722.1Description.
This work consists of constructing high-tension cable barrier (HTCB).
722.2Materials.
Level 4 (TL-4) installation.
for a Test Level 3 (TL-3) installation.
requirements for a Test Level 3 (TL-3) installation.
or equal. Two coats of inhibitor from the below-ground end to 6-inch above the final ground elevation.
requirements for a Test level 3 (TL-3) installation.
or equal. Two coats of inhibitor from the below-ground end to 6-inch above the final ground elevation.
722.3Construction.
722.3.1 Submittals.
concrete end-terminal anchors. Base the design of line post concrete footings and concrete end- terminal anchors on the specific project location, requirements as shown on the contract, what is specified here, and on Department supplied soil boring information.
722.3.2 Training.
engineer. Provide a minimum of 2 training sessions consisting of installation training before beginning cable barrier construction and maintenance training before primary inspection. The
manufacturer shall establish the training duration and shall provide field training on all aspects of the system. Coordinate the training schedule and location with the engineer. The engineer will advise the appropriate department staff, including construction inspectors and maintenance personnel regarding the training location and schedule. Provide all training materials in both hard copy and electronic PDF format.
date to the engineer a minimum of 14 calendar days before the session date for review and approval. At a minimum, the training shall include the following participants:
set of training handouts, the manufacturer’s installation manual, and the manufacturer’s plans for the approved system. Cover all aspects of the system installation, including the following subjects:
concrete design strength, curing time, concrete testing, and locations; ii. line post installation; iii. end terminal assembly installation; and iv. wire rope installation and tensioning.
system. Submit the proposed training date to the engineer a minimum of 14 calendar days prior to the training session date for review and approval. Include the following participants:
set of training handouts, the manufacturer’s maintenance manual, and the manufacturer’s plans for the approved system. The training course and accompanying course material shall cover, at a minimum, the following subjects:
722.3.3 Construction.
potential conflicts with underground utilities or drainage before construction. The engineer may require the contractor to excavate test pits to determine the exact location and depth of any existing utility that may conflict with the proposed alignment of the high-tension cable barrier system.
post foundations, terminals, transitions, or anchor systems. Excavate and grade as necessary for the HTCB maintenance strip in accordance with the contract. Pave the maintenance strip before excavating and drilling post foundations.
foundations in accordance with the manufacturer’s requirements and approved foundation shop drawings. Place foundation reinforcing steel as required in the approved shop drawings. Place the concrete and install sockets, keeping the top of the foundation flush with the final grade. Place line posts and fitting gaskets. Space the posts, in accordance with the manufacturer’s requirements. Set posts plumb and in a straight line.
engineer.
Position rigging screws to avoid interference with posts or other rigging screws unless recommended by the manufacturer.
testing equipment specified by the manufacturer at the beginning of the installation and throughout the project. The Department will only accept results from 1 model of tension testing device. Provide a certificate to the engineer showing that the tensioning instrument was calibrated no more than 30 calendar days before its first use on the project.
certifying that the tester is trained in the use of the testing equipment.
calendar days after the first test. Re-tension the cable when the test reading is less than the
manufacturer’s recommendations for the given temperature. Re-tension the cables to the manufacturer’s specifications by successively reading tension measurements at every rigging screw or turnbuckle. Repeat the testing and re-tension the cable in accordance with the manufacturer’s specifications until the manufacturer certifies the full cable system.
certifying that the contractor tensioned the cable in accordance with the manufacturer’s specifications and that the cable tension complies with the manufacturer’s requirements.
in each direction of a cable barrier segment, delineate posts at intervals no greater than 50-feet on tangents and curves with a radius of 3,500-feet or greater and 30-feet on curves having a radius less than 3,500-feet. Delineate all end terminal posts in accordance with the manufacturer’s recommendations. Ensure that delineation is visible from both directions of traffic unless otherwise shown on the plans. Use delineation consisting of yellow retroreflective sheeting meeting the requirements of ASTM D4956 Type IX material. The minimum area of sheeting required is 8 square inches. Attach the sheeting near the top of the post as recommended by the manufacturer. On posts with flat surfaces facing approaching traffic, the contractor may apply retroreflective sheeting directly to the post. On posts without flat surfaces facing approaching traffic, the contractor may apply the sheeting to the post cap.
construction or prior to final acceptance of the Project. Mark the affected area as directed by the engineer within 8-hours of the damage. If only line posts incurred damage, replace the posts and re-install the cable to the posts within 48-hours of contractor notification. If an end terminal is struck and the cables disengaged, repair, re-tension, and test the system within 24-hours of contractor notification. After each hit, re-tension the system in accordance with the manufacturer’s specifications, if required.
the parts to the DelDOT maintenance facility as directed by the engineer. Provide an extra supply of the following:
socket covers. Include 200 posts and accessories, or a number of posts and accessories equal to 10-percent of the total number of posts and accessories installed, whichever is more.
assemblies, or an amount of materials sufficient to complete a number of turnbuckle assembles equal to 10-percent of the total number of turnbuckle assemblies installed, whichever is more.
socket covers. Provide enough materials to complete 3 end anchor installations, or an amount of materials sufficient to complete a number of end anchor installations equal to 10-percent of the total number of end anchors installed, whichever is more.
to 10-percent of the total number of socket covers installed, whichever is more.
that bears a serial number and has a current Certificate of Calibration from a National Institute of Standards and Testing accredited laboratory.
722.4Method of Measurement.
The Department will measure the quantity of high-tension cable barrier as the number of linear feet constructed, tested, and accepted. The Department will measure the length from the first line post adjacent to each end terminal for the run of cable barrier. The Department will not include posts associated with the end terminal, as identified in the manufacturer’s shop drawings, in the linear foot quantity. The Department will measure the quantity of end terminals as the actual number of each end terminal constructed, tested and accepted.
722.5Basis of Payment.
linear foot. Price and payment will constitute full compensation for:
and payment will constitute full compensation for:
ITEM DESCRIPTION UNIT 722001 HIGH TENSION CABLE BARRIER LF 722002 HIGH TENSION CABLE BARRIER END TERMINAL EA