Temporary Works
817.01 DESCRIPTION . Furnish, construct, and remove temporary facilities
employed in the execution of the work. Such facilities include but are not limited to temporary bridges, temporary sheeting, falsework, shoring, formwork, scaffolding, form travelers, cofferdams, water control systems, and containment systems.
817.02 Materials.
Sheeting Sectio n 802 Drilled Shafts Piles Section 803 Section 804 Concrete Section 805 Reinforcing Steel Section 806 Steel Section 807 Granular Material 1003.09 Fence and Guard Rail Timber Section 1010 1014.01
817.03 CONSTRUCTION REQUIREMENTS . Design temporary works in
accordance with the latest version of AASHTO LRFD Bridge Construction Specifications . Consider appropriately distributed construction loads such as stockpiled materials and construction equipment. Determine member capacities based on field conditions accounting for section loss, deterioration of capacity, alterations of the structure, and support conditions during all construction phases. Conform to Section 801 for submittals.
817.03.1 Temporary Works Designed by Engineer of Record (EOR) :
817.03.1 1 Temporary Detour Bridge : Submit for review shop
drawings for fabricated elements . Submit installation, maintenance and removal plan for review. Conform to Section 803 for drilled shafts, Section 804 for piles and Section 704 for guardrails. Steel will not be required to be coated unless specified. Construct temporary detour bridge as specified . Construct temporary detour road in accordance with Section 725 . Temporary Works
817.01 DESCRIPTION . Furnish, construct, and remove temporary facilities
employed in the execution of the work. Such facilities include but are not limited to temporary bridges, temporary sheeting, falsework, shoring, formwork, scaffolding, form travelers, cofferdams, water control systems, and containment systems.
817.02 Materials.
Sheeting Sectio n 802 Drilled Shafts Piles Section 803 Section 804 Concrete Section 805 Reinforcing Steel Section 806 Steel Section 807 Granular Material 1003.09 Fence and Guard Rail Timber Section 1010 1014.01
817.03 CONSTRUCTION REQUIREMENTS . Design temporary works in
accordance with the latest version of AASHTO LRFD Bridge Construction Specifications . Consider appropriately distributed construction loads such as stockpiled materials and construction equipment. Determine member capacities based on field conditions accounting for section loss, deterioration of capacity, alterations of the structure, and support conditions during all construction phases. Conform to Section 801 for submittals.
817.03.1 Temporary Works Designed by Engineer of Record (EOR) :
817.03.1 1 Temporary Detour Bridge : Submit for review shop
drawings for fabricated elements . Submit installation, maintenance and removal plan for review. Conform to Section 803 for drilled shafts, Section 804 for piles and Section 704 for guardrails. Steel will not be required to be coated unless specified. Construct temporary detour bridge as specified . Construct temporary detour road in accordance with Section 725 . Temporary Works
817.01 DESCRIPTION . Furnish, construct, and remove temporary facilities
employed in the execution of the work. Such facilities include but are not limited to temporary bridges, temporary sheeting, falsework, shoring, formwork, scaffolding, form travelers, cofferdams, water control systems, and containment systems.
817.02 Materials.
Sheeting Sectio n 802 Drilled Shafts Piles Section 803 Section 804 Concrete Section 805 Reinforcing Steel Section 806 Steel Section 807 Granular Material 1003.09 Fence and Guard Rail Timber Section 1010 1014.01
817.03 CONSTRUCTION REQUIREMENTS . Design temporary works in
accordance with the latest version of AASHTO LRFD Bridge Construction Specifications . Consider appropriately distributed construction loads such as stockpiled materials and construction equipment. Determine member capacities based on field conditions accounting for section loss, deterioration of capacity, alterations of the structure, and support conditions during all construction phases. Conform to Section 801 for submittals.
817.03.1 Temporary Works Designed by Engineer of Record (EOR) :
817.03.1 1 Temporary Detour Bridge : Submit for review shop
drawings for fabricated elements . Submit installation, maintenance and removal plan for review. Conform to Section 803 for drilled shafts, Section 804 for piles and Section 704 for guardrails. Steel will not be required to be coated unless specified. Construct temporary detour bridge as specified . Construct temporary detour road in accordance with Section 725 . Temporary Works
817.01 DESCRIPTION . Furnish, construct, and remove temporary facilities
employed in the execution of the work. Such facilities include but are not limited to temporary bridges, temporary sheeting, falsework, shoring, formwork, scaffolding, form travelers, cofferdams, water control systems, and containment systems.
817.02 Materials.
Sheeting Sectio n 802 Drilled Shafts Piles Section 803 Section 804 Concrete Section 805 Reinforcing Steel Section 806 Steel Section 807 Granular Material 1003.09 Fence and Guard Rail Timber Section 1010 1014.01
817.03 CONSTRUCTION REQUIREMENTS . Design temporary works in
accordance with the latest version of AASHTO LRFD Bridge Construction Specifications . Consider appropriately distributed construction loads such as stockpiled materials and construction equipment. Determine member capacities based on field conditions accounting for section loss, deterioration of capacity, alterations of the structure, and support conditions during all construction phases. Conform to Section 801 for submittals.
817.03.1 Temporary Works Designed by Engineer of Record (EOR) :
817.03.1 1 Temporary Detour Bridge : Submit for review shop
drawings for fabricated elements . Submit installation, maintenance and removal plan for review. Conform to Section 803 for drilled shafts, Section 804 for piles and Section 704 for guardrails. Steel will not be required to be coated unless specified. Construct temporary detour bridge as specified . Construct temporary detour road in accordance with Section 725 . Temporary Works
817.01 DESCRIPTION . Furnish, construct, and remove temporary facilities
employed in the execution of the work. Such facilities include but are not limited to temporary bridges, temporary sheeting, falsework, shoring, formwork, scaffolding, form travelers, cofferdams, water control systems, and containment systems.
817.02 Materials.
Sheeting Sectio n 802 Drilled Shafts Piles Section 803 Section 804 Concrete Section 805 Reinforcing Steel Section 806 Steel Section 807 Granular Material 1003.09 Fence and Guard Rail Timber Section 1010 1014.01
817.03 CONSTRUCTION REQUIREMENTS . Design temporary works in
accordance with the latest version of AASHTO LRFD Bridge Construction Specifications . Consider appropriately distributed construction loads such as stockpiled materials and construction equipment. Determine member capacities based on field conditions accounting for section loss, deterioration of capacity, alterations of the structure, and support conditions during all construction phases. Conform to Section 801 for submittals.
817.03.1 Temporary Works Designed by Engineer of Record (EOR) :
817.03.1 1 Temporary Detour Bridge : Submit for review shop
drawings for fabricated elements . Submit installation, maintenance and removal plan for review. Conform to Section 803 for drilled shafts, Section 804 for piles and Section 704 for guardrails. Steel will not be required to be coated unless specified. Construct temporary detour bridge as specified . Construct temporary detour road in accordance with Section 725 . Maintain the detour bridge in safe condition. If the contra ctor fails to maintain the detour bridge in a safe condition, the Department reserves the right to act in accordance with 105.16 . Remove the detour bridge in accord ance with 202.03 when no longer required to carry traffic. Fill holes resulting from removal of bridge elements with a granular material. Temporary bridge materials shall remain the property of the contractor unless otherwise specified. Dispose of temporary bridge materials outside the right - of-way.
