Structural Excavation, Backfill and Earth Retaining Systems
802.01 DESCRIPTION. Excavate materials necessary to facilitate
construction. Furnish, place, and compact backfill. Dispose of excess excavated material and obstructions in accordance with Section 202 , as directed by the Project Engineer, so that such activities will neither adversely affect hydraulics nor be unsightly. Furnish and install sheet ing of the type, size, dimensions , and locations specified meeting the required penetration and resistance with an undamaged cross -section. Design, f urnish , and construct Mechanically Stabilized Earth Walls (MSEW) in conformance with the lines, grades, design, geotechnical requirements, and dimensions shown on the plans and the MSEW specifications .
802.02 MATERIALS . Comply with the following unless otherwise
specified: Concrete Section 901 Coal Tar Epoxy -Polyamide Paint 1008.04 Reinforcing Steel Section 1009 Hardware Section 1013 Metal Sheet Piles 1013.10 Timber and Preservatives Section 1014
802.03 Struc Tural Excavation .
802.03.1 General Requirements : Excavation s shall be shored,
sheeted, or braced in accordance with 701.03 or as required. With the approval of the Project Engineer, formwork for footings may be omitted when the control of water is sufficient to allow construction in the dry. In such cases, provide excavation to plan dimensions. When required, provide water control in accordance with Section 817 .
802.03.2 Preservation of Channel : Unless approved by the
Project Engineer, do not excavate outside of sheeting, cofferdams, cribs, or caissons or disturb the natural stream bed adjacent to the structure. If excavating or dredgi ng at the site of the foundation, then, under agreement Structural Excavation, Backfill and Earth Retaining Systems
802.01 DESCRIPTION. Excavate materials necessary to facilitate
construction. Furnish, place, and compact backfill. Dispose of excess excavated material and obstructions in accordance with Section 202 , as directed by the Project Engineer, so that such activities will neither adversely affect hydraulics nor be unsightly. Furnish and install sheet ing of the type, size, dimensions , and locations specified meeting the required penetration and resistance with an undamaged cross -section. Design, f urnish , and construct Mechanically Stabilized Earth Walls (MSEW) in conformance with the lines, grades, design, geotechnical requirements, and dimensions shown on the plans and the MSEW specifications .
802.02 MATERIALS . Comply with the following unless otherwise
specified: Concrete Section 901 Coal Tar Epoxy -Polyamide Paint 1008.04 Reinforcing Steel Section 1009 Hardware Section 1013 Metal Sheet Piles 1013.10 Timber and Preservatives Section 1014
802.03 Struc Tural Excavation .
802.03.1 General Requirements : Excavation s shall be shored,
sheeted, or braced in accordance with 701.03 or as required. With the approval of the Project Engineer, formwork for footings may be omitted when the control of water is sufficient to allow construction in the dry. In such cases, provide excavation to plan dimensions. When required, provide water control in accordance with Section 817 .
802.03.2 Preservation of Channel : Unless approved by the
Project Engineer, do not excavate outside of sheeting, cofferdams, cribs, or caissons or disturb the natural stream bed adjacent to the structure. If excavating or dredgi ng at the site of the foundation, then, under agreement Structural Excavation, Backfill and Earth Retaining Systems
802.01 DESCRIPTION. Excavate materials necessary to facilitate
construction. Furnish, place, and compact backfill. Dispose of excess excavated material and obstructions in accordance with Section 202 , as directed by the Project Engineer, so that such activities will neither adversely affect hydraulics nor be unsightly. Furnish and install sheet ing of the type, size, dimensions , and locations specified meeting the required penetration and resistance with an undamaged cross -section. Design, f urnish , and construct Mechanically Stabilized Earth Walls (MSEW) in conformance with the lines, grades, design, geotechnical requirements, and dimensions shown on the plans and the MSEW specifications .
802.02 MATERIALS . Comply with the following unless otherwise
specified: Concrete Section 901 Coal Tar Epoxy -Polyamide Paint 1008.04 Reinforcing Steel Section 1009 Hardware Section 1013 Metal Sheet Piles 1013.10 Timber and Preservatives Section 1014
802.03 Struc Tural Excavation .
802.03.1 General Requirements : Excavation s shall be shored,
sheeted, or braced in accordance with 701.03 or as required. With the approval of the Project Engineer, formwork for footings may be omitted when the control of water is sufficient to allow construction in the dry. In such cases, provide excavation to plan dimensions. When required, provide water control in accordance with Section 817 .
802.03.2 Preservation of Channel : Unless approved by the
Project Engineer, do not excavate outside of sheeting, cofferdams, cribs, or caissons or disturb the natural stream bed adjacent to the structure. If excavating or dredgi ng at the site of the foundation, then, under agreement Structural Excavation, Backfill and Earth Retaining Systems
802.01 DESCRIPTION. Excavate materials necessary to facilitate
construction. Furnish, place, and compact backfill. Dispose of excess excavated material and obstructions in accordance with Section 202 , as directed by the Project Engineer, so that such activities will neither adversely affect hydraulics nor be unsightly. Furnish and install sheet ing of the type, size, dimensions , and locations specified meeting the required penetration and resistance with an undamaged cross -section. Design, f urnish , and construct Mechanically Stabilized Earth Walls (MSEW) in conformance with the lines, grades, design, geotechnical requirements, and dimensions shown on the plans and the MSEW specifications .
802.02 MATERIALS . Comply with the following unless otherwise
specified: Concrete Section 901 Coal Tar Epoxy -Polyamide Paint 1008.04 Reinforcing Steel Section 1009 Hardware Section 1013 Metal Sheet Piles 1013.10 Timber and Preservatives Section 1014
802.03 Struc Tural Excavation .
802.03.1 General Requirements : Excavation s shall be shored,
sheeted, or braced in accordance with 701.03 or as required. With the approval of the Project Engineer, formwork for footings may be omitted when the control of water is sufficient to allow construction in the dry. In such cases, provide excavation to plan dimensions. When required, provide water control in accordance with Section 817 .
802.03.2 Preservation of Channel : Unless approved by the
Project Engineer, do not excavate outside of sheeting, cofferdams, cribs, or caissons or disturb the natural stream bed adjacent to the structure. If excavating or dredgi ng at the site of the foundation, then, under agreement Structural Excavation, Backfill and Earth Retaining Systems
802.01 DESCRIPTION. Excavate materials necessary to facilitate
construction. Furnish, place, and compact backfill. Dispose of excess excavated material and obstructions in accordance with Section 202 , as directed by the Project Engineer, so that such activities will neither adversely affect hydraulics nor be unsightly. Furnish and install sheet ing of the type, size, dimensions , and locations specified meeting the required penetration and resistance with an undamaged cross -section. Design, f urnish , and construct Mechanically Stabilized Earth Walls (MSEW) in conformance with the lines, grades, design, geotechnical requirements, and dimensions shown on the plans and the MSEW specifications .
802.02 MATERIALS . Comply with the following unless otherwise
specified: Concrete Section 901 Coal Tar Epoxy -Polyamide Paint 1008.04 Reinforcing Steel Section 1009 Hardware Section 1013 Metal Sheet Piles 1013.10 Timber and Preservatives Section 1014
802.03 Struc Tural Excavation .
802.03.1 General Requirements : Excavation s shall be shored,
sheeted, or braced in accordance with 701.03 or as required. With the approval of the Project Engineer, formwork for footings may be omitted when the control of water is sufficient to allow construction in the dry. In such cases, provide excavation to plan dimensions. When required, provide water control in accordance with Section 817 .
802.03.2 Preservation of Channel : Unless approved by the
Project Engineer, do not excavate outside of sheeting, cofferdams, cribs, or caissons or disturb the natural stream bed adjacent to the structure. If excavating or dredgi ng at the site of the foundation, then, under agreement with permitting agencies and the Project Engineer, backfill such excavation to the original ground surface or river bed with satisfactory material after the foundation is in place. Remove excess mate rial deposited within the area of the stream and return channel to its natural state.
802.03.3 Preparation of Footing Foundations : Do not make
final removal of foundation material to grade until just before concrete is placed. For soft foundation material, add c ompactable material to provide a firm foundation for footing. Clean hard foundation material of loose material and cut to a firm level, stepped , or roughened surface, as directed.
