Incidental Construction (600-699)

619WORK ZONE TRAFFIC CONTROL

NY · 2024 Standard SpecificationsBook pages 571632View official source ↗

619-1 01

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 SECTION 617 - INVASIVE SPECIES MANAGEMENT

617-1 DESCRIPTION . This work shall consist of the control, eradication and management of invasive

species.

617-2 MATERIALS. As specified in the special specifications.

617-3 CONSTRUCTION DETAILS. As specified in the special specifications.

617-4 METHOD OF MEASUREMENT. As specified in the special specifications.

617-5 BASIS OF PAYMENT. As specified in the special specifications.

SECTION 618 (VACANT) SECTION 619 - WORK ZONE TRAFFIC CONTROL (Last Revised May , 2023)

619-1 Description

619-1.01 General. Work zone traffic control shall consist of all work necessary to provide for the safe

and efficient movement of traffic through or around work zones, and to protect workers and the public from damage to person and property which may result, directly or indirectly, from any construction work. Work zone traffic control shall be completed under the direction of a trained, competent person, as shown in the contract documents, the MUTCD and as directed by the Engineer. The duration of this work shall be from the date any work is started on the contract site, including mobilization of equipment, signs, offices, and shops until the date of contract final acceptance. Temporary materials and components that are furnished by the Contractor shall remain the property of the Contractor. See Figures 619 -1A and 619 -1B Component Parts of a Typical Highway Work Zone for definitions of terms. Work shall be categorized based on the following work durations:

A.Long Term Operation. Long term is stationary work that occupies a location for more than 3 consecutive days. It includes nighttime work.
B.Intermediate Term Operation. Intermediate term is stationary work that occupies a location for more than 1 daylight period up to 3 consecutive days. It includes nighttime work lasting more than 1 hour.
C.Short Term Operation. Short term is stationary daytime work that occupies a location for more than 1 hour during a single daylight period .
D.Short Duration Operation. Short duration is work that occupies a location for up to 1 hour. It can be performed during the daytime or at night in accordance with §619 -3.19 Nighttime Operations.
E.Mobile Operation. Mobile is work that moves intermittently or continuously where the work at any specific location completes within 15 minutes. It is used for vehicle based operations and does not involve workers on foot. It can be performed during the daytime or at night i n accordance with §619 -3.19 Nighttime Operations.

619-1 02

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3

F.Special Operation. Special Operations are work operations that do not fit under one of the five categories mentioned in §619 -1.01A through §619 -1.01E. Special operations include:
1.Stop and Go Operations. Work that completes within five minutes and allows workers on foot.
2.Other Operations. Including but not limited to Mowing Operations, Mulching and Herbicide Operations, Pavement Marking Operations, Temporary Road/Intersection Closures, etc.

619-1.02 Basic Work Zone Traffic Control. Work shall consist of controlling traffic over a reasonably

smooth traveled way which shall be marked by signs, delineators, channelizing devices, pavement markings, and other devices as shown in the contract documents or as directed by the Engineer. Work after sunset and before sunrise shall include additional requirements for nighttime operations including, but not limited to, a written plan for nighttime operations, additional worker and equipment protection, additional channelizing devices and contract site patrol. The Contractor shall conduct its operations to ensure the safety and convenience of travelers and abutting property owners as well as the safety of all workers on the contract. Travelers include, but may not be limited to motorists, motorcyclists, bicyclists, and pedestrians. Work shall be scheduled to keep the time and distance that existing pavement is removed or substantially disturbed to a minimum and consistent with the physical requirements of the contract. Unless otherwise indicated in the contract documents, the distance over which traffic is maintained on an unpaved surface shall not exceed 1/2 mile at any one time. During seasonal shutdown periods, no part of the highway shall be closed to traffic unless provided for in the contract documents, or the Contractor has submitted , and the Engineer has approved a detailed schedule of operations reflecting a proposal to close the highway to traffic. Basic work zone traffic control shall include the following:

A.Surface Condition, Debris, Drainage and Dust Control. Work shall consist of maintaining the surface condition of the traveled way, including detours, consistent with the preconstruction posted speed limit; including maintaining positive drainage, dust control and keeping the roadway free from debris and materials spilled from or tracked by vehicles or equipment. Debris a nd dust shall be controlled on all operations.
B.Seasonal Operations and Snow and Ice Control. Work shall consist of maintaining the traveled way to facilitate safe, efficient travel and permit snow and ice control by others during winter months and during any period that work is suspended.
C.Maintain Public Access. Work shall consist of maintaining vehicular, bicycle, and ADA compliant pedestrian public access to intersecting roads, residences, business establishments, adjacent property, bus stops and transportation facilities.
D.Maintain Existing Roadside Signs, Delineators and Markers. Work shall consist of maintaining, in their existing condition, existing highway signs, delineators, and markers within the contract limits.
E.Maintain Existing Guide Rail, Median Barrier and Bridge Rail. Work shall consist of maintaining existing traffic barriers and other safety devices, in their existing condition, within the contract limits.
F.Construction Vehicles and Equipment. Work shall consist of equipping construction vehicles and equipment with warning lights and reflective markings; and maintenance of vehicles and equipment in safe operating condition.

619-1 02

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3

G.Protective Vehicles. Work shall consist of furnishing protective vehicles to guide traffic and to protect workers in stationary or moving temporary traffic control zones as shown in the contract documents or as directed by the Engineer. Protective Vehicles shall be provided in accordance with the requirements of Table 011 -01 Protective Vehicle Requirements on Standard Sheet 619 -011. The specific § 619 Standard Sheets illustrate the minimum number and positioning of Protective Vehicle(s) required. Protect ive Vehicle(s) in addition to those that are required may be utilized in situations where special hazards (ex. work area at the base of grade on a two lane two way road, etc.) exist. When a protective vehicle(s) is used between the work vehicle (crew) or h azard and the traffic in a stationary operation it is referred to as a barrier vehicle(s) and when used in a moving operation it is referred to as a shadow vehicle(s). When a protective vehicle is used in advance of a moving or stationary operation to disp lay sign messages it is referred to as an advance warning vehicle. Protective Vehicles (PVs) exposed to traffic with preconstruction speed limit ≥ 45 mph require Truck / Trailer Mounted Impact Attenuators (TMIAs) as part of any mobile, short -duration, or short -term operation. Protective Vehicles (PVs) exposed to traffic with preconstruction speed limit ≤ 40 mph require Truck / Trailer Mounted Impact Attenuators (TMIAs) in accordance with the requirements of Table 011 -01 of Standard Sheet 619 -011
1.Barrier Vehicles. Work shall consist of furnishing barrier vehicles to guide traffic and protect workers in stationary lane and shoulder closures and other stationary temporary traffic control zones, as shown in the contract documents or as directed by the Engineer.
2.Shadow Vehicles. Work shall consist of furnishing shadow vehicles to guide traffic and to protect workers in work zones not protected by stationary lane or shoulder closures, as shown in the contract documents, or as directed by the Engineer.
3.Advance Warning Vehicles. Work shall consist of furnishing advance warning vehicles to guide traffic and/or to protect workers, as shown in the contract documents or as directed by the Engineer .
H.Construction Signs. Work shall consist of furnishing, installing, moving, maintaining, deactivating, and removing construction signs, including warning lights, as shown in the contract documents, or as directed by the Engineer.
I.Arrow Panels. Work shall consist of furnishing, installing, maintaining, and removing arrow panels as shown in the contract documents or as directed by the Engineer. Arrow panels are used to warn and guide traffic when travel lanes are temporarily closed by construction activities.
J.Channelizing Devices. Work shall consist of furnishing, placing, maintaining, and removing channelizing devices, with warning lights where required, including drums, vertical panels, construction barricades, cones, and temporary tubular markers. Type III construction barricades and interim tubular markers may be specified under separate pay items.
K.Pavement Edge Drop -Off Protection. Work shall consist of furnishing and maintaining protection for edge drop -offs adjacent to the pavement or shoulder.

619-1 03

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 L. Flagging and Traffic Control. Work shall consist of furnishing the necessary traffic control equipment and flaggers for adequate traffic control. Portable traffic signal systems authorized by the Engineer may be utilized only on a highway designated as a Restricted Highway.

M.Maintain Existing Mailboxes. Work shall consist of maintaining postal route mailboxes serviced from vehicles, in a useable condition and location consistent with U.S. Postal Service requirements.
N.Contract Site Patrol. Work shall consist of furnishing personnel to patrol the contract area as necessary to ensure conditions on the site are adequate for public safety and convenience at all times.

619-1.03 Basic Work Zone Traffic Control (Daily Operations). Work shall consist of controlling and

protecting traffic during a single work shift as shown in the contract documents, or as directed by the Engineer. The Contractor will not be required to repair or maintain the surface of the traveled way and other roadway features not part of the work, except to repair damage resulting from the Contractor’s operations.

619-1.04 Temporary Business Signs. Work shall consist of furnishing, installing, moving, covering,

maintaining, and removing temporary business signs as shown in the contract documents or as directed by the Engineer.

619-1.05 Covering or Removal of Pavement Markings. Work shall consist of removing or covering

existing permanent pavement markings, interim pavement markings, and temporary pavement markings including, but not limited to: edge lines, lane lines, center lines, crosswalks, stop bars, arrows, symbols, and dia gonal markings in gores and medians as shown in the contract documents or as directed by the Engineer.

619-1.06 Temporary Pavement Markings. Work shall consist of furnishing and applying temporary

pavement markings as shown in the contract documents or as directed by the Engineer. The work for removable pavement tape, removable wet -night reflective tape, temporary overlay markers and removable raised pavement markers shall include removal. Temporary pavement markings are intended for use on any new pavement or milled surface until the subsequent course is placed or interim pavement markings or final pavement markings are installed .

619-1.07 Interim Pavement Markings. Work shall consist of furnishing, applying, and maintaining,

interim pavement markings as shown in the contract documents or as directed by the Engineer. Interim pavement markings are intended for use in diversions, temporary pavement realignments and crossovers, lane shifts and closures, and other traf fic patterns associated with construction activities. Interim pavement markings are intended for use for a given phase or season, for a maximum of 1 year.

619-1.08 Temporary Rumble Strips. Work shall consist of installing, maintaining, and removing

temporary rumble strips at the locations shown in the contract documents or as directed by the Engineer.

619-1.09 Interim Tubular Markers. Work shall consist of furnishing, installing, moving, and

maintaining interim tubular markers attached to the pavement as shown in the contract documents or as directed by the Engineer. Interim tubular markers are typically used for 2 -way, 2 -lane freeway w ork zones and long -term closures where available width is limited.

619-1.10 Portable Variable Message Signs (PVMS) and Truck Mounted Variable Message Signs

(TMVMS).

619-1 11

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 A. Portable Variable Message Signs (PVMS). Work shall consist of furnishing, installing, operating, maintaining, relocating, and removing PVMS as shown in the contract documents or as directed by the Engineer. PVMS with a pay unit of each shall be provided for the duration of the contract at the general locations specified in the contract documents and in accordance with the Special Note Requirements for Portable Variable Message Signs (PVMS). PVMS with a pay unit of weeks shall be provided at general locat ions and durations in accordance with the Special Note Requirements for Portable Variable Message Signs (PVMS) and the contract documents. PVMS are intended to supplement other traffic control devices by displaying symbolic or word messages but are not to be used alone to replace conventional traffic control devices.

B.Truck Mounted Variable Message Signs (TMVMS). Work shall consist of furnishing, installing, operating, maintaining, and relocating TMVMS as shown in the contract documents or as directed by the Engineer. TMVMS with a pay unit of each shall be provided for the duration of the contract at the general lo cations specified in the contract documents. TMVMS with a pay unit of weeks shall be provided at general locations and durations in accordance with the Special Note Requirements for Truck Mounted Variable Me ssage Signs and the contract documents. TMVMS are intended to supplement other traffic control devices by displaying symbolic or word messages. They may only be used alone to replace conventional traffic control devices in mobile and short duration work zo nes or situations of limited duration.

619-1.11 Type III Construction Barricades. Work shall consist of furnishing, installing, moving,

maintaining, and removing Type III construction barricades, with warning lights where specified, as shown in the contract documents or as directed by the Engineer.

619-1.12 Temporary Positive Barrier. Work shall consist of furnishing, installing, moving, maintaining,

and removing approved temporary positive barrier (concrete or steel), including barrier warning lights and transitions to and from guide rail where specified, as shown in the contract documents or as directed by the Engineer.

619-1.13 Temporary Glare Screen. Work shall consist of furnishing, installing, moving, maintaining,

and removing glare screen mounted on a concrete barrier as shown in the contract documents or as directed by the Engineer.

619-1.14 Temporary Impact Attenuator. Work shall consist of furnishing, installing, maintaining,

repairing, moving, and removing temporary impact attenuators as shown in the contract documents or as directed by the Engineer.

619-1.15 Temporary Sand Barrel Arrays. Work shall consist of furnishing, installing, maintaining,

relocating, and removing temporary sand barrel arrays as shown in the contract documents or as directed by the Engineer.

619-1.16 Vehicle Arresting Barrier. Work shall consist of providing vehicle arresting barriers (net -type)

and their anchorages as shown on the Standard Sheets to prevent errant vehicles from entering a closed work area as shown in the contract documents or as directed by the Engineer.

619-1.17 Maintain or Modify Traffic Signal Equipment. Work shall consist of modifying or

maintaining in proper operation, existing, relocated, modified, or newly installed traffic signals as shown in the contract documents or as directed by the Engineer.

619-1.18 Temporary Traffic Signals. Work shall consist of furnishing, installing, moving, maintaining,

and removing temporary traffic signals and necessary components as shown in the contract documents or

619-1 19

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 as directed by the Engineer. Temporary signals shall be installed only on a highway designated as a Restricted Highway.

619-1.19 Nighttime Operations. Work shall consist of developing a Nighttime Operations and Lighting

Plan; furnishing, installing, operating, maintaining, moving, and removing lighting equipment for nighttime construction operations; constructing devices and adapting equipment to be comp atible with lighting equipment; and furnishing nighttime safety apparel and devices as shown in the contract documents or as directed by the Engineer. Balloon lights, or equivalent lighting, shall be used on nighttime moving operations and are defined as a light source inside a translucent material that produces a low-glare, 360 -degree, diffuse light.

619-1.20 Traffic Control Supervisor. Work shall consist of providing a full -time traffic control

supervisor having adequate training, experience, and authority to implement and maintain all traffic control operations, as shown in the contract documents or as directed by the Engineer.

619-1.21 Temporary Structures and Approaches. Work shall consist of designing, constructing,

maintaining, inspecting, relocating, and removing temporary structures, their approaches and any required appurtenances at the location(s) shown in the contract documents.

619-1.22 Pavement Patching. Work shall consist of providing and installing pavement patching

materials to maintain pavements open to traffic in acceptable condition as shown in the contract documents or as directed by the Engineer.

619-1.23 Mailboxes. Work shall consist of relocating or replacing postal route mailboxes and/or mailbox

supports consistent with U.S. Postal Service requirements, as shown in the contract documents or as directed by the Engineer.

619-1.24 Portable Temporary Rumble Strips. Work shall consist of furnishing, installing, maintaining,

and removing Portable Temporary Rumble Strip (PTRS) Arrays in accordance with the contract documents and as directed by the Engineer.

619-1.25 Automated Flagger Assistance Devices (AFAD). Work shall consist of furnishing, installing,

maintaining, and removing Automated Flagger Assistance Devices (AFAD) in accordance with the contract documents and as directed by the Engineer.

619-1 25

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 FIGURE 619-1A COMPONENT PARTS OF A TYPICAL HIGHWAY WORK ZONE WITH PROTECTIVE VEHICLE

619-1 25

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 FIGURE 619 -1B COMPONENT PARTS OF A TYPICAL HIGHWAY WORK ZONE WITHOUT PROTECTIVE VEHICLE

619-2 01

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 619.2 MATERIALS.

619-2.01 General. All materials used shall comply with the requirements of the following subsections of

Section 700 Materials and Manufacturing , or as established by this section, the applicable Standard Sheets, and the contract documents. Concrete Grouting and Anchoring Material 701-05 Precast Concrete Barrier 704-05 Epoxy Polysulfide Grout 721-03 Traffic Signal Heads 724-04 Removable Raised Pavement Markers 727-02 Epoxy Paint 727-03 Permanent Pavement Tape 727-04 Glass Beads for Pavement Markings 727-05 Removable Pavement Tape 727-06 Removable Wet-Night Reflective Tape 727-07 Permanent Wet-Night Reflective Tape 727-08 Traffic Paint 727-09 Drums 729-01 Cones 729-02 Temporary Tubular Markers 729-03 Vertical Panels 729-04 Stop/Slow Paddles 729-05 Type III Construction Barricades 729-08 Temporary Sign Supports 729-09 Temporary Impact Attenuators - Redirective 729-10 Temporary Impact Attenuators - Gating 729-11 Truck -Mounted and Trailer Mounted Impact Attenuators 729-12 Temporary Sand Barrels 729-13 Vehicle Arresting Systems 729-14 Arrow Panels 729-15 Portable Variable -Message Signs 729-16 Temporary Glare Screens 729-17 Warning Lights 729-18 Automated Flagging Assistance Devices 729-19 Portable Traffic Signals 729-20 Temporary Overlay Markers 729-21 Truck Mounted Variable Message Signs 729-22 Aluminum Sign Panels 730-01 Temporary Plywood Sign Panels 730-02 Temporary Rigid Lightweight Sign Panels 730-03 Retro -Reflective Sign Sheeting 730-05 Temporary Wooden Sign Posts 730-19 Stiffeners, Overhead Brackets and Miscellaneous Hardware 730-22 Fiberglass Reinforced Plastic Sign Panels 730-23 Type A Sign Supports 730-24 Type B Sign Posts 730-25 Note: Signs and panels supplied before March 1, 2023, may be fabricated with NYSDOT approved ASTM D4956 Type III/IV and/or IX retro -reflective sign sheeting based on the sign type.

619-2 02

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 619-2.02 Basic Work Zone Traffic Control.

A.Surface Condition, Debris, Drainage and Dust Control. Materials used to repair pavement surfaces shall be compatible with the pavement. In general, plant -mixed asphalt is suitable for all pavement surfaces to be repaired. Material other than plant -mixed asphalt may be used if approved by the Engineer. Environmentally compatible, approved dust palliatives may be used in conformance with any conditions placed on their use.
B.Seasonal Operations and Snow and Ice Control. (None Specified)
C.Maintain Public Access. (None Specified)
D.Maintain Existing Roadside Signs, Delineators and Markers. All materials used to maintain existing roadside appurtenances shall be consistent with the features to be maintained.
E.Maintain Existing Guide Rail, Median Barrier and Bridge Rail. All materials used to maintain existing roadside appurtenances shall be consistent with the features to be maintained.
F.Construction Vehicles and Equipment. All vehicles with a GVWR greater than 10,000 lbs and with restricted visibility to the rear shall be equipped with an operational audible backup alarm. Any vehicle with a non -operational backup alarm shall be taken out of service until the alarm is repaired. All vehicles and equipment within the contract limits and on the roadway shall be equipped with a rotating amber or flashing Light Emitting Diode (LED) beacon visible from all directions for a minimum of 1,000 feet during daylight. Flashing LED beacons sha ll meet the requirements of SAE J845 Class 2. Strobe lights shall not be used. All trucks and trailers with a GVWR greater than 10,000 lbs shall display retro -reflective markings in compliance with Code of Federal Regulations 49 CFR 393.11 - Lamps and Reflective Devices. The markings need not be continuous, but the sum of the length o f the segments shall be at least one -half the length of the body or trailer. The centerline of the sheeting shall be between 15 inches and 60 inches above the ground. All other construction equipment shall display similarly compliant markings on the front and rear (100 square inches per end minimum), as practicable.
G.Protective Vehicles. Protective vehicles are divided into 2 categories based on the Gross Vehicle Weight (GVW): Protective Vehicle Light (PVL) shall have a minimum GVW of 9,500 lbs. or greater, and; Protective Vehicle Heavy (PVH) shall have a minimum GVW of 22,000 lbs. or grea ter. Ballast may be used to bring a lighter vehicle up to the indicated weight provided the ballast is securely contained within an enclosed body or otherwise securely fastened to the vehicle pursuant to Federal Motor Carrier Safety Administration (FMCSA) Cargo Securement Rules, such that: 1. the ballast will not separate from the vehicle upon impact, and 2. the ballast weight will not exceed the manufacturer's GVW. Protective vehicles when used as barrier or shadow vehicles always require either a Type B or Type C arrow panel. Protective vehicles when used as advanced warning vehicles may require an arrow panel as shown on the 619 Standard Sheets. A Truck / Trailer mounted Variable Message Sign (TMVMS) meeting the size, legibility and illumination requirements of Type B or Type C Arrow Panels displaying approved messages per NYSDOT VMS GUIDELINES is acceptable. TMVMS may be used, if available, to supplement required work zone traffic control devices. The requirements for use of a protective vehicle depend on the type of closure, work duration, preconstruction posted speed limit, and exposure conditions. Protective vehicles with or without Truck/Trailer Mounted Impact Attenuator (TMIA) shall be used in accordance with the requirements shown on Table 011 -01 Protective Vehicle Requirements as shown on Standard Sheet 619 -011.

619-2 02

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 1. TMIAs manufactured after December 31, 2019 shall be Manual for Assessing Safety Hardware (MASH) compliant.

2.Any TMIAs manufactured after December 31, 2019, must have been successfully tested to the 2015 edition of MASH and shall be used as follows:
a.Where the preconstruction posted speed limit is ≤ 45 mph protective vehicles shall be equipped with a MASH Test Level -2 or MASH Test Level -3 truck mounted or trailer mounted impact attenuator.
b.Where the preconstruction posted speed limit is > 45 mph protective vehicles shall be equipped with a MASH Test Level -3 truck mounted or trailer mounted impact attenuator.
3.Any National Cooperative Highway Research Program (NCHRP) -350 compliant TMIAs manufactured on or before December 31, 2019, and successfully tested to NCHRP Report 350 or the 2009 edition of MASH, may continue to be used throughout their normal service liv es as follows:
a.Where the preconstruction posted speed, limit is ≤ 45 mph, protective vehicles shall be equipped with a NCHRP 350 Test Level -2 or NCHRP 350 Test Level -3 truck mounted or trailer mounted impact attenuator.
b.Where the preconstruction posted speed, limit is > 45 mph, protective vehicles shall be equipped with a NCHRP 350 Test Level -3 truck mounted or trailer mounted impact attenuator.
4.Damaged TMIAs shall be evaluated in accordance with the manufacturer’s specifications and instructions and, if deemed repairable, may be repaired, and returned to service.
5.Truck / Trailer Mounted Impact Attenuators shall not be mounted / installed on vehicles with a Gross Vehicle Weight (GVW) less than what is minimally required by the manufacturer of the TMIA. Where a barrier vehicle remains stationary for extended periods of time, the Contractor may utilize a barrier trailer in lieu of a barrier vehicle. A barrier trailer is a trailer that may be detached from the tow vehicle and that meets barrier vehicle wei ght, arrow board, attenuator, and placement distance requirements.
H.Construction Signs. Fabrication of all components shall produce a finished sign panel. Holes may be punched or drilled. Edges shall be smooth and true and free from burrs or ragged breaks. Sign panels, including face shape, color, dimensions, and characters shall be fabricate d using colors, character series, character sizes, symbols, route shields and borders as shown in the MUTCD or in the contract documents.
1.Sign Panels. Modification of sign legends by overlaying an existing legend with a revised legend, changing a single word or distance, such as changing LEFT to RIGHT or 1000 to 1500 will be permitted if the overlay is a match to the rest of the sign in terms of legend s ize and type, sheeting color and retro -reflectivity. The overlay shall be firmly adhered to the underlying panel. Any such overlays shall provide a visual match to the rest of the sign when viewed from a distance of 100 feet or greater duri ng all periods in which the sign will be used.