817.03.1 2 Temporary Sheeting : Submit for record material type and
size, installation, and removal plan. Install and remove temporary sheeting as specified in the plans and specifications in accordance with Section 802 .
817.03.2 Temporary Works Designed by Contractor : Temporary
works are considered to be the contractor’s means and methods. Unless otherwise specified, submittals will be for record. Submit materials, drawings and construction details, and procedures for installation, operation, maintenance and removal. Submit supporti ng documentation such as engineering analysis and design and manufacturer’s information for prefabricated elements. A professional engineer registered in Louisiana shall perform, seal, sign, and date all submitted analysis, related drawings, and design.
817.03.2 1 Construction Access Bridge : Provide a bridge for
construction access within the limits of the specified right -of-way which meets the environmental commitments and hydraulic requirements at the site. Perform all necessary additional clearing and grubbing as required to complete this item. Remove construction access bridge in accordance with 202.03 . Fill holes resulting from removal of bridge elements with a granular material. All materials shall remain the property of the contractor and shall be removed beyond the limits of the right -of-way.
817.03.2 2 Contractor Sheeting: Install and remove contractor
sheeting in accordance with Section 802 when no longer needed for construction, unless otherwise approved.
817.03.2 3 Falsework and Formwork : Support falsework on a
satisfactory foundation and remove upon completion of work. Falsework and formwork shall be set to give the finished structure the specified final position under all loads.
817.03.2 4 Cofferdams : General cofferdam requirements for bidding
Maintain the detour bridge in safe condition. If the contra ctor fails to maintain the detour bridge in a safe condition, the Department reserves the right to act in accordance with 105.16 . Remove the detour bridge in accord ance with 202.03 when no longer required to carry traffic. Fill holes resulting from removal of bridge elements with a granular material. Temporary bridge materials shall remain the property of the contractor unless otherwise specified. Dispose of temporary bridge materials outside the right - of-way.
817.03.1 2 Temporary Sheeting : Submit for record material type and
size, installation, and removal plan. Install and remove temporary sheeting as specified in the plans and specifications in accordance with Section 802 .
817.03.2 Temporary Works Designed by Contractor : Temporary
works are considered to be the contractor’s means and methods. Unless otherwise specified, submittals will be for record. Submit materials, drawings and construction details, and procedures for installation, operation, maintenance and removal. Submit supporti ng documentation such as engineering analysis and design and manufacturer’s information for prefabricated elements. A professional engineer registered in Louisiana shall perform, seal, sign, and date all submitted analysis, related drawings, and design.
817.03.2 1 Construction Access Bridge : Provide a bridge for
construction access within the limits of the specified right -of-way which meets the environmental commitments and hydraulic requirements at the site. Perform all necessary additional clearing and grubbing as required to complete this item. Remove construction access bridge in accordance with 202.03 . Fill holes resulting from removal of bridge elements with a granular material. All materials shall remain the property of the contractor and shall be removed beyond the limits of the right -of-way.
817.03.2 2 Contractor Sheeting: Install and remove contractor
sheeting in accordance with Section 802 when no longer needed for construction, unless otherwise approved.
817.03.2 3 Falsework and Formwork : Support falsework on a
satisfactory foundation and remove upon completion of work. Falsework and formwork shall be set to give the finished structure the specified final position under all loads.
817.03.2 4 Cofferdams : General cofferdam requirements for bidding
Maintain the detour bridge in safe condition. If the contra ctor fails to maintain the detour bridge in a safe condition, the Department reserves the right to act in accordance with 105.16 . Remove the detour bridge in accord ance with 202.03 when no longer required to carry traffic. Fill holes resulting from removal of bridge elements with a granular material. Temporary bridge materials shall remain the property of the contractor unless otherwise specified. Dispose of temporary bridge materials outside the right - of-way.
817.03.1 2 Temporary Sheeting : Submit for record material type and
size, installation, and removal plan. Install and remove temporary sheeting as specified in the plans and specifications in accordance with Section 802 .
817.03.2 Temporary Works Designed by Contractor : Temporary
works are considered to be the contractor’s means and methods. Unless otherwise specified, submittals will be for record. Submit materials, drawings and construction details, and procedures for installation, operation, maintenance and removal. Submit supporti ng documentation such as engineering analysis and design and manufacturer’s information for prefabricated elements. A professional engineer registered in Louisiana shall perform, seal, sign, and date all submitted analysis, related drawings, and design.
817.03.2 1 Construction Access Bridge : Provide a bridge for
construction access within the limits of the specified right -of-way which meets the environmental commitments and hydraulic requirements at the site. Perform all necessary additional clearing and grubbing as required to complete this item. Remove construction access bridge in accordance with 202.03 . Fill holes resulting from removal of bridge elements with a granular material. All materials shall remain the property of the contractor and shall be removed beyond the limits of the right -of-way.
817.03.2 2 Contractor Sheeting: Install and remove contractor
sheeting in accordance with Section 802 when no longer needed for construction, unless otherwise approved.
817.03.2 3 Falsework and Formwork : Support falsework on a
satisfactory foundation and remove upon completion of work. Falsework and formwork shall be set to give the finished structure the specified final position under all loads.
817.03.2 4 Cofferdams : General cofferdam requirements for bidding
Maintain the detour bridge in safe condition. If the contra ctor fails to maintain the detour bridge in a safe condition, the Department reserves the right to act in accordance with 105.16 . Remove the detour bridge in accord ance with 202.03 when no longer required to carry traffic. Fill holes resulting from removal of bridge elements with a granular material. Temporary bridge materials shall remain the property of the contractor unless otherwise specified. Dispose of temporary bridge materials outside the right - of-way.
817.03.1 2 Temporary Sheeting : Submit for record material type and
size, installation, and removal plan. Install and remove temporary sheeting as specified in the plans and specifications in accordance with Section 802 .
817.03.2 Temporary Works Designed by Contractor : Temporary
works are considered to be the contractor’s means and methods. Unless otherwise specified, submittals will be for record. Submit materials, drawings and construction details, and procedures for installation, operation, maintenance and removal. Submit supporti ng documentation such as engineering analysis and design and manufacturer’s information for prefabricated elements. A professional engineer registered in Louisiana shall perform, seal, sign, and date all submitted analysis, related drawings, and design.
817.03.2 1 Construction Access Bridge : Provide a bridge for
construction access within the limits of the specified right -of-way which meets the environmental commitments and hydraulic requirements at the site. Perform all necessary additional clearing and grubbing as required to complete this item. Remove construction access bridge in accordance with 202.03 . Fill holes resulting from removal of bridge elements with a granular material. All materials shall remain the property of the contractor and shall be removed beyond the limits of the right -of-way.
817.03.2 2 Contractor Sheeting: Install and remove contractor
sheeting in accordance with Section 802 when no longer needed for construction, unless otherwise approved.
817.03.2 3 Falsework and Formwork : Support falsework on a
satisfactory foundation and remove upon completion of work. Falsework and formwork shall be set to give the finished structure the specified final position under all loads.