802.03.4 Water Control : Excavations below the groundwater table
or water level will require water control to permit construction in the dry and maintain stability of the excavation base and sides. Control water infiltrating the excavation with sheeting, sumps, pumps, seals, cofferdams, well point systems or other accepted methods. Submit the proposed method of water control to the Project Engineer for record. Conform to Section 817 for temporary works.
802.04 BACKFILL. For MSEW backfill, comply w ith 802.05.2 .
Provide backfill material of acceptable quality, free fr om large or frozen lumps, wood or other foreign material. Backfill all excavated spaces to natural ground maintaining uniform lateral loading. Backfill reinforced concrete box culverts and attached headwalls in accordance with 701.08 . Provide adequate cover over reinforced concrete box culverts before heavy construction equipment may cross the installation to prevent damage to the box culvert. Place backfill material in a dry excavation for footings in horizontal lifts and compact to the satisfaction of the Project Engineer. Place backfill material in a dry excavation for other structures in horizontal layers not exceeding 9 -inch loose thickness and uniformly compact by approved methods to the satisfaction of the Project Engineer. Jetting of backfill behind abutments and wingwalls will not be permitted. Do not place backfill against a concrete abutment, wing wall, or reinforced concrete box culvert u ntil concrete has been in place a minimum of 14 calendar days, or until test cylinders made in accordance with DOTD TR 226 and tested in accordance with DOTD TR 230 have obtained a minimum compressive strength of 3000 psi. with permitting agencies and the Project Engineer, backfill such excavation to the original ground surface or river bed with satisfactory material after the foundation is in place. Remove excess mate rial deposited within the area of the stream and return channel to its natural state.
802.03.3 Preparation of Footing Foundations : Do not make
final removal of foundation material to grade until just before concrete is placed. For soft foundation material, add c ompactable material to provide a firm foundation for footing. Clean hard foundation material of loose material and cut to a firm level, stepped , or roughened surface, as directed.
802.03.4 Water Control : Excavations below the groundwater table
or water level will require water control to permit construction in the dry and maintain stability of the excavation base and sides. Control water infiltrating the excavation with sheeting, sumps, pumps, seals, cofferdams, well point systems or other accepted methods. Submit the proposed method of water control to the Project Engineer for record. Conform to Section 817 for temporary works.
802.04 BACKFILL. For MSEW backfill, comply w ith 802.05.2 .
Provide backfill material of acceptable quality, free fr om large or frozen lumps, wood or other foreign material. Backfill all excavated spaces to natural ground maintaining uniform lateral loading. Backfill reinforced concrete box culverts and attached headwalls in accordance with 701.08 . Provide adequate cover over reinforced concrete box culverts before heavy construction equipment may cross the installation to prevent damage to the box culvert. Place backfill material in a dry excavation for footings in horizontal lifts and compact to the satisfaction of the Project Engineer. Place backfill material in a dry excavation for other structures in horizontal layers not exceeding 9 -inch loose thickness and uniformly compact by approved methods to the satisfaction of the Project Engineer. Jetting of backfill behind abutments and wingwalls will not be permitted. Do not place backfill against a concrete abutment, wing wall, or reinforced concrete box culvert u ntil concrete has been in place a minimum of 14 calendar days, or until test cylinders made in accordance with DOTD TR 226 and tested in accordance with DOTD TR 230 have obtained a minimum compressive strength of 3000 psi. with permitting agencies and the Project Engineer, backfill such excavation to the original ground surface or river bed with satisfactory material after the foundation is in place. Remove excess mate rial deposited within the area of the stream and return channel to its natural state.
802.03.3 Preparation of Footing Foundations : Do not make
final removal of foundation material to grade until just before concrete is placed. For soft foundation material, add c ompactable material to provide a firm foundation for footing. Clean hard foundation material of loose material and cut to a firm level, stepped , or roughened surface, as directed.
802.03.4 Water Control : Excavations below the groundwater table
or water level will require water control to permit construction in the dry and maintain stability of the excavation base and sides. Control water infiltrating the excavation with sheeting, sumps, pumps, seals, cofferdams, well point systems or other accepted methods. Submit the proposed method of water control to the Project Engineer for record. Conform to Section 817 for temporary works.
802.04 BACKFILL. For MSEW backfill, comply w ith 802.05.2 .
Provide backfill material of acceptable quality, free fr om large or frozen lumps, wood or other foreign material. Backfill all excavated spaces to natural ground maintaining uniform lateral loading. Backfill reinforced concrete box culverts and attached headwalls in accordance with 701.08 . Provide adequate cover over reinforced concrete box culverts before heavy construction equipment may cross the installation to prevent damage to the box culvert. Place backfill material in a dry excavation for footings in horizontal lifts and compact to the satisfaction of the Project Engineer. Place backfill material in a dry excavation for other structures in horizontal layers not exceeding 9 -inch loose thickness and uniformly compact by approved methods to the satisfaction of the Project Engineer. Jetting of backfill behind abutments and wingwalls will not be permitted. Do not place backfill against a concrete abutment, wing wall, or reinforced concrete box culvert u ntil concrete has been in place a minimum of 14 calendar days, or until test cylinders made in accordance with DOTD TR 226 and tested in accordance with DOTD TR 230 have obtained a minimum compressive strength of 3000 psi. with permitting agencies and the Project Engineer, backfill such excavation to the original ground surface or river bed with satisfactory material after the foundation is in place. Remove excess mate rial deposited within the area of the stream and return channel to its natural state.
802.03.3 Preparation of Footing Foundations : Do not make
final removal of foundation material to grade until just before concrete is placed. For soft foundation material, add c ompactable material to provide a firm foundation for footing. Clean hard foundation material of loose material and cut to a firm level, stepped , or roughened surface, as directed.
802.03.4 Water Control : Excavations below the groundwater table
or water level will require water control to permit construction in the dry and maintain stability of the excavation base and sides. Control water infiltrating the excavation with sheeting, sumps, pumps, seals, cofferdams, well point systems or other accepted methods. Submit the proposed method of water control to the Project Engineer for record. Conform to Section 817 for temporary works.
802.04 BACKFILL. For MSEW backfill, comply w ith 802.05.2 .
Provide backfill material of acceptable quality, free fr om large or frozen lumps, wood or other foreign material. Backfill all excavated spaces to natural ground maintaining uniform lateral loading. Backfill reinforced concrete box culverts and attached headwalls in accordance with 701.08 . Provide adequate cover over reinforced concrete box culverts before heavy construction equipment may cross the installation to prevent damage to the box culvert. Place backfill material in a dry excavation for footings in horizontal lifts and compact to the satisfaction of the Project Engineer. Place backfill material in a dry excavation for other structures in horizontal layers not exceeding 9 -inch loose thickness and uniformly compact by approved methods to the satisfaction of the Project Engineer. Jetting of backfill behind abutments and wingwalls will not be permitted. Do not place backfill against a concrete abutment, wing wall, or reinforced concrete box culvert u ntil concrete has been in place a minimum of 14 calendar days, or until test cylinders made in accordance with DOTD TR 226 and tested in accordance with DOTD TR 230 have obtained a minimum compressive strength of 3000 psi.
802.05 Earth Retaining Systems .
802.05.1 Sheet Piles: Concrete sheet piles shall be precast -
prestressed piles fabricated in accordance with 805.09 . Steel sheet piles shall be fabricated in accordance with Section 807 . Timber sheet piles shall have tongues and grooves of suitable proportions, either cut from the solid material or made by building up the piles with three planks fastened together. Piles shall be drift-sharpened at their lower ends to wedge adjacent piles tightly together during driving. Treated timber shall be either Southern Pine or Douglas Fir, complying with Section 812 . Use galvanized hardware .
802.05.1 1 Permanent Sheeting : Provide new sheeting as
shown in the contract plans. Clean and apply corrosion protection in accordance with 802.05.1.4 .
802.05.1 2 Temporary Sheeting : Where contract plans require
temporary sheeting, the plans will specify the required design for sheeting. Sheeting may be new or used and will not require corrosion protection. Typically, remove sheeting when no longer re quired. However, when impractical to remove or when required on the plans, sheeting may remain in the completed work.
