401-3 10
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Sections 200 - 599 STANDARD SPECIFICATIONS (USC) January 1, 202 4 Volume 2 evaluated into 4 sublots in accordance with the requirements of §40 4-3.08, Pavement Density Samples. The material will be left in -place when either of the following sets of conditions is met.
401-4 METHOD OF MEASUREMENT. The quantity will be the number of tons delivered as
determined from the automated proportioning system, the delivery vehicle weigh system, or the asphalt mixture holding bin weigh system. The measurement or calculation will be the quantity based on the measured amount and reported to the nearest 0.01 of a ton. SECTION 402 - VACANT SECTION 403 - VACANT SECTION 404 - ASPHALT PAVEMENTS
404-1 DESCRIPTION. These specifications apply to all plant mixed asphalt produced at a production
facility under Section 401 Plant Production This work will consist of providing, placing, and performing density monitoring of one or more courses of asphalt pavement constructed on the prepared foundation in accordance with the contract documents or as directed by the Engineer.
404-2 01
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Sections 200 - 599 STANDARD SPECIFICATIONS (USC) January 1, 202 4 Volume 2 404-2 – MATERIALS.
404-2.01 General. Aggregate, Performance Graded (PG) Binder, and Warm Mix Asphalt Technology
shall be from suppliers listed in the Department’s Approved List for Fine and Coarse Aggregates, Performance Graded (PG) Binders and Warm Mix Asphalt Technology for Asphalt Paving, respectively. Mineral filler shall meet the requirements of §703 -08. A PG Binder grade and the mix design gyration will be specified by Special Note in the contract documents. The use of the WMA Technology shall comply with the latest technology supplier’s approved “Production, Testing, and Compaction Details” .
404-2.02 Composition of Mixtures. Asphalt mixture shall meet the requirements of §401 -2 of the
Standard Specifications and the mixture design procedure in Materials Method (MM) 5.16, Asphalt Mixture Design and Mixture Verification Procedures . The Contractor shall be responsible for the quality and performance of the mixture created from approved components.
404-3 Construction Details .
• Mix Temperature. The desired asphalt mixture temperature shall be within the mixing and compaction range as recommended by the WMA technology provider and shall not exceed 295°F at the point of discharge of the haul vehicle, unless a higher temperature is approved by the Regional Materials En gineer. • Pre-pave Meeting. The Engineer will conduct a pre -pave meeting prior to any asphalt mixture placement. The attendees at this meeting will include the Regional Materials Engineer, Paving Superintendent, Chief Inspector or Paving Inspector(s), Asphalt Plant Representative, Density Gauge Operator (depending on the compaction method used), and a Work Zone Traffic Control (WZTC) representative. The participants should be prepared to discuss the steps necessary to complete the work successfully. • Participants will review all aspects of the requirements including, but not limited to, the following: o Warm Mix Technology dosage rates o Asphalt mixture target temperatures o Anticipated mixture production, delivery rate, and paving speed. o Seasonal considerations with operations o Equipment and setup o Mix codes to assure correct mixture is delivered o Gauge operator certification o Proper construction practice to provide quality product
404-3 01
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Sections 200 - 599 STANDARD SPECIFICATIONS (USC) January 1, 202 4 Volume 2 o WZTC Activities • Certified Gauge Operator. When a density gauge is used to monitor pavement density, the Contractor shall provide a certified operator with a current Density Gauge Inspector Certification from the Associated General Contractors (NY Chapter), or its equivalent*, as determined by the Director of the Materials Bureau. *Equivalence: Operators that possess a current Paving Inspector Certification from Northeast Transportation Technician Certification Program (NETTCP) and pass the current Density Gauge Inspector Certification exam shall be considered to have an equivalent certification.
404-3.01 Temperature and Seasonal Limitations .
404-3 02
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Sections 200 - 599 STANDARD SPECIFICATIONS (USC) January 1, 202 4 Volume 2 temperature and outside the seasonal limits to expedite the completion of the work.
404-3.02 Pavers. The paver shall be capable of spreading and finishing courses of asphalt mixture in lane
widths, shoulders, or similar construction applicable to the specified typical section and thicknesses shown on the plans. When a paver is found to be defective, either before or during its use, it shall be repaired or replaced immediately. The paver shall meet the following requirements:
404-3 03
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Sections 200 - 599 STANDARD SPECIFICATIONS (USC) January 1, 202 4 Volume 2 404-3.03 Hauling Equipment. Transport trucks shall have clean, smooth, tight metal beds with waterproof covers for transporting asphalt mixtures to the work site. A waterproof cover shall be mounted in such a manner that it covers the entire load and overlaps the vehicle’s sideboards and back by a minimum of 6 inches and is fastened except for live-bottom trucks that has a channelized tarp system. The inside surface of the vehicle body may be lightly coated with a release agent listed on the Approved List for Release Agents. The use of petroleum products or solvents as release agents is prohibited. All hauling equipment is subject to the approval of the Engineer.
