(Last Revised May 1, 2024)
680-1DESCRIPTION
680-1.01General. The work mentioned in this section shall consist of furnishing and installing new
traffic signal equipment in accordance with the contract documents, standard specifications, and traffic signal standard sheets. Definitions. The following definitions shall apply to all work, equipment, and materials included under this section: 680-1.01 337 Section 600 STANDARD SPECIFICATIONS (USC) January 1, 2026 VOLUME 3
Disabilities Act (ADA).
consisting of a control unit, batteries, and wiring harness, that provides emergency power to a traffic signal system.
cabinet.
power to generator supplied electric power and functions as an electrical disconnect as well.
electronic device that can sense the passage or presence of moving or stationary vehicles by a change in the electrical inductance characteristics of the wire loop.
electrical power cable, communication cable, etc. The messenger cable can be a separate cable or can be integrated with the other cable types.
assigned to an independent traffic movement or combination of movements.
emitters.
housed in a weatherproof enclosure.
programming that maximizes traffic flow at a signalized intersection.
controlling one or more traffic movements on a single approach.
traffic movements on one or more approaches.
latest color code system.
designed to provide precise lane control and high visibility to all vehicles entering the signalized intersection.
680-2.01 338 Section 600 STANDARD SPECIFICATIONS (USC) January 1, 2026 VOLUME 3
with necessary components to be used for displaying one signal indication.
indications, without reflector, lens, and lamp receptacle.
signal indications, without reflector, reflector ring, lens, and lamp receptacle.
680-2MATERIALS
680-2.01General. The components used in the construction of new or rebuilt traffic signal systems shall
meet the requirements of the following subsections included under §700 — Materials and Manufacturing: Bar Reinforcement, Grade 60 709-01 Pullbox Covers, Iron Castings 715-05 Breakaway Transformer Base (Aluminum) 723-15 Rigid Plastic Conduit 723-19 Metal Steel Conduit, Zinc Coated 723-20 Galvanized Steel Conduit (P.V.C. Coated) 723-23 Flexible Liquid-Tight Steel Conduit 723-24 Precast Reinforced Concrete Foundations and Pullboxes 723-45 Ground Wire 723-75 Signal Cable 724-01 Span Wire 724-02 Traffic Signal Poles 724-03 Vehicular and Pedestrian Traffic Signal Heads 724-04 Traffic Signal LED Indications 724-05 Traffic Signal Head with Optically Programmed Indications 724-06 Traffic Signal Head Mounting Hardware and Backplates 724-07 Shielded Communication Cable 724-08 Signal Cable with Integral Messenger 724-09 Shielded Communication Cable with Integral Messenger 724-10 Traffic Signal Pole Mounting Hardware 724-11 Traffic Signal Vehicle and Pedestrian Detectors 724-12 Electrical Service Disconnect/Generator Transfer Switch 724-13 Electrical Service Cable 724-14 Fire Pre-emption Tell-Tale Light 724-15 Inductance Loop Wire 724-20 Shielded Lead-in Cable 724-21 Roadway Loop Embedding Sealer 724-22 Pedestrian Push Button 724-23 Pedestrian Push Button Station 724-24
680-2.02Concrete. All concrete for cast-in-place pullboxes, signal pole foundations and controller
cabinet bases shall meet the appropriate mix design requirements specified in Table 2 of Materials Procedure (MP) 501-2 Mix Design and Approval Procedure for Performance Engineered Mixtures – Structural Concrete, except requirements for inspection facilities, automated batching controls and recordation do not apply. The batching, mixing, and curing methods and the inspection facilities shall 680-2.03 339 Section 600 STANDARD SPECIFICATIONS (USC) January 1, 2026 VOLUME 3 meet the approval of the Department or its representative. For situations which require depositing structural concrete under water, provide tremie concrete in accordance with the appropriate mix design requirements as specified in Table 2 of MP 501-2. All precast concrete pullboxes, signal pole foundations and controller cabinet bases shall be in accordance with §723-45 Precast Reinforced Concrete Pullboxes.
680-2.03thru 680-2.07 (Vacant)
680-2.08Contractor Responsibility with Utilities. (None Specified)
680-2.09(Vacant)
680-2.10Foundation Excavation and Concrete Foundation. Shall be in accordance with §680-2.02
Concrete.
680-2.11Traffic Signal Poles. Shall be in accordance with §724-03 Traffic Signal Poles
680-2.12Traffic Signal Grounding Systems. Necessary materials of a grounding system including
grounding rod, conduit, ground wire, and pullbox shall be in accordance with the contract documents.