802.05.1 3 Contractor Sheeting : Sheeting used at the
contractor’s option shall be in accordance with Section 817 , “Temporary Works.” The contractor shall be responsible for the design and details of the sheeting. Sheeting may be new or used, not require corrosion protection, and shall be removed when no l onger needed unless otherwise approved.
802.05.1 4 Corrosion Protection : Before driving sheeting
which requires corrosion protection, clean and paint, or galvanize surfaces of steel sheet piling from the top of the sheet pile to a point 10 feet below the ground or mudline. Clean in accordance with Section 811 using Commercial Blast Method. Paint using a two coat coal -tar epoxy - polyamide paint system or galvanize in accordance with Section 811 .
802.05.1 5 Driving : Drive sheet piles with hammers adequate to
drive the piles to required depth in satisfactory condition, in accordance with Section 804 . To maintain satisfactory alignment, drive sheet piles in increments of penetration necessary to prevent distortion, twisting out of position, or pulling apart at interlocks. Extract sheet piles damaged during driving, or driven out of proper position or driven below cut -off elevation, and replace with new piles at no additional cost or time to the Department.
802.05 Earth Retaining Systems .
802.05.1 Sheet Piles: Concrete sheet piles shall be precast -
prestressed piles fabricated in accordance with 805.09 . Steel sheet piles shall be fabricated in accordance with Section 807 . Timber sheet piles shall have tongues and grooves of suitable proportions, either cut from the solid material or made by building up the piles with three planks fastened together. Piles shall be drift-sharpened at their lower ends to wedge adjacent piles tightly together during driving. Treated timber shall be either Southern Pine or Douglas Fir, complying with Section 812 . Use galvanized hardware .
802.05.1 1 Permanent Sheeting : Provide new sheeting as
shown in the contract plans. Clean and apply corrosion protection in accordance with 802.05.1.4 .
802.05.1 2 Temporary Sheeting : Where contract plans require
temporary sheeting, the plans will specify the required design for sheeting. Sheeting may be new or used and will not require corrosion protection. Typically, remove sheeting when no longer re quired. However, when impractical to remove or when required on the plans, sheeting may remain in the completed work.
802.05.1 3 Contractor Sheeting : Sheeting used at the
contractor’s option shall be in accordance with Section 817 , “Temporary Works.” The contractor shall be responsible for the design and details of the sheeting. Sheeting may be new or used, not require corrosion protection, and shall be removed when no l onger needed unless otherwise approved.
802.05.1 4 Corrosion Protection : Before driving sheeting
which requires corrosion protection, clean and paint, or galvanize surfaces of steel sheet piling from the top of the sheet pile to a point 10 feet below the ground or mudline. Clean in accordance with Section 811 using Commercial Blast Method. Paint using a two coat coal -tar epoxy - polyamide paint system or galvanize in accordance with Section 811 .
802.05.1 5 Driving : Drive sheet piles with hammers adequate to
drive the piles to required depth in satisfactory condition, in accordance with Section 804 . To maintain satisfactory alignment, drive sheet piles in increments of penetration necessary to prevent distortion, twisting out of position, or pulling apart at interlocks. Extract sheet piles damaged during driving, or driven out of proper position or driven below cut -off elevation, and replace with new piles at no additional cost or time to the Department.
802.05 Earth Retaining Systems .
802.05.1 Sheet Piles: Concrete sheet piles shall be precast -
prestressed piles fabricated in accordance with 805.09 . Steel sheet piles shall be fabricated in accordance with Section 807 . Timber sheet piles shall have tongues and grooves of suitable proportions, either cut from the solid material or made by building up the piles with three planks fastened together. Piles shall be drift-sharpened at their lower ends to wedge adjacent piles tightly together during driving. Treated timber shall be either Southern Pine or Douglas Fir, complying with Section 812 . Use galvanized hardware .
802.05.1 1 Permanent Sheeting : Provide new sheeting as
shown in the contract plans. Clean and apply corrosion protection in accordance with 802.05.1.4 .
802.05.1 2 Temporary Sheeting : Where contract plans require
temporary sheeting, the plans will specify the required design for sheeting. Sheeting may be new or used and will not require corrosion protection. Typically, remove sheeting when no longer re quired. However, when impractical to remove or when required on the plans, sheeting may remain in the completed work.
802.05.1 3 Contractor Sheeting : Sheeting used at the
contractor’s option shall be in accordance with Section 817 , “Temporary Works.” The contractor shall be responsible for the design and details of the sheeting. Sheeting may be new or used, not require corrosion protection, and shall be removed when no l onger needed unless otherwise approved.
802.05.1 4 Corrosion Protection : Before driving sheeting
which requires corrosion protection, clean and paint, or galvanize surfaces of steel sheet piling from the top of the sheet pile to a point 10 feet below the ground or mudline. Clean in accordance with Section 811 using Commercial Blast Method. Paint using a two coat coal -tar epoxy - polyamide paint system or galvanize in accordance with Section 811 .
802.05.1 5 Driving : Drive sheet piles with hammers adequate to
drive the piles to required depth in satisfactory condition, in accordance with Section 804 . To maintain satisfactory alignment, drive sheet piles in increments of penetration necessary to prevent distortion, twisting out of position, or pulling apart at interlocks. Extract sheet piles damaged during driving, or driven out of proper position or driven below cut -off elevation, and replace with new piles at no additional cost or time to the Department.
802.05 Earth Retaining Systems .
802.05.1 Sheet Piles: Concrete sheet piles shall be precast -
prestressed piles fabricated in accordance with 805.09 . Steel sheet piles shall be fabricated in accordance with Section 807 . Timber sheet piles shall have tongues and grooves of suitable proportions, either cut from the solid material or made by building up the piles with three planks fastened together. Piles shall be drift-sharpened at their lower ends to wedge adjacent piles tightly together during driving. Treated timber shall be either Southern Pine or Douglas Fir, complying with Section 812 . Use galvanized hardware .
802.05.1 1 Permanent Sheeting : Provide new sheeting as
shown in the contract plans. Clean and apply corrosion protection in accordance with 802.05.1.4 .
802.05.1 2 Temporary Sheeting : Where contract plans require
temporary sheeting, the plans will specify the required design for sheeting. Sheeting may be new or used and will not require corrosion protection. Typically, remove sheeting when no longer re quired. However, when impractical to remove or when required on the plans, sheeting may remain in the completed work.
802.05.1 3 Contractor Sheeting : Sheeting used at the
contractor’s option shall be in accordance with Section 817 , “Temporary Works.” The contractor shall be responsible for the design and details of the sheeting. Sheeting may be new or used, not require corrosion protection, and shall be removed when no l onger needed unless otherwise approved.
802.05.1 4 Corrosion Protection : Before driving sheeting
which requires corrosion protection, clean and paint, or galvanize surfaces of steel sheet piling from the top of the sheet pile to a point 10 feet below the ground or mudline. Clean in accordance with Section 811 using Commercial Blast Method. Paint using a two coat coal -tar epoxy - polyamide paint system or galvanize in accordance with Section 811 .
802.05.1 5 Driving : Drive sheet piles with hammers adequate to
drive the piles to required depth in satisfactory condition, in accordance with Section 804 . To maintain satisfactory alignment, drive sheet piles in increments of penetration necessary to prevent distortion, twisting out of position, or pulling apart at interlocks. Extract sheet piles damaged during driving, or driven out of proper position or driven below cut -off elevation, and replace with new piles at no additional cost or time to the Department.
802.05 Earth Retaining Systems .
802.05.1 Sheet Piles: Concrete sheet piles shall be precast -
prestressed piles fabricated in accordance with 805.09 . Steel sheet piles shall be fabricated in accordance with Section 807 . Timber sheet piles shall have tongues and grooves of suitable proportions, either cut from the solid material or made by building up the piles with three planks fastened together. Piles shall be drift-sharpened at their lower ends to wedge adjacent piles tightly together during driving. Treated timber shall be either Southern Pine or Douglas Fir, complying with Section 812 . Use galvanized hardware .
802.05.1 1 Permanent Sheeting : Provide new sheeting as
shown in the contract plans. Clean and apply corrosion protection in accordance with 802.05.1.4 .