404-3.04 Rollers. Contractor shall use vibratory, oscillatory, static steel wheel type, or pneumatic tire
rollers capable of compacting asphalt pavement and weighing at least 8 tons. The Engineer will inspect rollers prior to the start of paving operations to determine acceptability. The rollers should be in good mechanical condition, and capable of operating at speeds slow enough to avoid displacement of the mixture. Rollers that result in excessive crushing of aggregate shall not be used. All rollers shall have either a sticker or a plate installed on the roller indicating the recommended settings for amplitude, frequency, and tire pressure (pneumatic) for the thickness of pavement being rolled. Vibratory rollers shall be set up such that they produce a minimum of 12 impacts per foot during the compaction process.
404-3.05 Conditioning of Existing Surface. The Contractor shall use the provisions of Section 633
Conditioning Existing Pavement Prior to Asphalt Overlay to clean the surface of the existing pavement prior to the application of new asphalt mixture or when specified in the contract documents, to fill joints and cracks, and perform repairs. Any foreign material resulting from construction operations shall be cleaned at no additional cost to the State. For filling the wheel ruts, the Contractor shall use Shim Course or 6.3 Top Course unless a specific asphalt mixture is specified. The mixture used for filling ruts shall be compacted with a minimum of three passes of a pneumatic rubber tire roller. If the true and leveling (T&L) course is specified in the contract documents using a specific mixture type, the Contractor shall place the course(s) with a minimum variable thickness to bring the surface of the existing pavement to the same transverse slope and longitudinal grade required for the finished pavement surface. If the mixture type is not specified, the Contractor shall use Table 404 -2 Mixture Selection for T&L Course , to select the appropriate mixture type. The selection of the mixture shall be such that dragging of stones at the thin edge is minimized, including when constructing wedges for super -elevation. If dragging is excessive in any T&L course, a different T&L mixture shall be selected for the application. The surface of this course will be tested in the same manner prescribed in §404 -3.10 Surface Tolerance , except that the allowable variation from the true surface after compaction shall not exceed ⅜ inch.
404-3.06 Spreading and Finishing
404-3 06
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Sections 200 - 599 STANDARD SPECIFICATIONS (USC) January 1, 202 4 Volume 2 required on the surface of Permeable Base courses. Paving over a tack coat should not commence until the emulsion has broken (goes from brown to black) or is tacky when touched.
404-3 07
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Sections 200 - 599 STANDARD SPECIFICATIONS (USC) January 1, 202 4 Volume 2 H. Wet Surface. Asphalt mixture shall not be placed on any wet surface. Wet surface is defined as one that is moistened, covered, or soaked with water.
404-3.07 Compaction. The Contractor shall compact the asphalt mixture sufficiently using the
appropriate compaction method to achieve pavement densities of at least 93%, expressed as a percentage of the mixture’s maximum theoretical density (MMTD). The asphalt mixture shall be compacted using rollers meeting the requirements of §404 -3.04 Rollers . A minimum of two rollers, one for breakdown and one finish roller, shall be used unless the asphalt mixture placement is on a bridge deck, bridge approaches, or other areas where one roller may be sufficient to achieve the required density. When paving multiple lanes simultaneously, the required number of rollers shall be increased proportionately for each additional full lane width unless otherwise approved by the Engineer. The asphalt mixture shall be compacted immediately after placement, and when the mixture is in the proper condition such that the rollers do not cause displacement, cracking, or shoving. Initially, all courses shall be compacted with the roller traveling parallel to the centerline of the pavement, beginning at each edge, and working toward the center. The super -elevated curves shall be compacted starting at the low-side edge and working toward the higher edge. Any displacement caused by the roller, or any other causes, shall be corrected immediately using rakes and additional asphalt mixture as required. The roller wheels shall be properly moistened with water, water mixed with small quantities of detergent, or other approved material, to prevent adhesion of the mixture to the rollers. The use of petroleum products or solvents are not allowed to prevent adhesion. The asphalt mixture along forms, curbs, headers, walls, and other areas not accessible to rollers shall be compacted with mechanical tampers, a trench roller, or a small vibratory roller with the approval of the Engineer. The Contractor shall remove and replace any asphalt mixture that becomes loose and broken, mixed with dirt, or is in any way defective and the new mixture shall be compacted to conform to the surrounding area. Any areas showing an excess or deficiency of asphalt material shall be corrected immediately. Vibratory compaction is not allowed when asphalt mixture is placed on a structural bridge deck or other structures with less than 2 feet of cover over the structure or when specified in contract documents. The Contractor shall repair all damages which may occur to the highway components and adjacent property, including buried utility and service facilities, at no additional cost to the State. Steel wheel rollers running on static mode, pneumatic rollers or oscillatory rollers shall be used on the bridge decks. The Contractor shall monitor pavement density for 60 and 70 Series compaction using density gauges meeting the provisions of §404 -3.07E Density Gauges . The density gauge operator shall possess a current Density Gauge Inspector Certification from The New York State Associated General Contractors, or its equivalent, as determined by the Director, Materials Bureau. Any asphalt placement under 60 and 70 Series monitored by a gauge operator whose certification is revoked for reasons outlined in the New York State Inspector Certification Program Manual under “Decertification”, shall be evaluated in accordanc e with §404 -3.14 Pavement Evaluation , using the results of pavement samples taken in accordance with §404 -3.08 Pavement Density Samples.