817.03.2 4 Cofferdams : General cofferdam requirements for bidding
Maintain the detour bridge in safe condition. If the contra ctor fails to maintain the detour bridge in a safe condition, the Department reserves the right to act in accordance with 105.16 . Remove the detour bridge in accord ance with 202.03 when no longer required to carry traffic. Fill holes resulting from removal of bridge elements with a granular material. Temporary bridge materials shall remain the property of the contractor unless otherwise specified. Dispose of temporary bridge materials outside the right - of-way.
817.03.1 2 Temporary Sheeting : Submit for record material type and
size, installation, and removal plan. Install and remove temporary sheeting as specified in the plans and specifications in accordance with Section 802 .
817.03.2 Temporary Works Designed by Contractor : Temporary
works are considered to be the contractor’s means and methods. Unless otherwise specified, submittals will be for record. Submit materials, drawings and construction details, and procedures for installation, operation, maintenance and removal. Submit supporti ng documentation such as engineering analysis and design and manufacturer’s information for prefabricated elements. A professional engineer registered in Louisiana shall perform, seal, sign, and date all submitted analysis, related drawings, and design.
817.03.2 1 Construction Access Bridge : Provide a bridge for
construction access within the limits of the specified right -of-way which meets the environmental commitments and hydraulic requirements at the site. Perform all necessary additional clearing and grubbing as required to complete this item. Remove construction access bridge in accordance with 202.03 . Fill holes resulting from removal of bridge elements with a granular material. All materials shall remain the property of the contractor and shall be removed beyond the limits of the right -of-way.
817.03.2 2 Contractor Sheeting: Install and remove contractor
sheeting in accordance with Section 802 when no longer needed for construction, unless otherwise approved.
817.03.2 3 Falsework and Formwork : Support falsework on a
satisfactory foundation and remove upon completion of work. Falsework and formwork shall be set to give the finished structure the specified final position under all loads.
817.03.2 4 Cofferdams : General cofferdam requirements for bidding
Maintain the detour bridge in safe condition. If the contra ctor fails to maintain the detour bridge in a safe condition, the Department reserves the right to act in accordance with 105.16 . Remove the detour bridge in accord ance with 202.03 when no longer required to carry traffic. Fill holes resulting from removal of bridge elements with a granular material. Temporary bridge materials shall remain the property of the contractor unless otherwise specified. Dispose of temporary bridge materials outside the right - of-way.
817.03.1 2 Temporary Sheeting : Submit for record material type and
size, installation, and removal plan. Install and remove temporary sheeting as specified in the plans and specifications in accordance with Section 802 .
817.03.2 Temporary Works Designed by Contractor : Temporary
works are considered to be the contractor’s means and methods. Unless otherwise specified, submittals will be for record. Submit materials, drawings and construction details, and procedures for installation, operation, maintenance and removal. Submit supporti ng documentation such as engineering analysis and design and manufacturer’s information for prefabricated elements. A professional engineer registered in Louisiana shall perform, seal, sign, and date all submitted analysis, related drawings, and design.
817.03.2 1 Construction Access Bridge : Provide a bridge for
construction access within the limits of the specified right -of-way which meets the environmental commitments and hydraulic requirements at the site. Perform all necessary additional clearing and grubbing as required to complete this item. Remove construction access bridge in accordance with 202.03 . Fill holes resulting from removal of bridge elements with a granular material. All materials shall remain the property of the contractor and shall be removed beyond the limits of the right -of-way.
817.03.2 2 Contractor Sheeting: Install and remove contractor
sheeting in accordance with Section 802 when no longer needed for construction, unless otherwise approved.
817.03.2 3 Falsework and Formwork : Support falsework on a
satisfactory foundation and remove upon completion of work. Falsework and formwork shall be set to give the finished structure the specified final position under all loads.
817.03.2 4 Cofferdams : General cofferdam requirements for bidding
Maintain the detour bridge in safe condition. If the contra ctor fails to maintain the detour bridge in a safe condition, the Department reserves the right to act in accordance with 105.16 . Remove the detour bridge in accord ance with 202.03 when no longer required to carry traffic. Fill holes resulting from removal of bridge elements with a granular material. Temporary bridge materials shall remain the property of the contractor unless otherwise specified. Dispose of temporary bridge materials outside the right - of-way.
817.03.1 2 Temporary Sheeting : Submit for record material type and
size, installation, and removal plan. Install and remove temporary sheeting as specified in the plans and specifications in accordance with Section 802 .
817.03.2 Temporary Works Designed by Contractor : Temporary
works are considered to be the contractor’s means and methods. Unless otherwise specified, submittals will be for record. Submit materials, drawings and construction details, and procedures for installation, operation, maintenance and removal. Submit supporti ng documentation such as engineering analysis and design and manufacturer’s information for prefabricated elements. A professional engineer registered in Louisiana shall perform, seal, sign, and date all submitted analysis, related drawings, and design.
817.03.2 1 Construction Access Bridge : Provide a bridge for
construction access within the limits of the specified right -of-way which meets the environmental commitments and hydraulic requirements at the site. Perform all necessary additional clearing and grubbing as required to complete this item. Remove construction access bridge in accordance with 202.03 . Fill holes resulting from removal of bridge elements with a granular material. All materials shall remain the property of the contractor and shall be removed beyond the limits of the right -of-way.
817.03.2 2 Contractor Sheeting: Install and remove contractor
sheeting in accordance with Section 802 when no longer needed for construction, unless otherwise approved.
817.03.2 3 Falsework and Formwork : Support falsework on a
satisfactory foundation and remove upon completion of work. Falsework and formwork shall be set to give the finished structure the specified final position under all loads.
817.03.2 4 Cofferdams : General cofferdam requirements for bidding
purposes may be included in the plans. Design, fabricate, install, maintain , and remove the cofferdam system. The cofferdam system consists of temporary elements such as walls, supporting structural elements, and water control system. The cofferdam seal is part of the permanent structure designed by the EOR. The seal is designed to prevent water ingress and to provide vertical stability to the cofferdam system and foundation during all construction stages. Place the upper one foot of seal concrete in the dry to provide a level surface for forming and constructing the foundation footing. The plan seal and foundation have been designed for vertical stability under the plan specified maximum allowable water surface elevation for dry foundation construction. Flood the cofferdam when the water elevation exceeds the specified maximum allowable water surface elevation. Flooding under this condition will be considered an excusable compensable delay in accordance with 108.07.4 . Cofferdam flooding occurring at water elevations below the specified maximum allowabl e value will be considered a non-excusable delay in accordance with
108.07.5 .