802.05.1 2 Temporary Sheeting : Where contract plans require
temporary sheeting, the plans will specify the required design for sheeting. Sheeting may be new or used and will not require corrosion protection. Typically, remove sheeting when no longer re quired. However, when impractical to remove or when required on the plans, sheeting may remain in the completed work.
802.05.1 3 Contractor Sheeting : Sheeting used at the
contractor’s option shall be in accordance with Section 817 , “Temporary Works.” The contractor shall be responsible for the design and details of the sheeting. Sheeting may be new or used, not require corrosion protection, and shall be removed when no l onger needed unless otherwise approved.
802.05.1 4 Corrosion Protection : Before driving sheeting
which requires corrosion protection, clean and paint, or galvanize surfaces of steel sheet piling from the top of the sheet pile to a point 10 feet below the ground or mudline. Clean in accordance with Section 811 using Commercial Blast Method. Paint using a two coat coal -tar epoxy - polyamide paint system or galvanize in accordance with Section 811 .
802.05.1 5 Driving : Drive sheet piles with hammers adequate to
drive the piles to required depth in satisfactory condition, in accordance with Section 804 . To maintain satisfactory alignment, drive sheet piles in increments of penetration necessary to prevent distortion, twisting out of position, or pulling apart at interlocks. Extract sheet piles damaged during driving, or driven out of proper position or driven below cut -off elevation, and replace with new piles at no additional cost or time to the Department.
802.05 Earth Retaining Systems .
802.05.1 Sheet Piles: Concrete sheet piles shall be precast -
prestressed piles fabricated in accordance with 805.09 . Steel sheet piles shall be fabricated in accordance with Section 807 . Timber sheet piles shall have tongues and grooves of suitable proportions, either cut from the solid material or made by building up the piles with three planks fastened together. Piles shall be drift-sharpened at their lower ends to wedge adjacent piles tightly together during driving. Treated timber shall be either Southern Pine or Douglas Fir, complying with Section 812 . Use galvanized hardware .
802.05.1 1 Permanent Sheeting : Provide new sheeting as
shown in the contract plans. Clean and apply corrosion protection in accordance with 802.05.1.4 .
802.05.1 2 Temporary Sheeting : Where contract plans require
temporary sheeting, the plans will specify the required design for sheeting. Sheeting may be new or used and will not require corrosion protection. Typically, remove sheeting when no longer re quired. However, when impractical to remove or when required on the plans, sheeting may remain in the completed work.
802.05.1 3 Contractor Sheeting : Sheeting used at the
contractor’s option shall be in accordance with Section 817 , “Temporary Works.” The contractor shall be responsible for the design and details of the sheeting. Sheeting may be new or used, not require corrosion protection, and shall be removed when no l onger needed unless otherwise approved.
802.05.1 4 Corrosion Protection : Before driving sheeting
which requires corrosion protection, clean and paint, or galvanize surfaces of steel sheet piling from the top of the sheet pile to a point 10 feet below the ground or mudline. Clean in accordance with Section 811 using Commercial Blast Method. Paint using a two coat coal -tar epoxy - polyamide paint system or galvanize in accordance with Section 811 .
802.05.1 5 Driving : Drive sheet piles with hammers adequate to
drive the piles to required depth in satisfactory condition, in accordance with Section 804 . To maintain satisfactory alignment, drive sheet piles in increments of penetration necessary to prevent distortion, twisting out of position, or pulling apart at interlocks. Extract sheet piles damaged during driving, or driven out of proper position or driven below cut -off elevation, and replace with new piles at no additional cost or time to the Department.
802.05 Earth Retaining Systems .
802.05.1 Sheet Piles: Concrete sheet piles shall be precast -
prestressed piles fabricated in accordance with 805.09 . Steel sheet piles shall be fabricated in accordance with Section 807 . Timber sheet piles shall have tongues and grooves of suitable proportions, either cut from the solid material or made by building up the piles with three planks fastened together. Piles shall be drift-sharpened at their lower ends to wedge adjacent piles tightly together during driving. Treated timber shall be either Southern Pine or Douglas Fir, complying with Section 812 . Use galvanized hardware .
802.05.1 1 Permanent Sheeting : Provide new sheeting as
shown in the contract plans. Clean and apply corrosion protection in accordance with 802.05.1.4 .
802.05.1 2 Temporary Sheeting : Where contract plans require
temporary sheeting, the plans will specify the required design for sheeting. Sheeting may be new or used and will not require corrosion protection. Typically, remove sheeting when no longer re quired. However, when impractical to remove or when required on the plans, sheeting may remain in the completed work.
802.05.1 3 Contractor Sheeting : Sheeting used at the
contractor’s option shall be in accordance with Section 817 , “Temporary Works.” The contractor shall be responsible for the design and details of the sheeting. Sheeting may be new or used, not require corrosion protection, and shall be removed when no l onger needed unless otherwise approved.
802.05.1 4 Corrosion Protection : Before driving sheeting
which requires corrosion protection, clean and paint, or galvanize surfaces of steel sheet piling from the top of the sheet pile to a point 10 feet below the ground or mudline. Clean in accordance with Section 811 using Commercial Blast Method. Paint using a two coat coal -tar epoxy - polyamide paint system or galvanize in accordance with Section 811 .
802.05.1 5 Driving : Drive sheet piles with hammers adequate to
drive the piles to required depth in satisfactory condition, in accordance with Section 804 . To maintain satisfactory alignment, drive sheet piles in increments of penetration necessary to prevent distortion, twisting out of position, or pulling apart at interlocks. Extract sheet piles damaged during driving, or driven out of proper position or driven below cut -off elevation, and replace with new piles at no additional cost or time to the Department.
802.05 Earth Retaining Systems .
802.05.1 Sheet Piles: Concrete sheet piles shall be precast -
prestressed piles fabricated in accordance with 805.09 . Steel sheet piles shall be fabricated in accordance with Section 807 . Timber sheet piles shall have tongues and grooves of suitable proportions, either cut from the solid material or made by building up the piles with three planks fastened together. Piles shall be drift-sharpened at their lower ends to wedge adjacent piles tightly together during driving. Treated timber shall be either Southern Pine or Douglas Fir, complying with Section 812 . Use galvanized hardware .
802.05.1 1 Permanent Sheeting : Provide new sheeting as
shown in the contract plans. Clean and apply corrosion protection in accordance with 802.05.1.4 .
802.05.1 2 Temporary Sheeting : Where contract plans require
temporary sheeting, the plans will specify the required design for sheeting. Sheeting may be new or used and will not require corrosion protection. Typically, remove sheeting when no longer re quired. However, when impractical to remove or when required on the plans, sheeting may remain in the completed work.
802.05.1 3 Contractor Sheeting : Sheeting used at the
contractor’s option shall be in accordance with Section 817 , “Temporary Works.” The contractor shall be responsible for the design and details of the sheeting. Sheeting may be new or used, not require corrosion protection, and shall be removed when no l onger needed unless otherwise approved.
802.05.1 4 Corrosion Protection : Before driving sheeting
which requires corrosion protection, clean and paint, or galvanize surfaces of steel sheet piling from the top of the sheet pile to a point 10 feet below the ground or mudline. Clean in accordance with Section 811 using Commercial Blast Method. Paint using a two coat coal -tar epoxy - polyamide paint system or galvanize in accordance with Section 811 .
802.05.1 5 Driving : Drive sheet piles with hammers adequate to
drive the piles to required depth in satisfactory condition, in accordance with Section 804 . To maintain satisfactory alignment, drive sheet piles in increments of penetration necessary to prevent distortion, twisting out of position, or pulling apart at interlocks. Extract sheet piles damaged during driving, or driven out of proper position or driven below cut -off elevation, and replace with new piles at no additional cost or time to the Department. The contractor assumes full responsibility for any damage, settlement, or movement of adjacent structures or emba nkment settlement caused by the pile driving operation. Use of jets, pre-boring, or vibratory hammer will require written approval of the Project E ngineer. If the sheeting is used to support the structure, vibratory hammers will not be allowed for driving .
802.05.1 6 Cut-offs for Sheeting to Remain in Place : Cut
off tops of sheet piles or drive to a straight line at the elevation indicated on the plans or as directed. If heads of sheeting are appreciably distorted or otherwise damaged below cut -off level, remove and replace damaged portions. Treat tops of timber sheet piles after cut -off in accordance with 812.06 or use bent down galvanized metal coverings. Bend down coverings at least 3 inches on each side and nail to the vertical surface of sheet piles with large - headed galvanized roofing nails.