619-2 02

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 a. Rigid Sign Panels. Rigid sign panels shall be aluminum, fiberglass, plywood, or lightweight plastic. All construction sign faces on rigid panels shall conform to §730 -05 Retro -Reflective Sign Sheeting NYSDOT Class A sheeting. Characters including letters, numerals, route shi elds, symbols, logos, and borders shall conform to §645 -2.02 Sign Panels -

E.Sheeting Sign Characters.
b.Flexible Sign Panels. Flexible sign panels shall be a solid, fluorescent -orange, durable elastomeric material. Flexible panels fabricated from mesh will not be allowed. Flexible sign panels shall be mounted on supports with adequate bracing, so as to minimize flutter and to support the intended shape of the sign.
2.Mounting Temporary Signs. Temporary sign supports, except those located beyond the deflection distances of guide rail or temporary barrier as given in Table 619 -5 Guide Rail & Concrete Barrier Standard Deflection Distances or otherwise protected against impact by errant vehicles, shall meet the following requirements for portable or fixed supports. If rigid diagonal bracing is used, the high end of the bracing shall face away from approaching traffic. All wood supports shall be painted white.
a.Portable Temporary Sign Supports. Ballast used to stabilize supports shall be bagged sand or other suitable material and shall be located at ground level. Portable supports shall be a configuration which is NCHRP 350 approved or be constructed in accordance with a Standard Sheet(s).
b.Fixed Temporary Sign Supports. The Contractor shall provide NCHRP 350 approved Type A, Type B or wooden sign posts in accordance with §730 -19 Temporary Wooden Sign Posts , §730 -24 Type A Sign Supports , or §730 -25 Type B Sign Supports as appropriate .
3.Sign Covers. Covers used to inactivate unneeded construction signs shall be a single dark color, opaque material containing no wording or images. Rigid covers shall match the size and shape of the sign panel(s). Fabric sign covers may require more than one layer of fabric to prevent legibility of the si gn being covered. Rigid Lightweight panels used as covers shall meet the requirements §730 -03 Temporary Rigid Lightweight Sign. Signs hinged on the back side of the sign face to fold at the center and completely cover the sign face may be used.
I.Arrow Panels. Arrow panels shall be in accordance with §729 -15 Arrow Panels .
J.Channelizing Devices. Drums shall be in accordance with §729 -01 Drums. Standard cones, tall cones and extra tall cones shall be in accordance with §729 -02 Cones. Temporary tubular markers shall be in accordance with §729 -03 Temporary Tubular Markers. Standard and oversized vertical panels shall be in accordance with §729 -04 Vertical Panels .
K.Pavement Edge Drop -off Protection. (None Specified)
L.Flagging and Traffic Control. Hand signaling devices used to control traffic shall meet the requirements of the MUTCD. The standard signaling device shall be STOP/SLOW signal paddles in accordance with §729 -05 Stop/Slow Paddles. Red signal flags shall be a minimum of 24 inches x 24 inches. Automated Flagging Assistance Devices shall be in accordance with §729 -19 Automated Flagging Assistance Devices. Portable traffic signals shall be in accordance with §729 -20 Portable Traffic Signals.
M.Maintain Existing Mailboxes . (None Specified)

619-2 03

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 N. Contract Site Patrol . (None Specified)

619-2.03 Basic Work Zone Traffic Control (Daily Operations). (None Specified)

619-2.04 Temporary Business Signs . Temporary business signs shall conform to the MUTCD. Sign

panels shall be in accordance with 619 -2.02H.1. Sign Panels, except that the panels shall be white on a blue background. Supplemental arrows, as required, shall be white on a blue background (M5 -1 to M6 -2). Temporary business signs shall be mounted on temporary sign supports .

619-2.05 Covering or Removal of Pavement Markings . Tape used to cover existing pavement

markings shall be non -reflective, pavement marking masking tape, substantially similar in color to the pavement surface, in accordance with §727 -06 Removable Pavement Tape.

619-2.06 Temporary Pavement Markings . Temporary pavement markings shall consist of removable

raised pavement markers in accordance with §727 -02 Removable Raised Pavement Markers, or removable pavement tape in accordance with §727 -06 Removable Pavement Tape , or removable wet-night reflective tape in accordance with §727 -07 Removable Wet -Night Reflective Tape , or traffic paint in accordance with §727 -09 Traffic Paint and §727 -05 Glass Beads for Pavement Markings, or temporary overlay markers in accordance with §729 -21 Temporary Overlay Markers.

619-2.07 Interim Pavement Markings . Interim pavement markings shall consist of traffic paint in

accordance with §727 -09 Traffic Paint and §727 -05 Glass Beads for Pavement Markings , epoxy paint in accordance with §727 -03 Epoxy Paint and §727 -05 Glass Beads for Pavement Markings , removable pavement tape in accordance with §727 -06 Removable Pavement Tape , removable wet-night reflective tape in accordance with §727 -07 Removable Wet -Night Reflective Tape. Interim pavement markings shall be supplemented, where specified, with removable raised pavement markers in accordance with §727 -02 Removable Raised Pavement Markers.

619-2.08 Temporary Rumble Strips.

A.Raised Asphalt Rumble Strips. Raised asphalt rumble strips shall be formed from 6.3 or 9.5 asphalt pavement . Asphalt Emulsion Tack Coat shall be used to adhere the rumble strip to the existing pavement.
B.Raised, Removable -Tape Rumble Strips. Removable -tape rumble strips shall be formed from black, non -reflectorized, removable pavement -marking tape. Raised, removable -tape rumble strips shall have a minimum width of 6 inches, measured in the direction of traffic, with sufficient layers of tape such that each finished rumble strip ha s a thickness of 3/8 inches ± 1/8 inch.
C.Raised, Preformed Rumble Strips. Raised, preformed rumble strips shall be manufactured specifically as temporary rumble strips. Raised, preformed rumble strips shall have a minimum width of 4 inches, measured in the direction of traffic, with a thickness of between ¼ inch and ½ inch.
D.Saw-Cut Rumble Strips. Saw-cut rumble strips shall have a width of 4 inches ± ½ inch measured in the direction of traffic. The depressions shall have a rectangular cross section with a depth of 3/8 inches ± 1/8 inch.
E.Milled -in Rumble Strips. Milled -in rumble strips shall have a nominal width of 6 inches measured in the direction of traffic. The depressions shall have a semicircular, concave cross section with a depth of 3/8 inches ± 1/8 inch.

619-2 09

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 F. Removing Temporary Rumble Strips. Rumble strip depressions shall be filled in with a 6.3 or a 9.5 asphalt pavement meeting the requirements of Section 40 4, Asphalt Pavements.

619-2.09 Interim Tubular Markers. Interim tubular markers shall be in accordance with §729 -03

Temporary Tubular Markers .

619-2.10 Portable Variable -Message Signs (PVMS) & Truck Mounted Variable Message Signs

(TMVMS). Portable Variable -Message Signs shall be in accordance with §729 -16 Portable Variable - Message Signs (PVMS) . Truck Mounted Variable Message Signs (TMVMS) shall be in accordance with §729 -22 Truck Mounted Variable Message Signs. When a TMVMS is used as an arrow board, it shall comply with 729-15 Arrow Panels .

619-2.11 Type III Construction Barricades. Type III construction barricades shall be fabricated in

accordance with §729 -08 Type III Construction Barricades . All barricades used at night shall be equipped with warning lights in accordance with §729 -18 Warning Lights .

619-2.12 Temporary Positive Barrier. Temporary positive barrier segments shall be precast concrete

units in accordance with the Standard Sheets or steel or concrete barrier meeting the approved Materials Details of the products on the Department’s Approved List. All temporary positive barrier supplied after January 1, 2015, shall be produced in accordance with the requirements of §704 -05 Precast Concrete Barrier and shall have a legible permanent marking. Temporary positive barrier supplied prior to January 1, 2015, which was not produced in accordance with the requirements of §704 -05 Precast Concrete Barrier, shall be material certified in accordance with specific Standard Sheets or Materials Details used for fabrication. Warning lights for temporary barrier shall be in accordance with §729 -18 Warning Lights. Where warning lights are not required, temporary barrier segments shall be delineated using reflective panels covered with §730 -05 Retro -Reflective Sign Sheeting NYSDO T Class A sheeting, approximately 3 x 6 inch, having a minimum area of 18 square inches. Where warning lights are required, barrier need not be delineated with panels. Reflective pavement marking material applied to the face of the barrier shall not, by itself, be considered acceptable delineation. Where transitions between Temporary Positive Barrier and box beam are required, the box beam shall be in accordance with the requirements of §710 -21 Box Beam Guide Railing and Median Barrier. Where required, the Transition End Pieces shall be precast concrete units in accordance with the Standard Sheets and shall be produced in accordance with the requirements of §704 -05 Precast Concrete Barrier with a legible permanent marking. Where transitions between Temporary Concrete Barrier and Corrugated Beam are required, the corrugated beam shall be in accordance with the requirements of §710 -20 Corrugated Beam Guide Railing and Median Barrier

619-2.13 Temporary Glare Screen. Temporary glare screen shall be in accordance with §729 -17

Temporary Glare Screens .

619-2.14 Temporary Impact Attenuator. Temporary impact attenuators shall be in accordance with

§729 -10 Temporary Impact Attenuators - Redirective or §729 -11 Temporary Impact Attenuators - Gating.

619-2.15 Temporary Sand Barrel Arrays. Temporary sand barrels shall meet the requirements of

§729 -13 Temporary Sand Barrels . Sand fill shall meet the material requirements of §703 -06 Cushion Sand or §733 -15 Sand Backfill . Deicing material shall meet the requirements of §712 -03 Sodium Chloride .

619-2.16 Vehicle Arresting Barrier (VAB). Vehicle arresting barriers shall meet the requirements of

§729 -14 Vehicle Arresting Systems . Portland Cement Concrete used for bases shall be Class A or C, in

619-2 17

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 accordance with §501 Portland Cement Concrete – General, except that requirements for automated batching shall not apply.

619-2.17 Maintain or Modify Traffic Signal Equipment. All traffic signal hardware, including but not

limited to wire, cable, conduit, pull boxes, switch packs, modules and relays, detectors, signal heads, poles, and pedestrian push buttons used to maintain proper operation, shall meet the applicable requirements of §680 Traffic Signals . Materials which will be permanently incorporated into the work shall be in accordance with §680 Traffic Signals .

619-2.18 Temporary Traffic Signals. Equipment for temporary traffic signals shall meet the

requirements of Section §680 Traffic Signals , except that used equipment in good operating condition may be furnished, and for which material certifications are not required. All span wire, inductance -loop wire, shielded lead -in cable, traffic signal cable, and other wire used for temporary traffic signals shall be new material. Portable traffic signals shall be in accordance with §729 -20 Portable Traffic Signals . All other equipment for temporary traffic signals shall meet the requirements of §680 Traffic Signals except for the following modifications:

A.Temporary Poles. Temporary timber poles shall be ANSI O5.1, Class 2, treated with an appropriate waterborne wood preservative. Preservative retention shall be appropriate for the species when used in ground -contact application.
B.Signal Controller. The signal controller may be either solid -state or electro - mechanical.
C.Traffic Signal Heads. The materials and painting requirements of §724 -04 Vehicular and Pedestrian Traffic Signal Heads shall not apply except that the signal head housing shall be dark green.
D.Conflict Monitor. Means shall be provided to prevent the signal from displaying indications which will result in two or more conflicting traffic movements being permitted simultaneously.

619-2.19 Nighttime Operations. (None Specified)

619-2.20 Traffic Control Supervisor . (None Specified)

619-2.21 Temporary Structures and Approaches . When specific details and materials are shown in the

contract documents for temporary structures and approaches, substitutions or alterations may be permitted if approved by Deputy Chief Engineer (Structures) (DCES). When specific materials are not shown in the contract documents, the Contractor shall assume all liability and responsibility for certifying that all materials required to complete the work conform to the AASHTO Standard Specifications for Highway Bridges or NYSDOT Load and Resistance Factor Design (LRFD) Bridge Design Specifications or NYSDOT Standard Specification, Construction and Materials, unless otherwise approved by the DCES. If the Contractor proposes to fabricate/construct the temporary structure with used materials, the Contractor shall include with his submittal for the temporary structure, documentation that all primary member material meets the physical properties required by the design. In the absence of record plans, or other valid material certification for the used materials, physical testing shall be performed. The type of physical testing and the results of the testing shall be documented and submitted with the design computations. Excluded from the documentation and testing of physical properties provision are proprietary structures.

619-2 22

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 Used material shall not be furnished for fracture -critical members. Mill certifications shall be provided for all fracture critical material. Excluded from these fracture -critical provisions are pedestrian and pre-engineered (fabricated) proprietary structures .

619-2.22 Pavement Patching . In general, asphalt is suitable for all pavement surfaces. During winter

months when asphalt mixture is not available, a bituminous cold-patch material shall be used.

619-2.23 Mailboxes . Materials used shall meet the requirements of the U.S. Postal Service.

619-2.24 Portable Temporary Rumble Strips (PTRS ). PTRS material shall consist of thermoset cast

urethane, engineered polymers, or rubber materials and shall be manufactured for use at temperatures from 0 to 180°F. PTRSs shall be able to withstand vehicles up to 80,000 pounds with minimal dislocation or lateral movement. PTRSs shall be less than one inch in height and consist of a single segment or multiple interlocking sections. Each PTRS shall be capable of being installed without adhesives or bolts. The face of PTRS shall have a non -slip textured surface. PTRS shall be black in color.

619-3 Construction Details

619-3.01 General . The Contractor shall designate a work zone traffic control competent person who has

the primary responsibility and sufficient authority for implementing the work zone traffic control plan and other safety and mobility aspects as necessary. The Contractor’s work zone traffic control competent person shall be appropriately experienced and adequately trained in traffic control operations by recog nized training programs, including the American Traffic Safety Services Association (ATSSA) “Traffic Control Supervisor”, the National Safety Council, unions, or construction industry associations, or by an individual instructor from such a program in acco rdance with the level of decisions that the individual will be required to make, reflecting current industry practices and Department requirements. The Contractor shall generally maintain a traveled way suitable for moving traffic, in accordance with the contract documents and ensure construction equipment, vehicles, and materials are safely stored beyond the clear zone or behind protective barrier du ring non -working hours so as not to constitute a hazard to vehicles, bicycles and pedestrians. Construction operations shall be conducted to ensure a minimum of delay to traffic. Stopping traffic for more than 5 minutes shall not be permitted unless specif ically authorized in the contract documents or in writing by the Engineer. All operations shall be carried out in a manner that provides workers with safe access to the worksite and protects workers, pedestrians, and bicyclists from moving traffic. If the work zone affects the movement of pedestrians, pedestrian access and walkways shall be provided. If the work zone affects an accessible and detectable pedestrian facility, the accessibility and detectability shall be maintained along the alternate pedestri an route. The work zone traffic control competent person shall routinely inspect all work zone traffic control equipment and devices to make sure they are in a safe operating condition in accordance with §619 -3.02N Contract Site Patrol . Unless otherwise noted, temporary items supplied in accordance with this section shall remain the property of the Contractor. Where pedestrians are not prohibited from the street or highway, pedestrian traffic shall be maintained to allow their safe passage as shown in the contract documents. Where sidewalks, walkways, or shoulders must be temporarily closed to facilitate constru ction operations, safe pedestrian passage shall be maintained on at least one side of the roadway at all times, unless other temporary pedestrian accommodations are provided in the contract documents or are approved by the Engineer. Where pedestrian access is prohibited, workers shall not cross or enter travel lanes open to traffic . The requirements in this section refer to posted speed limits. If prevailing or operating speeds for a highway exceed the preconstruction posted limits, the contract documents may direct the Contractor to assume that the preconstruction posted speed limits are different than posted.

619-3 02

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 619-3.02 Basic Work Zone Traffic Control . The Contractor shall control traffic so that a person who has no knowledge of conditions may safely and with a minimum of discomfort and inconvenience ride, drive, or walk, day or night, over all or any portion of the highway and/or structure under constru ction where traffic is to be maintained. The Contractor shall cease operations and restore the traveled way to safe operating condition during any specific periods listed in the contract documents, at such times as traffic renders conditions unsafe to continue work, and during periods of darkness (before sunrise or after sunset), fog, snow or rain, high winds, or other inclement weather that renders conditions unsafe to continue work, for either the traveling public or the workers. The Engineer will determine when traffic or weather conditions ren der work operations unsafe.

A.Surface Condition, Debris, Drainage and Dust Control. The traveled way, sidewalks and pedestrian walkways shall be kept reasonably smooth and hard at all times, and shall be well drained and free of potholes, bumps, irregularities, and depressions that hold water. Except when construction operations necessita te disturbance of the normal surface, the Contractor shall maintain the pavement surface in such a condition as to permit the safe, comfortable passage of vehicles at the posted speed limit. A satisf actory riding surface shall be maintained both when work is underway, and when work is inactive. Special attention shall be given to maintenance of the traveled surface during hours of inactivity, including nights, weekends, holidays, and the winter season . Milling operations shall be conducted to prevent pavement runoff from collecting along milled joints. Bumps and transverse irregularities shall be eliminated to the extent practical. Pavement joints and milling rebates resulting in longitudinal or transver se vertical faces exceeding 1 inch in height that would be exposed to traffic during non -work hours shall be sloped or tapered with temporary patches or shims providing a taper rate in accordance with Table 619 -1 Required Treatment for Transverse Bumps . Where longitudinal tapered wedge paving joints are used, temporary pavement markings shall be provided prior to reopening lanes to traffic. The joints may be left open to traffic provided traffic is not expected to frequently change lanes, and UNEVEN LANES (W8-11) signs are posted in advance of the condition, posted at each ramp and roadway intersection, and repeated every ½ mile, supplemented with NEXT [X] MILES (W7 -3aP) auxiliary signs. Transverse bumps or vertical faces, unpaved surfaces, milled or grooved pavement, rough pavement, and other surface irregularities 1 inch or more in height shall be adequately sloped or tapered, or BUMP (W8 -1) or other appropriate warning signs shall be po sted in advance of the condition. A Type 1 Object Marker (OM1 -3) or a drum with a flashing warning light shall be installed on the right side of the roadway at the bump or other condition. On expressways and freeways, an object marker or a drum with a flas hing warning light shall be installed on both sides of the roadway. Where traffic will be riding on milled pavement, the Contractor shall install GROOVED PAVEMENT (W8 -15) signs on the approaches. On multilane highways where only one lane in a direction is milled and multiple lanes are open to traffic, the Contractor shall supplement the GROOVED PAVEMENT sign with a black on orange LEFT LANE (M5 -4), CENTER LANE (M5-5) or RIGHT LANE (M5 -6) panel below the warning sign. Where only an entrance or exit ramp is milled, the Contractor shall sign the mainline with a GROOVED PAVEMENT sign and a supplemental ON RAMP (W13 -4) panel. Where both BUMP and GROOVED PAVEMENT signs are warranted, the GROOVED PAVEMENT sign shall be installed 500 feet upstream of the BUMP sign in non -urban areas, and 300 feet upstream in urban areas. Where the posted speed limit is 45 mph or higher, the Contr actor shallplace a portable variable message sign (PVMS) in advance of pavement that has been milled or grooved and is open to traffic, warning motorcycle riders to use caution. The PVMS will be paid for separately.

619-3 02

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 For expressways where the posted speed limit is 45 mph or higher, the Contractor shall not leave milled or grooved pavement for more than 7 calendar days before placement of the next pavement course. The Contractor shall keep the traveled way, sidewalks, and walkways free of construction materials and foreign objects that fall from vehicles or equipment. Materials spilled by, dropped from, or tracked by traffic or by any vehicle used in the Contractor’s operations along or across any public traveled way shall be removed immediately. The Contractor shall keep all surface drainage facilities operative at all times. Positive drainage shall be provided at all times, even during grading operations and periods of accumulated plowed snow, to adequately drain the traveled way and the remainder of the right -of-way areas. Maintaining positive drainage shall include cleaning of drainage grates on roadway pavements. Cleaning of drainage structures and drainage pipes of material not deposited due to the Contractor’s operations will be paid for separately. Repair of drainage structures will be paid for separately. Dust control measures shall be applied to control dust resulting from traffic on unpaved surfaces and from Contractor operations on or adjacent to the roadway. Dust control shall be adequate to prevent dust which hinders driver visibility, or which creates a nuisance condition for property owners and residents adjacent to the contract. Dusty conditions resulting from the Contractor’s operations may be corrected by the use of calcium chloride and/or water. If used, water shall be distributed uniformly using a suitable spray head or spray bar. TABLE 619-1 REQUIRED TREATMENT FOR TRANSVERSE BUMPS Height of Bump (in) Anticipated Exposure Time (Calendar Days) Posted Speed ≤ 45 mph Posted Speed > 45 mph 1 to 6 ≤ 7 6:1 10:1 > 7 15:1 30:1

B.Seasonal Operations and Snow and Ice Control. The Contractor shall maintain the traveled way in such a condition and conduct operations in such a manner that snow, and ice may readily be controlled by others as and when necessary, and in such a manner that proper drainage is provided for the melting of snow banks resulting from normal plowing. The Contractor will not be responsible for snow and ice control on the pavement, shoulder, or sidewalks which are not restricted by construction operations and open to the public During periods of seasonal shutdown, the traveled way shall be maintained in an acceptable manner for travel, and all traffic control devices and safety features maintained in a safe, operable condition. All construction signs and temporary traffic control devices that are not needed during shutdown periods shall be covered or removed.
C.Maintain Public Access. The Contractor shall provide and maintain at all times safe and adequate ingress and egress for intersecting roads, residences, business establishments, adjacent properties, bus stops and other transportation facilities for vehicles, pedestrians, and bicycles; at existing or at new access points, consistent with the work, unless otherwise authorized by the Engineer. Whenever construction operations disrupt or interfere with normal traffic patterns, intersections, business establis hment access points, and driveways shall be clearly marked using channelizing devices. A ROAD CLOSED (R11 -2) sign on a temporary sign support and Type III construction barricades with warning lights shall be used whenever an entire roadway or ramp is closed to traffic Where pedestrian facilities exist, or where pedestrian traffic is reasonably anticipated, the Contractor shall maintain pedestrian access on at least one side of the highway or street at all times, in accordance with the contract documents and the MUTCD. Where an existing pedestrian facility is disrupted, closed, or relocated, the temporary facility shall include accessibility features consistent with the features in the existing pedestrian facility. Pedestrian access may be provided using existing

619-3 02

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 pedestrian facilities, temporary sidewalks or walkways, or alternate paths. Where a sidewalk is closed, it shall be marked with a Type III construction barricade and a SIDEWALK CLOSED (R9 -9) sign. Advance warning signs and directional guidance shall be provided to direct pedestrians to alternate paths and crosswalks and to alert motorists. Where bus service is maintained, the Contractor shall provide suitable areas or locations for the loading and unloading of passengers. Potentially hazardous areas adjacent to sidewalks, walkways, or other areas used by pedestrians shall be protected to prevent pedestrian intrusion in accordance with §107 -05F. Restricted Areas . Open sidewalks and walkways shall be maintained and kept smooth and free from holes, obstructions, and tripping hazards. Surfaces shall consist of pavement, firmly compacted granular material, or other surfaces noted in the contract documents or approved by the Engineer. The width of the temporary facility shall match that of the existing facility where practicable. When it is not possible to meet the minimum width of 5 ft. for the entire length of the facility, a 5 ft. by 5 ft. passing space should be prov ided every 200 ft. Construction materials, vehicles, equipment, debris, temporary sign supports, or other materials shall not be placed or stored on open sidewalks or walkways unless expressly shown in the contract documents or approved by the Engineer. Where bicycles are not prohibited from the highway, adequate accommodations for bicyclists shall be maintained in the travel lanes, on the shoulder, or on alternate paths or facilities.