404-3 07
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Sections 200 - 599 STANDARD SPECIFICATIONS (USC) January 1, 202 4 Volume 2 maximum of 8 cores for a lot. Ramps less than 1500 feet in length and shoulders will not be considered part of the traveled way and are not subject to coring. The Engineer will mark a pavement core location in each sublot in accordance with §404 -3.08A Pavement Cores once the compaction operation is completed, excluding the first 300 feet of the day’s placement. The Contractor shall extract pavement cores at the marked locations in each sublot and fill the pavement core holes before the road is open to traffic in accordance with §404 -3.08 B Filling Core Holes . The pavement cores shall be extracted no later than the end of the following day’s placement. The Contractor shall deliver the sealed pavement cores to the Regional Materials Laboratory in accordance with §404 -3.08 E Sample Delivery . The Regional Laboratory will test core samples and determine the percent density using the maximum theoretical density samples taken in accordance with §404 -3.08 C Loose Mix Samples . The results of this analysis will be used to determine the pavement density Quality Adjustment Factor (QAF) in accordance with MP 404-02 and submitted to the Engineer prior to the end of the next business day upon the delivery of the samples . The Engineer will apply the pavement density QAF to the material placed on that day in accordance with §404.4 Method of Measurement , Table 404-6, Quality Adjustment Factors for 50 Series . When two consecutive lots are found to have a density QAF equal to or less than 0.85, the Contractor shall stop paving operations and provide a corrective action plan. The Contractor shall compact material on shoulders, widening, crossovers, bridges, and ramps with a uniform full-width section of less than 1500 feet in length using the same roller pattern as traveled way. If the shoulder subbase is structurally insufficient to sustain the level of compaction such that the shoulder shows sign of distress during compaction, the compaction effort shall be decreased until no further damage occurs to the shoulder or subbase.
404-3 07
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Sections 200 - 599 STANDARD SPECIFICATIONS (USC) January 1, 202 4 Volume 2 c. The Contractor shall extract pavement cores at the marked location in each sublot and fill the core holes before the road is opened to traffic. The density gauge readings and sealed pavement cores shall be delivered to the Regional Materials Laboratory in accordance with §404 -3.08 Pavement Density Samples .
404-3 07
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Sections 200 - 599 STANDARD SPECIFICATIONS (USC) January 1, 202 4 Volume 2 sustain the level of compaction such that they show signs of distress, the Contractor shall decrease the compaction effort until no damage occurs to the shoulder or subbase.
404-3 07
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Sections 200 - 599 STANDARD SPECIFICATIONS (USC) January 1, 202 4 Volume 2 c. Gauge readings do not seem to accurately represent the asphalt pavement density.
404-3 07
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Sections 200 - 599 STANDARD SPECIFICATIONS (USC) January 1, 202 4 Volume 2 a. A frequency range of 1,000 vpm to 4,000 vpm
404-3 08
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Sections 200 - 599 STANDARD SPECIFICATIONS (USC) January 1, 202 4 Volume 2 404-3.08 Pavement Density Samples
404-3 09
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Sections 200 - 599 STANDARD SPECIFICATIONS (USC) January 1, 202 4 Volume 2 E. Sample Delivery. The Contractor shall deliver the pavement samples to the Regional Materials Laboratory no later than the end of the following day’s placement. If these samples are not submitted for any paving lot within the required duration, a QAF of 1.00 or less will be assigned for that lot if a QAF is applicable. When, for any reason, a delay occurs in the delivery of the lot samples for three consecutive lots, the Engineer will stop paving operations until the samples are delivered and tested.