802.05.2 Mechanically Stabilized Earth Wall (MSEW) : Two
categories of MSEW systems are permitted: Modular Concrete Block and Panel walls. Adhere to the design details for the MSEW structures such as specified geogrid, strip, or mesh; facing element dimensions; lo ading conditions; leveling pad dimensions; temporary surcharge retaining walls; and details for appurtenances. Value engineering proposals for other MSEW systems will not be considered. Only approved MSEW systems will be considered. The list of approved MSEW systems, MSEW system approval policy, and the MSEW design guide are available at the Department’s Pavement and Geotechnical Services web site.
802.05.2 1 MSEW Submittals: Comply with 801.05 .
802.05.1 6 Cut-offs for Sheeting to Remain in Place : Cut
off tops of sheet piles or drive to a straight line at the elevation indicated on the plans or as directed. If heads of sheeting are appreciably distorted or otherwise damaged below cut -off level, remove and replace damaged portions. Treat tops of timber sheet piles after cut -off in accordance with 812.06 or use bent down galvanized metal coverings. Bend down coverings at least 3 inches on each side and nail to the vertical surface of sheet piles with large - headed galvanized roofing nails.
802.05.2 Mechanically Stabilized Earth Wall (MSEW) : Two
categories of MSEW systems are permitted: Modular Concrete Block and Panel walls. Adhere to the design details for the MSEW structures such as specified geogrid, strip, or mesh; facing element dimensions; lo ading conditions; leveling pad dimensions; temporary surcharge retaining walls; and details for appurtenances. Value engineering proposals for other MSEW systems will not be considered. Only approved MSEW systems will be considered. The list of approved MSEW systems, MSEW system approval policy, and the MSEW design guide are available at the Department’s Pavement and Geotechnical Services web site.
802.05.2 1 MSEW Submittals: Comply with 801.05 .
802.05.1 6 Cut-offs for Sheeting to Remain in Place : Cut
off tops of sheet piles or drive to a straight line at the elevation indicated on the plans or as directed. If heads of sheeting are appreciably distorted or otherwise damaged below cut -off level, remove and replace damaged portions. Treat tops of timber sheet piles after cut -off in accordance with 812.06 or use bent down galvanized metal coverings. Bend down coverings at least 3 inches on each side and nail to the vertical surface of sheet piles with large - headed galvanized roofing nails.
802.05.2 Mechanically Stabilized Earth Wall (MSEW) : Two
categories of MSEW systems are permitted: Modular Concrete Block and Panel walls. Adhere to the design details for the MSEW structures such as specified geogrid, strip, or mesh; facing element dimensions; lo ading conditions; leveling pad dimensions; temporary surcharge retaining walls; and details for appurtenances. Value engineering proposals for other MSEW systems will not be considered. Only approved MSEW systems will be considered. The list of approved MSEW systems, MSEW system approval policy, and the MSEW design guide are available at the Department’s Pavement and Geotechnical Services web site.
802.05.2 1 MSEW Submittals: Comply with 801.05 .
802.05.1 6 Cut-offs for Sheeting to Remain in Place : Cut
off tops of sheet piles or drive to a straight line at the elevation indicated on the plans or as directed. If heads of sheeting are appreciably distorted or otherwise damaged below cut -off level, remove and replace damaged portions. Treat tops of timber sheet piles after cut -off in accordance with 812.06 or use bent down galvanized metal coverings. Bend down coverings at least 3 inches on each side and nail to the vertical surface of sheet piles with large - headed galvanized roofing nails.
802.05.2 Mechanically Stabilized Earth Wall (MSEW) : Two
categories of MSEW systems are permitted: Modular Concrete Block and Panel walls. Adhere to the design details for the MSEW structures such as specified geogrid, strip, or mesh; facing element dimensions; lo ading conditions; leveling pad dimensions; temporary surcharge retaining walls; and details for appurtenances. Value engineering proposals for other MSEW systems will not be considered. Only approved MSEW systems will be considered. The list of approved MSEW systems, MSEW system approval policy, and the MSEW design guide are available at the Department’s Pavement and Geotechnical Services web site.
802.05.2 1 MSEW Submittals: Comply with 801.05 .
802.05.2 2 MSEW Design : The plans will specify a minimum
reinforced backfill length that satisfies the external stability of the MSEW system. Design MSEW structures as gravity walls for internal stability of the reinforced backfill. Design internal stability for the required reinforced backfill length and strength, facing/soil reinforcement connection strength, and facing stability. Specify the minimum required wall fa ce batter to limit the amount of horizontal movement resulting from the outward rotation of the wall. Design any temporary MSEW facings required during phased construction, temporary surcharge retaining walls located above the permanent MSEW structure, or other temporary construction systems that are required to build the permanent MSEW. Submit to the Project Engineer the MSEW Certification Package for review. Allow 21 calendar days for each review cycle. Do not deliver soil reinforcement or facing elements to the site without written acceptance of the MSEW Certi fication Package. Submit a Certification Package prepared by the MSEW supplier or MSEW component manufacturer. Document certified values as indicated in the Department’s MSEW Design Guide. Include a Certificate of Compliance that certifies the following meet or exceed MSEW design requirements (as applicable to the MSEW system):
802.05.2 2 MSEW Design : The plans will specify a minimum
reinforced backfill length that satisfies the external stability of the MSEW system. Design MSEW structures as gravity walls for internal stability of the reinforced backfill. Design internal stability for the required reinforced backfill length and strength, facing/soil reinforcement connection strength, and facing stability. Specify the minimum required wall fa ce batter to limit the amount of horizontal movement resulting from the outward rotation of the wall. Design any temporary MSEW facings required during phased construction, temporary surcharge retaining walls located above the permanent MSEW structure, or other temporary construction systems that are required to build the permanent MSEW. Design permanent MSEW and temporary construction systems in accordance with the Department’s MSEW Design Guide and current edition of the AASHTO LRFD Bridge Design Specific ations . The Department will not accept designs based on methodology other than required by these specifications. Provide top of wall elevations in accordance with the plans, except an increase of up to 8 inches may be allowed, and will be at no additional cost or time to the Department. Design top of wall elevations to allow for proper interfacing with barriers, copings, surface ditches, bridge abutments, etc. as shown in the plans. Provide top of leveling pad elevations in accordance with the plans, excep t an increase in the embedment depth of the pad of up to 20 inches may be allowed, and will be at no additional cost or time to the Department. Set leveling pad elevations to allow for transverse and longitudinal drainage structures shown on the plans. Do not terminate wall over pile supported foundations.
802.05.2 3 MSEW Materials: Provide all applicable materials
and components such as the facing elements, reinforced backfill materials, backfill reinforcement, geotextile fabric, facing aggregate, internal drainage system (if required), and all other necessary components.
802.05.2 3 MSEW Materials: Provide all applicable materials
and components such as the facing elements, reinforced backfill materials, backfill reinforcement, geotextile fabric, facing aggregate, internal drainage system (if required), and all other necessary components.
802.05.2 4 MSEW Construction Requirements:
802.05.2 4 MSEW Construction Requirements:
802.06 Measurement.
802.06.1 Structural Excavation : When a pay item is not provided,
excavation will not be measured for payment. Structural excavation will be measured per cubic yard, based on plan dimensions plus excavation allowance. The excavation allowance is 18 inches outsid e the neat line of the vertical planes of the footing. Backfill and disposal of excess excavated material will not be measured for payment.
802.06.1 1 Reinforced Concrete Box Culverts: Excavation
and backfill required for box culvert construction will not be measu red for payment, except as specified in 203.14.1 .
802.06.1 2 Cofferdams: When the Contract does not contain an
item for “Cofferdams,” the cofferdams and cribs will not be measured for payment. When an item for “Cofferdams” is included in the Contra ct, the cofferdams will be measured on a lump sum basis and conform to Section 817, “Temporary Works.”