D.Maintain Existing Roadside Signs, Delineators and Markers. Existing Department authorized signs, delineators, markers, and their supports within the contract limits shall remain under the control and jurisdiction of the Engineer. Signs not authorized by the Department shall be removed from the right of way, as directed by the Engineer, in accordance with Section 647 Removing, Storing and Relocating Signs .
1.Maintenance. Existing signs, delineators, markers, and their supports shall be maintained by the Contractor. Adequate visibility of route markers and directional signing shall be provided for drivers at all times. If relocation of route markers and directional signing is necessary to accommodate construction operations, the temporary or new locations shall be subject to approval by the Engineer. Existing roadside delineators shall be removed or relocated only to the minimum extent necessary to accommodate the work under the contract. Where contract operations require the temporary removal of existing delineators to facilitate work operations, temporary roadside delineation consisting of the existing delineators, temporary delineators, or channelizing devices shall be in place each night and at any time work operations at that location are suspended. Temporary devices shall be placed at the outer edge of the shoulder at a spacing similar to the existing delineator spacing.
2.Storage. Existing signs, delineators, markers, and their supports which directly interfere with the construction operations shall be removed, stored, protected, cleaned, and replaced in accordance with the contract documents and the provisions of Section 647 Removing, Storing and Relocating Signs and will be paid for separately. Existing signs, delineators and markers removed for the Contractor’s convenience shall be stored, cleaned, and replaced at no additional cost to the State. Existing signs, deline ators and markers lost or damaged due to negligence of the Contractor shall be replaced at no additional cost to the State.
E.Maintain Existing Guide Rail, Median Barrier, and Bridge Rail. When construction operations require the temporary removal of existing bridge rail, guide rail or median barrier; or when existing rail will be removed and replaced with new rail, the Contractor shall schedule operations to minimize the time period that rail is not installed. Unless otherwise specified in the contract documents, guide rail or median barrier shall be replaced, or the location otherwise protected within 14 calendar days. Bridge rail systems shall be maintained in service at all times on any structure on which vehicle or

619-3 02

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 pedestrian traffic is maintained, unless a temporary barrier is installed, or other means are used to ensure that vehicles, bicyclists, and pedestrians are not exposed to the unprotected edge of a bridge. During non -work hours when traffic is being maintained on the facility, all temporary ends (free ends) of guide rail, median barrier and bridge rail shall be temporarily terminated and marked with a channelizing drum or object marker equipped with a Type A flashing warning light. Corrugated beam guide rail and median barrier, and heavy -post, blocked -out, corrugated beam guide rail and median barrier shall be temporarily terminated by having the exposed ends (free ends) dropped to the ground and pinned. The approach ends of box beam guide rail, median barrier and bridge rail shall be temporarily terminated with box beam guide rail end assemblies utilizing two splice plates and the proper number of bolts per connection. No posts for anchorages will be required. Special temporary splice plates are required to adapt box beam guide rail end assemblies to box beam median barriers. During any overnight period when existing guide rail or median barrier is temporarily removed, the Contractor shall install channelizing devices in the location where the guide rail or median barrier was removed in accordance with §619 -3.02J.6. Removed Existing Guide Rail or Median Barrier .

F.Construction Vehicles and Equipment. All construction vehicles and equipment operating within the contract limits, whether in the work space, in the traffic space, in spoil areas, in storage areas, or any other areas under the contract, shall be operated at all times with due consideration for the safety of the public and workers. All vehicles and equipment within the contract limits and on the roadway shall operate a rotating or flashing amber beacon. If visibility of the beacon is blocked by a portion of the vehicle or equipment, additional beacons shall be provided. Beacons shall be mounted in a manner which does not cause glare for the driver or operator. Short -term delivery vehicles not equipped with rotating or flashing amber beacon shall display four -way emergency flashers when in the temporary traffic control zone. Other than vehicles registered and meeting all applicable requirements of the NYS Vehicle and Traffic Law, no construction vehicle or equipment used in the performance of the work shall be permitted to operate in travel lanes or shoulders open to traffic unless proper traffic control devices and other safety measures are in place to warn drivers of the presence of the equipment. On any highway where the posted speed limit is 45 mph or higher, no construction vehicle or equipment shall operate in a travel lane or shoulder open to and unimpeded by traffic at a speed less than 15 mph slower than the posted speed limit unless followed by a vehicle equipped with flashing warning lights and SLOW MOVING VEHICLE (W21 -4) sign on the rear. The Contractor shall ensure that all construction vehicles and equipment are safely stored beyond the clear zone during non -working hours so as not to constitute a hazard to vehicles and pedestrians, unless protected by traffic barrier.
G.Protective Vehicles.
1.Barrier Vehicles (Stationary Operation). The Contractor shall provide barrier vehicles to guide traffic and protect workers at the beginning of stationary shoulder closures, lane closures and other stationary work zones in accordance with the contract documents. Barrier vehicles with or without Truck/Trailer Mounted Impact Attenuator (TMIA) shall be used in accordance with the requirements shown on Table 011 -01 Protective Vehicle Requirements as shown on standard sheet 619 -011. The §619 Standard Sheets illustrate the minimum quantity and positio ning of Barrier Vehicles required. When located in the taper of a lane closure and another arrow panel is not present, arrow panels on barrier vehicles shall be operated in the appropriate flashing arrow mode . For all other applications, arrow panels shall display the four -corner flashing caution mode.

619-3 02

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 a. More Than One Hour Operation. Barrier vehicles used in a stationary operation that occupies a location for more than one hour should be unoccupied . The u noccupied vehicle shall be positioned parallel to traffic, parking brake set, placed in 2nd gear (Manual transmissions /engine off) or Park / Neutral (Automatic transmissions) and have the front wheels aligned with the lane striping and lane to maintain la ne discipline and to stay in lane if struck. ba. One Hour or Less Operation. Barrier vehicles used in a stationary operation that occupies a location for one hour or less shall be occupied . For an occupied vehicle, the operator shall remain in the vehicle with the safety belt and headrest properly adjusted, parking brake set whenever possible, keep the wheels aligned with the lane striping and lane to maintain lane discipline and to stay in lane if struck. cb. Use of Protective Vehicle Light (PVL) as a Barrier Vehicle. The use of a Protective Vehicle Light (PVL) as a Barrier Vehicle(s) is limited to Non -freeway roadways where the posted speed limit is ≤ 40 mph. dc. Use of Protective Vehicle Heavy (PVH) as a Barrier Vehicle. The use of a Protective Vehicle Heavy (PVH) as a Barrier Vehicle(s) is appropriate on all roadway types. A Protective Vehicle Heavy (PVH) shall be used on roadways with a posted speed limit ≥ 45 mph. Barrier vehicles shall be moved, if necessary, as the work progresses. The roll ahead distance (distance a vehicle is located in advance of the first workers or hazard) shall be based on Table

011-04 Roll Ahead Distance for Protective Vehicles as shown on Standard Sheet 619 -011.

2.Shadow Vehicles (Moving Operation). For posted speed limits of ≥30 mph, the Contractor shall provide shadow vehicles to guide traffic and protect workers conducting moving work operations except where the travel lane is closed to traffic by traffic barriers or by channelizing devices in accordance with the contract doc uments or as directed by the Engineer. Shadow vehicles with or without Truck/Trailer Mounted Impact Attenuator (TMIA) shall be used in accordance with the requirements shown on Table 011 -01 Protective Vehicle Requirements as shown on standard sheet 619 -011. The §619 Standard Sheets illustrate the minimum quantity and positioning of Shadow Vehicles required. When located in an open travel lane of a multi -lane roadway, the shadow vehicle shall display the flashing arrow panel in the appropriate mode. When located in a travel lane closed by barrier or channelizing devices, on a shoulder, otherwise not in an open travel lane, or on a two - lane, two -way roadway, th e arrow panel shall display the four -corner flashing caution mode. Shadow vehicles shall be occupied for the entire duration of the work. For an occupied vehicle, the operator shall remain in the vehicle with the safety belt and headrest properly adjusted and keep the wheels aligned with the lane striping. The parking bra ke shall be applied wherever possible. The shadow vehicle shall be moved as necessary to keep pace with the work operations. The roll ahead distance (distance the vehicle is in advance of the first workers or hazard) shall be based on Table 011 -04 Roll Ahead Distance for Protective Vehicles as shown on Standard Sheet 619-011. When mobile or short duration work operations occupy a long distance of a travel lane not closed to traffic by barrier or channelizing devices, such that traffic may reenter the lane between work operations, the Contractor shall provide additional shadow v ehicles for any gaps in the operation of ≥ 500 ft .

619-3 02

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3

a.Use of Protective Vehicle Light (PVL) as a Shadow Vehicle. The use of a Protective Vehicle Light (PVL) as a Shadow Vehicle is limited to Non -freeway roadways where the posted speed limit is ≤ 40 mph unless otherwise authorized by the engineer . A Protective Vehicle Light (PVL) shall be equipped with an appropriately rated Truck / Trailer Mounted Impact Attenuator pursuant to Table 011 -01: Protective Vehicle Requirements of Standard Sheet 619 -011.
b.Use of Protective Vehicle Heavy (PVH) as a Shadow Vehicle. The use of a Protective Vehicle Heavy (PVH) as a Shadow Vehicle is appropriate on all roadway types. A Protective Vehicle Heavy (PVH) shall be used on roadways with a posted speed limit ≥ 45 mph.
3.Advance Warning Vehicles (Moving or Stationary Operation). The purpose of the Advance Warning Vehicle is to display sign messages which advise motorists of what to expect ahead in Incident Management, Mobile and Short Duration operations. Advance Warning Vehicles with or without Truck/Trailer Mounted Impact Attenuator (TMIA) shall be used in accordance with the requirements shown on Table 011 -01 Protective Vehicle Requirements as shown on standard sheet 619 -011.The §619 Standard Sheets illustrate the minimum quantity and positioning of Advance Warning Vehicles required. If the vehicle encroaches the travel lane and reduces the traffic space below 10 feet on Non -freeway roads or 11 feet on Freeways it shall be equipped with a TMIA accordingly.
a.More Than One Hour Operation. Advance Warning Vehicles used in a stationary operation that occupies a location for more than one hour should be unoccupied . Unoccupied vehicle shall be positioned parallel to traffic, parking brake set, placed in 2nd gear (Manual transmissions /engine off) or Park / Neutral (Automatic transmissions) and have the front wheels aligned with the lane striping and lane to maintain lane discipline and to stay in lane if struck.
b.One Hour or Less Operation. Advance Warning Vehicles used in a stationary operation that occupies a location for one hour or less shall be occupied . For an occupied vehicle, the operator shall remain in the vehicle with the safety belt and headrest properly adjusted, parking brake set whenever possible, keep the wheels aligned with the lane striping and lane to maintain lane discipline and to stay in lane if struck.
c.Use of Protective Vehicle Light (PVL) as an Advance Warning Vehicle. The use of a Protective Vehicle Light (PVL) as an Advance Warning Vehicle is limited to Non-Freeway roadways where the posted speed limit is ≤ 40 mph. A Protective Vehicle Light (PVL) equipped with an appropriately rated Truck / Trailer Mounted Impact Attenuator may be used as an Advance Warning Vehicle on other roadway types where it is necessary for the Advance Warning Vehicle to remain completely on t he shoulder.
d.Use of Protective Vehicle Heavy (PVH) as an Advance Warning Vehicle. The use of a Protective Vehicle Heavy (PVH) as an Advance Warning Vehicle is appropriate on all roadway types. A Protective Vehicle Heavy (PVH) shall be used on roadways with a posted speed limit ≥ 45 mph.
H.Construction Signs. The Contractor shall install and maintain construction signs in good condition to adequately and safely inform and direct motorists, bicyclists, and pedestrians. Existing and construction signs shall indicate actual roadway conditions, and shall be covered, uncovered, changed, relocated, or removed immediately to reflect current conditions. Construction signs shall be

619-3 02

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 covered or removed when they no longer indicate actual conditions. The Contractor shall provide measures to protect workers during placement and removal of construction signs adequate for the prevailing speed, volume of traffic and roadway geometry where the work is to occur. Such protection may include, but is not limited to, the use of flaggers, spotters, and shadow vehicles equipped with truck -mounted or trailer mounted attenuators. Where pedestrian access is prohibited, workers shall not cross or enter travel lanes open to traffic. All signs shall be kept clean, mounted at the required height on acceptable supports, and installed in the proper position, alignment, and orientation so as to give maximum visibility. Construction signs will be evaluated for acceptability in accordance with the American Traffic Safety Services Association (ATSSA) Quality Guidelines for Work Zone Traffic Control Devices . When auxiliary panels are mounted above or below a warning or regulatory sign, they shall not cover any part of the warning or regulatory sign. Signs shall be placed so that each sign is visible at night, at the desired distance, without being obscured b y another sign, existing features on the highway, or foliage. The faces of stored signs shall not be visible to traffic in any direction, regardless of the orientation of the sign.

1.Sign Panels. Panels shall be flat and shall not be bowed or warped. Panel shapes shall not be altered, such as trimming corners of diamond shaped panels. If insufficient clearance exists, rectangular and/or smaller signs shall be used to obtain proper clearance. Panels with any wrinkling, delamination, or lack of adhesion of the reflective sheeting or legend will be evaluated for acceptability in accordance with the American Traffic Safety Services Association (ATSSA) Quality Guidelines for Work Zone Traffic Control Devices. Signs shall not bear any advertising message or any other message. A nonretroreflective logo or identifying information of the owner may be located on the back of the sign. The logo shall not exceed 1 square foot. The owner information shall not exceed 2 inches in height. Flexible, or roll -up, sign panels shall only be used for short -term, daytime use. All flexible sign panels shall be mounted on supports with adequate bracing, so as to minimize flutter and to support the intended shape of the sign. Fluorescent -orange colored flexible sign panels shall be approved by the Engineer prior to and for the duration of their use.
2.Mounting Temporary Signs. Unless otherwise noted in the contract documents or in the MUTCD, construction signs shall be mounted on a separate support. In cases where construction signs on an existing support will replace or supplement existing sign(s), they shall be mounted in accordance with the Standard Sheet(s). The type of temporary sign supports used shall be selected by the Contractor. Signs that are erected and removed or relocated on a daily basis, or that must be frequently relocated to adjust to the location of construction operations, may be mounted on portable temporary sign supports. If rigid diagonal bracing is used, the high end of the bracing shall face away from approaching traffic. Signs that are to remain at one location may be supported on fixed temporary sign supports. Supports for construction signs shielded by barrier or guide rail and located beyond the deflection distance described in Table 619 -5 Guide Rail and Temporary Positive Barrier Standard Deflection Distances are not required to be NCHRP 350 approved. When not in service, temporary signs mounted on portable temporary sign supports shall be stored in such a manner and location that they do not interfere with or present a hazard to vehicular, bicycle or pedestrian traffic. No signs or supports shall be stored on the traveled way, shoulders, or sidewalks during non -working hours. Portable temporary sign supports stored within the clear zone shall be laid flat such that no part of the support is more than 4 inches above the ground. No portable temporary sign supports shall be leaned against or overhang the traffic side of traffic barrier. All mounting heights are measured from the bottom of the lower sign panel to the nearest edge of pavement or to the ground directly below the sign, whichever results in a higher

619-3 02

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 mounting. Rigid sign panels shall have a minimum mounting height of 5 feet, or a minimum mounting height of 7 feet, where pedestrians or parked vehicles are present. For signs incorporating an auxiliary panel below the primary panel, the minimum mounting heights shall be 4 feet and 6 feet, respectively. For pedestrian, regulatory, and guide signs the minimum mounting height shall be 4 feet. Flexible panel and lightweight rigid panel signs shall be mounted at the same height as rigid panel signs, except they may be mounted, when approved by the Engineer, as low as 1 foot when all the following conditions are met:

a.(1) On two-lane, two-way roadways, or;
2.When signs are placed on the left and right sides of expressways and freeways.
b.Where there will be no parked vehicles to obstruct the view.
c.Where the first warning sign(s) of a work zone warning sign sequence is mounted at a height of 5 feet or higher and is located in advance of any flexible signs to alert motorists that they are entering a temporary traffic control zone.
d.When the lower mounting height does not adversely affect visibility of the sign by motorists.
3.Sign Covers. Covers for unneeded construction and/or permanent signs shall be attached in such a manner to cover the entire sign face including auxiliary panels above or below the main sign panel. The cover shall be firmly attached to the sign in a secure manner using straps, small hand clamps, small brackets, or other means to prevent dislodging. Sign covers shall be maintained in good condition to present a neat appearance and minimize distraction to motorists. Damaged covers which are no longer effective shall be promptly replaced. Sign covers for permanent signs that are unrelated to work zone traffic control operations will be paid for separately.
4.State Law Signs. Signs advising motorists of increased fines or license suspension for speeding within the work zone shall be installed in accordance with the contract documents. The LICENSE SUSPENDED AFTER TWO WORK ZONE SPEEDING TICKETS (NYR9 -11) or the FINES DOUBLED FOR SPEEDING IN WORK ZONES (NYR9 -12) sign shall be posted in advance of work zones not having a reduced regulatory speed limit for long term operations. For intermediate term operations, the NYR9 -11 or NYR9 -12 sign is recommended in advance of a work zone not having a reduced regulatory speed. The FINES DOUBLED FOR SPEEDING IN WORK ZONES (NYR9 -12) sign shall be posted in advance of work zones having a reduced regulatory speed limit regardless of the work duration. The state law sign shall be installed approximately 1,000 feet upstream of the first construction warning sign on highways with preconstruction posted speed limits equal to or greater than 45 mph and 300-500 feet upstream of the first construction warning sign on highways with preconstruction posted speed limits of less than 45 mph. For contracts with multiple work zones, the state law sign shall be installed at the aforementioned distances upstream of the ROAD WORK NEXT XX MILES (G20 -1) sign or at the contract limits and need not be installed prior to each activity area. If any of the individual activity areas have a reduced regulatory speed limit, the FINES DOUBLED FOR SPEEDING IN WORK ZONES (NYR9 -12) shall be used.

619-3 02

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 5. Special Use Work Zone Signs. Special use work zone signs shall be installed in accordance with the contract documents. Reduced regulatory speed limits in work zones shall be posted in accordance with contract documents with SPEED LIMIT signs (R2 -1) supplemented with WORK ZONE plaques (G20 - 5aP) of the same width mounted above the speed limit signs. The work zone plaques shall be placed on the same post and as the speed limit signs. REDUCED SPEED LIMIT AHEAD sign(s) (W3-5) shall be posted in advance of the first speed limit sign reducing the speed limit in a work zone. All reduced regulatory speed limit signs shall be installed on both sides of expressways and freeways. When traffic is reduced to a single lane, reduced regulatory speed limit signs should be installed only on the right side of the highway. Reduced regulatory speed limit signs shall be placed within the work zone activity area at a maximum spacing of ½ mile. Reduced regulatory speed limit signs shall be completely covered or removed, and preconstruction posted speed limit signs shall be uncovered or replaced, after a work zone activity area is restored. A work zone plaque shall not be mounted above preconstruction posted speed limit signs within a work zone. The END WORK ZONE SPEED LIMIT signs (R2 -12) or the preconstruction posted speed limit sign (R2 -1) shall be posted 100 ft beyond the end of a work zone activity area having a reduced regulatory speed limit. An END HIGHER FINES sign (R2 -11) shall be placed 200 feet beyond the END WORK ZONE SPEED LIMIT sign. If the regulatory speed is maintained throughout the work activity area, an END ROAD WORK (G20 -2) sign shall be placed a minimum of 80’ and a maximum of 400’ past the end of the downstream taper. For short, intermediate, and long term operations, and where shown in the contract documents, the Contractor shall install BE PREPARED TO STOP (W3 -4) signs to inform oncoming traffic of potential stopped, queued or very slow conditions. Each BE PREPARED TO STOP sign shall be mounted on a temporary sign support. For approaches on expressways and freeways with three lanes or more, both sides of the approach shall be signed unless the median is too narrow to fit the sign and the support. When used for a short or intermediate term operation, the BE PREPARED TO STOP (W3-4) sign shall be placed halfway between the first two advance warning signs. A PVMS may be used to supplement but not replace the required sign. For long term operations, the BE PREPARED TO STOP signs shall be posted approximately ½ mile in advance of the anticipated end of the queue. If the end of the queue is beyond the sign, the sign location shall be adjusted for the subsequent work day until the desired advance warning reflects typical conditions for that location. If the resulting adjustment places the sign in advance of the first warning sign, the Contractor shall also furnish and place a ROAD WORK (W20 -1) sign approximately 1,000 feet in advance of the BE PREPARED TO STOP signs. XX miles is the total expected length of work to be completed within a work day. A supplement distance plaque W7 -3a NEXT XX MILES shall be used with the first advance warning sign when the distance between the advance warning signs and the work area becomes greater than 2 miles as a result of the following situations:

a.Multiple work locations are anticipated within XX miles from the first advance warning sign.
b.Work area is expected to be relocated during the duration of the work within XX miles from the first advance warning sign. The supplement W7 -3a sign shall indicate the maximum anticipated distance between the first advance warning sign and the farthest work location. When multiple work locations exist within XX miles from the first advance warning sign, a

619-3 02

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 G20- 1 sign shall be placed every two miles indicating the distance to the farthest work location.