404-3.09 Joints. The finished pavement at all joints shall comply with the surface tolerance requirements
and exhibit the same uniformity of texture and compaction as other sections of the pavement course. Rollers shall not pass over the unprotected edges of a freshly laid mixture unless approved by the Engineer. All joints, excluding the tapered wedge joint, shall be constructed such that the exposed edge has the required lift thickness, and the alignment of the pavement course is straight, unless the exposed joint will not be part of the joint. If the edge of the newly placed pavement course is not straight or smoothly curved, the Contractor shall sawcut the edge by using a power saw or other approved tools to cut a neat straight edge . Prior to placing the adjacent course, a joint adhesive shall be applied in accordance with §404 -3.06 Joint Adhesive , to all pavement edges to provide bonding with the newly laid pavement. Successive asphalt pavement courses shall be placed over an underlying course such that all longitudinal joints are offset no more than 6 inches from the longitudinal joint of the lower pavement course, unless otherwise approved by the Engineer. Pavement courses on existing PCC pavement shall be placed such that all longitudinal joints are stacked on top of the joint of the underlying PCC pavement.
404-3 09
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Sections 200 - 599 STANDARD SPECIFICATIONS (USC) January 1, 202 4 Volume 2 B. Longitudinal Joints. The longitudinal joints in the asphalt Top Course shall correspond with the edges of the proposed traffic lanes. Other joint arrangements will require approval of the Engineer. For 70 and 80 Series, the dual -drum vibratory roller shall be operated in a vibratory mode, unless static rolling is required, to construct the longitudinal joint. Rollers shall be as close to the paver as practical. The first pass shall be made traveling toward the paver and operating on the hot mat with 6 to 8 inches of the roller drum overlapping onto the cold mat. The second pass shall be made to the joint with the roller traveling back away from the paver along the same path. If a single -drum vibratory roller with pneumatic drive wheels is used, the roller shall be operated in vibratory mode and following the same procedure as the dual -drum roller. The exception to this is that the roller will be aligned on the joint so that the pneumatic drive wheels travel on the joint. All turning movements of the roller shall be made on previously compacted material. After applying two roller passes on the longitudinal joint, the roller shall proceed to the low side of the lane and compact as described in §404 -3.07 Compaction . The longitudinal joint shall be constructed such that the compacted thickness of the newly placed mat shall not exceed ¼ inch of the adjacent mat. When the joint is constructed with an overlap, the overlap shall not exceed 2 inches. For all asphalt pavement courses other than Top Course, the longitudinal pavement joint shall not be exposed more than 100 feet at the end of the working day when traffic is maintained on the roadway during paving operations. For Top Course of 2.5 inches or less, refer to §404 -3.09D Exposed Longitudinal Joint . The longitudinal joint shall be constructed using one of the two options below:
404-3 10
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Sections 200 - 599 STANDARD SPECIFICATIONS (USC) January 1, 202 4 Volume 2 Cores will be taken from the total length of the joint matched daily. The number of cores extracted shall be in accordance with Table 404 -4 Longitudinal Joint Cores for 50 & 60 Series . The Engineer will randomly mark core locations centered over the constructed joint in accordance with MP
404-02 using the X coordinates only. A matched joint of 1500 feet or less is not subject to coring. The
Contractor shall extract cores on the same day the joint is matched or before the completion of next day’s placement. The cores shall be extracted in accordance with §404 -3.08A Pavement Density Samples and delivered to the Regional Laboratory. The Regional Materials Engineer will determine the core density using the mixture’s maximum theoretical density specified in §404 -3.08C. TABLE 404-4 LONGITUDINAL JOINT CORES FOR 50 & 60 SERIES Daily Joint Length (feet) No. of Cores 1,500 < Length ≤ 10,000 4 10,000 < Length ≤ 20,000 6 Length > 20,000 8
404-3.10 Surface Tolerance. The Contractor shall construct each pavement course to a ¼ inch surface
tolerance. The Engineer may test the surface with a 16 -foot straight edge or string line placed parallel to the centerline of the pavement and with a 10 -foot straight edge or string line placed transversely to the centerline of the pavement. Variations exceeding ¼ inch shall be appropriately corrected or the pavement be removed and replaced at no additional cost to the State.