802.06.2 Water Control System : When the Contract does not
contain a n item for “Water Control System,” use an accepted method to control seepage and runoff. The “Water Control System” will not be measured for payment. When an item for “Water Control System” is included in the Contract, the water control system will be measured on a lump sum basis and shall conform to Section 817 , “Temporary Works. ”
802.06.3 Sheeting : Permanent sheeting will be measured based on
the design quantities shown on the plans per square foot. Temporary sheeting will be measured for payment based on the design shown on the plans per square foot . Contractor sheeting will not be measured for payment. Jetting or pre -boring of sheeting will not be measured for payment.
802.06 Measurement.
802.06.1 Structural Excavation : When a pay item is not provided,
excavation will not be measured for payment. Structural excavation will be measured per cubic yard, based on plan dimensions plus excavation allowance. The excavation allowance is 18 inches outsid e the neat line of the vertical planes of the footing. Backfill and disposal of excess excavated material will not be measured for payment.
802.06.1 1 Reinforced Concrete Box Culverts: Excavation
and backfill required for box culvert construction will not be measu red for payment, except as specified in 203.14.1 .
802.06.1 2 Cofferdams: When the Contract does not contain an
item for “Cofferdams,” the cofferdams and cribs will not be measured for payment. When an item for “Cofferdams” is included in the Contra ct, the cofferdams will be measured on a lump sum basis and conform to Section 817, “Temporary Works.”
802.06.2 Water Control System : When the Contract does not
contain a n item for “Water Control System,” use an accepted method to control seepage and runoff. The “Water Control System” will not be measured for payment. When an item for “Water Control System” is included in the Contract, the water control system will be measured on a lump sum basis and shall conform to Section 817 , “Temporary Works. ”
802.06.3 Sheeting : Permanent sheeting will be measured based on
the design quantities shown on the plans per square foot. Temporary sheeting will be measured for payment based on the design shown on the plans per square foot . Contractor sheeting will not be measured for payment. Jetting or pre -boring of sheeting will not be measured for payment.
802.06 Measurement.
802.06.1 Structural Excavation : When a pay item is not provided,
excavation will not be measured for payment. Structural excavation will be measured per cubic yard, based on plan dimensions plus excavation allowance. The excavation allowance is 18 inches outsid e the neat line of the vertical planes of the footing. Backfill and disposal of excess excavated material will not be measured for payment.
802.06.1 1 Reinforced Concrete Box Culverts: Excavation
and backfill required for box culvert construction will not be measu red for payment, except as specified in 203.14.1 .
802.06.1 2 Cofferdams: When the Contract does not contain an
item for “Cofferdams,” the cofferdams and cribs will not be measured for payment. When an item for “Cofferdams” is included in the Contra ct, the cofferdams will be measured on a lump sum basis and conform to Section 817, “Temporary Works.”
802.06.2 Water Control System : When the Contract does not
contain a n item for “Water Control System,” use an accepted method to control seepage and runoff. The “Water Control System” will not be measured for payment. When an item for “Water Control System” is included in the Contract, the water control system will be measured on a lump sum basis and shall conform to Section 817 , “Temporary Works. ”
802.06.3 Sheeting : Permanent sheeting will be measured based on
the design quantities shown on the plans per square foot. Temporary sheeting will be measured for payment based on the design shown on the plans per square foot . Contractor sheeting will not be measured for payment. Jetting or pre -boring of sheeting will not be measured for payment.
802.06 Measurement.
802.06.1 Structural Excavation : When a pay item is not provided,
excavation will not be measured for payment. Structural excavation will be measured per cubic yard, based on plan dimensions plus excavation allowance. The excavation allowance is 18 inches outsid e the neat line of the vertical planes of the footing. Backfill and disposal of excess excavated material will not be measured for payment.
802.06.1 1 Reinforced Concrete Box Culverts: Excavation
and backfill required for box culvert construction will not be measu red for payment, except as specified in 203.14.1 .
802.06.1 2 Cofferdams: When the Contract does not contain an
item for “Cofferdams,” the cofferdams and cribs will not be measured for payment. When an item for “Cofferdams” is included in the Contra ct, the cofferdams will be measured on a lump sum basis and conform to Section 817, “Temporary Works.”
802.06.2 Water Control System : When the Contract does not
contain a n item for “Water Control System,” use an accepted method to control seepage and runoff. The “Water Control System” will not be measured for payment. When an item for “Water Control System” is included in the Contract, the water control system will be measured on a lump sum basis and shall conform to Section 817 , “Temporary Works. ”
802.06.3 Sheeting : Permanent sheeting will be measured based on
the design quantities shown on the plans per square foot. Temporary sheeting will be measured for payment based on the design shown on the plans per square foot . Contractor sheeting will not be measured for payment. Jetting or pre -boring of sheeting will not be measured for payment.
802.06 Measurement.
802.06.1 Structural Excavation : When a pay item is not provided,
excavation will not be measured for payment. Structural excavation will be measured per cubic yard, based on plan dimensions plus excavation allowance. The excavation allowance is 18 inches outsid e the neat line of the vertical planes of the footing. Backfill and disposal of excess excavated material will not be measured for payment.
802.06.1 1 Reinforced Concrete Box Culverts: Excavation
and backfill required for box culvert construction will not be measu red for payment, except as specified in 203.14.1 .
802.06.1 2 Cofferdams: When the Contract does not contain an
item for “Cofferdams,” the cofferdams and cribs will not be measured for payment. When an item for “Cofferdams” is included in the Contra ct, the cofferdams will be measured on a lump sum basis and conform to Section 817, “Temporary Works.”
802.06.2 Water Control System : When the Contract does not
contain a n item for “Water Control System,” use an accepted method to control seepage and runoff. The “Water Control System” will not be measured for payment. When an item for “Water Control System” is included in the Contract, the water control system will be measured on a lump sum basis and shall conform to Section 817 , “Temporary Works. ”
802.06.3 Sheeting : Permanent sheeting will be measured based on
the design quantities shown on the plans per square foot. Temporary sheeting will be measured for payment based on the design shown on the plans per square foot . Contractor sheeting will not be measured for payment. Jetting or pre -boring of sheeting will not be measured for payment.
802.06 Measurement.
802.06.1 Structural Excavation : When a pay item is not provided,
excavation will not be measured for payment. Structural excavation will be measured per cubic yard, based on plan dimensions plus excavation allowance. The excavation allowance is 18 inches outsid e the neat line of the vertical planes of the footing. Backfill and disposal of excess excavated material will not be measured for payment.
802.06.1 1 Reinforced Concrete Box Culverts: Excavation
and backfill required for box culvert construction will not be measu red for payment, except as specified in 203.14.1 .
802.06.1 2 Cofferdams: When the Contract does not contain an
item for “Cofferdams,” the cofferdams and cribs will not be measured for payment. When an item for “Cofferdams” is included in the Contra ct, the cofferdams will be measured on a lump sum basis and conform to Section 817, “Temporary Works.”
802.06.2 Water Control System : When the Contract does not
contain a n item for “Water Control System,” use an accepted method to control seepage and runoff. The “Water Control System” will not be measured for payment. When an item for “Water Control System” is included in the Contract, the water control system will be measured on a lump sum basis and shall conform to Section 817 , “Temporary Works. ”
802.06.3 Sheeting : Permanent sheeting will be measured based on
the design quantities shown on the plans per square foot. Temporary sheeting will be measured for payment based on the design shown on the plans per square foot . Contractor sheeting will not be measured for payment. Jetting or pre -boring of sheeting will not be measured for payment.
802.06 Measurement.
802.06.1 Structural Excavation : When a pay item is not provided,
excavation will not be measured for payment. Structural excavation will be measured per cubic yard, based on plan dimensions plus excavation allowance. The excavation allowance is 18 inches outsid e the neat line of the vertical planes of the footing. Backfill and disposal of excess excavated material will not be measured for payment.
802.06.1 1 Reinforced Concrete Box Culverts: Excavation
and backfill required for box culvert construction will not be measu red for payment, except as specified in 203.14.1 .
802.06.1 2 Cofferdams: When the Contract does not contain an
item for “Cofferdams,” the cofferdams and cribs will not be measured for payment. When an item for “Cofferdams” is included in the Contra ct, the cofferdams will be measured on a lump sum basis and conform to Section 817, “Temporary Works.”