I.Arrow Panels. The Contractor shall provide, operate, and maintain arrow panels, also known as arrow boards, on highways having two or more travel lanes in the same direction, where the posted speed limit is 40 mph or higher, whenever a lane or lanes are closed to traffic and vehicles are required to merge with traffic in adjacent lanes. One arrow panel shall be provided for each lane closed to traffic regardless of the duration. Arrow panels shall be mounted so that the base of the panel is at least 7 feet above the pavement surface. Arrow panels shall be legible continuously from any point within the roadway (inclusive of shoulders) from 1,500 feet in advance of the lane closure taper to the beginning of the lane closure taper. Any arrow panel which cannot provide a sufficiently bright and clearly legible arrow display at any point within the roadway within the above distance shall be immediately repaired or replaced. Arrow panels shall not be used where they would interfere with the operation of a traffic signal or flasher or where there is an operation controlled by a signal or flagger(s). Arrow panels will not be permitted for alignment changes or lane diversions where the number of through traffic lanes is not reduced, or for any application on two-lane, two-way roadways except in the caution mode.
J.Channelizing Devices. Where construction operations obliterate pavement markings, or otherwise change or disrupt the normal traffic pattern, the Contractor shall use channelizing devices to physically separate traffic from portions of the roadway not available for travel; to separate traffic from hazards adjacent to the roadway; to separate opposing or adjacent travel lanes; to mark the location of hazards within or adjacent to the roadway; and to clearly define the intended travel path for vehicles, bic ycles, and pedestrians. Spacing of devices shall be sufficiently close at all times to provide clear and adequate guidance to ensure that vehicles, bicycles, and pedestrians follow the intended travel path. Channelizing device spacing requirements are stated in center -to-center distances. Channelizing devices shall be maintained upright, at proper spacing, in proper alignment and orientation, and kept clean. Channelizing devices used at night shall be retroreflective. Channelizing devices shall not bear any advertising or other message. A non -retroreflective logo or identifying information of the owner may be located on the back, base or top of channelizing devices where it does not obstruct the face, color, or reflectivity. The logo shall not exceed 1 square foot. The owner information shal l not exceed 2 inches in height. The Contractor shall make frequent checks commensurate with traffic conditions to identify and reset channelizing devices dislodged by traffic. Deformed or damaged devices and devices that do not maintain appearance, color, and reflectivity will be evaluated for acceptability in accordance with the American Traffic Safety Services Association (ATSSA) Quality Guidelines for Work Zone Traffic Control Devices . Ballast and/or mailboxes shall not be placed on top of a device or at any point above ground level. Ballast rings may be added to traffic cones, or traffic cones may be doubled, with one cone on top of the other, to serve as ballast. One Type A flashing warning light shall be installed on the first channelizing device in each series of a nightwork shoulder or travel lane closure. One Type A flashing warning light shall be installed on channelizing devices used to mark the location of hazards in or adjacent to the travel lane, including, but not limited to, pavement discontinuities, drainage structures, excavations, fixed objects, and other obstructions and potential hazards remaining at the end of the work shift. Where the placement of numerous Type A flashing warning lights may present a distraction to motorists, flashing warning lights may be eliminated at intermediate locations such as driveway entrances or intersections. Cones may be used in work zones where workers are not exposed to traffic, where the cones are placed to protect the work, and the placement does not create a hazard for traffic. In this application, cones are not considered channelizing devices.

619-3 02

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 Channelizing device application is summarized in Table 619 -2A Channelizing Device Application for Short -Term Stationary Work Zones and Table 619 -2B Channelizing Device Application for Intermediate -Term and Long -Term Stationary Work Zones . Where permitted, the Contractor may opt to substitute interim tubular markers or Type III construction barricades for other channelizing devices at no additional cost to the State.

1.Tapers. Tapers are defined as a transition area where motorists are redirected out of their normal path to a new path, including the tapered portion of lane closures, lane shifts, transitions, crossovers, ramps, intersections, or interchanges. The Contractor shall use drums or oversized vertical panels to delineate tapers. The Contractor may also use standard cones, tall cones, extra tall cones, and vertical panels for short term work zones during daylight hours only. At stationary work zones where worke rs are exposed to traffic and the posted speed limit is 40 mph or more, the spacing between channelizing devices shall not exceed 40 feet. Where the posted speed limit is less than 40 mph, the spacing between channelizing devices shall not exceed 20 feet.
2.Traveled Way (Including Lane and Shoulder Closures). The Contractor shall use drums , tall cones, extra tall cones, vertical panels, or oversized vertical panels to delineate the traveled way. The Contractor may also use standard cones and vertical panels for short term work zones during daylight hours only. At stationary work zones, where no workers are exposed to traffic or no workers are present, the spacing between channelizing devices shall not exceed 80 feet. At stationary work zones, where workers are exposed to traffic, the spacing between channelizing devices shall not exceed 40 feet. Wh ere necessary to permit ingress or egress by construction vehicles, wider gaps may be provided between channelizing devices, not to exceed the deletion of every fifth device. At expressway gores, the Contractor shall use drums, tall cones, extra tall cones, or oversized vertical panels. The Contractor may also use standard cones and vertical panels for short term work zones (during daylight hours) only. The Contractor may opt to substitute Type III construction barricades except in locations where they restrict driver vision. The spacing between channelizing devices shall not exceed 20 feet. At transverse bumps and other hazards on roadways where the posted speed limit is 40 mph or less, the Contractor shall use drums, extra tall cones, or oversized vertical panels. Along lane or shoulder closures, where traffic will be traveling adjacent to the closures, two channelizing devices consisting of tall cones, extra tall cones, drums, vertical panels, or oversized vertical panels shall be placed transversely across each cl osed lane and shoulder at maximum 800 feet intervals except in locations where it would interfere with milling, paving or other ongoing work, to discourage traffic from driving through the closed lane. The Contractor may also use standard cones for short t erm work zones (during daytime hours) only. The Contractor may opt to substitute one Type III construction barricade for two transverse devices. These transverse devices may be relocated or adjusted as necessary to permit passage of construction vehicles.
3.Roadway or Pavement Edge. The Contractor shall use drums, tall cones, extra tall cones, vertical panels, or oversized vertical panels where the work introduces or exposes hazards within the roadway or at the outside edge of the roadway, and pavement edge markings or permanent delin eators are not installed. The Contractor may opt to substitute Type III construction barricades. The spacing between channelizing devices shall not exceed 200 feet. If barrier is within 4 feet of the nearest travel lane, barrie r delineation at a spacing not exceed 20 feet may be provided in place of channelizing devices.

619-3 02

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 4. Roadway Intersections and Commercial Driveway Radii. The Contractor shall use drums, or extra tall cones to delineate roadway intersections and commercial driveways. The Contractor may also use standard cones, tall cones, and temporary tubular markers for short term work zones during daylight hours only. The spacing between channelizing devices shall not exceed 6 feet. Reduced spacing near roadway intersections and commercial driveways may be necessary to provide clear guidance. Vertical panels oversized vertical panels, and Type III barricades shall not be used. A non -signalized intersecting roadway shall be delineated by a new series of channelizing devices, and the series will start with one drum equipped with a Type A flashing warning light, placed along the primary roadway after the intersection.

5.Residential Driveway Radii. The Contractor shall use drums, or extra tall cones to delineate residential driveways. The Contractor may also use standard cones, tall cones, and temporary tubular markers for short term work zones during daylight hours only. The spacing between channelizing devices shall not exceed 6 feet. Reduced spacing near residential driveways may be necessary to provide clear guidance. Vertical panels oversized vertical panels, and Type III barricades shall no t be used.
6.Removed Existing Guide Rail or Median Barrier. The Contractor shall use drums, tall cones, extra tall cones, temporary tubular markers, vertical panels, oversized vertical panels, Type III construction barricades to delineate the edge of the shoulder or median in locations where guide rail or median ba rrier was removed. The spacing between channelizing devices shall not exceed 80 feet where the shoulder width is 4 feet or greater and shall not exceed 40 feet where the shoulder width is less than 4 feet. A minimum of three devices shall be provided for each individual run of guide rail or median barrier that has been removed.
7.Placing, Maintaining and Removing Channelizing Devices. The Contractor shall take all necessary precautions to protect the public and workers during the placement, maintenance, and removal of channelizing devices. Warning signs shall be in place in advance of and prior to the start of channelizing device placem ent and shall remain in place until after the channelizing devices have been removed. Channelizing devices shall be set up and removed by properly trained worker(s). The Contractor shall protect workers during placement and removal of channelizing devices, using measures adequate for the prevailing speed, volume of traffic and roadway geome try where the work is to occur. Protection shall include the use of automatic devices or from protected areas of a vehicle where practicable. Such protection may include, but is not limited to, the use of cone - setting equipment, cone baskets mounted on wo rk vehicles, flaggers, spotters, and shadow vehicles equipped with impact attenuators. Workers placing or removing traffic control channelizing devices onto/from the roadway from the back or side of a moving vehicle shall be protected by a fall restraint s ystem consisting of side racks, harness, and lanyard and/or cone basket so that a worker cannot fall off the vehicle and strike the pavement. Workers shall be seated in seats having seatbelts on moving work vehicles when not in the process of placing or removing channelizing devices. A shadow vehicle shall protect the channelizing device placement or removal operation on multi -lane highways, or a vehicle with a side or front cone basket shall meet the requirements of a shadow vehicle. Vehicles with front mounted cone baskets shall be u sed only on expressways and freeways traveling in the same direction as traffic.

619-3 02

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 TABLE 619 -2A CHANNELIZING DEVICE APPLICATION FOR SHORT -TERM STATIONARY WORK ZONES Maximum Device Spacing (center to center) MUTCD compliant Channelizing Device Work Zone Provisions Drums Standard Cones Tall Cones Extra Tall Cones Temporary Tubular Markers Interim Tubular Markers Vertical Panels Oversized Vertical Panels Type III Barricades Short -Term Stationary Work Zones involve daytime work that occupies a location for more than one hour and up to a single daylight period Shoulder/Merging/Shifting Tapers < 40 mph 20 ft. X X X X X X ≥ 40 mph 40 ft. X X X X X X One-Lane Taper for Alternating Two-Way Traffic 20 ft. X X X X X X Longitudinal Lane or Shoulder Closure w/Workers 40 ft. X X X X X X Longitudinal Lane or Shoulder Closure w/No Workers 80 ft. X X X X X X Freeway / Expressway Gores 20 ft. X X X X X X O Marking for Transverse Bumps 1 N/A X2 X2 X2 Transverse Device within Closed Traffic Lane and/or 800 ft X X X X X X O Roadway edge exposed with no Edgeline or Permanent Delineators 200 ft. X X X X X O Roadway Intersection or Commercial Driveway Radii 6 ft. X X X X X Residential Driveway Radii 6 ft X X X X X Removal of existing guide rail Shoulder width ≥ 4 ft. 80 ft. X X X X X X O Shoulder width < 4 ft. 40 ft. Pavement Drop offs > 2 in. and < 24 in. See Table 619-3 Drop off ≥ 24 in. within 10 ft. of active travel way; Posted speed ≤ 45 mph; Drop off Length ≤ 100 ft.; Not to last longer than 1 work shift 20 ft. X X X Closed Roads N/A X Closed Sidewalks N/A X NOTES: X = Allowed Blank = Not Allowed O = Optional at Contractor's expense 1 - A Type 1 Object Marker may be used in lieu of channelizing device 2 - Channelizing devices shall be equipped with a flashing warning light

619-3 02

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 TABLE 619 -2B CHANNELIZING DEVICE APPLICATION FOR INTERMEDIATE -TERM AND LONG -TERM STATIONARY WORK ZONES Maximum Device Spacing (center to center) MUTCD compliant Channelizing Device Work Zone Provisions Drums Standard Cones Tall Cones Extra Tall Cones Temporary Tubular Markers Interim Tubular Markers Vertical Panels Oversized Vertical Panels Type III Barricades Intermediate -term and Long -Term Stationary Work Zones involve work that occupies a location for more than 1 daylight period or nighttime work that occupies a location for more than 1 hour Shoulder/Merging/Shifting Tapers <40 mph 20 ft. X X ≥ 40 mph 40 ft. X X One-Lane Taper for Alternating Two-Way Traffic 20 ft. X X Longitudinal Lane or Shoulder Closure w/Workers 40 ft. X X X X Longitudinal Lane or Shoulder Closure w/No Workers 80 ft. X X X X Freeway / Expressway Gores 20 ft. X X X X O Marking for Transverse Bumps 1 N/A X2 X2 X2 Transverse Device within Closed Traffic Lane and/or 800 X X X X X O Roadway edge exposed with no Edgeline or Permanent Delineators 200 ft. X X X X X O Roadway Intersection or Commercial Driveway Radii 6 ft. X X Residential Driveway Radii 6 ft. X X Removal of existing guide rail shoulder width ≥ 4 80 ft. X X X X X X O shoulder width < 4 40 ft. Pavement Drop offs > 2 in. and < 24 in. See Table 619-3 Drop off ≥ 24 in. within 10 ft. of active travel way; Posted speed ≤45 mph; Drop off Length ≤ 100 ft.; Not to last longer than 1 work shift 20 ft. X X X Two-Lane Two -Way Operations on expressways and freeways at along curves 20 ft. X X O along tangents 40 ft. Two-Lane Two -Way Operations on expressways and freeways between Crossovers 40 ft. X X X X X X Closed Roads N/A X Closed Sidewalks N/A X NOTES: X = Allowed Blank = Not Allowed O = Optional at Contractor's expense 1 - A Type 1 Object Marker may be used in lieu of channelizing device. 2 - Channelizing devices shall be equipped with a flashing warning light.

619-3 02

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 K. Pavement Edge Drop -Off Protection. A drop -off is an abrupt difference in surface elevation of more than 2 inches at approximately 1V:3H or steeper. In the absence of adequate Traffic Control Plans in the contract documents, the Contractor shall submit alternate Traffic Control Plans to the Engineer for approval at least 30 calendar days prior to proposed work which will create a drop -off of over 24 inches within 10 feet from the edge of the traveled way for durations longer than one shift. The Contractor shall provide pavement edge drop -off protection in accordance with Table 619 -3 Pavement Edge Drop -Off Protection. Channelizing devices used to mark drop -offs shall be placed, as practicable, to not reduce the available travel lane width, at the elevation of the open travel lane in order to provide maximum target value and visibility for motorists. A drop -off of greater than 24 inches within 10 feet from the edge of the traveled way to remain at the end of the work shift shall be separated from traffic with temporary or permanent barrier. For posted speed limit of 45 mph and less, a drop -off of great er than 24 inches within 10 feet from the edge of the traveled way that is 100 feet or less in length will be allowed with channelizing devices consisting of drums, extra tall cones, or oversized vertical panels only at a maximum spacing of 20 feet for sho rt durations not to exceed one work shift. Unless otherwise noted in the contract documents, the Contractor shall begin work to eliminate unprotected drop -offs created by contract work within 7 calendar days of the completion of the work creating the drop -off. Work shall continue in a timely manner until such time as the unprotected drop - off condition is eliminated. Where pavement edge lines are not provided, channelizing devices shall be preceded by a NO SHOULDER (W8 -23) sign, repeated at all ramps and roadway intersections. Signs shall be repeated every ½ mile and supplemented with a NEXT [X] MILES (W7 -3aP) plaque w here applicable. Where pavement edge lines are provided, channelizing devices shall be preceded by SHOULDER DROP -OFF (W8 -17) signs, repeated at all ramps and roadway intersections. Signing shall be repeated every ½ mile and supplemented with NEXT [X] MILES (W7 -3aP) plaque where applicable. TABLE 619 -3 PAVEMENT EDGE DROP -OFF PROTECTION Drop -Off Height Edge Line Pavement Markings Drum Spacing (feet) Vertical Panel Spacing (feet) Tubular Marker Spacing (feet) Tall Cone Spacing (feet) Signs DROP -OFF AT OR WITHIN SHOULDER AREA Within 4 ft. from Travel Lane 2 – 6 in. Yes 100 100 N/A N/A Shoulder Drop -off No 40 40 N/A N/A No Shoulder 6 - 24 in. Yes 40 40 N/A N/A Shoulder Drop -off No 20 20 N/A N/A No Shoulder More than 4 ft. from Travel Lane 2 – 6 in. Yes 200 200 100 100 Shoulder Drop -off No 100 100 40 40 No Shoulder

619-3 02

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 6 - 24 in. Yes 40 40 N/A N/A Shoulder Drop -off No 40 40 N/A N/A No Shoulder DROP -OFF OUTSIDE OF SHOULDER EDGE Shoulder width ≤ 4 ft. 2 – 6 in. Yes 100 100 N/A N/A Shoulder Drop -off No 100 100 N/A N/A No Shoulder 6 - 24 in. Yes 40 40 N/A N/A Shoulder Drop -off No 40 40 N/A N/A No Shoulder Shoulder width > 4 ft. 2 – 6 in. Yes 200 200 100 100 Shoulder Drop -off No 100 100 40 40 No Shoulder 6 - 24 in. Yes 100 100 40 40 Shoulder Drop -off No 40 40 N/A N/A No Shoulder

L.Flagging and Traffic Control. The Contractor shall provide an adequate number of competent flaggers to control traffic when it is necessary to maintain alternating one -way traffic in one lane of a two-lane, two -way roadway, and at all other locations where construction operations, cons truction vehicles and equipment, and temporary traffic patterns related to the construction operations require positive temporary traffic control for safe, efficient traffic operations. These locations include, but are not lim ited to, locations where construction traffic enters, exits, or crosses open traffic lanes, locations of temporary stoppage of traffic for work operations, rail crossings, locations requiring slowing of traffic adjacent to work operations, on -ramps with re stricted site distance, pedestrian crossings, intersections, and other locations where traffic needs to be alerted to unexpected conditions ahead. Multiple lane approaches shall be reduced to a single lane prior to a flagger station. Automated flagger assistance devices (AFAD), portable traffic signals, and temporary traffic signals used to control traffic at the Contractor’s option in lieu of flagge rs shall be at no additional expense to the State.
1.Flagger Training. All flaggers shall be adequately trained in flagging operations by recognized training programs, including the American Traffic Safety Services Association, the National Safety Council, unions, or construction industry associations, or by an individual who holds a current certification as a flagger training instructor from such a program. Prior to the start of flagging operations, the Contractor shall provide to the Engineer a list of certified flaggers to be used in the operation, identifying the source of flagger training for each individual. When requested by the Engineer, flaggers shall demonstrate their competency in flagging procedures. Flaggers not competent in flagging procedures shall be retrained or replaced at once.
2.Flagger Equipment. Flaggers shall wear orange protective helmets and traffic control apparel in accordance with ' § 107 -05A. High Visibility Apparel. Flaggers shall be appropriately dressed, including apparel that covers the legs, torso, and arms with sleeves a minimum of 4 inches long and appropriate footwear. Immodest or sloppy dress will not be permitted. Flaggers shall be

619-3 02

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 equipped with an emergency air horn to alert workers of errant vehicles or other dangerous situations. Where flaggers are not within sight of each other, each flagger shall be equipped with a communication device, such as portable phone or two -way radio. T he communication device shall only be used to communicate with other flaggers, other workers, or supervisor(s) regarding the flagging operations. Where the distance between flaggers is more than ½ mile or where shown in the contract documents, the Contract or shall use pilot cars to lead lines of vehicles through the work zone. The standard signaling device for flagging operations, where one or more flaggers are controlling a single stream of traffic or two alternating streams of traffic in opposite directions, shall be STOP/SLOW signal paddles. Red signal flags may be used where display of the STOP and SLOW faces in opposite directions may be inappropriate or misleading.

3.Operational Control . Flaggers shall be located in a position clearly visible to, but not in the path of, approaching traffic, with an available escape path to avoid an oncoming errant vehicle. The number of flaggers to be furnished for each operation shall be sufficient to pr ovide safe, efficient flow of vehicle and pedestrian traffic. A spotter is not a flagger, and shall only direct construction vehicles or equipment, and shall not direct traffic in any manner. Work zones utilizing flaggers shall comply with the Standard Sheet for flagger operation and a Flagger symbol (W20 -7) sign shall be provided in advance of each flagger. For control of alternating one -way traffic, one flagger shall be provided at each end of the one-way section, with additional flaggers provided to control traffic entering the one -way section from intermediate intersections and major commercial driveways. Where the length of the one - way section is less than 150 feet, the posted speed limit is less than 40 mph, traffic volumes are such that queues do not develop, and sight distances are adequate, the Contractor may request approval from the Engineer to use a single flagger. For intersection control, at least one flagger shall be provided for each intersection approach. Where traffic speeds and/or volumes are unusually low, and adequate sight distance is available, such that safe operations can be ensured with fewer flaggers, the Contractor may request approval from the Engineer to use fewer flaggers. When flagging at an intersection with a traffic signal, the signal shall be turned off unless directed otherwise by the Engineer. The Contractor shall provide enhanced flagger stations consisting of additional cones at all approaches to flaggers, in accordance with the Standard Sheet, in order to provide effective advanced warning to motorists. On roadways with posted speed limits le ss than 40 mph, in locations having obstructed traffic flow, such as those having controlled intersections along the approach or approaches, where conditions do not permit placing the devices in a manner that will provide effective advanced warning to moto rists, enhanced flagger stations need not be provided. Flaggers shall be alert at all times and shall not stand with their backs to approaching traffic. Flaggers shall only direct traffic to stop, to slow or to proceed, using hand signals to supplement the signaling device in accordance with the flagging proce dures shown in the MUTCD. Flaggers shall be provided periodic breaks (minimum 15 minutes every 4 hours) throughout the work day, with competent substitutes provided during breaks to maintain continuous coverage of the flagging operation. A spotter shall be provided at all locations where construction vehicles or equipment must back across or into open travel lanes, sidewalks, or pedestrian walkways. A spotter shall only direct construction vehicles or equipment and shall not direct traffic in any manner. For ongoing flagging operations at a specific location, the Contractor may request approval from the Engineer to substitute portable traffic signals in lieu of flaggers.
4.Automated Flagging Assistance Devices (AFAD). AFADs are devices to control traffic through work zones remotely by a single flagger at a central location or at one end of the work zone.