404-3 11
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Sections 200 - 599 STANDARD SPECIFICATIONS (USC) January 1, 202 4 Volume 2 404-3.11 Thickness Tolerance. The Contractor shall construct the pavement such that the final compacted thickness is as near to the nominal thickness as is practical, and within the tolerances specified below. The Engineer may request pavement cores to determine the thickness of the completed pavement course for final acceptance and payment. The Contractor shall provide work zone traffic control and take pavement cores in accordance with §404 -3.08 Pavement Density Sample, at no additional cost to the State. The Engineer may use another acceptance method such as yield calculations to determine the final thickness for acceptance and payment. Asphalt mixture placed as a Truing and Leveling (T&L) course as described in §404 -3.05 Conditioning of Existing Surface shall not be considered in pavement thickness determinations. The allowable tolerance for asphalt mixture specified under a single pay item is as follows:
404-3.12 Paver and Equipment Cleaning. Tools and equipment used for asphalt placement shall not be
cleaned on the pavement surface, or near streams, ponds, drainage structures or other areas that are tributaries to waterways. The designated area approved by the Engineer shall be used for cleaning all paving equipment and tools. If petroleum products are used for cleaning, the use of tarpaulins, sand pails, pails or other methods shall be used to collect all liquid product produced by cleaning operations to prevent any contaminates from spilling or being accidentally released into the environ ment. Hand sprayers or other similar devices may be used to minimize the amount of petroleum product applied. Any sand, soil and/or collected petroleum products from cleaning operations shall be properly disposed of as petroleum contaminated soil at no additional cost to the State.
404-3.13 Shoulder Edge Wedge. The Contractor shall construct a shoulder edge wedge as detailed in the
contract documents. The asphalt mixture shall be placed on the pavement shoulders where the outside edge of Top and Binder Course consist of an angle of 35° or flatter measured from finished grade to the preceding course surface. The shoulder edge wedge shall be constructed using a device attached to the screed to minimize hand work. The top of the tapered section shall be at the end of the shoulder width such that the tapered section will be an additional width of material outside of the paved shoulder width.
404-3.14 Pavement Evaluation. The Engineer will evaluate mixtures either placed or produced outside
the specification limits which results in low quality adjustment factors.
404-3 15
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Sections 200 - 599 STANDARD SPECIFICATIONS (USC) January 1, 202 4 Volume 2 404-3.15 Pavement Defects. Upon completion of the asphalt mixture placement, the Engineer will ensure there are no visible defects in the pavement, such as ruts, ridges, roller marks, cracking, tearing, segregation, bleeding, or any other irregularities. The Contractor shall correct any defects that become apparent or replace the defective pavement at no additional cost to the State.
404-4 Method of Measurement
404-4.01 Asphalt. The quantity of asphalt mixture to be measured for payment will be measured in tons
and rounded to the nearest 0.01 tons. Requirements of §401 -4 shall apply.
404-4.02 Plant Production Quality Adjustment. Plant Production Quality Adjustments will be measured
in Quality Units determined for each day’s production using the daily Quality Adjustment Factor (QAF) for plant production. Also, this will be determined in accordance with §401 -3.07 Documentation . Quality Units for plant production quality adjustments will be calculated using the formula below. Quality Units = (Quality Adjustment Factor - 1.00) x Asphalt Placed (Tons) No plant adjustment will be made for temporary pavement, shim, permeable base items, and other miscellaneous items.
404-4.03 Pavement Density Quality Adjustment. Pavement Density Quality Adjustments will be
measured in Quality Units determined for each day’s production using the daily Quality Adjustment Factor (QAF) for pavement density. The quantity of asphalt mixture subject to adjustment will be determined from quantity placed on the mainline. The pavement density QAF will not apply to asphalt mixture placed on ramps with a uniform full width section less than 1500 feet, shoulders, widening, crossovers, and bridges. Payment in these areas will be a QAF of 1.00 based on satisfactory placement and compaction. When shoulders and mainline are placed together, the mainline quantity may be determined using typical sections shown in the contract documents. Quality Units for pavement density quality adjustments under 50 and 60 Series compaction methods will be calculated using the formula below. No pavement density quality adjustments will be made under 70 and 80 Series compaction methods. Quality Units = (Quality Adjustment Factor - 1.00) x Asphalt Placed (Tons)
