706.1Description.

This work consists of setting PCC monuments and capped rebar right-of-way markers.

706.2Materials.

A.PCC, Class B Section 1022
B.Bar Reinforcement Section 1037
C.Aluminum 2-Inch Flat Survey Marker
D.Monument Delineators
1.Wood Section 1041
2.Flexible Delineator Section 1073.4

706.3Construction.

A.Monuments.
1.The engineer will provide the exact monument and right-of-way marker locations, which are to

be set by a Delaware professional land surveyor, in accordance with the contract.

2.Place monuments vertically in excavated holes at the depths shown in the contract, with 2 sides

approximately parallel with the roadway. Place backfill material in layers and firmly tamp without disturbing the location set by the surveyor.

3.Take care not to break or damage monuments when removing and resetting.
4.Replace broken or damaged monuments in kind.
5.Install wooden delineator, unless otherwise required by the contract.
B.Capped Rebar Right-of-way Markers.
1.Place capped rebar right-of-way markers in accordance with the contract.
2.Place rebar vertically at the depth shown in the contract.
3.Place aluminum 2-inch flat survey markers on rebar taking care not to move the rebar location.
4.Install wooden delineator, unless otherwise required by the contract.
C.Flexible Right of Way Marker Delineators
1.Place flexible delineators as indicated in the contract.
2.Install flexible delineators in accordance with manufacturer recommendations to a final top

elevation of no less than 36-inches as measured from the ground surface elevation.

a.Do not install delineators in frozen ground.
3.Affix vertical lettering to the top portion of the delineator.

706.4Method of Measurement.

The Department will measure monuments and capped rebar right-of-way markers as the number placed and accepted.

706.5Basis of Payment.

A.The Department will pay for the quantity of monuments and capped rebar right-of-way markers at

the contract unit price per each placed. Price and payment constitute full compensation for:

1.Excavating;
2.backfilling;
3.providing and placing all materials; and
4.setting monument by a Delaware Professional Land Surveyor.

ITEM DESCRIPTION UNIT 706000 MONUMENT EACH 706001 RELOCATE MONUMENT EACH 706002 RIGHT-OF-WAY MARKER, CAPPED REBAR EACH

Get an email when 706 changes

Delaware revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Delaware Standard Specifications for Road and Bridge Construction, 2026 Edition. Pages 370–0 of 786. View official source ↗

Ask about this section

Scoped to Delaware Standard Specifications for Road & Bridge Construction, Section 706 — MONUMENT. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.