Alterations to the plan seal and foundation will require a Contractor or VE Proposal. Submit the proposal for review. The specified maximum water surface elevation will not be altered. Department cost to review, redesign and detail the seal and foundation will be reimbursed to the Department through Change Order regardless of whether or not the proposal is constructed. Submit a Cofferdam Installation Plan to the Project Engineer for record. Include design assumptions, computations, details of cofferdam system elements, and sequences and methods of construction including excavation, installation of cofferdam system, and construction of seal and foundation, and cofferdam system removal. Include cofferdam system components to remain in the perman ent work, repair methods and repair materials. The Cofferdam Installation Plan shall be designed, sealed, signed and dated by a professional engineer registered in Louisiana. Design and construct cofferdam so that system and components safely perform under all aspects of global, external and structural stability during each stage of construction, including anchorage, embedment, and loads from balanced and unbalanced soil, water, and construction activities. Provide sufficient interior clearances for form construction, inspection of form exteriors, and to permit control of water. Cofferdams that tilt or move laterally shall be righted, reset, and enlarged as needed to provide necessary interior clearances. Control ingress of water so that construction can be performed in the dry. Dewater after seal concrete has cured. When weighted cofferdams are employed and the weight is utilized to participate in vertical stability of the system, provide anchorage to transfer cofferdam system weight to the seal. During placing and curing of seal, control the water elevation inside the cofferdam to prevent water flow through the seal. If the cofferdam is permitted by the engineer or required by the plans to remain in place, vent or port cofferdam at or below low-water level. Re-establish pre-construction ground elevations inside and outside of the cofferdam in accordance with Section 802 . Remove cofferdam system after completion of the work without damaging the finished work or existing adjacent structures. Portions of the cofferdam system which remain within concrete perman ent work in accordance with the Cofferdam Installation Plan shall be removed to at least 6 inches from the surface of the permanent work. Use block outs to facilitate removal and patch permanent work with compatible materials conforming to the plans and the Cofferdam Installation Plan.
817.03.2 5 Water Control Systems :
817.03.2 5.1 Well Point System : When required by plans or the
engineer, a well point system shall be designed, detailed, installed, maintained, and removed by the contractor. Install the well point system arou nd the perimeter of the excavated area in a location such that other operations will not be impeded. The well point system shall continuously maintain the piezometric level in the soil at least 5 feet below the bottom of the excavated area. When well poin ts are no longer required for water control, plug abandoned well in accordance with 202.06 . Install piezometers or other suitable means of monitoring within the exc avated area as required by field conditions. Make daily readings or measurements of the piezometers to verify that the well point system is operational. Excavation may begin when the level is 5 feet below the proposed excavation bottom surface for at least four hours. Provide the well point system with a back -up system of pumps and power units. If failure of the well point system occurs, add water to the excavation as rapidly as possible at no additional cost or time to the Department. Notify the enginee r after completing each excavation. Do not place concrete until the engineer has accepted the excavation.
817.03.2 6 Cleaning and Painting Containment Systems : General
containment system requirements for bidding purposes may be included in the Control ingress of water so that construction can be performed in the dry. Dewater after seal concrete has cured. When weighted cofferdams are employed and the weight is utilized to participate in vertical stability of the system, provide anchorage to transfer cofferdam system weight to the seal. During placing and curing of seal, control the water elevation inside the cofferdam to prevent water flow through the seal. If the cofferdam is permitted by the engineer or required by the plans to remain in place, vent or port cofferdam at or below low-water level. Re-establish pre-construction ground elevations inside and outside of the cofferdam in accordance with Section 802 . Remove cofferdam system after completion of the work without damaging the finished work or existing adjacent structures. Portions of the cofferdam system which remain within concrete perman ent work in accordance with the Cofferdam Installation Plan shall be removed to at least 6 inches from the surface of the permanent work. Use block outs to facilitate removal and patch permanent work with compatible materials conforming to the plans and the Cofferdam Installation Plan.
817.03.2 5 Water Control Systems :
817.03.2 5.1 Well Point System : When required by plans or the
engineer, a well point system shall be designed, detailed, installed, maintained, and removed by the contractor. Install the well point system arou nd the perimeter of the excavated area in a location such that other operations will not be impeded. The well point system shall continuously maintain the piezometric level in the soil at least 5 feet below the bottom of the excavated area. When well poin ts are no longer required for water control, plug abandoned well in accordance with 202.06 . Install piezometers or other suitable means of monitoring within the exc avated area as required by field conditions. Make daily readings or measurements of the piezometers to verify that the well point system is operational. Excavation may begin when the level is 5 feet below the proposed excavation bottom surface for at least four hours. Provide the well point system with a back -up system of pumps and power units. If failure of the well point system occurs, add water to the excavation as rapidly as possible at no additional cost or time to the Department. Notify the enginee r after completing each excavation. Do not place concrete until the engineer has accepted the excavation.
817.03.2 6 Cleaning and Painting Containment Systems : General
containment system requirements for bidding purposes may be included in the Control ingress of water so that construction can be performed in the dry. Dewater after seal concrete has cured. When weighted cofferdams are employed and the weight is utilized to participate in vertical stability of the system, provide anchorage to transfer cofferdam system weight to the seal. During placing and curing of seal, control the water elevation inside the cofferdam to prevent water flow through the seal. If the cofferdam is permitted by the engineer or required by the plans to remain in place, vent or port cofferdam at or below low-water level. Re-establish pre-construction ground elevations inside and outside of the cofferdam in accordance with Section 802 . Remove cofferdam system after completion of the work without damaging the finished work or existing adjacent structures. Portions of the cofferdam system which remain within concrete perman ent work in accordance with the Cofferdam Installation Plan shall be removed to at least 6 inches from the surface of the permanent work. Use block outs to facilitate removal and patch permanent work with compatible materials conforming to the plans and the Cofferdam Installation Plan.
817.03.2 5 Water Control Systems :
817.03.2 5.1 Well Point System : When required by plans or the
engineer, a well point system shall be designed, detailed, installed, maintained, and removed by the contractor. Install the well point system arou nd the perimeter of the excavated area in a location such that other operations will not be impeded. The well point system shall continuously maintain the piezometric level in the soil at least 5 feet below the bottom of the excavated area. When well poin ts are no longer required for water control, plug abandoned well in accordance with 202.06 . Install piezometers or other suitable means of monitoring within the exc avated area as required by field conditions. Make daily readings or measurements of the piezometers to verify that the well point system is operational. Excavation may begin when the level is 5 feet below the proposed excavation bottom surface for at least four hours. Provide the well point system with a back -up system of pumps and power units. If failure of the well point system occurs, add water to the excavation as rapidly as possible at no additional cost or time to the Department. Notify the enginee r after completing each excavation. Do not place concrete until the engineer has accepted the excavation.
817.03.2 6 Cleaning and Painting Containment Systems : General
containment system requirements for bidding purposes may be included in the Control ingress of water so that construction can be performed in the dry. Dewater after seal concrete has cured. When weighted cofferdams are employed and the weight is utilized to participate in vertical stability of the system, provide anchorage to transfer cofferdam system weight to the seal. During placing and curing of seal, control the water elevation inside the cofferdam to prevent water flow through the seal. If the cofferdam is permitted by the engineer or required by the plans to remain in place, vent or port cofferdam at or below low-water level. Re-establish pre-construction ground elevations inside and outside of the cofferdam in accordance with Section 802 . Remove cofferdam system after completion of the work without damaging the finished work or existing adjacent structures. Portions of the cofferdam system which remain within concrete perman ent work in accordance with the Cofferdam Installation Plan shall be removed to at least 6 inches from the surface of the permanent work. Use block outs to facilitate removal and patch permanent work with compatible materials conforming to the plans and the Cofferdam Installation Plan.