404-4 04
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Sections 200 - 599 STANDARD SPECIFICATIONS (USC) January 1, 202 4 Volume 2 TABLE 404-6 DENSITY SEGMENT PAY FACTORS Density Segment Segment Pay Factor 88 – 90 0.60 90 – 91 0.70 91 – 92 0.80 92 – 93 0.90 93 – 94 1.00 94 – 100 1.05
404-4.04 Joint Density Quality Adjustment. The Engineer will determine the density of each joint core
and calculate the average percent of the mixture’s maximum theoretical density (%MMTD) of the longitudinal joint cores. The Engineer will measure the length of longitudinal joints, in linear feet, and determine the number of segments. A segment is defined as a 528-foot section of a joint. A partial segment of 264 feet or greater (≥ 0.5 of a segment) will be considered a full segment. The Engineer will determine the segment Quality Units (QU) from Table 404-8 Quality Adjustment for Longitudinal Joint Density based on the average density of the joint cores and calculate the total Quality Units using the formula below. Quality Units = Segment QUs X # of Segments A payment adjustment will be made using the Quality Unit Index Price to the longitudinal joint length on the traveled way for the day the joint cores represent. TABLE 404-8 QUALITY ADJUSTMENT FOR LONGITUDINAL JOINT DENSITY Average Core Density, % MMTD Segment Quality Units (QU) Density ≥ 93.0 4 86.0≤ Density <93.0 QU = 1.143*Avg Core Density – 102.31 Density <86 -4
404-5 BASIS OF PAYMENT. The unit price bid for all asphalt mixture shall include the cost of all
labor, materials, and equipment necessary to satisfactorily complete the work, including cleaning of pavement, extracting the pavement cores, filling, and compaction of all core holes. Application of tack
404-4 04
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Sections 200 - 599 STANDARD SPECIFICATIONS (USC) January 1, 202 4 Volume 2 coat, joint adhesive, and repairs of pavement, and filling of cracks will be paid separately except when the joint adhesive is applied under §404 -3.01E. Payment of Quality Adjustments will be made based on the number of Quality Units multiplied by the fixed index price for Quality Adjustment to asphalt Items listed in the contract documents for the quantity placed on the day the Quality Units represent. Payment will be made under: Item No. Item Pay Unit 404.011901 Type 2 F9, Asphalt -Treated Permeable Base Course Ton 404.017901 Truing & Leveling F9, Asphalt, 70 Series Compaction Ton 404.018901 Truing & Leveling F9, Asphalt, 80 Series Compaction Ton 404.058901 Shim Course F9, Asphalt Ton 404.068101 6.3 F1 Top Course Asphalt, 80 Series Compaction Ton 404.068201 6.3 F2 Top Course Asphalt, 80 Series Compaction Ton 404.068301 6.3 F3 Top Course Asphalt, 80 Series Compaction Ton 404.095101 9.5 F1 Top Course Asphalt, 50 Series Compaction Ton 404.095201 9.5 F2 Top Course Asphalt, 50 Series Compaction Ton 404.096101 9.5 F1 Top Course Asphalt, 60 Series Compaction Ton 404.096201 9.5 F2 Top Course Asphalt, 60 Series Compaction Ton 404.096301 9.5 F3 Top Course Asphalt, 60 Series Compaction Ton 404.097101 9.5 F1 Top Course Asphalt, 70 Series Compaction Ton 404.097201 9.5 F2 Top Course Asphalt, 70 Series Compaction Ton 404.097301 9.5 F3 Top Course Asphalt, 70 Series Compaction Ton 404.098101 9.5 F1 Top Course Asphalt, 80 Series Compaction Ton 404.098201 9.5 F2 Top Course Asphalt, 80 Series Compaction Ton 404.098301 9.5 F3 Top Course Asphalt, 80 Series Compaction Ton 404.098901 9.5 F9 T&L or Shoulder Course Asphalt, 80 Series Compaction Ton 404.125101 12.5 F1 Top Course Asphalt, 50 Series Compaction Ton 404.125201 12.5 F2 Top Course Asphalt, 50 Series Compaction Ton 404.126101 12.5 F1 Top Course Asphalt, 60 Series Compaction Ton 404.126201 12.5 F2 Top Course Asphalt, 60 Series Compaction Ton 404.126301 12.5 F3 Top Course Asphalt, 60 Series Compaction Ton 404.127101 12.5 F1 Top Course Asphalt, 70 Series Compaction Ton 404.127201 12.5 F2 Top Course Asphalt, 70 Series Compaction Ton 404.127301 12.5 F3 Top Course Asphalt, 70 Series Compaction Ton 404.128101 12.5 F1 Top Course Asphalt, 80 Series Compaction Ton 404.128201 12.5 F2 Top Course Asphalt, 80 Series Compaction Ton 404.128301 12.5 F3 Top Course Asphalt, 80 Series Compaction Ton 404.128901 12.5 F9 T&L or Shoulder Course Asphalt, 80 Series Compaction Ton 404.125901 12.5 F9 Binder Course, 50 Series Compaction Ton 404.126901 12.5 F9 Binder Course, 60 Series Compaction Ton 404.127901 12.5 F9 Binder Course, 70 Series Compaction Ton 404.195901 19 F9 Binder Course Asphalt, 50 Series Compaction Ton 404.196901 19 F9 Binder Course Asphalt, 60 Series Compaction Ton 404.197901 19 F9 Binder Course Asphalt, 70 Series Compaction Ton 404.198901 19 F9 Binder Course Asphalt, 80 Series Compaction Ton 404.255901 25 F9 Binder Course Asphalt, 50 Series Compaction Ton 404.256901 25 F9 Binder Course Asphalt, 60 Series Compaction Ton 404.257901 25 F9 Binder Course Asphalt, 70 Series Compaction Ton 404.258901 25 F9 Binder Course Asphalt, 80 Series Compaction Ton
