, Materials, and the following:
609.03 Construction Requirements.
610.02 Materials.
Additional pins, regardless of location, shall be installed as necessary to prevent any slippage of the geo textile filter. Each securing pin shall be pushed through the filter until the washer bears against the filter and secures it firmly to the foundation. The filter shall be protected at all times during construction from contamination by surface runoff and any filter so contaminated shall be removed and replaced with uncontaminated filter. Any damage to the filter during its installation or during placement of riprap shall be replaced by the Contractor. The work shall be scheduled so that 30 days does not ex pire between placement of the filter and the covering of the filter with the graded aggregate. Aggregate shall not be dropped on the filter from a height greater than 1 foot {300 mm}. Greater drop heights will be permitted if the Contractor provides a cush ioning layer of sand on top of the filter before dumping of stone. The combination of drop height for stone and sand cushion layer thickness to be approved shall be demonstrated to not puncture or damage the filter. No measurement or separate payment shall be made for a sand cushion layer placed for the purpose of allowing an increased drop height of stones. Any damage to the geotextile filter during placement of aggregate shall be corrected prior to proceeding with the work.
609.04 Method of Measurement.
Accepted aggregate slope protection and geotextile filter for aggregate slope protection, if applicable, will each be measured in square yards {square meters}, complete in place, computed from actual measurements taken along the top surface of the treated area to the nearest 0.1 square yard {0.1 m²}.
609.05 Basis of Payment.
610.01 Description.
This Section shall cover the work of furnishing and constructing the several classes or types of r iprap, each of which shall consist of a protective course of stone or other approved materials on embankment slopes, in channels and ditches, wave protection for causeways and shoreline roadway embankments, bridge piers and abutments, or other work as shown on the plans or directed, with or without a geotextile filter, all in accordance with these specifications and in conformity with the lines, and grades note d in the plan details.
610.02 Materials.
If a geotextile filter is required, it shall meet the requirements of AASHTO M 288 for Permanent Erosion Control Geotextile, Class 1, and Section 810 of these specifications. All other materials shall