817.03.2 5 Water Control Systems :
817.03.2 5.1 Well Point System : When required by plans or the
engineer, a well point system shall be designed, detailed, installed, maintained, and removed by the contractor. Install the well point system arou nd the perimeter of the excavated area in a location such that other operations will not be impeded. The well point system shall continuously maintain the piezometric level in the soil at least 5 feet below the bottom of the excavated area. When well poin ts are no longer required for water control, plug abandoned well in accordance with 202.06 . Install piezometers or other suitable means of monitoring within the exc avated area as required by field conditions. Make daily readings or measurements of the piezometers to verify that the well point system is operational. Excavation may begin when the level is 5 feet below the proposed excavation bottom surface for at least four hours. Provide the well point system with a back -up system of pumps and power units. If failure of the well point system occurs, add water to the excavation as rapidly as possible at no additional cost or time to the Department. Notify the enginee r after completing each excavation. Do not place concrete until the engineer has accepted the excavation.
817.03.2 6 Cleaning and Painting Containment Systems : General
containment system requirements for bidding purposes may be included in the plans. Design, fabricate, install, operate, maintain, and remove the containment system. Design and construct the containment system in accordance with the Contract and SSPC Guide 6, Guide for Containing Debris Generated During Paint Removal Activities. Unless speci fied otherwise, provide a Class 1A containment system. Determine member capacities based on field conditions accounting for section loss, deterioration of capacity, alterations of the structure, and support conditions during all construction phases. In addition, suspended scaffolding shall be designed in accordance with the requirements of 29 CFR § 1926 Subpart (L).
817.03.2 6.1 Containment System Plan Submittal : Prepare and
submit for review Containment System Plan in accordance with 811.05 . The Containment System Plan and calculations shall be prepared, sealed, signed and dated by a professional engineer registered in Louisiana. Submit reviewed and accepted Containment S ystem Plan as part of the Pollution Control and Monitoring Plan in accordance with 811.05.9 . Include in the Containment System Plan as a minimum the following :
817.03.2 6.1 Containment System Plan Submittal : Prepare and
submit for review Containment System Plan in accordance with 811.05 . The Containment System Plan and calculations shall be prepared, sealed, signed and dated by a professional engineer registered in Louisiana. Submit reviewed and accepted Containment S ystem Plan as part of the Pollution Control and Monitoring Plan in accordance with 811.05.9 . Include in the Containment System Plan as a minimum the following :
817.03.2 6.2 Design and Construction Requirements :
Design, construct, operate, and maintain containment system in accordance with
811.09.5 and Section 817 .
Provide environmental, public and worker protection complying with 811.09 and the contract. Provide specified and required external and internal clearances. Design, construct, operate, and maintain containment system to minimize vehicular, railway, and marine traffic disruptions. Unless otherwise specified, maintain existing vertical and horizontal highway, railway and waterway clearances. Provide capability of being removed, retracted, or opened to reduce wind load on the structure during adverse weather or to maintain required vertical and horizontal highway, railway, and waterway clearances. Provide a containment system that can be removed or lowered and secured within 24 hours. Limit the containment system size to an area that will not damage the structure under a 55 mph wind speed. Design, construct, operate, and maintain containment system so that the additional dead, live, and wind loads imposed by the containment system and construction activities do not cause damage to the structure, overstress of bridge members, or compromise the structural integrity of the bridge. Permanent attachment s or removal of existing fasteners to make temporary connections to the structure will not be allowed without written approval of the Bridge Engineer. Weld ing or drilling and bolting connections to steel bridge members are prohibited . Attachments to substructure elements are subject to review and acceptance by the Bridge Engineer. Attachments shall be temporary and shall not cause damage to the structure . Design and construct platforms and their components to support at least four times their maximum applied load. Design, construct, operate, and maintain cables to support at least six times their maximum applied load. Comply with applicable OSHA regulations regarding rigging, staging, and scaffolding. At a minimum, meet OSHA 3150, A Guide to Scaffolding Use in the Construction Industry and Federal Specification RR-C-27-102, Chains and Attachments -Welded and Weldless. Design, construct, operate, and maintain inside lighting in accordance with SSPC Guide 12, Guide for Illumination of Industrial Painting Projects. Provide lighting to a minimum intensity of 20 ft-cd for general, 50 ft-cd for work, and 200 ft-cd for inspection. Use fire retardant materials. The containment system EOR shall certify that each installation conforms to the submitted, reviewed, and accepted Containment System Plan prior to use and shall inspect and recertify after each modification and after any hurricane, tropical storm, or local storm event affecting the work area.
817.03.2 6.2 Design and Construction Requirements :
Design, construct, operate, and maintain containment system in accordance with
811.09.5 and Section 817 .
Provide environmental, public and worker protection complying with 811.09 and the contract. Provide specified and required external and internal clearances. Design, construct, operate, and maintain containment system to minimize vehicular, railway, and marine traffic disruptions. Unless otherwise specified, maintain existing vertical and horizontal highway, railway and waterway clearances. Provide capability of being removed, retracted, or opened to reduce wind load on the structure during adverse weather or to maintain required vertical and horizontal highway, railway, and waterway clearances. Provide a containment system that can be removed or lowered and secured within 24 hours. Limit the containment system size to an area that will not damage the structure under a 55 mph wind speed. Design, construct, operate, and maintain containment system so that the additional dead, live, and wind loads imposed by the containment system and construction activities do not cause damage to the structure, overstress of bridge members, or compromise the structural integrity of the bridge. Permanent attachment s or removal of existing fasteners to make temporary connections to the structure will not be allowed without written approval of the Bridge Engineer. Weld ing or drilling and bolting connections to steel bridge members are prohibited . Attachments to substructure elements are subject to review and acceptance by the Bridge Engineer. Attachments shall be temporary and shall not cause damage to the structure . Design and construct platforms and their components to support at least four times their maximum applied load. Design, construct, operate, and maintain cables to support at least six times their maximum applied load. Comply with applicable OSHA regulations regarding rigging, staging, and scaffolding. At a minimum, meet OSHA 3150, A Guide to Scaffolding Use in the Construction Industry and Federal Specification RR-C-27-102, Chains and Attachments -Welded and Weldless. Design, construct, operate, and maintain inside lighting in accordance with SSPC Guide 12, Guide for Illumination of Industrial Painting Projects. Provide lighting to a minimum intensity of 20 ft-cd for general, 50 ft-cd for work, and 200 ft-cd for inspection. Use fire retardant materials. The containment system EOR shall certify that each installation conforms to the submitted, reviewed, and accepted Containment System Plan prior to use and shall inspect and recertify after each modification and after any hurricane, tropical storm, or local storm event affecting the work area. Maintain the containment system and comply with the working drawings. Modifications require prior submittal, review and acceptance by the Project Engineer. Coordination through the Project Engineer with permitting agencies is required for construction activities involving structures over waterways. U.S. Coast Guard approval will be required for any closures of, obstructions within, or reductions of vertical or horizontal clearance within navigable waterways. Comply with all requirements for interruptions, closures, obstructions, and clearance reductions affecting marine traffic . Waterway permits and requirements shall be obtained and coordinated through the Project Engine er. For emergencies affecting navigation, immediately and directly contact the U.S. Coast Guard and/or the U.S. Coast Guard Marine Safety Office, and then notify the Project Engineer. Activities in the waterway will not be allowed without prior approval of the US Coast Guard. Existing navigation lighting and aerial beacons shall be maintained at all times for the duration of the contract as well as additional containment obstructio n lighting required by the U.S. Coast Guard. In the event of a named hurricane or tropical storm forecasted to enter the work area within 72 hours, or in the event of an evacuation order in the work area, remove and re-install the containment system, equipment, and materials. The resulting delay will be considered an excusable, compensable delay in accordance with 108.07 and reimbursement will be made by force account in accordance with 109.0 4.3. Repair damage to the structure caused by the containment system or construction activities to the satisfaction of the Project Engineer. Submit repair procedures to the Project Engineer for review prior to performing repairs.