405-2 01
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Sections 200 - 599 STANDARD SPECIFICATIONS (USC) January 1, 202 4 Volume 2 404.376901 37.5 F9 Base Course Asphalt, 60 Series Compaction Ton 404.377901 37.5 F9 Base Course Asphalt, 70 Series Compaction Ton 404.378901 37.5 F9 Base Course Asphalt, 80 Series Compaction Ton 404.418901 9.5 F9 Temporary Top Course Asphalt, 80 Series Compaction Ton 404.428901 12.5 F9 Temporary Top Course Asphalt, 80 Series Compaction Ton 404.438901 19 F9 Temporary Binder Course Asphalt, 80 Series Compaction Ton 404.448901 25 F9 Temporary Binder Course Asphalt, 80 Series Compaction Ton 404.458901 37.5 F9 Temporary Binder Course Asphalt, 80 Series Compaction Ton 404.000011 Plant Production Quality Adjustment to Asphalt Items Quality Unit 404.000021 Pavement Density Quality Adjustment to Asphalt Items Quality Unit 404.000031 Longitudinal Joint Density Quality Adjustment to Asphalt Items Quality Unit SECTION 405 - COLD MIX BITUMINOUS PAVEMENT (OPEN GRADED)
405-1 DESCRIPTION. This work shall consist of constructing one or more courses of cold mix
bituminous pavement on a prepared base in accordance with these specifications and in substantial conformance with the lines, grades, thicknesses, and typical cross -sections shown o n the plans or established by the Engineer.
405-2 Materials
405-2.01 Bituminous Material. The bituminous materials required for mixing and for sealing shall meet
the requirements of section 702, Bituminous Materials. The type and grade of bituminous material shall be that indicated on the plans or in the proposal.
405-2.02 Aggregates. The aggregates shall be Department approved aggregates meeting the
requirements of § 703 -02, Coarse Aggregates, for the sizes specified. Screened gravel shall not be permitted unless specified on the plans or in the proposal.
405-2.03 Composition of Mixtures. The bituminous cold mix shall be composed of a mixture of
aggregate and bituminous material as ordered and approved by the Engineer. The mix shall be proportioned as specified in Table 405 -1, Composition of Cold Bituminous Mixtures. TABLE 405 -1 COMPOSITION OF COLD BITUMINOUS MIXTURES Sieve Size Mixes Type 1 General Limits % passing1 Type 2 General Limits % passing1 Type 3 General Limits % passing1 2 in - - 100 1 1/2 in - 100 75-100 1 in 100 90-100 50-80 1/2 in 90-100 15-45 0-15 1/4 in 15-45 0-10 - 1/8 in 0-10 - - No. 200 0-1.0 0-1.0 0-1.0 Bituminous Material2,3 4.7-7.0 4.0-6.0 3.5-5.5 Description Open, Coarse Texture Open, Coarse Texture Open, Coarse Texture Typical Uses Surface Course Intermediate Base Course
405-3 01
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Sections 200 - 599 STANDARD SPECIFICATIONS (USC) January 1, 202 4 Volume 2 1 Percentage based on total aggregate weight.
405-3 Construction Requirements
405-3.01 Weather Limitations. Bituminous material or mixture shall not be applied on any soft
surfaces, when the surface is wet, when the temperature of the surface on which the mi xture is to be placed is below 45°F , or when other weather conditions would prevent proper construction of the pavement.
405-3.02 Equipment. The following equipment shall be required:
405-3.03 Preparation of the Base. The roadway surface to be covered shall be free from holes,
depressions, bumps, waves and corrugations. Any unsuitable surface areas shall be repaired by replacement of the unstable materials or by patching with a material to produce a tight surface hav ing the same elevation as the surrounding surface. The roadway surface shall be broomed when ordered by the Engineer to remove loose material.
405-3 04
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Sections 200 - 599 STANDARD SPECIFICATIONS (USC) January 1, 202 4 Volume 2 405-3.04 Mixing and Spreading. The aggregate and asphalt shall be thoroughly mixed so that the bituminous material is uniformly distributed throughout and all aggregate particles are uniformly coated. The mixture shall be deposited on the prepared base either in a windrow at the back of the travel mixer or mechanically spread in a uniform layer so as to produce the specified thickness after compaction. If deposited in a windrow, it shall be spread over the entire roadway surface by motor grader or other approved spreader to produce the specified thickness after compaction. The maximum allowable compacted thickness shall be 2 inch es for the Type 1 mix (Table 405 -1) and 4 inches for the Type 2 and Type 3 mixes (Table 405 -1).