619-3 03

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 A minimum of 7 calendar days prior to initial deployment of the AFAD system, the Contractor shall submit a traffic control plan to the Engineer, for review and approval, detailing AFAD operation including a list of competent flaggers trained to operate the AFAD. AFADs shall be used only on two -lane two -way or single lane one -way roadways. AFADs shall not be used where there are intersections and/or commercial driveways or where construction operations within the controlled highway segment frequently disrupt traffic flow. Appropriate flagger apparel and equipment shall be maintained near each AFAD to facilitate flagging in the event of a malfunction or operational need due to frequent disruptions of traffic flow. The Contractor shall immediately provide traff ic control with flaggers if a AFAD malfunctions; fails to properly or adequately control traffic; creates congestion, queues or gridlock which cannot be remedied by timely on -site adjustments to the signal operation; or is otherwise inadequate. A competent flagger, who has been trained on the operation of the AFAD, shall operate and not leave the AFAD(s) unattended at any time. The flagger shall have an unobstructed view of the AFAD(s) and approaching traffic in both directions at all times. The distance between AFADs shall not exceed ½ mile. Work zones utilizing AFADs shall comply with Standard Sheet 619-309. Red/Yellow lens AFAD shall have a STOP HERE ON RED (R10 -6) sign installed on the right - hand shoulder at least 8 ft in advance of the AFAD wh ere vehicles are expected to stop. A portable traffic signal may be used, at the Contractor’s option, as an AFAD. A Signal Ahead symbol (W3 -3) sign shall replace the BE PREPARED TO STOP sign. An 18 inch wide removable stop line with a STOP HERE ON RED (R10 -6) sign shall be installed at inte nded stopping point. The Engineer may waive the requirement for a stop line if the roadway is unpaved or it is otherwise impractical to install a stop line and the STOP HERE ON RED sign is in place. When the work no longer necessitates use of the AFAD or portable traffic signal, the units shall be removed or turned off and moved out of view from the traveled way. Specified AFAD’s may be replaced with human flaggers for a time period of no longer than 24 hours.

M.Maintain Existing Mailboxes. The Contractor shall not move any mailbox which contains mail. The Contractor will advise the owner to remove mail before the box is moved. Mailboxes shall be mounted, either permanently or temporarily, on a post. Before acceptance of the work, any mailbox which has been disturbed or moved shall be restored by the Contractor at a location consistent with the requirements of the U.S. Postal Service and the contract documents. Mailboxes shall not block the Pedestrian Accessible Route such that the location does not comply with ADA requirements. Posts set in pavement shall be set in a 6” or 8” sleeve to facilitate replacement. Wood posts should not be set in concrete but in soil or compacted crushed stone.
N.Contract Site Patrol. The Contractor shall provide adequate personnel and supervision to conduct operations and patrol the contract site to ensure that conditions are adequate for public safety and convenience at all times. The Contractor shall patrol the site as often as necessary during working and non-working hours to adjust and maintain signs, channelizing devices, and other traffic control devices and safety features.

619-3.03 Basic Work Zone Traffic Control (Daily Operations). The Contractor shall control traffic in

accordance with §619 -3.02 Basic Work Zone Traffic Control paragraphs A. Surface Condition; C. Maintain Public Access; D. Maintain Existing Roadside Signs; F. Construction Vehicles; G. Barrier/Shadow Vehicles; H. Construction Signs; I. Arrow Panels; J. Channelizing Devices; L. Flagging;

M.Maintaining Existing Mailboxes ; and O. Portable Traffic Signals so that a person who has no knowledge of conditions may safely and with a minimum of discomfort and inconvenience drive, ride, or walk, during the day or at night, over all or any portion of the highway and/or structure under construction where traffic is to be maintained. The Contractor will not be required to repair or maintain the roadway except to repair any damages resulting from its operations. The Contractor shall cease operations and clear the traveled way, shoulders, and clear zones of all

619-3 04

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 obstructions including traffic control devices, construction equipment, and materials at the end of each work shift.

619-3.04 Temporary Business Signs. The Contractor shall provide temporary business signs (NYI8 -4)

mounted on temporary sign supports to identify business entrances in accordance with the contract documents. Entrances shall be identified by only a single sign. Temporary business signs shall be mounted at a minimum height of 7 feet, and at a location that will guide traffic seeking access to the business, but where they will not interfere with traffic flow or other traffic control devices.

619-3.05 Covering or Removal of Pavement Markings. The Contractor shall remove or cover existing

permanent pavement markings, interim pavement markings and temporary pavement markings, as indicated in the contract documents or directed by the Engineer, to accommodate traffic pattern changes by covering the mar kings with preformed removable pavement marking masking tape, or by removing the markings. Masking tape shall be placed in blocks to prevent the underlying shape of pavement marking symbols or letters from being confused with existing markings.

A.Removal of Pavement Markings. The removal method will be at the Contractor’s option, subject to its ability to achieve satisfactory results. Removal shall be completed prior to the installation of temporary pavement markings or interim pavement markings. Grinding to remove pavement markings will typically remove 1/8 to ¼ inch of pavement surface. Prior to installation, the existing marking and adjacent pavement shall be cleaned of debris by compressed air or sweeping.
B.Masking Pavement Markings. Removable pavement marking masking tape shall be installed in accordance with the manufacturer’s written instructions. Prior to installation, the existing pavement marking, and adjacent pavement shall be cleaned by compressed air, sweeping, or other means adequate to remove debris, but that does not result in damage to the existing pavement marking. The width of the removable pavement marking masking tape shall be sufficient to completely cover the existing pavement marking. The masking tape shall firmly adhere to the entire length and width of the existing pavement marking to be covered. The Contractor shall maintain the tape for the duration of its use. Any tape that is loosened, removed, or that fails to retain its original matte finish, or that for any other reason fails to obliterate the existing pavement marking shall be replaced immediately, at no additional expense to the State. When the covered pavement markings are to be restored to service, masking tape shall be removed. Temporary adhesive residues will be allowed to remain, providing that the existing pavement marking visibility is not impaired. Any damage to the existing pavement markings or to the pavement surface that results from the removal of the masking tape shall be repaired at no additional cost to the State. If the existing marking cannot be repaired satisfactorily, the Contractor shall remove damaged pavement markings completely and/or replace the pavement section at no additional cost to the State.

619-3.06 Temporary Pavement Markings. The Contractor shall install and maintain temporary

pavement markings in accordance with the contract documents, using patterns and colors shown in the MUTCD to establish temporary traffic pattern(s) during construction on any pavement, including milled or grooved surface, resurfaced, new pavement, or other paved surface without pavement markings, for a maximum of 14 calendar days. Within 14 calendar days after placement, the Contractor shall either (1) install the succeeding pavement course or (2) install the remaining temporary pavement markings including edge lines, stop bars, and simple crosswalks, with no hatching. Pavements whi ch will be open to traffic shall be properly

619-3 07

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 marked before being opened, before nightfall, or before the end of the work day, whichever is soonest, except areas that are open during the work shift and delineated with channelizing devices or flaggers. Traffic paint need not be removed before placing a subsequent course. Removable pavement tape, removable wet -night reflective tape, temporary overlay markers and removable raised pavement markers shall be removed before placing a subsequent course at no ad ditional cost to the State. Temporary pavement marking stripes shall be a minimum of 4 inches in width. Temporary pavement markings shall be applied to a clean, dry pavement in accordance with the manufacturer’s recommendations. Hatch lines and symbols will not be required as tempora ry pavement markings unless required by the contract documents. Traffic paint pavement markings shall be applied at a minimum wet film thickness of 20 mil, immediately followed by an application of glass beads, at a rate of 6 lb/gal of paint. Where specified, removable raised pavement markers shall be used to supplement line pavement markings. The raised markers shall not be a substitute for line pavement markings, letters, or symbols. Removable raised pavement markers spaced every 5 feet may be used to supplement line pavement markings. Two removable raised pavement markers spaced at each end of the 2 foot marking may be used to supplement a 2 foot broken line pavement marking. If unanticipated weather or other conditions prevent the application of temporary pavement markings, the Contractor shall apply 2 foot removable pavement tape markings or temporary overlay markers at 40 foot spaces at no additional cost to the State, for a maximum of 3 days until such time as temporary pavement markings may be applied, or the next pavement course is installed.

A.Divided Highways. On freeways, expressways and parkways, the Contractor shall install broken lines a minimum of 2 feet long at 40 foot spacing to separate traffic lanes in the same direction. The Contractor shall install solid edge lines for a minimum of 100 feet on either side of the apex of a gore.
B.Undivided Multilane Highways. On three or more lane highways, and two or more lane highways with center two way left turn lanes, the Contractor shall install white broken lines a minimum of 2 feet long at 40 foot spacing to separate traffic flows in the same direction, and partial barr ier or full barrier centerline to separate traffic flows in opposite directions.
C.Two-Lane, Two -Way Highways. For two -lane, two -way highways, the Contractor shall install a temporary pavement markings consisting of full barrier centerline markings in no passing zones and 2 foot broken line markings at 40 foot spacing in passing zones. Two-lane, two -way highways may for a maximum of 3 days have the centerline marked with yellow 2 foot by 4 inch removable pavement tape or yellow temporary overlay markers at 40 foot spaces with NO CENTER LINE (W8 -12) signs and DO NOT PASS (R4 -1) signs at n o additional cost to the State. A NO CENTER LINE sign shall be installed in advance of the area marked with yellow 2 foot removable pavement tape markings or temporary overlay markers, as well as after major intersections and after major traffic generators within the area marked with the removable pavement tape markings or temporary overlay markings. A DO NOT PASS sign shall be installed within 100 feet of the beginning of the area with the removable pavement tape markings or temporary overlay markers, and a second DO NOT PASS sign shall be installed within 1,100 feet of the first DO NOT PASS sign and subsequent DO NOT PASS sign(s) shall not exceed 3,000 feet spacing. On an approach without centerline pavement markings where passing will not be permitted, a black on orange NO PASSING ZONE (W14 -3) pennant shaped sign shall be installed on that approach. Full barrier, partial barrier or broken line temporary centerline pavement markings shall be placed within three calendar days.

619-3.07 Interim Pavement Markings. Work shall consist of furnishing, applying, and maintaining

interim pavement markings as shown in the contract documents or as directed by the Engineer. The work for removable tape, removable wet -night reflective tape, temporary overlay markers and removable raised

619-3 08

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 pavement markers shall include removal. Interim pavement markings are intended for use in diversions, temporary pavement realignments and crossovers, lane shifts and closures, and other traffic patterns associated with construction activities. Interim pave ment markings are intended for use for a given phase or season, for a maximum of 1 year.

A.Installation. Interim pavement markings shall be applied to a clean, dry pavement in accordance with the manufacturer’s recommendations. Interim pavement markings on roadways open to traffic shall be applied in the direction of traffic. Traffic paint and epoxy paint pav ement markings shall be applied at a minimum wet film thickness of 20 mils, immediately followed by an application of glass beads at a rate of 6 lb/gal of paint. Painted markings may be supplemented with removable raised pavement markers. Removable raised pavement markers shall be spaced at 5 feet to supplement a solid line, and 4 markers spaced shall be used to supplement a 10 foot segment of broken line. When use d to supplement a solid or broken line, markers shall be spaced a maximum of 80 feet on tangents and a maximum of 40 feet for curves with a radius less than 2,800 feet. Removable raised pavement markers shall not be used alone to simulate interim pavement markings.
B.Maintenance/Replacement. Traffic paint or removable tape shall be replaced upon (1) abrasion of the line such that more than 10 percent of the underlying pavement is visible within any 300 feet segment of line or (2) loss of more than 2 consecutive skip lines or (3) loss of more t han 50 feet of continuous line or (4) failure of any line to be clearly visible at night under low -beam headlamp illumination when viewed from a distance of 200 feet. Missing removable raised pavement markers shall be replaced upon (1) loss of more than 10 percent of the markers within a 300 feet long segment of line or (2) loss of more than 3 consecutive markers or (3) failure of any line to be clearly visible at night under low -beam headlamp illumination when viewed from a distance of 200 feet. The Contractor will not be responsible for damage or loss caused by snowplowing. In the event that such pavement markings are damaged or lost, the Engineer will determine whether to replace the lost pavement markings in kind or with other marking materials . Separate payment will be made for pavement markings replaced or installed due to damage or loss caused by snowplowing.

619-3.08 Temporary Rumble Strips. The Contractor shall install temporary rumble strips in three sets

of 6-strip patterns with 10 foot between individual strips. The type of strip installed will be at the Contractor’s option, except that sawcut or milled -in strips shall not be installed on new top course surfaces or existing surfaces that will not be paved over. Where there is no usable shoulder, or the shoulder is less than 3 feet wide, the rumble strips s hould be ended 3 feet short of the edge of usable pavement. On curbed roadways, rumble strips should end a minimum of 3 feet from the curb in order not to interfere with drainage. Rumble strips shall typically be placed in advance of each of the last three long-term advance warning signs such that drivers are alerted in time to see and read the signs. Rumble strips will typically be installed for a minimum of one week.

A.Raised Asphalt Rumble Strips. The roadway surface on which the rumble strips are to be attached shall be dry, free of surface contaminants such as dust or oil, and thoroughly swept with a stiff broom. The surface temperature of the pavement shall be 45°F or greater unless otherwise authorized by the Engineer. The pavement surface shall be cleaned with compressed air just prior to tack coating and subsequent installation of the rumble strips. The strips shall be formed using a rumble strip paver (drag box ) pulled transversely across the pavement, or by hand placement between forms fixed to the pavement. If forms are used, they shall be removed prior to compaction of the asphalt mixture. Compaction shall be accomplished using a plate tamper or a static roll er. Raised asphalt rumble strips shall have a width of 6 to 9 inches, measured in the direction of traffic, and have a final compacted thickness of 3/8 inch ± 1/8 inch.

619-3 09

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3

B.Raised Removable Tape Rumble Strips. Raised removable tape rumble strips shall be formed by applying one or more layers of removable preformed pavement marking masking tape. The tape shall be applied to a clean, dry pavement surface in accordance with the manufacturer’s recommendations. The p avement surface shall be swept or cleaned with compressed air just prior to application of the tape.
C.Raised, Preformed Rumble Strips. Raised preformed rumble strips shall be applied to a clean, dry pavement surface in accordance with the manufacturer’s recommendations. The pavement surface shall be swept or cleaned with compressed air just prior to application of the strip.
D.Saw-cut Rumble Strips. Saw-cut rumble strips shall be saw cut into existing pavement using wet cutting methods. The blade or blades shall be of such configuration that the desired dimensions of the saw cut can be made with one pass. No spacers between blades will be allowed. Before a travel lane with saw -cut rumble strips is reopened to traffic, the pavement shall be cleaned by sweeping, flushing, or with a stream of compressed air. Sawing slurry from the wet - sawing process shall be flushed from the pavement surface immediate ly.
E.Milled -in Rumble Strips. Milled -in rumble strips shall be milled into existing pavement using a rotary -type cutting head with a maximum nominal outside diameter of 24 inches. The cutting head shall be on its own suspension system, independent from that of the power unit, to allow the head to align itself with the slope of the pavement and/or any irregularities in the pavement surface. The pattern of cutting tips on the head shall be arranged to produce a relativel y smooth cut with no more than 3/32 inches between peaks and valleys. Prior to beginning work, the Contractor shall demonstrate to the Engineer the ability to achieve the desired surface without tearing or snagging the pavement. Before a travel lane with milled -in rumble strips is reopened to traffic, the pavement shall be cleaned by sweeping, flushing, or with a stream of compressed air.
F.Removing Temporary Rumble Strips. The Contractor shall either completely remove raised rumble strips from the pavement or fill in the depressions from saw -cut or milled -in rumble strips prior to the start of the winter plowing season, prior to the placement of successive pavement courses, or as directed by the Engineer. Any damage to the pavement surface resulting from the removal of raised rumble strips shall be repaired at no additional cost to the State. Rumble strip depressions shall be filled in with asphalt mixture . Before they are filled, the depressions shall be cleaned by sweeping, flushing, or with a stream of compressed air, and coated with Asphalt Emulsion Tack Coat. The rumble strips shall be overfilled slightly and compacted using a plate tamper or static ro ller so that the final compacted surface is flush with the existing pavement.

619-3.09 Interim Tubular Markers. The Contractor shall install interim tubular markers in accordance

with the contract documents. The Contractor shall attach interim tubular markers to the pavement in a manner that prevents them from being moved or dislodged by traffic. Interim tubular mar kers shall be installed on pavement that has been cleaned to remove pavement markings, oil, dirt, or other debris or substances that may interfere with a proper bond. Attachment to the pavement shall be by mechanical faste ner or by adhesive, in accordance with the manufacturer’s recommendations. Bonding agents shall be of sufficient amount or size to ensure proper bonding of the base to the pavement. Interim tubular markers removed or damaged by the Contractor’s operations or by traffic shall be replaced immediately, so that positive separation is maintained between opposing lanes of traffic at all times. Damaged reflective sheeting on interim tubular markers shall be replaced before nightfall as necessary to maintain adequate visibility of the markers. In cases where only isolated individual markers

619-3 10

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 are lost or damaged, and adequate visibility is maintained by the remaining markers, replacement will not be required until more than 3 consecutive markers, or 25 percent of all markers within ½ mile have been damaged or lost. The replacement of markers da maged or lost by traffic, where the Contractor has demonstrated reasonable effort to collect the costs from the person(s) responsible for damage will be considered extra work.

619-3.10 Portable Variable Message Signs (PVMS) and Truck Mounted Variable Message Signs

(TMVMS). The Contractor shall provide, operate, and maintain PVMS & TMVMS as indicated in the contract documents until the progress of work no longer requires their use. The Contractor shall relocate or reorient PVMS with a pay unit of each, if necessary, up to 4 t imes per year as conditions dictate, at no additional cost to the State. The Contractor shall provide, operate, and maintain PVMS with a pay unit of weeks at the general locations and duration stated in the contract documents and in accordance with the Special Note Requirements for Portable Variable Message Signs (PVMS). There shall be no extra payment due for each relocation or reorientation of TMVMS. On the P VMS & TMVMS, the message to be displayed shall be as required by the contract documents and may change on a daily basis or more frequently as conditions dictate. NYSDOT’s Variable Message Sign Guidelines shall be reviewed to ensure compliance with Chapter 5 - Messages. If the contract requires a NTCIP compliant PVMS, the Contractor shall provide the Engineer with the model, manufacture date and manufacturer of the NTCIP compliant PVMS the Contractor plans to use from the Approved List. After delivery to the work site, th e Contractor shall allow the Regional Transportation Management Center (TMC) to conduct operations and communications tests on one or more samples supplied by the Contractor. The testing will determine if the proposed PVMS meets the TMC’s operational requi rements by demonstrating remote communications to and from the TMC using NTCIP compliant operating software. TMVMS do not require NTCIP compliant communications. The message to be displayed shall be as required by the contract documents or as directed by t he Engineer. PVMS specified with cellular communications shall be equipped with control software compatible with the current computer operating system used in the Engineer’s Field Office. PVMS with Cellular Communications Option shall have cellular telephone service pr ovided by the Contractor. The Contractor shall supply the Engineer with two copies of operating instructions for the PVMS and the control software. The Contractor shall supply the Engineer with a copy of control software a minimum of 14 calendar days prior to installation of the first unit. Electronic copies of software instructions are acceptable. PVMS shall be placed so that the base of the message panel is at least 7 feet above the adjacent pavement surface and aligned to provide optimum viewing by approaching motorists. The Contractor shall supply the Engineer with an accurate log of the text of all messages and times messages were displayed monthly, not later than the 15th of the following month. The log of messages may be either a listing in a manual register or printouts from the control software. The Contractor shall inform the Engineer of PVM S and TMVMS locations and update as they are relocated and removed. The PVMS shall be protected from unauthorized use. All cabinet doors shall be secured and/or padlocked, and default manufacturer’s passwords shall be changed. Additional security measures shall be implemented as needed.

619-3.11 Type III Construction Barricades. Type III construction barricades shall be installed at all

locations where a highway, bridge, ramp, or other segment of the roadway is closed to traffic. Type III construction barricades shall be maintained upright, in proper alignment and orientation. If ballast is used to maintain alignment and position of the barricade, it shall consist of dry sand contained in a closed waterproof bag and shall be placed at ground level. Barricade rails shall be oriented such that the stripes slope downward toward the side on which traffic is to pass. If traffic may pass to either side, adjacent barricades shall be arranged such that the stripes slope downward toward each side starting at the center. Where no passage is intended or permitted, the stripes shall slope downward toward the center of the barricade or barricades.

619-3 12

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 At night, each Type III construction barricade used to close a roadway, a segment of a roadway or a sidewalk shall be equipped with one flashing warning light.

619-3.12 Temporary Positive Barrier. Temporary Positive Barriers are categorized by their standard

MASH TL -3 (pickup truck) deflection and their deflection reduction measures (pinning and or box -beam - stiffening). The barriers that satisfy a given deflection category are shown on the Departme nt’s Approved List for Temporary Positive Barriers. The system chosen and the segment length used must be capable of meeting the curvatures indicated in the Plans. The Engineer will inspect temporary barrier segments upon delivery. Any barrier segment having damage and/or defects in the segment and/or joint connections will be rejected if the performance of the barrier may be affected. Temporary positive barrier segments shall be fastened together to form a continuous string. When joined together, the barrier segments shall form a smooth and continuous barrier. Any segments damaged or misaligned shall be corrected or replaced. The connec tions shall conform to the approved details for the particular barrier. Tapered end sections shall not be used in traversable medians, gores, or other areas where impacts on a tapered end section could allow vehicles to penetrate opposing or adjacent lanes of traffic. Where the posted speed limit is 45 mph or higher, a tempora ry impact attenuator or temporary sand barrel array shall be provided on approach ends of temporary positive barrier when the offset from the edge of the traveled way to end of the barrier is less than 12 feet and will be paid for separately. Where space is available, approach ends of the barrier string shall be flared away from the traveled way at the taper rate shown in Table 619 -4 Flare Rates for Positive Barrier and terminated in a tapered end section, embedded in a slope, or otherwise prot ected against impact by errant vehicles. The Contractor shall install temporary barrier where indicated, and of the deflection Category indicated in the contract documents. Where pinning is indicated for the given barrier, the pinning shall be in conformance with the pinning requirements indicate d in the Approved List. Where pins extend above the top surface of the barrier anchor recess, they shall be covered with plastic or rubber. TABLE 619-4 FLARE RATES FOR TEMPORARY POSITIVE BARRIER POSTED PRECONSTRUCTION SPEED LIMIT (mph) 30 40 50 55 65 TEMPORARY POSITIVE BARRIER 8:1 11:1 14:1 16:1 20:1 BOX BEAM OR HEAVY POST CORRUGATED BEAM 7:1 9:1 11:1 12:1 15:1 TABLE 619-5 GUIDE RAIL AND NYSDOT TEMPORARY CONCRETE BARRIER STANDARD** DEFLECTION DISTANCES BARRIER TYPE POST SPACING (ft) DEFLECTION DISTANCE (ft) CABLE GUIDE RAIL 16 11.0* 12 9.5* 8 8.0* 4 7.0* CORRUGATED W -BEAM (WEAK POST) GUIDE RAIL 12.5 8.0 6.25 6.0 4.16 5.0 CORRUGATED W -BEAM (HEAVY POST BLOCKED OUT) 6.25 4.0 3.12 2.0 BOX BEAM GUIDE RAIL 6.0 5.0 3.0 4.0 CORRUGATED W -BEAM 12.5 7.0

619-3 12

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 (WEAK POST) MEDIAN BARRIER 6.25 5.0 CORRUGATED W -BEAM (HEAVY POST) MEDIAN BARRIER 6.25 2.0 BOX BEAM MEDIAN BARRIER 6.0 3.0 NYSDOT TEMPORARY CONCRETE BARRIER Unpinned 3.25** Box-Beam -Stiffened 2.2** Pinned 0.8** * Note: NCHRP 350 Standard Deflection caused by a 4,400 -lb test vehicle traveling 62 mph impacting the barrier at a 25° angle **Note: Standard Deflections are those assumed to occur with a Standard TL-3 Impact. MASH Standard Impact is produced by a 5,000 -lb test pickup traveling 62 mph impacting the barrier at a 25° angle. The temporary concrete barrier stiffened with box beam shall be installed at least 50 feet prior to, be continuous through, and extend at least 50 feet beyond the area requiring limited deflection, wherever practicable. Where space limits extending the string of barrier stiffened with box beam, one segment at either end of the string shall be pinned with 4 pins on the construction, or non -traffic, side. At any transition between pinned and unpinned portions of a temporary positive barrier run, to provide a gradual change in fixity, one piece of barrier shall be partially pinned using 2 pins on the construction side of the barrier. The partially pinned pi ece shall be included in the measurement of pinned barrier. Pins shall have the following minimum embedment lengths: • Bridge Decks and Cement Concrete Pavement 5 in. • Flexible Pavement 18 in. • Unpaved Areas 30 in. After removal of the barrier, pin holes created in the surface shall be filled, unless that area will be further disturbed. Holes in flexible pavement shall be filled with warm or cold mix top course asphalt material rodded in 3” lifts. Holes in portland cement concrete pavement or structural decks shall be filled with material meeting the requirements of §701 -05 Concrete Grout Material or §721 -03 Epoxy Polysulfide Grout . Holes in unpaved area shall be filled with sand backfill.