817.04 Measurement .
817.04.1 Temporary Detour Bridge : Temporary detour bridge will be
measured by the square foot of completed bridge and shall include construction, all striping, removal of the detour bridge, and restor ation of the affected project site to pre-construction condition. When constructed in accordance with the design shown on the plans, measurement will be made by multiplying the clear roadway width by the length of bridge from beginning bridge joint at abu tment to ending bridge joint at abutment. When allowed, and constructed with an alternate design, the measurement will not exceed the quantity required for the design shown on the plans. When the contract does not include items for “Temporary Pavement Mar kings,” these markings will be included in the items for “Temporary Detour Bridge.” Maintain the containment system and comply with the working drawings. Modifications require prior submittal, review and acceptance by the Project Engineer. Coordination through the Project Engineer with permitting agencies is required for construction activities involving structures over waterways. U.S. Coast Guard approval will be required for any closures of, obstructions within, or reductions of vertical or horizontal clearance within navigable waterways. Comply with all requirements for interruptions, closures, obstructions, and clearance reductions affecting marine traffic . Waterway permits and requirements shall be obtained and coordinated through the Project Engine er. For emergencies affecting navigation, immediately and directly contact the U.S. Coast Guard and/or the U.S. Coast Guard Marine Safety Office, and then notify the Project Engineer. Activities in the waterway will not be allowed without prior approval of the US Coast Guard. Existing navigation lighting and aerial beacons shall be maintained at all times for the duration of the contract as well as additional containment obstructio n lighting required by the U.S. Coast Guard. In the event of a named hurricane or tropical storm forecasted to enter the work area within 72 hours, or in the event of an evacuation order in the work area, remove and re-install the containment system, equipment, and materials. The resulting delay will be considered an excusable, compensable delay in accordance with 108.07 and reimbursement will be made by force account in accordance with 109.0 4.3. Repair damage to the structure caused by the containment system or construction activities to the satisfaction of the Project Engineer. Submit repair procedures to the Project Engineer for review prior to performing repairs.
817.04 Measurement .
817.04.1 Temporary Detour Bridge : Temporary detour bridge will be
measured by the square foot of completed bridge and shall include construction, all striping, removal of the detour bridge, and restor ation of the affected project site to pre-construction condition. When constructed in accordance with the design shown on the plans, measurement will be made by multiplying the clear roadway width by the length of bridge from beginning bridge joint at abu tment to ending bridge joint at abutment. When allowed, and constructed with an alternate design, the measurement will not exceed the quantity required for the design shown on the plans. When the contract does not include items for “Temporary Pavement Mar kings,” these markings will be included in the items for “Temporary Detour Bridge.” Maintain the containment system and comply with the working drawings. Modifications require prior submittal, review and acceptance by the Project Engineer. Coordination through the Project Engineer with permitting agencies is required for construction activities involving structures over waterways. U.S. Coast Guard approval will be required for any closures of, obstructions within, or reductions of vertical or horizontal clearance within navigable waterways. Comply with all requirements for interruptions, closures, obstructions, and clearance reductions affecting marine traffic . Waterway permits and requirements shall be obtained and coordinated through the Project Engine er. For emergencies affecting navigation, immediately and directly contact the U.S. Coast Guard and/or the U.S. Coast Guard Marine Safety Office, and then notify the Project Engineer. Activities in the waterway will not be allowed without prior approval of the US Coast Guard. Existing navigation lighting and aerial beacons shall be maintained at all times for the duration of the contract as well as additional containment obstructio n lighting required by the U.S. Coast Guard. In the event of a named hurricane or tropical storm forecasted to enter the work area within 72 hours, or in the event of an evacuation order in the work area, remove and re-install the containment system, equipment, and materials. The resulting delay will be considered an excusable, compensable delay in accordance with 108.07 and reimbursement will be made by force account in accordance with 109.0 4.3. Repair damage to the structure caused by the containment system or construction activities to the satisfaction of the Project Engineer. Submit repair procedures to the Project Engineer for review prior to performing repairs.
817.04 Measurement .
817.04.1 Temporary Detour Bridge : Temporary detour bridge will be
measured by the square foot of completed bridge and shall include construction, all striping, removal of the detour bridge, and restor ation of the affected project site to pre-construction condition. When constructed in accordance with the design shown on the plans, measurement will be made by multiplying the clear roadway width by the length of bridge from beginning bridge joint at abu tment to ending bridge joint at abutment. When allowed, and constructed with an alternate design, the measurement will not exceed the quantity required for the design shown on the plans. When the contract does not include items for “Temporary Pavement Mar kings,” these markings will be included in the items for “Temporary Detour Bridge.”
817.04.2 Construction Access Bridge : When an item for “Construction
Access Bridge” is included in the contract, the construction access bridge will be measured on a lump sum basi s and shall include construction and removal of the access bridge and restoration of the affected project site to pre -construction condition. When the contract does not contain an item for “Construction Access Bridge,” the construction access bridge constr uction, removal and restoration of the affected project site to pre -construction condition will not be measured for payment. Incidental items such as additional clearing and grubbing will not be measured for payment.
817.04.3 Temporary and Contractor Sheeting : Temporary sheeting
will be measured in accordance with Section 802 . Contractor sheeting will not be measured for payment.
817.04.4 Falsework and Formwork : Falsework and formwork will not be
measured for payment.
817.04.5 Cofferdams : When an item for “Cofferdams” is incl uded in the
contract, the cofferdams will be measured on a lump sum basis. When the contract does not contain an item for “Cofferdams,” the cofferdams and cribs will not be measured for payment.
817.04.6 Water Control System: When an item for “Water Control
System,” is included in the contract, the water control system will be measured on a lump sum basis. Plugging of wells for well point systems will not be measured for payment and will be included in the cost for the water control system. When the contract does not contain an item for “Water Control System”, the contractor may use any approved method to control the seepage water as required within the specifications. The water control system used will not be measured for payment.
817.04.7 Cleaning and Painting Cont ainment System : The cleaning
and painting containment system will not be measured for payment and will be constructed in accordance with Section 811 and Section 817 .