680-2.13Conduit. Shall be in accordance with §723 -19 Rigid Plastic Conduit through §723-24 Flexible
Liquid-Tight Steel Conduit.
680-2.14Pullboxes. Shall be in accordance with §680-2.02 Concrete and §723-45 Precast Reinforced
Concrete Foundations and Pullboxes. Pullboxes of other material types shall be as specified in the contract documents.
680-2.15Signal Control Cable and Shielded Communication Cable. Shall be in accordance with §724-
01 Signal Cable and §724-08 Shielded Communication Cable.
680-2.16Cable Splices. (None Specified)
680-2.17Span Wire Assembly. S hall be in accordance with §724 -02 Span Wire. The hardware
requirements for this assembly shall be in accordance with §724-03 Traffic Signal Poles.
680-2.18Messenger Assembly. Shall be in accordance with §724-02 Span Wire
680-2.19Guy Assembly. Shall be in accordance with §724-02 Span Wire
680-2.20Riser Assembly. Shall be in accordance with §723-20 Metal Steel Conduit, Zinc Coated
680-2.21Vehicular and Pedestrian Traffic Signal Bracket and Mounting Assembly. Shall be in
accordance with §724-04 Vehicular and Pedestrian Traffic Signal Heads and §724-07 Traffic Signal Head Mounting Hardware and Backplates.
680-2.22Wiring Color Code. (None specified)
680-2.23Pedestrian Push Button and Sign. Shall be in accordance with §724-23 Pedestrian Push Button
680-2.24 340 Section 600 STANDARD SPECIFICATIONS (USC) January 1, 2026 VOLUME 3
680-2.24Fire Pre-Emption Tell-Tale Light. Shall be in accordance with §724-15 Fire Pre-emption Tell-
Tale Light.
680-2.25Flashing Beacon Sign Assembly. Shall be in accordance with §CHAPTER 18 - Detailed
Specifications for School Zone Flashing Sign Beacon Assembly – Solar Powered of Transportation Management Equipment Specifications (TMES). The flashing beacon sign assembly consists of the following: Traffic Signal Pole. Shall be in accordance with §724-03 Traffic Signal Poles. Traffic Signal Head. Shall be in accordance with §724 -04 Vehicular and Pedestrian Traffic Signal Heads. Pedestrian Push Button (if required). Shall be in accordance with §724-23 Pedestrian Push Button Sign Panel. Shall be in accordance with §645 Signs. Flasher Cabinet. Shall be in accordance with Transportation Management Equipment Specifications
Breakaway Transformer Base (if required) . Shall be in accordance with §723 -15 Breakaway Transformer Base (Aluminum). Solar Power System (if required). Shall be in accordance with §680-2.27 Solar Power System. School Zone Flashing Beacon (if required). Shall be in accordance with Transportation Management Equipment Specifications (TMES) Chapter 18.
680-2.26Inductance Loop Installation. Shall be in accordance with §724-20 Inductance Loop Wire
680-2.27Solar Power System. This solar power system shall be used in flashing beacon sign assemblies
(This would include school zone flashing beacons, warning, and truck inspection signs). • Operating Temperature shall be -35 to 165 °F • Operates at rated usage for a minimum of 30 days without solar charging at an ambient temperature of 23 °F. • Battery and solar panel sizing shall be based on no more than 3.5 kWh/m² per day of solar insolation. • The solar panel shall be tiltable for operation and shall be adjustable to enable a southerly orientation without any additional hardware. • The solar panel housing shall be anodized, or powder coated aluminum. • The system shall be designed to be mounted to a standard 4.5-inch-diameter traffic pole or a type B signpost. • Mounting brackets for solar panels shall be ductile iron or 6061-T6 powder coated aluminum and painted to match the signal head color. • Solar Power System shall include battery (rated for cold temperatures), solar panel, charge controller which prevents overcharging and pole mounted battery box. Battery system shall be 12 VDC. • All wiring shall be 14 AWG stranded; 600 V rated wire. • The enclosure shall be equipped with a grounding lug and shall be tied to earth ground by a 6 AWG stranded, 600 V rated wire. • Wire routing shall be internal to the unit and pole attachment. No exposed conductors shall be permitted. • Battery and electronics shall be enclosed in a ventilated, anodized or powder coated aluminum enclosure. 680-2.28 341
Section 600 STANDARD SPECIFICATIONS (USC) January 1, 2026 VOLUME 3
680-2.28Meter Pan. The power meter pan shall be U.L. listed, in accordance with the electrical utility
standards, be self-contained, and have a hinged door enclosure equipped with a locking hasp. All meter pan fittings shall be weather tight. The meter pan shall be rated: • 120/240 volts single phase, 200 amps, or as directed by the Utility • Constructed out of Type NEMA 3R galvanized steel painted or powder coated with bypass facilities.