A.Temporary Barrier Without Warning Lights. Where warning lights for temporary positive barrier are not required, the Contractor shall provide and maintain delineation on the temporary barrier in accordance with Section 619 -2.12. The delineation shall be visible and free of dirt and snow, including during shutdown periods. The maximum spacing of delineation shall be 20 feet.
B.Temporary Barrier With Warning Lights. Where warning lights are specified, Type C warning lights shall be provided on temporary barrier. The maximum spacing of warning lights shall be 40 feet in tangents and 20 feet in curves with radii less than 2,800 feet. Warning lights shall be attached to the barrier so that the lights remain securely in place and so that the attachment minimizes damage to the barrier.

619-3 12

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 All warning lights shall be kept clean, properly aligned, and in operating condition. Batteries shall be replaced as necessary. Where channelizing devices with Type A flashing warning lights are not provided immediately preceding a run of barrier to be marked with warning lights, the first warning light on that run of barrier shall be a Type A warning light.

C.Box Beam Guide Rail to Temporary Positive Barrier (Concrete) Transition. Where required, the Contractor shall install the Transition from Box Beam to Flared Temporary Concrete Barrier or the Transition from Box Beam to Unflared Temporary Concrete Barrier in accordance with the details shown on the Standard Sheets. With the appr oval of the Engineer, the Contractor may choose to switch options, at no additional cost to the State. Where the Contractor elects or is required to bolt the box beam to the face of the Temporary Concrete Barrier, the pieces of box beam thus bolted shall be removed and become the Contractor’s property when the Temporary Concrete Barrier is removed. After re moval of the Temporary Concrete Barrier, any rail and posts removed to facilitate placement of the Temporary Concrete Barrier transition shall be promptly replaced with new posts and new or acceptable reset box beam guide rail. When an unflared Box to Temporary Concrete Barrier transition is removed, the heavy posts, blockouts, rub rail, and Transition End Piece and associated hardware shall become the property of the Contractor and shall be removed from the project before its co mpletion.
D.Temporary Positive Barrier (Concrete) to Box Beam Guide Rail Transition. Where required, the Contractor shall install “Temporary Concrete Barrier Face to Box Beam Transition” or “Temporary Concrete Barrier Back to Box Beam Transition” in accordance with the details shown on the Standard Sheets. When the box beam is mounted to the traffic -side face , a tapered box beam end piece shall be used. When the box beam is behind the Temporary Concrete Barrier, the Contractor shall bolt to the Temporary Concrete Barrier or shall provide an overlap of box beam extending upstream past four segments of the downs tream end of the Temporary Concrete Barrier. When box beam is required to be bolted to the Temporary Concrete Barrier, or the Contractor elects to do so, the necessary positions for the bolts shall be located on the Temporary Concrete Barrier and drilled in the field. The pieces of box beam thus bolt ed shall be removed and become the Contractor’s property when the Temporary Concrete Barrier is removed. After removal of the Temporary Concrete Barrier, any rail and posts removed to facilitate placement of the Temporary Concrete Barrier transition shall be promptly replaced with new posts and new or acceptable reset box beam guide rail.
E.Corrugated Beam Guide Rail to Temporary Positive Barrier (Concrete) Transition. Where required, the Contractor shall install the W -Beam to Flared TCB Transition (Leading End) in accordance with the details shown on the Standard Sheets. After removal of the Temporary Concrete Barrier, any rail and posts removed to facilitate placement of the Temporary Concrete Barrier transition shall be promptly replaced with new posts, new or acceptable reset corrugated guide rail, new hardware, and new blockouts, backup plates, or other hardware required to meet current standards. Any terminal rail pieces, posts, or other guide rail components not required for the restored guide rail shall become the property of the Contractor and shall be removed f rom the project before its completion.
F.Temporary Positive Barrier (Concrete) to Corrugated Beam Guide Rail Transition. Where required, the Contractor shall install “Temporary Concrete Barrier Face to Corrugate Beam Transition” or “Temporary Concrete Barrier Back to Corrugated Beam Transition” in accordance with the details shown on the Standard Sheets. When the corrugate d beam is mounted to the traffic - side face, a W -beam end piece shall be used. When the corrugated beam is behind the Temporary Concrete Barrier, the Contractor shall bolt to the Temporary Concrete Barrier as shown on the

619-3 13

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 Standard Sheets or shall provide an overlap of corrugated beam extending upstream past four segments of the downstream end of the Temporary Concrete Barrier. When corrugated beam is required to be bolted to the Temporary Concrete Barrier, or the Contractor elects to do so, the necessary positions for the bolts shall be located on the Temporary Concrete Barrier and drilled in the field. The terminal rail piec es or W -Beam End Pieces thus bolted shall be removed and become the Contractor’s property when the Temporary Concrete Barrier is removed. After removal of the Temporary Concrete Barrier, any rail and posts removed to facilitate placement of the Temporary C oncrete Barrier transition shall be promptly replaced with new posts and new or acceptable reset corrugated beam guide rail

619-3.13 Temporary Glare Screen. Temporary glare screen shall be installed in accordance with the

manufacturer’s instructions. All components of the glare screen shall be maintained in a safe and functional condition. Damaged components shall be repaired or replaced. If blades are utilized, the blades shall be spaced and angled to provide approximately a 22E headlight cutoff angle. The screen shall not overhang the face of the barrier and shall not cover delineation or lights. The screen shall be kept plumb and properl y positioned on the barrier, with reflectorization securely affixed to the screen. Cleaning of the reflectorization shall be by a method that does not damage the paddles, reflectorization or barrier, and is not hazardous to traffic. The Contractor shall remove and dispose of the temporary glare screen upon completion of the contract or when it is no longer required. Upon removal of the temporary glare screen, there shall be no protrusions remaining on the top face of the barrier. Bolt holes or other damage to permanent barrier from glare screen installation shall be repaired by the Contractor at no additional cost to the State.

619-3.14 Temporary Impact Attenuator. The Contractor shall install temporary impact attenuators in

accordance with the contract documents, the manufacturer’s instructions, and materials details. The Contractor shall provide the Engineer a copy of the manufacturer’s materials details and instal lation instructions a minimum of 7 calendar days prior to use, to allow verification of the attenuator supplied and proper installation. The selection of the manufacturer and model of temporary impact attenuator shall be at the Contractor’s option, provided the attenuator supplied is of the type indicated, gating or redirective; shields the hazard; and fits in the location without encroachment into travel lanes or required offsets. The Contractor shall maintain temporary impact attenuators for continuous operation. If an attenuator is out of operation, the Contractor shall immediately mark the hazard with drums, vertical panels and or extra tall cones until repairs are made or a new attenuator is installed. The Contractor shall promptly begin repairs to damaged attenuators, and shall complete repairs to a damaged attenuator or mitigate the hazard within 1 work day. Attenuators damaged beyond repair shall be replaced within 3 work days . When temporary impact attenuators are removed or moved to another location, the Contractor shall restore the location to match the surrounding area.

619-3.15 Temporary Sand Barrel Arrays. The Contractor shall install sand barrel arrays in accordance

with the patterns shown on the Standard Sheet or a NCHRP 350 approved pattern and fill the barrels with sand to provide the desired module weight, plus or minus 5 percent. Units that will be in use between November 1 and March 31 shall have sodium chloride, as dry rock salt, equal to 3% - 5% by weight of the sand, thoroughly mixed into the sand to prevent fr eezing. The sand shall be placed in the modules loose, not in bags or sacks. If the contract documents indicate that the site necessitates securing of the modules, the work shall be performed as recommended by the manufacturer. The Contractor shall maintain sand barrel arrays for continuous 24 hour operation. If an array is out of operation, the Contractor shall immediately mark the hazard with drums, vertical panels and or extra tall cones until repairs are made or new module(s) are installed. The Contractor shall promptly begin

619-3 16

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 repairs to damaged arrays, and shall complete repairs to a damaged array or mitigate the hazard within one work day.

619-3.16 Vehicle Arresting Barrier (VAB). Vehicle arresting barriers (VAB) shall be installed in

accordance with the contract documents and the manufacturer's instructions and materials details. The Contractor shall provide the Engineer a copy of the manufacturer’s materials details and installation instructions a minimum of 5 work days prior to use, to allow verification of the barrier supplied and proper insta llation. The deceleration area behind the VAB shall be kept clear of workers, vehicles, or stored materials. The Contractor shall provide for periodic surveillance of each VAB by workers or by electronic device. The Contractor shall maintain vehicle arresting barrier for continuous operation. If a barrier is out of operation, the entire barrier shall be restored within 4 hours after the incident, or prior to the next shift the barrier will be used. No work may be progressed in an unprotected area, and the hazard shall be eliminated or minimized, until restorations have been completed. The VAB, except anchorages, shall be dismantled and removed prior to reopening the road to traffic. After the last day of use, if directed by the Engineer, temporary anchorages shall be removed, and disturbed areas shall be restored to match the surroundin g area.

619-3.17 Maintain or Modify Traffic Signal Equipment. Traffic signals shall be maintained in proper

operation, including the maintenance of all features of the traffic signal operation in effect and operating at the time any work begins on the contract. Traffic -actuated phases shall remain actuated, and signa ls operating within signal systems shall remain coordinated with the remainder of the system unless otherwise approved by the Engineer. Except for emergencies, no changes in the signal operation or timi ng shall be made without prior approval by the Engineer. If emergency conditions dictate a change in the operation, the Engineer shall be notified by the start of the next work day. Unless otherwise approved by the Engineer, an altered signal operation mus t be returned to the original signal operation within 24 hours. The Contractor shall maintain in operation all equipment including signal heads, supports, cable, wiring, span -wire-mounted signing, controllers, master controllers, detector systems, conflict and current monitors, relays, switch packs, and all other acces sory and necessary equipment. Maintenance shall also include the repair and replacement of existing detector loops, paid for separately. The Contractor shall have capable traffic signal repair personnel on call 24 hours a day, seven days a week, and shall provide to the Engineer a single telephone number for contacting them. If for any reason a signal is not functioning properly, the Contra ctor shall commence work on the signal within 2 hours of notification. If directed by the Engineer, the Contractor shall notify the appropriate police agency for traffic control operations. If the police agency cannot or will not provide traffic control, t he Contractor shall provide flaggers at locations specified by the Engineer within the 2 -hour time period. The Contractor shall continue the flagger services until the signal is in proper operation. A flagger warning (W20 -7 or W20 -7a) sign shall be used on all approaches to an intersection controlled by flaggers. If the malfunction is in the equipment supplied by the State, due to an area wide power outage, or due to a localized power outage beyond the Contractor’s control, the Contractor shall notify the Engineer and, if directed by the Engineer, provide flaggers until the malfunction is corrected or State personnel take over. Such flagging operations in excess of 4 hours for the first call and for any subsequent call will be considered extra work. The Contractor shall provide the Engineer, on a monthly basis, with a record of all maintenance calls received and responded to, as well as a record of all corrective action taken by the Contractor.

A.Requirement A. The Contractor shall maintain in proper operation the indicated existing, relocated, modified, and newly installed signals in accordance with the contract documents. If such signals are to be removed, the Contractor shall be responsible for operation and m aintenance until the signals are removed. The Contractor shall be responsible for their continuous operation except for reasonable shutdown periods authorized by the Engineer during relocation and transfer operations.

619-3 18

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3

B.Requirement B. The State shall assume operation and maintenance responsibility for the signal from the Contractor following successful completion by the Contractor of the installation /modification testing as required by Section 680 Traffic Signals. The six month warranty/guarantee period shall be measured from the day the State assumes maintenance responsibility.
C.Requirement C. At relocated, modified, or newly installed signals, the Department will assume responsibility for the following items after successful testing as required by Section 680 Traffic Signals has been completed. Assumption of the below listed responsibilities by the State will not relieve the Contractor of the responsibility for operation and maintenance of the signal. At existing microcomputer controlled traffic signals, the Department will be responsible for the following items:
1.Supply and maintenance of the microcomputer assembly and software.
2.Programming of the microcomputer furnished by the State.
3.Operation or timing changes directed by the Engineer.
4.Normal (no abuse or vandalism) equipment failures of existing, relocated, modified or new traffic signal equipment furnished by the State.
D.Modify Traffic Signal Equipment. Where the Contractor is required to temporarily modify or relocate existing traffic signals because of construction operations, all existing equipment, fittings, wire, cable, conduit, and related materials shall be reinstalled and extended where necessary. Temporary timber poles, guys, and related material shall be furnished and installed where necessary.

619-3.18 Temporary Traffic Signals. The Contractor shall install temporary traffic signals in

accordance with the contract documents and the MUTCD. The Contractor shall maintain traffic signal systems, including traffic detectors, in proper operation until approved removal, and be responsibl e for its continuous 24 -hour operation except for reasonable shutdown during relocation and transfer operations. Substitution of temporary traffic signals for flaggers shall be at no additional cost to the State. If for any reason a signal does not function as required, the Contractor shall commence repair work on this signal within 2 hours after notification of a malfunction. In the event flashing operation occurs, all signal faces shall show flashing red indicati ons. Flashing operation of a signal is considered a malfunction. The Contractor shall provide an adequate number of flaggers to control traffic at each malfunctioning traffic signal, in accordance with '619 -3.02L. Flagging and Traffic Control until the sig nal is restored to proper operation. If the malfunction is due to an area wide power outage or due to a localized power outage beyond the Contractor’s control, the Contractor shall notify the Engineer and, if directed by the Engineer, provide flaggers until the malfunction is corrected or Sta te personnel take over. Flagging operations in excess of 4 hours for the first maintenance call shall be paid for as extra work.

619-3.19 Nighttime Operations . Work occurring after sunset and before sunrise will be considered

nighttime operations. A nighttime operations meeting shall be held prior to the start of any nighttime operations. For static and moving operations, the Contractor shall implement a lighting plan and provide illumination throughout the work areas. For moving operations, the Contractor shall mount lighting to construction equipment that consists of balloon lights, or equivalent lighting that illuminates the work area with low glare for oncoming traffic and enhances visibility of the equipment from al l directions. The Contractor should maintain traffic in a single lane during nighttime moving operations on freeways.

619-3 19

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 All workers involved in nighttime operations shall wear protective helmets and nighttime apparel in accordance with §107 -05A. High Visibility Apparel at all times. All signs, Stop/Slow paddles, and red flags used to warn/alert/control traffic shall be retr oreflective. Flaggers shall use a flashlight with red glow cone/ red LED baton for flagging in non -illuminated flagger stations during nighttime operations. Where the Contractor implements a mobile lighting plan, PPE shall meet ANSI Class 3. The Contractor shall equip workers on foot with a personal active safety system which enhances the visibility of the worker from all directions, such as a powered hardhat light ring or an illuminated safety vest. ANSI Class E gaiters or pants are required to meet ANSI Class 3 if ANSI Class 2 vests are used. The Contractor shall provide the Department with the same personal active safety systems and ANSI Class 3 garments for Department inspectors and pertinent field office staff. When workers on foot are passing between illuminated work areas, the Contractor shall provide personal headlamps or flashlights producing a minimum of 5 foot -candles at the ground to navigate their p ath if hardhat light rings do not provide this function and illumination. Vehicles operating on the pavement of a closed roadway or travel lane shall display rotating amber beacons or flashing LED beacons at all times. Vehicles using headlights, except for rollers and vehicles retrieving channelizing devices, shall travel facing in the same direction as adjacent traffic in order to avoid glare and confusion to drivers. The Contractor shall meet the following additional requirements for work zone traffic control during nighttime operations.

A.Nighttime Operations and Lighting Plan. Thirty days prior to the start of nighttime operations, the Contractor shall submit a written Nighttime Operations and Lighting Plan to the DOT Engineer for approval. The plan shall detail all aspects of the traffic control setup, the functions, responsibi lities and identities of the nighttime traffic control competent person and other details as necessary. It shall include a contingency plan identifying foreseeable problems and emergencies that may arise, and the approach that will be used to address them. This plan shall be revised and updated by the Contractor as necessary during the progress of the work to accommodate conditions on the contract. The Contractor shall submit a Nighttime Operations and Lighting Plan to the Engineer, at a scale and printed size similar to the contract plans and appropriate to adequately describe the work, including the following applicable items:
1.Layout showing location of light towers, including typical spacing, lateral placement and mounting height, and clearly show the location of all lights necessary for all work to be done at night.
2.The general layout of equipment involved in the moving operation, including typical or variable spacing.
3.Schematic of the equipment -mounted balloon lights and supplemental lights.
4.Listing of the anticipated workforce to be located within the work zone.
5.Internal traffic control plan to coordinate the flow of deliveries, moving equipment, workers, and vehicles at the worksite to minimize or eliminate vehicles and employees from crossing paths, and how this plan will be communicated to all individuals invol ved.
6.Specific illuminated areas for cleanout, specific areas for trucks entering and exiting the work area, and how this plan will be communicated to the workers and truck drivers prior to arrival on site.
7.Means to illuminate areas to perform tasks not in the immediate vicinity of the major work.

619-3 19

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 8. Means to ensure visibility of personnel and equipment involved with the set -up and removal of work zone traffic control devices.

9.Description of light towers to be used and electrical power source.
10.Specific technical details on all lighting equipment, including brand names, model numbers, power rating and photometric data.
11.Details of any hoods, louvers, shields or other means to be used to control glare.
12.Attachment and mounting details for lights to be attached to equipment.
13.Lighting calculations confirming that the illumination requirements will be met by the layout. The Contractor shall maintain a supply of emergency flares for use in the event of unanticipated situations such as traffic accidents, equipment breakdowns, failure of lighting equipment, etc.
B.Lighting for Nighttime Operations. Prior to the first night of nighttime operations, the Contractor shall set up and operate the lighting equipment at night as a trial run to demonstrate its ability to establish a safe, properly illuminated, nighttime operation. The Contractor shall furnis h the Engineer with a photometer, capable of measuring the level of illumination, for use as necessary to check the adequacy of illumination throughout nighttime operations. The Contractor shall have backup lighting equipment available onsite. In the event that any required lighting equipment is no longer operational or available to perform the work, the Contractor shall remove the work zone associated with the operation until the lighting equipment is restored.
1.Equipment. The Contractor shall supply all lighting equipment required to provide a work zone safe for the workers and traffic. Material and/or equipment shall be in good operating condition and in compliance with applicable safety and design codes.
a.Light Towers. Light towers shall be provided as a primary means of illumination for stationary operations and shall provide Level I illumination throughout the workspace. They may be supplemented to the extent necessary by lighting fixtures mounted on construction equipment to provide Level II or Level III illumination where required for paving, milling and similar moving operations. Light towers shall be sturdy and free -standing, without the aid of guy wires or bracing, and shall be capable of being moved as necessary to keep pace with construction operations. Light towers shall be positioned to minimize the risk of being impacted by traffic on the roadway or b y construction traffic or equipment.
b.Balloon Lighting and Additional Lighting on Paving, Milling, and Finishing Machines. If needed to supplement portable and/or trailer -mounted light towers, lighting shall be affixed to paving, milling, and finishing machines to provide the required level of illumination for the specified distance in front of and behind the machine. Primary lighting for nighttime moving operations should consist of balloon lighting, or equivalent low glare lighting visible from all directions. Additional lighting of an appropriate type shall be required, where obstructions exist, to perform the work safely and adequately. Luminaires shall be aimed and adjusted to provide uniform illumination with a maximum uniformity ratio of 5:1. The hopper, auger, and screed areas of pavers and the operator’s controls on all machines shall be uniformly illuminated. The Contractor shall equip the following equipment in conjunction with nighttime moving operations with balloon lights, or equivalent low glare lighting visible from all

619-3 19

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 directions, to sufficiently illuminate the work area, enhance visibility of the equipment from all directions, and to carry out the work safely and accurately: all rollers, pavers, milling machines, material transfer vehicles, crack and seat equipment, and other miscellaneous equipment utilized for the moving operation that could be a hazard if not illuminated. There shall be a minimum of one balloon light mounted to each piece of equipment. Pavers and large milling machines should be equipped with a minimu m of two balloon lights. Mechanical sweepers shall have forward -facing lights and tack trucks shall have rearward - facing lights, consisting of balloon lights, or equivalent low glare lighting visible from all directions, supplemented with flood lights as r equired. Balloon lighting, or equivalent, equipment shall be sufficiently ballasted and durable to withstand the anticipated weather conditions and vibrations from the host equipment.

c.Construction Equipment Lights. All construction equipment, including rollers, backhoes, loaders, and other equipment operating in areas not illuminated to a minimum of Level I Illumination, shall be equipped with a minimum of two suitable lights facing in each direction, to provide a mi nimum of 1 foot -candle of horizontal illumination measured 60 feet in front of and behind the equipment. In areas illuminated to a minimum of Level I, construction equipment may move unescorted. In non -illuminated areas, c onstruction equipment shall be equipped with conventional vehicle headlights, shall be illuminated with flood lights on the vehicle, or shall be escorted to permit safe movement. Headlights shall not be permitted as the sole means of illumination while wor king.
d.Equipment Mounting. The Contractor shall provide suitable brackets and hardware to mount lighting fixtures and generators on machines and equipment. Mountings shall be designed so that light fixtures can be aimed and positioned as necessary to reduce glare and to provide the required illumination. Mounting brackets and fixtures shall not interfere with the equipment operator or any overhead structures, or utilities, and shall provide for secure connection of the fixtures with minimum vibration.
e.Portable Generators. The Contractor shall provide portable generators to furnish adequate power to operate all required lighting equipment. Fuel tank capacity and availability of fuel on site shall be sufficient to permit uninterrupted operation throughout the planned shift. Adequate switches shall be provided to control the various lights. All wiring shall be weatherproof and installed in accordance with 29 CFR 1926 Subpart K. All power sources shall be equipped with a Ground -Fault Circuit Interrupter.
2.Illumination Requirements. Balloon lights or equivalent lighting, and tower -mounted luminaires, whether fixed, portable, trailer -mounted, or equipment -mounted, shall be of sufficient wattage and/or quantity to provide the required level of illumination and uniformity over the area of operation while minimizing glare. The uniformity of illumination, defined as the ratio of the average illumination to the minimum illumination over an area requiring an indicated illumination level, shall not exceed 5:1. Illumination levels on approach roadways should be increased sequenti ally to prevent motorists from becoming disoriented by rapid changes from full dark to very bright conditions. Existing street and highway lighting shall not eliminate the need for the Contractor to provide lighting. Consideration will be given to the amount of illumination provided by existing lights in determining the wattage and/or quantity of lights to be prov ided. Such consideration shall be presented in the Contractor’s lighting plan. In the event of any failure of the lighting system, nighttime operation(s) shall be discontinued until the required level of illumination is restored.