817.05 PAYMENT. Payment for Temporary Works furnished, constructed,
maintained, removed and restoration of the affected project site to pre -construction condition will be made at the contract unit price, which will include all material, labor, equipment, maintenance, submittals, and incidentals necessary to complete the item. When design is required, include the cost in the respective items. Payment will be made under:
817.04.2 Construction Access Bridge : When an item for “Construction
Access Bridge” is included in the contract, the construction access bridge will be measured on a lump sum basi s and shall include construction and removal of the access bridge and restoration of the affected project site to pre -construction condition. When the contract does not contain an item for “Construction Access Bridge,” the construction access bridge constr uction, removal and restoration of the affected project site to pre -construction condition will not be measured for payment. Incidental items such as additional clearing and grubbing will not be measured for payment.
817.04.3 Temporary and Contractor Sheeting : Temporary sheeting
will be measured in accordance with Section 802 . Contractor sheeting will not be measured for payment.
817.04.4 Falsework and Formwork : Falsework and formwork will not be
measured for payment.
817.04.5 Cofferdams : When an item for “Cofferdams” is incl uded in the
contract, the cofferdams will be measured on a lump sum basis. When the contract does not contain an item for “Cofferdams,” the cofferdams and cribs will not be measured for payment.
817.04.6 Water Control System: When an item for “Water Control
System,” is included in the contract, the water control system will be measured on a lump sum basis. Plugging of wells for well point systems will not be measured for payment and will be included in the cost for the water control system. When the contract does not contain an item for “Water Control System”, the contractor may use any approved method to control the seepage water as required within the specifications. The water control system used will not be measured for payment.
817.04.7 Cleaning and Painting Cont ainment System : The cleaning
and painting containment system will not be measured for payment and will be constructed in accordance with Section 811 and Section 817 .
817.05 PAYMENT. Payment for Temporary Works furnished, constructed,
maintained, removed and restoration of the affected project site to pre -construction condition will be made at the contract unit price, which will include all material, labor, equipment, maintenance, submittals, and incidentals necessary to complete the item. When design is required, include the cost in the respective items. Payment will be made under:
817.04.2 Construction Access Bridge : When an item for “Construction
Access Bridge” is included in the contract, the construction access bridge will be measured on a lump sum basi s and shall include construction and removal of the access bridge and restoration of the affected project site to pre -construction condition. When the contract does not contain an item for “Construction Access Bridge,” the construction access bridge constr uction, removal and restoration of the affected project site to pre -construction condition will not be measured for payment. Incidental items such as additional clearing and grubbing will not be measured for payment.
817.04.3 Temporary and Contractor Sheeting : Temporary sheeting
will be measured in accordance with Section 802 . Contractor sheeting will not be measured for payment.
817.04.4 Falsework and Formwork : Falsework and formwork will not be
measured for payment.
817.04.5 Cofferdams : When an item for “Cofferdams” is incl uded in the
contract, the cofferdams will be measured on a lump sum basis. When the contract does not contain an item for “Cofferdams,” the cofferdams and cribs will not be measured for payment.
817.04.6 Water Control System: When an item for “Water Control
System,” is included in the contract, the water control system will be measured on a lump sum basis. Plugging of wells for well point systems will not be measured for payment and will be included in the cost for the water control system. When the contract does not contain an item for “Water Control System”, the contractor may use any approved method to control the seepage water as required within the specifications. The water control system used will not be measured for payment.
817.04.7 Cleaning and Painting Cont ainment System : The cleaning
and painting containment system will not be measured for payment and will be constructed in accordance with Section 811 and Section 817 .
817.05 PAYMENT. Payment for Temporary Works furnished, constructed,
maintained, removed and restoration of the affected project site to pre -construction condition will be made at the contract unit price, which will include all material, labor, equipment, maintenance, submittals, and incidentals necessary to complete the item. When design is required, include the cost in the respective items. Payment will be made under:
817.04.2 Construction Access Bridge : When an item for “Construction
Access Bridge” is included in the contract, the construction access bridge will be measured on a lump sum basi s and shall include construction and removal of the access bridge and restoration of the affected project site to pre -construction condition. When the contract does not contain an item for “Construction Access Bridge,” the construction access bridge constr uction, removal and restoration of the affected project site to pre -construction condition will not be measured for payment. Incidental items such as additional clearing and grubbing will not be measured for payment.
817.04.3 Temporary and Contractor Sheeting : Temporary sheeting
will be measured in accordance with Section 802 . Contractor sheeting will not be measured for payment.
817.04.4 Falsework and Formwork : Falsework and formwork will not be
measured for payment.
817.04.5 Cofferdams : When an item for “Cofferdams” is incl uded in the
contract, the cofferdams will be measured on a lump sum basis. When the contract does not contain an item for “Cofferdams,” the cofferdams and cribs will not be measured for payment.
817.04.6 Water Control System: When an item for “Water Control
System,” is included in the contract, the water control system will be measured on a lump sum basis. Plugging of wells for well point systems will not be measured for payment and will be included in the cost for the water control system. When the contract does not contain an item for “Water Control System”, the contractor may use any approved method to control the seepage water as required within the specifications. The water control system used will not be measured for payment.
817.04.7 Cleaning and Painting Cont ainment System : The cleaning
and painting containment system will not be measured for payment and will be constructed in accordance with Section 811 and Section 817 .
817.05 PAYMENT. Payment for Temporary Works furnished, constructed,
maintained, removed and restoration of the affected project site to pre -construction condition will be made at the contract unit price, which will include all material, labor, equipment, maintenance, submittals, and incidentals necessary to complete the item. When design is required, include the cost in the respective items. Payment will be made under:
817.04.2 Construction Access Bridge : When an item for “Construction
Access Bridge” is included in the contract, the construction access bridge will be measured on a lump sum basi s and shall include construction and removal of the access bridge and restoration of the affected project site to pre -construction condition. When the contract does not contain an item for “Construction Access Bridge,” the construction access bridge constr uction, removal and restoration of the affected project site to pre -construction condition will not be measured for payment. Incidental items such as additional clearing and grubbing will not be measured for payment.
817.04.3 Temporary and Contractor Sheeting : Temporary sheeting
will be measured in accordance with Section 802 . Contractor sheeting will not be measured for payment.
817.04.4 Falsework and Formwork : Falsework and formwork will not be
measured for payment.
817.04.5 Cofferdams : When an item for “Cofferdams” is incl uded in the
contract, the cofferdams will be measured on a lump sum basis. When the contract does not contain an item for “Cofferdams,” the cofferdams and cribs will not be measured for payment.
817.04.6 Water Control System: When an item for “Water Control
System,” is included in the contract, the water control system will be measured on a lump sum basis. Plugging of wells for well point systems will not be measured for payment and will be included in the cost for the water control system. When the contract does not contain an item for “Water Control System”, the contractor may use any approved method to control the seepage water as required within the specifications. The water control system used will not be measured for payment.
817.04.7 Cleaning and Painting Cont ainment System : The cleaning
and painting containment system will not be measured for payment and will be constructed in accordance with Section 811 and Section 817 .
817.05 PAYMENT. Payment for Temporary Works furnished, constructed,
maintained, removed and restoration of the affected project site to pre -construction condition will be made at the contract unit price, which will include all material, labor, equipment, maintenance, submittals, and incidentals necessary to complete the item. When design is required, include the cost in the respective items. Payment will be made under:
817.04.2 Construction Access Bridge : When an item for “Construction
Access Bridge” is included in the contract, the construction access bridge will be measured on a lump sum basi s and shall include construction and removal of the access bridge and restoration of the affected project site to pre -construction condition. When the contract does not contain an item for “Construction Access Bridge,” the construction access bridge constr uction, removal and restoration of the affected project site to pre -construction condition will not be measured for payment. Incidental items such as additional clearing and grubbing will not be measured for payment.
