EARTHWORK

204TEST HOLES

DE · 2026 Standard Specifications✓ Full text on BuildSpecBook pages 126–0 Save this section

Ask about Section 204

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

204.1Description.

This work consists of excavating to locate underground utilities.

204.2Materials.

Not applicable.

204.3Construction.

A.Determine existing underground utility type, size, depth, and condition.
B.Excavate and backfill holes using equipment approved by the engineer. Take care not to damage

wrappings, coatings, or other protective coverings on existing utilities.

204.4Method of Measurement.

The Department will measure test holes by the cubic yard.

204.5Basis of Payment.

A.The Department will pay for test holes at the contract unit price per cubic yard. Payment will

constitute full compensation for excavating and backfilling test holes.

B.The Department will pay for:
1.Removal of existing pavement in accordance with Section 202.
2.Temporary roadway patch in accordance with Section 401.

ITEM DESCRIPTION UNIT 204000 TEST HOLE CY

Get an email when 204 changes

Delaware revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Delaware Standard Specifications for Road and Bridge Construction, 2026 Edition. Pages 126–0 of 786. View official source ↗