619-3 19

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 a. Illumination for moving operations . Equipment -mounted balloon lights, or equivalent low glare lighting visible from all directions, shall provide illumination to a minimum of 5 foot - candles measured at the work surface for 20 feet from the equipment on sides where workers generally work. Bal loon lights or equivalent lighting shall be located to optimally illuminate the work area and enhance equipment visibility, mounted at a minimum height of 10 feet above the ground, and temporarily relocated as necessa ry to not interfere with overhead obstructions. Other types of equipment -mounted light sources shall be used as supplemental illumination around the equipment, where necessary, to carry out the work safely and adequately. The hopper, auger, and screed area s of pavers shall be uniformly illuminated. The operator’s controls on all machines shall be illuminated. Tack shall be illuminated as it is applied. In areas throughout the entire zone of mobile operations without existing roadway lighting, light towers shall be located at maximum intervals of 500 feet. The Contractor shall provide illumination to a minimum of 5 foot-candles at locations where miscellaneous or incidental tasks, such as saw cutting, are performed. The illumination shall be accomplished via floodlights or balloon lights (or equivalent) mounted to a truck, cart, or terrain vehicle, tow behind trailer lights, lights on light stands, or other suitable means. No tasks shall be performed without adequate illumination. The Contractor shall furnish adequate illumination for Department construction inspection and quality assurance. The illumination shall be accomplished via floodlights or balloon lights (or equivalent) mounted to a truck, cart, or terrain vehicle, tow behi nd trailer lights, lights on light stands, or other suitable means. The Contractor shall furnish and maintain illumination equipment. The Contractor shall provide a minimum of 10 foot -candles in locations where the Department’s representatives will perform tasks such as core drilling, density testing, and concrete testing.

b.Level I (5 foot -candles) for static operations. Level I illumination shall be provided for all areas of general construction operations to include all work operations by Contractor’s personnel, including work zone traffic control set -up and operations, staging, excavation, cleaning and sweeping, pavemen t marking, spoil disposal, landscaping, planting, and seeding, layout and measurements ahead of the actual work, borrow areas, spoil areas, and truck cleanout areas. Level I illumination shall be provide d near the beginning of lane closure tapers and at road closures for nighttime work zones, including the setup and removal of the closure tapers. Level I illumination shall be provided a minimum of 400 feet ahead and 800 feet behind a paving or milling ma chine, or for the entire area of pavement work if less than this distance. This area shall be extended as necessary to incorporate all vehicle and equipment operations associated with the paving operation. The only exception to the requirement for Level I illumination throughout the area of construction operations is that finish rollers can work beyond the area of Level I illumination using sufficient lights mounted on the roller.
c.Level II (10 foot -candles) for static operations. Level II illumination shall be provided for flagging stations, asphalt paving, milling, and concrete placement and/or removal operations, including bridge decks, 50 feet ahead of and 100 feet behind a paving or milling machine. Illumination shall be set -up to avoid adverse backlighting, a condition which presents the object intended to be illuminated as a shadow due to a bright light from behind.
d.Level III (20 foot -candles) for static operations. Level III illumination shall be provided for pavement or structural crack filling, joint repair, pavement patching and repairs, installation of signal equipment or other electrical/mechanical equipment, and other tasks involving fine details or intricate p arts and equipment.

619-3 20

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3

3.Glare Control. All lighting shall be designed, installed, and operated to avoid glare that affects traffic on the roadway or that causes annoyance or discomfort for residences adjoining the roadway. The Contractor shall locate and aim lighting fixtures to provide the re quired level of illumination and uniformity in the work zone without the creation of objectionable glare. The Engineer will determine when glare exceeds acceptable levels, either for traffic or for adjoining residences. The Contractor shall provide shields, visors, or louvers on luminaires as necessary to reduce objectionable levels of glare. As a minimum, the following requirements shall be met to avoid objectionable glare on roadways open to traffic in either direction:
a.Tower -mounted luminaires shall be aimed either generally parallel or perpendicular to the roadway.
b.Luminaires shall be aimed such that the angle between the center of the beam axis and the vertical mounting pole is no greater than 45o.
c.No luminaires shall be permitted that provide a luminous intensity greater than 20,000 candelas at an angle of 72o above the vertical.
d.Except where prevented by overhead utilities or structures, towers shall be extended to their full working height when in use to reduce glare and provide uniform illumination .

619-3.20 Traffic Control Supervisor. When indicated in the contract documents, the Contractor shall

provide a dedicated traffic control supervisor having adequate training, experience, and authority to implement and maintain all traffic control operations. The traffic control supervisor shall not be assigned other duties that interfere with performance as a traffic control supervisor. The traffic control supervisor shall be adequately trained in traffic control operations by recognized training programs, including the American Traffic Safety Services Association “Traffic Control Supervisor”, the National Safety Council, unions, or const ruction industry associations, or by an individual instructor from such a program. Traffic control supervisors not competent to the satisfaction of the Engineer shall be replaced immediately. During setup and removal of lane closures and other traffic control setups, the traffic control supervisor shall be assisted by additional workers as necessary. The traffic control supervisor shall patrol the contract area to ensure that conditions on the site are adequate for public safety and convenience at all times, to monitor worker safety from intrusions into the work area, and to ensure that the work adheres to the provisions for work zone traffic control. The traffic control supervisor shall ensure signs, channelizing devices, barricades, barrier, impact attenuators and other traffic control devices are adjusted and maintained as necessary. The Contractor shall provide workers to install, maintain, adjust, and remove traffic control devices as requir ed by the work operations. When the work does not require closure of an active lane, roadway, or ramp; when no construction operations occur within 30 feet of active traffic lanes; and when there is no delivery of materials or equipment; the Engineer may waive the requirements for a traffic control supervisor.

619-3.21 Temporary Structures and Approaches. The Contractor shall design, construct, maintain,

relocate, and remove temporary structures and their approaches at the location(s) shown in and in accordance with the contract documents. The Contractor shall install temporary structures and their approach es, including any required earth support structures and any necessary appurtenances, in a manner and sequence that interference with and inconvenience to the traveling public and abutting properties is kept to a minimum. The Contractor shall be responsible for the workmanship, upkeep, and safety of all temporary structures and approaches.

619-3 21

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 When specific details are not included in the contract documents, or when the Contractor receives approval to deviate from the contract documents, the Contractor shall design all elements of the temporary structure and approaches including the railing syst em, on the structure and its approaches. The design of temporary structures and their approaches shall be in conformance with the NYSDOT Load and Resistance Factor Design (LRFD) Bridge Design Specifications, the only design live load shall be HL -93, in addition to any anticipated construction or pedestrian loading. Alternatively, the design shall be in conformance with the NYSDOT Standard Specifications for Highway Bridges, the minimum design live load shall be AASHTO HS 20. Exception, any structure, and approaches that are expected to be in servi ce for more than 5 years, shall be designed as a permanent structure in accordance with the NYSDOT Load and Resistance Factor Design (LRFD) Bridge Design Specifications. The bridge rail shall be designed for loads commensurate with those specified for TL -2 unless a higher level is shown in the project plans. The Contractor shall also be responsible for designing, furnishing, and installing the transition from bridge rail t o highway rail for the temporary structure. All design computations and associated working drawings shall bear the stamp and signature of a Professional Engineer and shall be submitted to the DCES for review. Design for non -highway temporary bridges shall be in accordance with AASHTO specifications for the design codes, loading, railing/barrier, ADA requirements and vertical clearance it is intended to serve or as specified in the project plans. All fabrication and construction of a temporary structure shall conform to the AASHTO Standard Specifications for Highway Bridges, Division II or the AASHTO LRFD Bridge Construction Specifications, except as modified herein. Fabrication shall be performed by a fabricator that is certified by AISC for the type of work being performed. For fracture -critical member (FCM) work, the fabricator shall also have an FCM endorsement through AISC. The Contractor shall notify the DCES of the fabrication schedule at lea st 21 calendar days prior to commencement of any non -pre-engineered proprietary shop fabrication. All welding required for the fabrication of temporary steel structures shall be performed in accordance with the provisions of the NYS Steel Construction Manual. The Contractor is responsible for furnishing and installing any stone fill slope protection in accordance with Section 620 used to guard against erosion and/or scour of the end slopes and all temporary substructures. The type of the fill slope protection shall be as shown in the contract plans and paid under Item 619.05nn. If the bridge connects sidewalk at each end of the bridge, payment for all approach sidewalk and earthwork necessary to connect the temporary structure with the existing sidewalk system shall be as shown in the contract plans and paid under Item 619.05nn. Load rating calculations for the temporary structure shall bear the stamp and signature of a professional Engineer and shall be submitted to the DCES for review. Load ratings shall be computed using the Load Factor Design (LFD) or Allowable Stress Design (ASD) methodology. The Inventory and Operation load ratings shall be based on an AASHTO HS -20 live loading. Additionally, if the structure was designed using the NYSDOT LRFD Bridge Design Specifications, the load ratings shall also be computed by the Load a nd Resistance Factor Rating (LRFR) method. LRFR ratings shall be provided at the Inventory and Operating levels as rating factors of the AASHTO HL -93 live load. All Load Ratings shall be calculated in accordance with AASHTO’s The Manual for Bridge Evaluation . Prior to beginning construction of any temporary structure designed by the Contractor, the Contractor shall submit detailed plans and calculations to the DCES for review and approval in accordance with §585 -3.03 Working Drawings . The review by the DCES, does not and shall not relieve the Contractor of the responsibility for the adequacy and design of the temporary structures and approaches. Prior to opening a temporary structure to traffic, the structure shall be inspected by a Professional Engineer who shall certify in writing to the Engineer that the structure was constructed in accordance with the design. The Contractor shall have the temporary structure inspected, under the direction of a Professional Engineer, by a person familiar with bridge construction at least once a month. On or before each anniversary of the opening of a temporary structure that has been open to traffic for

619-3 22

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 one year or more, the structure shall be inspected by a Professional Engineer, who shall certify in writing that:

A.The plans of the structure, including its foundations, have been reviewed.
B.A hands -on inspection of the structure has been performed in accordance with the latest edition of the NYSDOT Bridge Inspection Manual by an inspection team whose leader is a Professional Engineer that meets qualifications of a Team Leader as described in the NYSDOT Bridge Inspection Manual.
C.A detailed inspection of those areas of the structure critical to its integrity has been performed.
D.The structure is currently adequate for its design loads. A signed and stamped copy of the inspection results shall be provided to the Engineer within one week of the inspection.

619-3.22 Pavement Patching. The Contractor shall place paving materials suitable to provide temporary

pavement patches on paved surfaces where vehicular, bicycle or pedestrian traffic is to be maintained, including the traveled way, shoulders, sidewalks, and other paved surfaces damaged by traffic or environmental factors and not by Contractor operations. During periods of active work on the contract, the C ontractor shall complete needed patches on a daily basis. During periods of winter shutdown, the Engineer will inspect the pavement on frequent and regular intervals and will notify the Contractor of areas to be patched. The Contractor shall install paveme nt patching, at locations identified by the Engineer, within 24 hours of notification. The Contractor shall place pavement patches to provide a relatively smooth, uniform driving surface suitable for safe travel at the posted speed limit. Pavement patches shall be placed to repair surface irregularities including, but not limited to, holes, depressions, cracks, and uneven joints. Areas to be patched shall be adequately cleaned and tack -coated if necessary, and patching material shall be thoroughly compacted by hand or by roller.

619-3.23 Mailboxes. In the event the original mounting post has been lost, damaged, is unusable, or is

not consistent with U.S. Postal Service requirements, the Contractor shall furnish and install a new mounting post and/or mailbox with mounting post at the designated locati on and at the proper height in accordance with the requirements of the U.S. Postal Service. The replacement mailbox shall be of a similar or larger size than the original. Where the mailbox will be placed over a guide rail and/or ot her location where the postal patron will have easiest access to the rear of the mailbox, the replacement mailbox shall be one having a door on each end.

619-4 Method of Measurement

619-4.01 General . (None Specified.)

619-4.02 Basic Work Zone Traffic Control . The work under basic work zone traffic control will be

measured for payment on a lump sum basis.

619-4.03 Basic Work Zone Traffic Control (Daily Operations). The work under basic work zone traffic

control (daily operations) will be measured for payment on a lump sum basis.

619-4.04 Temporary Business Signs. The quantity to be measured for payment will be in square feet to

the nearest 0.1 square feet of business signs installed.

619-4 05

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3

619-4.05 Covering or Removal of Pavement Markings . The quantity to be measured for payment will

be in feet to the nearest whole foot along the centerline of the pavement stripes covered or removed. No measurement will be made for the gaps between broken and dotted line segments. If preformed tape is used to cover an existing line, payment will be based on the width of the line covered. Measurement for covering or removal of striping with a width greater than 4 inches will be made by the following method: Width of Striping (in) x Number of Feet 4 (in) Letters and symbols will be measured by each unit covered or removed. A unit will consist of one letter or one symbol except that a double -headed arrow will be measured as two units and triple headed arrow will be measured as three units. Example: "SCHOOL" would be measured as six units. Each R in a railroad crossing marking will be measured as a single unit, but the "X" will be measured by the number of feet of 4 inch stripe.

619-4.06 Temporary Pavement Markings . The quantity to be measured for payment will be in feet to the

nearest whole foot along the centerline of the pavement stripes installed, and will be based on a 4 inch wide stripe. No measurement will be made for the length of skips in the dashed line. M easurement for installation of striping with a width greater than 4 inches will be made by the following method: Width of Striping (in) x Number of Feet 4 (in)

619-4.07 Interim Pavement Markings . The quantity to be measured for payment will be in feet to the

nearest whole foot along the centerline of the pavement stripes installed, and will be based on a 4 inch wide stripe. No measurement will be made for the length of skips in the dashed line. Measurement for installation of striping with a width greater than 4 inches will be made by the following method: Width of Striping (in) x Number of Feet 4 (in) Letters and symbols will be measured by each unit installed. A unit will consist of one letter or one symbol except that a double -headed arrow will be measured as two units and triple headed arrow will be measured as three units. Example: “SCHOOL” would be measured as six units. Each R in a railroad crossing marking will be measured as a single unit, but the “X” will be measured by the number of feet of 4 inch stripe.

619-4.08 Temporary Rumble Strips . The quantity to be measured for payment will be in feet to the nearest

whole foot of individual temporary rumble strip installed, measured transverse to the direction of traffic flow.

619-4.09 Interim Tubular Markers . The quantity to be measured for payment will be the number of

interim tubular markers installed.

619-4.10 Portable Variable -Message Signs (PVMS) and Truck Mounted Variable Message Signs

(TMVMS). The quantity of PVMS or TMVMS with a pay unit of each to be measured for payment will be the number of signs provided. The quantity of PVMS or TMVMS with a pay unit of weeks to be measured for payment will be in weeks to the nearest whole week.

619-4.11 Type III Construction Barricades . The quantity to be measured for payment will be the number

of barricade units installed.

619-4 12

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 619-4.12 Temporary Positive Barrier . . The quantity to be measured for payment of temporary positive barrier will be in feet to the nearest foot along the centerline of temporary positive barrier installed. The quantity to be measured for payment of Box Beam to Flared Temporary Concrete Barrier Transition will be the number of such transitions installed. The quantity to be measured for payment of Box Beam to Unflared Temporary Concrete Barrier Transition will be the number of such transitions installed. The quantity to be measured for payment of Temporary Concrete Barrier Face to Box Beam Transition will be the number of such transitions installed. The quantity to be measured for payment of Temporary Concrete Barrier Back to Box Beam Transition will be the number of such transitions installed. The quantity to be measured for payment of Corrugated Beam to Flared Temporary Concrete Barrier Transition will be the number of such transitions installed. The quantity to be measured for payment of Temporary Concrete Barrier Face to Corrugated Beam Transition will be the number of such transitions installed. The quantity to be measured for payment of Temporary Concrete Barrier Back to Corrugated Beam Transition will be the number of such transitions installed. The quantity to be measured for payment of temporary positive barrier will be in feet to the nearest foot along the centerline of temporary positive barrier installed .

619-4.13 Temporary Glare Screen . The quantity to be measured for payment will be in feet to the nearest

whole foot along the length of the temporary glare screen installed.

619-4.14 Temporary Impact Attenuator . The quantity to be measured for payment will be the number of

temporary impact attenuators installed.

619-4.15 Temporary Sand Barrel Arrays . The quantity to be measured for payment will be the number

of individual sand barrel modules installed.

619-4.16 Vehicle Arresting Barrier . The quantity to be measured for payment will be the number of

barriers installed.

619-4.17 Maintain or Modify Traffic Signal Equipment . The quantity of signalized intersections

maintained to be measured for payment will be in months to the nearest 1/4 month. The quantity of traffic signal equipment modified to be measured for payment will be on an each location basis.

619-4.18 Temporary Traffic Signals . The work under temporary traffic signals will be measured for

payment on an each location basis.

619-4.19 Nighttime Operations . The work under nighttime operations will be measured for payment on a

lump sum basis.

619-4.20 Traffic Control Supervisor . The work under traffic control supervisor will be measured for

payment on a monthly basis to the nearest 1/4 month.

619-4.21 Temporary Structures and Approaches . The work performed under temporary structures and

approaches will be measured for payment on a lump sum basis.

619-4.22 Pavement Patching . The work under Pavement Patching, Winter will be measured for payment

on a Dollars -Cents basis.

619-4 23

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 619-4.23 Mailboxes. The quantity to be measured for payment will be the number of mailboxes installed in accordance with the contract documents or as directed by the Engineer. Mailboxes installed for the Contractor’s convenience or due to damage during the contract period wi ll not be compensated for.

619-4.24 Portable Temporary Rumble Strips (PTRS). PTRS arrays will be measured by Device -Day.

When measured by Device -Day the quantity will be the number of devices (PTRS arrays) used each calendar day which are satisfactorily furnished, installed, maintained, and operated at each work zone location. If P TRS arrays are utilized at more than one work zone location on the same day, the total number of PTRS array -days measured for payment will be the total number of PTRS arrays setup on that day. For the purpose of this specification, one Device -Day is defined as one PTRS array, set up and in use in a calendar day exceeding one hour. Two Device -Days is one PTRS array over two days or two PTRS arrays used on one day. A PTRS array relocated within th e same work zone on the same day or same shift will count as one PTRS array.

619-4.25 Automated Flagger Assistance Devices (AFAD). The quantity measured for payment will be

the number of AFAD’s used each day which are satisfactorily furnished, installed, maintained, and operated at each work zone location. If AFAD’s are operated at more than one work zone location on the same day, the total number of AFAD -days measured for payment will be the total number of AFAD setup on that day, however no additional payment will be made for AFAD’s relocated within the same work zone on the same day. Work shifts spanning over two consecutive calendar days will be considered to occur on the “same day”. For the purpose of this specification, one AFAD -Day is defined as two AFAD’s, set up and in use for a portion of a day exceeding one hour.

619-5 Basis of Payment

619-5.01 General. The price bid shall include all labor, materials, and equipment necessary to complete

the work. No payment will be made for damage caused by vehicle accidents, vandalism, or any other similar causes.

A.Non-Payment . For each calendar day during which there are substantial deficiencies in compliance with the requirements of this section, no payment will be made under basic work zone traffic control. The amount of such calendar day nonpayment will be deducted from monie s due the Contractor in accordance with Table 619 -6 Basic Work Zone Traffic Control Nonpayment . TABLE 619 -6 BASIC WORK ZONE TRAFFIC CONTROL NON -PAYMENT Original Contract Amount Nonpayment Amount From More Than To and Including $ 0 $ 500,000 $ 200 $ 500,000 $ 2,000,000 $ 400 $ 2,000,000 $ 5,000,000 $ 500 $ 5,000,000 $ 10,000,000 $ 750 $ 10,000,000 $ 20,000,000 $ 1,000 $ 20,000,000 ----- $ 3,000
B.Liquidated Damages. If the Contractor fails to adequately correct substantial cited deficiencies within 24 hours of notification by the Engineer for any item under this section, or those deficiencies reoccur on a subsequent, but not necessarily concurrent calendar day, liquidated damages will be assessed for each calendar day or part thereof in addition to non -payment for deficiencies.

619-5 02

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 C. Major Non -Conformance. Where major non -conformance with the requirements of this specification is noted by the Engineer, and prompt Contractor compliance is deemed not to be obtainable, the Engineer may stop contract work. Where major non -conformance with the requirements of this specification is noted by the Engineer, and the Contractor fails to correct deficiencies for a period of 24 hours, the Department may correct the adverse conditions by any means deemed appropriate a nd will deduct the cost of the corrective work from any monies due the Contractor. The cost of this corrective work will be in addition to the non - payment for basic work zone traffic control, non -payment of any other items of work under this section and li quidated damages assessed.

619-5.02 Basic Work Zone Traffic Control . The lump sum price bid for basic work zone traffic control

shall include all labor, materials, and equipment necessary to complete the work. Construction signs; arrow panels; warning lights on signs, barricades, and channelizing devices; the cost of temp orarily terminating guide rail, median barrier, or bridge rail during non -work hours; work required to maintain drainage facilities during construction operations; and dust control shall be included in the lump sum p rice bid for basic work zone traffic control. Removal of debris from drainage features that was present at the time of contract award shall be paid for separately. Progress payments will be made at 10 percent of the lump sum price when the initial construction sign installation is complete, as determined by the Engineer, and an additional 10 percent of the lump sum price bid when 10 percent of the contract work, excl uding basic work zone traffic control, contingency items, and mobilization, has been completed. The remaining 80 percent will be paid in subsequent contract payments, in proportion to the amount of other contract work completed, less any non -payment for de ficient work zone traffic control. If the contract completion date is extended, no additional payment will be made for basic work zone traffic control.