817.04.3 Temporary and Contractor Sheeting : Temporary sheeting
will be measured in accordance with Section 802 . Contractor sheeting will not be measured for payment.
817.04.4 Falsework and Formwork : Falsework and formwork will not be
measured for payment.
817.04.5 Cofferdams : When an item for “Cofferdams” is incl uded in the
contract, the cofferdams will be measured on a lump sum basis. When the contract does not contain an item for “Cofferdams,” the cofferdams and cribs will not be measured for payment.
817.04.6 Water Control System: When an item for “Water Control
System,” is included in the contract, the water control system will be measured on a lump sum basis. Plugging of wells for well point systems will not be measured for payment and will be included in the cost for the water control system. When the contract does not contain an item for “Water Control System”, the contractor may use any approved method to control the seepage water as required within the specifications. The water control system used will not be measured for payment.
817.04.7 Cleaning and Painting Cont ainment System : The cleaning
and painting containment system will not be measured for payment and will be constructed in accordance with Section 811 and Section 817 .
817.05 PAYMENT. Payment for Temporary Works furnished, constructed,
maintained, removed and restoration of the affected project site to pre -construction condition will be made at the contract unit price, which will include all material, labor, equipment, maintenance, submittals, and incidentals necessary to complete the item. When design is required, include the cost in the respective items. Payment will be made under:
817.04.2 Construction Access Bridge : When an item for “Construction
Access Bridge” is included in the contract, the construction access bridge will be measured on a lump sum basi s and shall include construction and removal of the access bridge and restoration of the affected project site to pre -construction condition. When the contract does not contain an item for “Construction Access Bridge,” the construction access bridge constr uction, removal and restoration of the affected project site to pre -construction condition will not be measured for payment. Incidental items such as additional clearing and grubbing will not be measured for payment.
817.04.3 Temporary and Contractor Sheeting : Temporary sheeting
will be measured in accordance with Section 802 . Contractor sheeting will not be measured for payment.
817.04.4 Falsework and Formwork : Falsework and formwork will not be
measured for payment.
817.04.5 Cofferdams : When an item for “Cofferdams” is incl uded in the
contract, the cofferdams will be measured on a lump sum basis. When the contract does not contain an item for “Cofferdams,” the cofferdams and cribs will not be measured for payment.
817.04.6 Water Control System: When an item for “Water Control
System,” is included in the contract, the water control system will be measured on a lump sum basis. Plugging of wells for well point systems will not be measured for payment and will be included in the cost for the water control system. When the contract does not contain an item for “Water Control System”, the contractor may use any approved method to control the seepage water as required within the specifications. The water control system used will not be measured for payment.
817.04.7 Cleaning and Painting Cont ainment System : The cleaning
and painting containment system will not be measured for payment and will be constructed in accordance with Section 811 and Section 817 .
817.05 PAYMENT. Payment for Temporary Works furnished, constructed,
maintained, removed and restoration of the affected project site to pre -construction condition will be made at the contract unit price, which will include all material, labor, equipment, maintenance, submittals, and incidentals necessary to complete the item. When design is required, include the cost in the respective items. Payment will be made under:
817.04.2 Construction Access Bridge : When an item for “Construction
Access Bridge” is included in the contract, the construction access bridge will be measured on a lump sum basi s and shall include construction and removal of the access bridge and restoration of the affected project site to pre -construction condition. When the contract does not contain an item for “Construction Access Bridge,” the construction access bridge constr uction, removal and restoration of the affected project site to pre -construction condition will not be measured for payment. Incidental items such as additional clearing and grubbing will not be measured for payment.
817.04.3 Temporary and Contractor Sheeting : Temporary sheeting
will be measured in accordance with Section 802 . Contractor sheeting will not be measured for payment.
817.04.4 Falsework and Formwork : Falsework and formwork will not be
measured for payment.
817.04.5 Cofferdams : When an item for “Cofferdams” is incl uded in the
contract, the cofferdams will be measured on a lump sum basis. When the contract does not contain an item for “Cofferdams,” the cofferdams and cribs will not be measured for payment.
817.04.6 Water Control System: When an item for “Water Control
System,” is included in the contract, the water control system will be measured on a lump sum basis. Plugging of wells for well point systems will not be measured for payment and will be included in the cost for the water control system. When the contract does not contain an item for “Water Control System”, the contractor may use any approved method to control the seepage water as required within the specifications. The water control system used will not be measured for payment.
817.04.7 Cleaning and Painting Cont ainment System : The cleaning
and painting containment system will not be measured for payment and will be constructed in accordance with Section 811 and Section 817 .
817.05 PAYMENT. Payment for Temporary Works furnished, constructed,
maintained, removed and restoration of the affected project site to pre -construction condition will be made at the contract unit price, which will include all material, labor, equipment, maintenance, submittals, and incidentals necessary to complete the item. When design is required, include the cost in the respective items. Payment will be made under: Item No. Pay Item Pay Unit 817-01 Temporary Detour Bridge Square Foot 817-02 Construction Access Bridge Lump Sum 817-03 Cofferdams Lump Sum 817-04 Water Control System (Type) Lump Sum Section 818 Marine Pier Protection
818.01 DESCRIPTION. Furnish, install, and construct pier protection systems
and components of the type and dimensions at locations specified.
818.02 MATERIALS. Comply with the following:
Structural Concrete Deformed Reinforcing Steel Metals Section 805 Section 806 , Section 1009 Section 807 , Section 1013 Welding 809 Treated Tim ber Portland Cement Concrete Section 812 Section 901 Unless otherwise specified, use AASHTO M270 Grade 50 steel for structural steel components and hot dip galvanize after fabrication in accordance with Section 811. For structural steel connections, u se ASTM A325 Type 1 mechanically galvanized high strength fastener assemblies in the sizes and lengths specified and in accordance with Section 807 . Mechanically galvanize in accordance with 811.08 . Unless otherwise specified , use ASTM F593 stainless steel bolts with ASTM F594 stainless steel nuts and stainless steel washers (Alloy 304) for whaler and panel connections. Unless otherwise specified, use 0.5 inch 1x19 Type 316 stainless steel wire rope and stainless steel hardwar e. For materials in 818.02.2 through 818.02.5 , use an accredited third party laboratory to test materials for compliance with perform ance requirements. For material compliance verification, submit to the Project Engineer for review the “Certificate of Analysis” and material test results showing that the material meets the specification criteria .
818.02.1 Pier Protection Systems : Use materials specified in the plans.
818.02.2 Ultra -High Molecular Weight Polyethylene (UHMW -PE)
Panels : use ultra -high molecular weight polyethylene panels conforming to ASTM D4020. Use material with a specific gravity of 0.926 to 0.945 in accordance with ASTM D792, a mini mum ultimate tensile strength of 4100 to 5100 psi and elongation at break of 330 to 420 percent in accordance with ASTM D638. Chamfer the outer edges to the specified dimensions. Color material as specified in