802.06.2 Water Control System : When the Contract does not
contain a n item for “Water Control System,” use an accepted method to control seepage and runoff. The “Water Control System” will not be measured for payment. When an item for “Water Control System” is included in the Contract, the water control system will be measured on a lump sum basis and shall conform to Section 817 , “Temporary Works. ”
802.06.3 Sheeting : Permanent sheeting will be measured based on
the design quantities shown on the plans per square foot. Temporary sheeting will be measured for payment based on the design shown on the plans per square foot . Contractor sheeting will not be measured for payment. Jetting or pre -boring of sheeting will not be measured for payment.
802.06.4 Mechanically Stabilized Earth Wall: Mechanically
Stabilized Earth Walls, designed, furnished, installed and accepted, will be measured by plan quantity per square foot of facing, as adjusted for field conditions. Embankment or reinforced backfill material will be measured per cubic yard as embankment under Section 203 .
802.06.5 MSEW Structural Excavation and Backfill: MSEW
Structural Excavation and Backfill will be measured on a lump sum basis.
802.07 PAYMENT . Payment for structural excavation, backfill, disposal
of excess excavated material, installation and/or removal of sheeting, and earth retaining structures will be made at the contract unit prices which includes all materials, labor, and equipment necessary to complete this item in accordance with th e Contract.
802.07.1 Structural Excavation : Payment for structural
excavation will be made at the contract unit price per cubic yard which includes required excavation and backfill, installation and removal of contractor sheeting, and disposal of excess excavate d material. When the required excavation depth is in excess of that specified, payment for the additional excavation required will be made in accordance with Table 802 -4. Table 802-4 Payment for Additional Excavation Depth of Foundation Excavation Below Specified Elevation (Feet) Percent of Contract Unit Price for the Excavation Item 0 to 2.0 100 2.1 to 4.0 125 4.1 to 6.0 150 6.1 to 8.0 175 8.1 to 10.0 200 Over 10.0 Extra Work
802.07.2 Sheeting : Payment for permanent and temporary sheeting
will be made at the contract unit prices.
802.07.3 Mechanically Stabilized Earth Wall (MSEW):
Permanent and temporary MSEW will be paid for at the contract unit price per square foot which includes furnishing design, materials, labor, equipment, and other incidentals require d to complete this item. Payment
802.06.4 Mechanically Stabilized Earth Wall: Mechanically
Stabilized Earth Walls, designed, furnished, installed and accepted, will be measured by plan quantity per square foot of facing, as adjusted for field conditions. Embankment or reinforced backfill material will be measured per cubic yard as embankment under Section 203 .
802.06.5 MSEW Structural Excavation and Backfill: MSEW
Structural Excavation and Backfill will be measured on a lump sum basis.
802.07 PAYMENT . Payment for structural excavation, backfill, disposal
of excess excavated material, installation and/or removal of sheeting, and earth retaining structures will be made at the contract unit prices which includes all materials, labor, and equipment necessary to complete this item in accordance with th e Contract.
802.07.1 Structural Excavation : Payment for structural
excavation will be made at the contract unit price per cubic yard which includes required excavation and backfill, installation and removal of contractor sheeting, and disposal of excess excavate d material. When the required excavation depth is in excess of that specified, payment for the additional excavation required will be made in accordance with Table 802 -4. Table 802-4 Payment for Additional Excavation Depth of Foundation Excavation Below Specified Elevation (Feet) Percent of Contract Unit Price for the Excavation Item 0 to 2.0 100 2.1 to 4.0 125 4.1 to 6.0 150 6.1 to 8.0 175 8.1 to 10.0 200 Over 10.0 Extra Work
802.07.2 Sheeting : Payment for permanent and temporary sheeting
will be made at the contract unit prices.
802.07.3 Mechanically Stabilized Earth Wall (MSEW):
Permanent and temporary MSEW will be paid for at the contract unit price per square foot which includes furnishing design, materials, labor, equipment, and other incidentals require d to complete this item. Payment
802.06.4 Mechanically Stabilized Earth Wall: Mechanically
Stabilized Earth Walls, designed, furnished, installed and accepted, will be measured by plan quantity per square foot of facing, as adjusted for field conditions. Embankment or reinforced backfill material will be measured per cubic yard as embankment under Section 203 .
802.06.5 MSEW Structural Excavation and Backfill: MSEW
Structural Excavation and Backfill will be measured on a lump sum basis.
802.07 PAYMENT . Payment for structural excavation, backfill, disposal
of excess excavated material, installation and/or removal of sheeting, and earth retaining structures will be made at the contract unit prices which includes all materials, labor, and equipment necessary to complete this item in accordance with th e Contract.
802.07.1 Structural Excavation : Payment for structural
excavation will be made at the contract unit price per cubic yard which includes required excavation and backfill, installation and removal of contractor sheeting, and disposal of excess excavate d material. When the required excavation depth is in excess of that specified, payment for the additional excavation required will be made in accordance with Table 802 -4. Table 802-4 Payment for Additional Excavation Depth of Foundation Excavation Below Specified Elevation (Feet) Percent of Contract Unit Price for the Excavation Item 0 to 2.0 100 2.1 to 4.0 125 4.1 to 6.0 150 6.1 to 8.0 175 8.1 to 10.0 200 Over 10.0 Extra Work
802.07.2 Sheeting : Payment for permanent and temporary sheeting
will be made at the contract unit prices.
802.07.3 Mechanically Stabilized Earth Wall (MSEW):
Permanent and temporary MSEW will be paid for at the contract unit price per square foot which includes furnishing design, materials, labor, equipment, and other incidentals require d to complete this item. Payment
802.06.4 Mechanically Stabilized Earth Wall: Mechanically
Stabilized Earth Walls, designed, furnished, installed and accepted, will be measured by plan quantity per square foot of facing, as adjusted for field conditions. Embankment or reinforced backfill material will be measured per cubic yard as embankment under Section 203 .
802.06.5 MSEW Structural Excavation and Backfill: MSEW
Structural Excavation and Backfill will be measured on a lump sum basis.
802.07 PAYMENT . Payment for structural excavation, backfill, disposal
of excess excavated material, installation and/or removal of sheeting, and earth retaining structures will be made at the contract unit prices which includes all materials, labor, and equipment necessary to complete this item in accordance with th e Contract.
802.07.1 Structural Excavation : Payment for structural
excavation will be made at the contract unit price per cubic yard which includes required excavation and backfill, installation and removal of contractor sheeting, and disposal of excess excavate d material. When the required excavation depth is in excess of that specified, payment for the additional excavation required will be made in accordance with Table 802 -4. Table 802-4 Payment for Additional Excavation Depth of Foundation Excavation Below Specified Elevation (Feet) Percent of Contract Unit Price for the Excavation Item 0 to 2.0 100 2.1 to 4.0 125 4.1 to 6.0 150 6.1 to 8.0 175 8.1 to 10.0 200 Over 10.0 Extra Work
802.07.2 Sheeting : Payment for permanent and temporary sheeting
will be made at the contract unit prices.
802.07.3 Mechanically Stabilized Earth Wall (MSEW):
Permanent and temporary MSEW will be paid for at the contract unit price per square foot which includes furnishing design, materials, labor, equipment, and other incidentals require d to complete this item. Payment
802.06.4 Mechanically Stabilized Earth Wall: Mechanically
Stabilized Earth Walls, designed, furnished, installed and accepted, will be measured by plan quantity per square foot of facing, as adjusted for field conditions. Embankment or reinforced backfill material will be measured per cubic yard as embankment under Section 203 .
802.06.5 MSEW Structural Excavation and Backfill: MSEW
Structural Excavation and Backfill will be measured on a lump sum basis.
802.07 PAYMENT . Payment for structural excavation, backfill, disposal
of excess excavated material, installation and/or removal of sheeting, and earth retaining structures will be made at the contract unit prices which includes all materials, labor, and equipment necessary to complete this item in accordance with th e Contract.
802.07.1 Structural Excavation : Payment for structural
excavation will be made at the contract unit price per cubic yard which includes required excavation and backfill, installation and removal of contractor sheeting, and disposal of excess excavate d material. When the required excavation depth is in excess of that specified, payment for the additional excavation required will be made in accordance with Table 802 -4. Table 802-4 Payment for Additional Excavation Depth of Foundation Excavation Below Specified Elevation (Feet) Percent of Contract Unit Price for the Excavation Item 0 to 2.0 100 2.1 to 4.0 125 4.1 to 6.0 150 6.1 to 8.0 175 8.1 to 10.0 200 Over 10.0 Extra Work
802.07.2 Sheeting : Payment for permanent and temporary sheeting
will be made at the contract unit prices.