619-5.03 Basic Work Zone Traffic Control (Daily Operations). The lump sum price bid for basic work

zone traffic control (daily operations) shall include all labor, materials, and equipment necessary to complete the work. Construction signs; arrow panels; warning lights on signs, barricades, and channelizing devices ; and the cost of temporarily terminating guide rail, median barrier, or bridge rail during non -work hours; shall be included in the lump sum price bid for basic work zone traffic control (daily o perations). Progress payments will be made at 10 percent of the lump sum price when the initial construction sign installation is complete, as determined by the Engineer, and an additional 10 percent of the lump sum price bid when 10 percent of the contract work, excl uding basic work zone traffic control, contingency items, and mobilization, has been completed. The remaining 80 percent will be paid in subsequent contract payments, in proportion to the amount of other contract work completed, less any non -payment for de ficient work zone traffic control. If the contract completion date is extended, no additional payment will be made for basic work zone traffic control.

619-5.04 Business Signs. The unit price bid for temporary business signs shall include the cost of labor,

materials, and equipment necessary to complete the work, including sign supports.

619-5.05 Covering or Removal of Pavement Markings. The unit price bid for the covering or removal

of pavement markings shall include the cost of all labor, materials, and equipment necessary to complete the work, including the costs of any repairs or replacement of damaged pavement or existing pavement markings resulting from pavement marking removal operations.

619-5.06 Temporary Pavement Markings. The unit price bid for temporary pavement markings shall

include the cost of furnishing all labor, materials, and equipment necessary to complete the work. Payment shall be provided each time temporary pavement markings are first applied on a pavement course in accordance with the contract requirements.

619-5 07

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 No additional payment shall be provided for the installation of construction signs, temporary delineators, and channelizing devices necessitated by the Contractor’s failure to place temporary pavement markings before the pavement is opened to traffic, or f or temporary roadside pavement channelization, until edge lines are placed. No additional payment shall be provided for markings required because the Contractor failed to place the next pavement course or the final pavement markings within 14 calendar days.

619-5.07 Interim Pavement Markings . The unit price bid for interim pavement markings shall include

the cost of furnishing all labor, materials, and equipment necessary to complete the work. The work to remove traffic paint or epoxy paint will be paid for separately.

619-5.08 Temporary Rumble Strips . The unit price bid for temporary rumble strips shall include the cost

of all labor, materials, and equipment necessary to complete the work. Payment will include the cost of pavement cleaning, asphalt concrete, and other materials used to form or fill in the rumble strips and tack coat. On multiyear contracts where it is desired to have rumble strips in place for more than one construction season, the rumble strips will be paid for separately each year they are installed.

619-5.09 Interim Tubular Markers. The unit price bid for interim tubular markers shall include the cost

of furnishing all labor, materials, and equipment necessary to complete the work, including removal and the cost of replacing damaged markers. Interim tubular markers that are in satisf actory condition may be relocated. When interim tubular markers are relocated, payment will be made for another interim tubular marker.

619-5.10 Portable Variable -Message Signs (PVMS) and Truck Mounted Variable Message Signs

(TMVMS). The unit price bid for PVMS or TMVMS shall include the cost of all labor, materials, testing and equipment necessary to complete the work, including cellular telephone service initial start -up and monthly charges for the cellular communications option. Th e TMVMS does not require cellular communications service. Progress payments for PVMS or TMVMS with a pay unit of each will be made for 90 percent of the unit price bid when each unit has been satisfactorily installed and is operational at the first location. The remaining 10 percent will be paid upon removal.

619-5.11 Type III Construction Barricades. The unit price bid for Type III construction barricades shall

include all labor, materials, and equipment necessary to complete the work, including lighting when required. When barricades are relocated or the diagonal stripes are changed to allow traffic to pass on the other side of the barricade, additional payment will be made for another barricade. Movements of the barricade from one side of the roadway to the other side, movements within 100 feet of the initial location, or daily replacement to approximately the same location, not requiring any change in the diagonal stripes, will not be considered as relocation, and will not be paid for as additional barricades. No payment will be made for Type III construction barricades used at the option of the Contractor in lieu of channelizing devices.

619-5.12 Temporary Positive Barrier. The unit price bid for temporary positive barrier shall include all

labor, materials, and equipment necessary to satisfactorily complete the work, including any required connection devices, end treatments, end section pinning, temporary delineation and rep air of pavement after removal of temporary positive barrier. Temporary impact attenuators, if required, will be paid for separately. When temporary positive barriers are relocated, except movements necessary to maintain, realign, or replace damaged units and daily relocat ion of segments to allow access to the work area which are restored at the end of the work shift, additional payment for the relocation will be made for additional length of temporary concrete barrier.

619-5 12

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 The unit price bid for temporary positive barrier – Category X shall include the cost of furnishing all labor, materials, and equipment necessary to satisfactorily complete the work, including pinning. The unit price bid for warning lights on temporary positive barrier with shall include the cost of furnishing all labor, materials, equipment, and electrical power necessary to complete the work. Should a barrier that is equipped with warning lights be moved to a new location where temporary concrete barrier with warning lights is required, payment will be made for additional warning lights on temporary positive barrier. The unit price bid for Box Beam to Flared Temporary Concrete Barrier Transition shall include the cost of furnishing all labor, materials, and equipment necessary to satisfactorily complete the work, including removal and replacement or resetting of exi sting rail; placement and removal of the temporary berm; seeding of the disturbed area; and replacement of rail with holes in its face. No separate payment will be made for box beam used to provide an overlap. The unit price bid for Box Beam to Unflared Temporary Concrete Barrier Transition shall include the cost of furnishing all labor, materials, and equipment necessary to satisfactorily complete the work, including removal and replacement or resetting of e xisting rail: furnishing of Transition End Pieces, rub rail heavy posts and blockouts; and replacement of rail with holes in its face. The unit price bid for Temporary Concrete Barrier Face to Box Beam Transition shall include the cost of furnishing all labor, materials, and equipment necessary to satisfactorily complete the work, including removal and replacement or resetting of exist ing rail and furnishing of box beam tapered end piece. The unit price bid for Temporary Concrete Barrier Back to Box Beam Transition shall include the cost of furnishing all labor, materials, and equipment necessary to complete the work, including removal and replacement or resetting of existing rail and re placement of rail with holes in its face. No separate payment will be made for box beam used to provide an overlap. The unit price bid for Corrugated Beam to Flared Temporary Concrete Barrier Transition shall include the cost of furnishing all labor, materials, and equipment necessary to satisfactorily complete the work, including removal and replacement or resetting of existing rail; placement and removal of the temporary berm; seeding of the disturbed a rea; and furnishing and removal of terminal rail section. No separate payment will be made for corrugated beam used to provide an overlap. The unit price bid for Temporary Concrete Barrier Face to Corrugated Beam Transition shall include the cost of furnishing all labor, materials, and equipment necessary to satisfactorily complete the work, including removal and replacement or resetting o f existing rail and furnishing and removal of W beam end piece. The unit price bid for Temporary Concrete Barrier Back to Corrugated Beam Transition shall include the cost of furnishing all labor, materials, and equipment necessary to complete the work, including removal and replacement or resetting of existing rail and furnishing and removal of terminal rail section. No separate payment will be made for corrugated beam used to provide an overlap. Progress payments will be made at the unit price bid for 90 percent of the quantity, after placement and demonstration of satisfactory operation. The remaining 10 percent will be paid upon removal. No payment will be made for temporary concrete barrier installed at the Contractor’s option, required solely due to a delay caused by the Contractor’s operations, or installed to protect pavement edge drop -offs, unless required in the contract documents. The unit price bid for temporary positive barrier shall include all labor, materials, and equipment necessary to satisfactorily complete the work, including any required connection devices, end treatments, end section pinning, temporary delineation and rep air of pavement after removal of temporary positive barrier. Temporary impact attenuators, if required, will be paid for separately. When temporary positive barriers are relocated, except movements necessary to maintain, realign, or replace damaged units a nd daily relocation of segments to allow access to the work area which are restored at the end of the work shift, additional payment will be made for additional length of temporary positive barrier. The unit price bid for pinned temporary positive barrier shall include the cost of furnishing all labor, materials, and equipment necessary to satisfactorily complete the work, including pinning.

619-5 13

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 The unit price bid for temporary positive barrier stiffened with box beam shall include the cost of furnishing all labor, materials, and equipment necessary to satisfactorily complete the work, including the box beam. The unit price bid for temporary positive barrier with warning lights shall include the cost of furnishing all labor, materials, equipment, and electrical power necessary to complete the work. Should a barrier that is equipped with warning lights be moved to a new location where temporary positive barrier with warning lights is required, payment will be made for additional length of temporary positive barrier with warning lights. The unit price bid for Box Beam to Flared Temporary Positive Barrier Transition shall include the cost of furnishing all labor, materials, and equipment necessary to satisfactorily complete the work, including removal and replacement or resetting of existi ng rail: placement and removal of the temporary berm; seeding of the disturbed area; and replacement of rail with holes in its face. No separate payment will be made for box beam used to provide an overlap. The unit price bid for Box Beam to Unflared Temporary positive Barrier Transition shall include the cost of furnishing all labor, materials, and equipment necessary to satisfactorily complete the work, including removal and replacement or resetting of exis ting rail: furnishing of Transition End Pieces, rub rail heavy posts and blockouts; and replacement of rail with holes in its face. The unit price bid for Temporary Positive Barrier Face to Box Beam Transition shall include the cost of furnishing all labor, materials, and equipment necessary to satisfactorily complete the work, including removal and replacement or resetting of existing rail and furnishing of box beam tapered end piece. The unit price bid for Temporary Positive Barrier Back to Box Beam Transition shall include the cost of furnishing all labor, materials, and equipment necessary to complete the work, including removal and replacement or resetting of existing rail and repla cement of rail with holes in its face. No separate payment will be made for box beam used to provide an overlap. Progress payments will be made at the unit price bid for 90 percent of the quantity, after placement and demonstration of satisfactory operation. The remaining 10 percent will be paid upon removal. No payment will be made for temporary positive barrier ins talled at the Contractor’s option, required solely due to a delay caused by the Contractor’s operations, or installed to protect pavement edge drop -offs, unless required in the contract documents.

619-5.13 Temporary Glare Screen . The unit price bid for temporary glare screen shall include all labor,

materials, and equipment necessary to complete the work. When glare screens are relocated, except movements necessary to maintain, realign, or replace damaged units and daily relocation of temporary positive barrier segments with glare screen attached to allow access to the work area which are restored at the end of the work shift, additional payment will be made for the length of glare screen relocated. No payment will be made for repair or replacement of damaged components.

619-5.14 Temporary Impact Attenuator. The unit price bid shall include the cost of all labor, materials,

and equipment necessary to complete the work, including the connection to temporary or existing barrier, the back -up system, the pad, if indicated, and any excavation or backfill. When atte nuators are relocated, payment will be made for a new temporary impact attenuator, except minor movements within a site, such as movements to maintain, realign, or adjust an attenuator. No payment will be made to repai r, restore or replace an attenuator damaged by public traffic or by the Contractor’s operations. Progress payments will be made based on the unit price bid as follows: 90 percent when the attenuator is adequately installed and operational; the remaining 10 percent will be paid upon removal .

619-5.15 Temporary Sand Barrel Arrays. The unit price bid for temporary sand barrel arrays shall

include the cost of all labor, materials and equipment necessary to complete the work, including the cost of the sand fill and salt additive. Replacement of individual modules damaged by public tra ffic will be paid for at the unit price bid for each temporary sand barrel. Relocation of barrels to a new location will be paid for as a new installation.

619-5 16

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 Progress payments will be made based on the unit price bid as follows: 90 percent when the barrels are adequately installed and operational; the remaining 10 percent will be paid upon removal.

619-5.16 Vehicle Arresting Barrier . The unit price bid for vehicle arresting barrier shall include the cost

of all labor, materials, and equipment necessary to complete the work. No payment will be made to repair, restore, or replace an attenuator damaged by public traffic or by the Contra ctor’s operations.

619-5.17 Maintain or Modify Traffic Signal Equipment. The unit price bid for maintaining traffic signal

equipment shall include the cost of all labor, materials, and equipment necessary to perform the work, with the exception of inductance loop replacement, if necessary, which will be paid for separately. Th e cost of the electric power shall be the responsibility of the original maintaining agency. No payment will be made during any period for which the Contractor has been granted an extension of time with engineering charges. The unit price bid for modifying traffic signal equipment per location shall include the cost of all labor, materials, and equipment necessary to perform the work.

619-5.18 Temporary Traffic Signals . The unit price bid for temporary traffic signals per location shall

include the cost of all labor, materials, and equipment necessary to complete the work, including the cost of electric power necessary to operate the signal until its removal is approved or directed by the Engineer. A location may be an intersection, a work zone with two or more signal faces interconnected and operating together, or other limits as defined in the contract documents. Portable or temporary traffic signals used at the Contractor’s option in lieu of flaggers shall be included in the lump sum price bid for basic work zone traffic control. Progress payments will be made at 50 percent of the unit price bid for each location after installation and demonstration of satisfactory operation. The remaining 50 percent will be paid in progress payments per week of temporary traffic signal provided. T he amount of such weekly payment will be determined by dividing 50 percent of the unit price bid by the number of weeks the temporary traffic signal is to remain in operation, as shown on the approved progress schedule.

619-5.19 Nighttime Operations . The lump sum price bid for portable lighting shall include all labor,

materials, and equipment necessary to complete the work, including the cost to adapt equipment and provide power to light sources. Progress payments will be made based on the lump sum price bid as follows: 20 percent when the Nighttime Operations and Lighting Plan has been accepted and satisfactory lighting of nighttime operations has begun; the remaining 80 percent will be paid in progress payments per week of nighttime operations completed. The amount of such weekly payment will be determined by dividing 80 percent of the lump sum amount bid by the number of weeks of nighttime operations in the approved Nighttime Operations and Lighting Plan.

619-5.20 Traffic Control Supervisor . The unit price bid for traffic control supervisor shall include the

cost of furnishing all labor, materials, equipment, training, and direct supervision necessary to provide and support the activities of a traffic control supervisor.

619-5.21 Temporary Structures and Approaches . The lump sum price bid for temporary structures and

approaches shall include the cost of all labor, materials, and equipment necessary to complete the work including design preparation, submittals, and inspection of the structure. Progress payments will be made at the unit price bid for 90 percent of the quantity after the temporary structures and approaches are complete and operable. The remaining 10 percent will be paid upon removal.

619-5.22 Pavement Patching . Payment shall include the cost of furnishing all labor, materials, and

equipment necessary to patch pavement during periods of winter shutdown when work on the contract is inactive, or when asphalt material is not available, including mobilization of wor k crews and work zone

619-5 23

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 traffic control. The cost of all work associated with providing and installing suitable pavement patching materials to maintain pavements open to traffic in acceptable condition when work on the contract is active, or when asphalt material is available, wi ll be paid under an asphalt sidewalk item if that item is in the contract, or alternatively, under a top course paving item, regardless of the material actually used. Payment for winter patching will be based on force account records submitted to the Engin eer, plus 10% overhead and 10% profit in accordance with §109 -05.

619-5.23 Mailboxes . The unit price bid for mailboxes shall include all labor, materials, and equipment

necessary to complete the work. Only one payment for each mailbox will be made regardless of the number of times it is moved or replaced and shall be made when the mailbox has been placed in its final location. Where multiple mailboxes are installed on a single post, payment will be based upon the number of individual mailboxes so installed.

619-5.24 Portable Temporary Rumble Strips (PTRS). The price bid shall include the cost of furnishing

all labor, materials, and equipment necessary to satisfactorily complete the work. Pavement cleaning, if necessary, shall be included.

619-5.25 Automated Flagger Assistance Devices (AFAD). The unit price bid shall include the cost of all

labor, materials, and equipment necessary to satisfactorily complete the work. The cost of advance warning signs shall be included in the unit bid price for Item 619.01 – Basic Work Zone Traffic Control. Payment will be made under: Item No. Item Pay Unit 619.01 Basic Work Zone Traffic Control Lump Sum 619.0101 Basic Work Zone Traffic Control (Daily Operations) Lump Sum 619.04 Type III Construction Barricades Each 619.05nn Temporary Structures and Approaches Lump Sum 619.0701 Temporary Business Signs Square Feet 619.0801xx Remove Pavement Marking Stripes Feet 619.0802xx Remove Pavement Marking Letters or Symbols Each xx = Material 01 = Traffic Paint, 02 = Epoxy Paint, 06 = Permanent Pavement Tape 619.0803 Cover Existing Pavement Marking Stripes (Removable Tape) Feet 619.0804 Cover Existing Pavement Marking Letters or Symbols (Removable Tape) Each 619.09xx Temporary Pavement Markings, Stripes Feet xx = Material 01= Traffic Paint, 03= Removable Tape, 04= Removable Wet Reflective Tape 619.1001xx Interim Pavement Markings, Stripes Feet 619.1002xx Interim Pavement Markings, Symbols Each 619.1003xx Interim Pavement Markings, Letters Each xx = Material 01= Traffic Paint, 02= Epoxy Paint, 03= Removable Tape,

619-5 25

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 04= Removable Wet Reflective Tape, 05= Traffic Paint Supplemented with Raised Markers 619.1105XY Portable Variable Message Sign (PVMS) Standard size – Full Matrix (LED) Each 619.1106XY Portable Variable Message Sign (PVMS) Standard size – Full Matrix (LED) Week 619.1107XY Portable Variable Message Sign (PVMS) Large size - Full Matrix (LED) Each 619.1108XY Portable Variable Message Sign (PVMS) Large size - Full Matrix (LED) Week 619.1109XY Portable Variable Message Sign (PVMS) Small size - Full Matrix (LED) Each 619.1110XY Portable Variable Message Sign (PVMS) Small size - Full Matrix (LED) Week 619.1111XY Portable Variable Message Sign (PVMS) Standard size – Line or character matrix (LED) Each 619.1112XY Portable Variable Message Sign (PVMS) Standard size – Line or character matrix (LED) Week XY = Options X= Equipment Options Y= Cellular Communication Options 1 = No optional equipment specified 1 = No Cellular Communications required 2= Radar 2 = Cellular Communications 3= CCTV Camera 3 = Cellular Communication with NTCIP compliance 4= Radar & CCTV Camera 619.1113 Truck Mounted Variable Message Signs (TMVMS) Each 619.1114 Truck Mounted Variable Message Signs (TMVMS) Week 619.12 Temporary Glare Screen Feet 619.13nn Temporary Traffic Signals Each Location 619.14 Automated Flagger Assistance Device (AFAD) DVDY 619.1611 Maintain Traffic Signal Equipment (Requirement A) Intersection Month 619.1612 Maintain Traffic Signal Equipment (Requirement B) Intersection Month 619.1613 Maintain Traffic Signal Equipment (Requirement C) Intersection Month 619.1614nn Modify Existing Traffic Signal Equipment (Temporary) Each Location 619.1711 Temporary Positive Barrier – Category 1 (Pinning Prohibited) Feet 619.1712 Temporary Positive Barrier – Category 2 (Pinning Permitted) Feet 619.1713 Temporary Positive Barrier – Category 3 (Pinning Prohibited) Feet 619.1714 Temporary Positive Barrier – Category 4 (Pinning Permitted) Feet 619.1715 Temporary Positive Barrier – Category 5 (Pinning Prohibited) Feet 619.1716 Temporary Positive Barrier – Category 6 (Pinning Required) Feet 619.1717 Temporary Positive Barrier – Category 7 (Pinning and Box -Beam -Stiffening Required) Feet 619.1719 Warning Lights on Temporary Positive Barriers Each 619.1720 Box Beam to Flared Temporary Concrete Barrier Transition Each 619.1721 Box Beam to Unflared Temporary Concrete Barrier Transition Each 619.1722 Temporary Concrete Barrier Face to Box Beam Transition Each 619.1723 Temporary Concrete Barrier Back to Box Beam Transition Each 619.1724 Corrugated Beam to Flared Temporary Concrete Barrier Transition Each 619.1725 Temporary Concrete Barrier Face to Corrugated Beam Transition Each 619.1726 Temporary Concrete Barrier Back to Corrugated Beam Transition Each

620-1 01

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 619.1802 Temporary Impact Attenuator - Redirective (Test Level 2) Each 619.1803 Temporary Impact Attenuator - Redirective (Test Level 3) Each 619.1812 Temporary Impact Attenuator - Gating (Test Level 2) Each 619.1813 Temporary Impact Attenuator - Gating (Test Level 3) Each 619.20 Interim Tubular Markers Each 619.21 Temporary Sand Barrel Module Each 619.22 Temporary Rumble Strips Feet 619.2202 Portable Temporary Rumble Strips DVDY 619.23 Vehicle Arresting Barrier Each 619.24 Nighttime Operations (Entire Project) Lump Sum 619.24nn Nighttime Operations Lump Sum 619.25 Traffic Control Supervisor Month 619.2601 Pavement Patching, Winter Dollars -Cents 619.27 Mailboxes Each NOTE: nn denotes a serialized pay item. DVDY denotes Devices per Day SECTION 620 - BANK AND CHANNEL PROTECTION (Last Revised May 1, 201 9)

620-1 DESCRIPTION. This work shall consist of furnishing all labor, equipment, and materials to place

a protective covering of erosion -resistant material in the locations indicated in the contract documents or as directed by the Engineer. The work shall be done in accordan ce with these specifications and in conformity with the lines, grades, thicknesses, and typical sections shown in the contract documents or established by the Engineer.

620-1.01 Vacant .

620-1.02 Stone Filling. Stone filling shall consist of a layer of well graded stone.

620-1.03 Dry Rip -Rap. Dry rip -rap shall consist of a fitted layer of shaped and graded stone.

620-1.04 Grouted Rip -Rap. Grouted rip -rap shall consist of a layer of stone, similar to dry rip -rap, with

the spaces between the stones filled with cement grout.

620-1.05 Bedding Material. Bedding material shall consist of a layer of granular material placed to

prevent underlying finer material from passing into and through the stone filling or rip -rap.

620-1.06 Concrete Block Paving. Concrete block paving shall consist of concrete blocks placed on

embankment slopes under structures as protection against erosion.

620-1.07 Gabions. Gabions shall consist of open wire mesh baskets, filled with stones.

620-2 Materials

620-2.01 General. The requirements for bank and channel protection materials are described below. The

procedure for acceptance or rejection of stone filling and rip -rap materials shall be in conformance with the procedures contained in the geotechnical control procedure “ Procedure for the Control of Stone Filling and Rip -Rap Items ”.

Source: New York Standard Specifications, 2024 Edition. Pages 571632 of 1,264.