405-3.05 Compaction. After spreading, the mixture shall be thoroughly and uniformly compacted with a
self-propelled steel -wheeled roller or an approved vibratory roller to obtain a thoroughly compacted pavement. The number of roller passes to achieve the desired compaction shall be approved by the Engineer.
405-3.06 Surface Testing. The finished surface of the pavement shall be tested with a 16 foot straight
edge laid parallel with the center line of the pavement. Any area exceeding a 1/4 inch variation from the surrounding area shall be satisfactorily corrected or removed and replaced.
405-3.07 Pavement Sealing. Either prior to initial compaction or immediately after compacting the mix,
No. 1A size key stone meeting the requirements of § 703 -02, Coarse Aggregates, shall be uniformly spread upon the surface at the rate of 10 to 15 lb/sy and the course rolled. No. 1 size key stone meeting the requirements of § 703 -02, Coarse Aggregates, at the rate of 10 to 20 lb/ sy, may be used for key stone on the base course mixes. After placement of the No. 1A size key stone, the pavement shall be opened to traffic for a mini mum of 3 days before placing the seal coat. Prior to the application of the seal coat, the pavement surface shall be thoroughly swept and cleaned of all excess material. The seal coat shall be bituminous material asphalt emulsion meeting the requirements of § 702 -3101 or § 702 -4101 applied at the r ate of 0.3 to 0.5 gal/sy (Type 1 mix, Table 405 -
405-4 METHOD OF MEASUREMENT. The bituminous cold mix pavement shall be meas ured by the
number of tons of compacted aggregate, including key and cover stone, placed in accordance with the specifications. The liquid bituminous material shall be measured by the liter.
405-5 BASIS OF PAYMENT. The unit price bid per ton shall include the preparation of base, the cost
of furnishing all the aggregate, the mixing, placing, compaction and all labor and equipment necessary to complete the work. The bituminous material will be paid for under its appropriate item. Payment will be made under: Item No. Item Pay Unit 405.01 Cold Mix Bituminous Pavem ent (Open Graded) Ton SECTION 406 ASPHALT PAVEMENT WITH POLYMER FIBERS
406-1 DESCRIPTION. The work shall include the production and placement of warm mix asphalt with
polymer fibers.
407-3 01
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Sections 200 - 599 STANDARD SPECIFICATIONS (USC) January 1, 202 4 Volume 2 406-2 MATERIALS. Material requirements shall be as specified in the special specifications.
406-3 CONSTRUCTION DETAILS. The construction requirements shall be as specified in the special
specifications.
406-4 METHOD OF MEASUREMENT. As specified in the special specifications.
406-5 BASIS OF PAYMENT. As specified in the special specifications.
SECTION 407 - TACK COAT
407-1 DESCRIPTION. This work shall consist of preparing and treating an existing Portland cement
concrete surface or asphalt pavement surface with tack coat in accordance with the Contract documents and as directed by the Engineer.
407-2 MATERIALS. The tack coat shall meet the applicable requirements of §702. Use of alternative
tack coat material requires prior approval by the Director, Materials Bureau.
407-3 Construction Details.
407-3.01 Equipment. A distributor shall be used for applying tack coat. The distributor shall be capable
of applying the tack coat uniformly on variable widths of surface up to 15 feet. The distributor equipment shall include a quantity measuring system and a thermometer for measuring temperature of tank contents. Prior to being used on a project, this equipment shall be calibrated in accordance with ASTM D 2995 Standard Practice for Estimating Application Rate of Bituminous Distributors or an equivalent calibration procedure acceptable to the Engineer . The Engineer will witness the equipment calibration or require the Contractor to provide documentation certifying the calibration. Distributors shall be equipped with circulation spray bars which shall be adjustable both laterally and vertically. An attached bristle broom that drags on the pavement behind the spray bars may be attached to the distributor. If the broom is used, it shal l be adjustable laterally and vertically so that the full width of the applied tack coat is bristled uniformly into the pavement surface. A bituminous material sampling valve shall be attached to the distributor. The distributor tank shall be equipped with an agitator that is capable of ensuring the tack coat remains homogeneous. Tack coat stored in the distributor tank shall be heated and maintained at a temperature between 85ºF and 160ºF. Hand operated spray units will be permitted only in areas where the use of a distributor is impractical. The Engineer will determine the final acceptance of all equipment used for applying the tack coat.
407-3.02 Application of Tack Coat. The tack coat contained in the distributor tank shall be
homogeneous. The tack coat shall be applied to a prepared clean pavement. Material shall be applied uniformly across the width of the designated area. The tack coat shall not be applied on a wet pavement surface or when the pavement surface temperature is below 40°F. The application rate shall be as determined in Table 407 -1 Tack Coat Application Rates . These are recommended application rates for tack coat on various surface types and may be modified by the Engineer.