802.07.3 Mechanically Stabilized Earth Wall (MSEW):
Permanent and temporary MSEW will be paid for at the contract unit price per square foot which includes furnishing design, materials, labor, equipment, and other incidentals require d to complete this item. Payment
802.06.4 Mechanically Stabilized Earth Wall: Mechanically
Stabilized Earth Walls, designed, furnished, installed and accepted, will be measured by plan quantity per square foot of facing, as adjusted for field conditions. Embankment or reinforced backfill material will be measured per cubic yard as embankment under Section 203 .
802.06.5 MSEW Structural Excavation and Backfill: MSEW
Structural Excavation and Backfill will be measured on a lump sum basis.
802.07 PAYMENT . Payment for structural excavation, backfill, disposal
of excess excavated material, installation and/or removal of sheeting, and earth retaining structures will be made at the contract unit prices which includes all materials, labor, and equipment necessary to complete this item in accordance with th e Contract.
802.07.1 Structural Excavation : Payment for structural
excavation will be made at the contract unit price per cubic yard which includes required excavation and backfill, installation and removal of contractor sheeting, and disposal of excess excavate d material. When the required excavation depth is in excess of that specified, payment for the additional excavation required will be made in accordance with Table 802 -4. Table 802-4 Payment for Additional Excavation Depth of Foundation Excavation Below Specified Elevation (Feet) Percent of Contract Unit Price for the Excavation Item 0 to 2.0 100 2.1 to 4.0 125 4.1 to 6.0 150 6.1 to 8.0 175 8.1 to 10.0 200 Over 10.0 Extra Work
802.07.2 Sheeting : Payment for permanent and temporary sheeting
will be made at the contract unit prices.
802.07.3 Mechanically Stabilized Earth Wall (MSEW):
Permanent and temporary MSEW will be paid for at the contract unit price per square foot which includes furnishing design, materials, labor, equipment, and other incidentals require d to complete this item. Payment
802.06.4 Mechanically Stabilized Earth Wall: Mechanically
Stabilized Earth Walls, designed, furnished, installed and accepted, will be measured by plan quantity per square foot of facing, as adjusted for field conditions. Embankment or reinforced backfill material will be measured per cubic yard as embankment under Section 203 .
802.06.5 MSEW Structural Excavation and Backfill: MSEW
Structural Excavation and Backfill will be measured on a lump sum basis.
802.07 PAYMENT . Payment for structural excavation, backfill, disposal
of excess excavated material, installation and/or removal of sheeting, and earth retaining structures will be made at the contract unit prices which includes all materials, labor, and equipment necessary to complete this item in accordance with th e Contract.
802.07.1 Structural Excavation : Payment for structural
excavation will be made at the contract unit price per cubic yard which includes required excavation and backfill, installation and removal of contractor sheeting, and disposal of excess excavate d material. When the required excavation depth is in excess of that specified, payment for the additional excavation required will be made in accordance with Table 802 -4. Table 802-4 Payment for Additional Excavation Depth of Foundation Excavation Below Specified Elevation (Feet) Percent of Contract Unit Price for the Excavation Item 0 to 2.0 100 2.1 to 4.0 125 4.1 to 6.0 150 6.1 to 8.0 175 8.1 to 10.0 200 Over 10.0 Extra Work
802.07.2 Sheeting : Payment for permanent and temporary sheeting
will be made at the contract unit prices.
802.07.3 Mechanically Stabilized Earth Wall (MSEW):
Permanent and temporary MSEW will be paid for at the contract unit price per square foot which includes furnishing design, materials, labor, equipment, and other incidentals require d to complete this item. Payment will include, but will not be limited to: modular concrete facing blocks, precast concrete panels, galvanized steel reinforcing and tie strips or galvanized steel mesh and mesh connectors or geosynthetic reinforcement, geotextile fabric, level up concrete, coping, leveling pad, internal and external drainage and dewatering systems, temporary retaining systems, temporary surcharge wall, special backfill material requirements, and removal of temporary items. Embankment or rei nforced backfill material will be paid for as embankment under Section 203 . Additional cost associated with its special material requirements will be included in th e MSEW item.
802.07.4 MSEW Structural Excavation and Backfill:
Excavation below the original ground line and subsequent backfill to the original ground line required for the construction of the MSEW structure will be paid for at the contract lump sum price, which includes all materials, labor, equipment, and other incidentals required for completion of this work. Payment will include, but not be limited to, furnishing and subsequently removing any temporary retaining systems and dewatering systems necessary for execution of the work, and disposal of all excavated materials below the original ground elevation to the final grading line. If no pay item for MSEW structural excavation and backfill is included in the contract, payment will be incidental to the MSE W. Payment will be made under: Item No. Pay Item Pay Unit 802-01 Structural Excavation (Type) Cubic Yard 802-02 Permanent Sheeting (Type) Square Foot 802-03 Temporary Sheeting (Type) Square Foot 802-04 Mechanically Stabilized Earth Wall Square Foot 802-05 MSEW Structural Excavation and Backfill Lump Sum will include, but will not be limited to: modular concrete facing blocks, precast concrete panels, galvanized steel reinforcing and tie strips or galvanized steel mesh and mesh connectors or geosynthetic reinforcement, geotextile fabric, level up concrete, coping, leveling pad, internal and external drainage and dewatering systems, temporary retaining systems, temporary surcharge wall, special backfill material requirements, and removal of temporary items. Embankment or rei nforced backfill material will be paid for as embankment under Section 203 . Additional cost associated with its special material requirements will be included in th e MSEW item.
802.07.4 MSEW Structural Excavation and Backfill:
Excavation below the original ground line and subsequent backfill to the original ground line required for the construction of the MSEW structure will be paid for at the contract lump sum price, which includes all materials, labor, equipment, and other incidentals required for completion of this work. Payment will include, but not be limited to, furnishing and subsequently removing any temporary retaining systems and dewatering systems necessary for execution of the work, and disposal of all excavated materials below the original ground elevation to the final grading line. If no pay item for MSEW structural excavation and backfill is included in the contract, payment will be incidental to the MSE W. Payment will be made under: Item No. Pay Item Pay Unit 802-01 Structural Excavation (Type) Cubic Yard 802-02 Permanent Sheeting (Type) Square Foot 802-03 Temporary Sheeting (Type) Square Foot 802-04 Mechanically Stabilized Earth Wall Square Foot 802-05 MSEW Structural Excavation and Backfill Lump Sum Section 803 Drilled Shafts
803.01 DESCRIPTION. Furnish and install drilled shafts of the
specified type, dimensions, locations, elevations, integrity, and resistance.
803.02 MATERIALS. Comply with the following sections and
subsections: Slurry 803.02 Portland Cement Concrete Section 901 Granular Material 1003.09 Cold Tar Epoxy Polyamide Paint 1008.04 Reinforcing Steel 1009.01 Concrete Admixtures 1011.02 Permanent Steel Casing 1013.11
803.02.1 Concrete Use Class S concrete conforming to Section 901
and with the following slump requirements: Dry placement methods: 5 – 7 inches Casing removal methods: 8 – 10 inches Tremie placement methods: 8 – 10 inches Slump loss of more than 4 inches shall not be permitted during the period equal to the anticipated placement period plus two hours. Slump life may be extended through use of retarders and mid-range water reducers .
803.02.2 Steel Casing: Casing shall be of ample strength to resist
damage and deformation from transportation and handling, installation and extraction stresses, and all pressures and forces acting on the casing. Casing shall be watertight and clean prior to placement in the excavation.
803.02.2 1 Permanent Casin g: Use steel conforming to ASTM
A36 or ASTM A252 Grade 2 unless specified otherwise on the plans. Corrugated casing is not allowed. All splicing of permanent structural casing shall be in accordance with Section 6 of the LRFD Bridge Design Specificati ons, latest edition . The inside diameter of permanent casing shall be as shown on the plans unless a larger diameter is approved by the