680-2.29Traffic Signs. Shall be in accordance with §645 Signs
680-2.30Field Galvanizing. Shall be in accordance with §719-01 Galvanized Coatings and Repair
Methods. 680-2.31. Rectangular Rapid Flashing Beacon (RRFB). RRFB unit shall consist of two rapidly flashed, rectangular-shaped yellow indications with an LED-array-based light source. It shall be designed, located, and operated in accordance with the detailed requirements of the contract documents.
680-2.32Signal Operation Tests. (None Specified)
680-2.33Accessible Pedestrian Signal (APS). Shall be in accordance with §724-12 Traffic Signal
Vehicle and Pedestrian Detectors, §724-23 Pedestrian Push Button, §724-24 Pedestrian Push Button Station and §730-01 Aluminum Sign Panels. In addition to the above references, the APS shall consist of a Central Control Unit (CCU) and Accessible Pedestrian Push Button Stations (PBS). The System shall meet the functionality requirements of the MUTCD. The Accessible Pedestrian Push Button Station shall be ADA compliant. It shall contain all electronic control equipment, Audible-Tactile push button, 9-inch by 15-inch informational pedestrian sign (MUTCD # R10-3E), all mounting hardware and bracket assembly. The Audible-Tactile push button shall be designed to provide both a button with a raised, directional, vibrating tactile arrow on the button and a variety of audible sounds for different pedestrian signal functions. The unit shall have a weatherproof speaker and the appropriate informational sign for each location. Environmental Requirements • Speaker with microphone shall be non-visible and located in a PBS. • PBS enclosure shall meet NEMA 250-Type 4X E. • APS unit shall be operational within the temperature range: -35 to 165 °F. • APS unit temperature and humidity requirements shall meet NEMA TS 2 Section 2.1. • CCU enclosure shall meet NEMA 250-Type 1. • Mechanical shock and vibration requirements shall meet NEMA TS 2 Section 2.1. Electrical Requirements • Voltage protection requirements shall meet NEMA TS 2 Section 2.1. • Transient suppression requirements shall meet IEC 61000-4-4, ICC 61000-4-5. • Electronic noise requirements shall meet FCC Title 47, Part 15, Class A. • Electrical reliability requirements shall meet NEMA TS4 (Applicable Portions of Section 8). 680-2.34 342 Section 600 STANDARD SPECIFICATIONS (USC) January 1, 2026 VOLUME 3 • The LED on the button shall illuminate when the button is pushed and remain illuminated until the next walk phase. • LED luminous intensity shall be greater than 1200 mcd. • The LED on the button shall be sunlight visible, ultra-bright red and shall have a viewing angle of 160 degrees. Audio and Sound Requirements • The volume of audible walk indications and pushbutton locator tones should be set to be a maximum of 5 dBA louder than ambient sound. • Automatic volume adjustment in response to ambient traffic sound level shall be provided up to a maximum volume of 100 dBA. • Microphone for ambient noise shall have an approximate frequency range of 0.17 to 2.3 kHz • Button tone shall be a brief audible “tick” confirming each button push • Audible locating tone shall be 880 Hz plus harmonic, 0.1-second duration, 1-second interval and shall operate during pedestrian clearance and “Don’t Walk” interval. • The system shall provide the following audible features: a locating tone, 5 Walk sound choices, 3 pedestrian clearance sound choices, direction of travel, user programmable informational message and an audible sound must emanate from the push button. • The system shall provide an audible “Wait” message that plays once the button is activated.
680-2.34Traffic Signal Battery Backup System. Shall be in accordance with the Transportation
Management Equipment Specifications (TMES) Chapter 19.
680-2.35thru 680-2.36 (Vacant)
680-2.37Vehicular and Pedestrian Traffic Signal LED Module. Shall be in accordance with §724-05
Traffic Signal LED Indications.
680-2.38Watertight Disconnect Box. Shall be in accordance with §724-13 Electrical Service
Disconnect/Generator Transfer Switch
680-2.39Generator Transfer Switch. Shall be in accordance with §724-13 Electrical Service
Disconnect/Generator Transfer Switch
680-3CONSTRUCTION DETAILS
680-3.01General. Unless waived, the Contractor shall submit detailed specifications, catalog cuts, parts
lists, instruction sheets, and shop drawings of the equipment and materials proposed for installation to the Engineer within 30 days following the award of the contract.
680-3.02Concrete. The batching, mixing, and curing methods, sample testing, e.g., slump testing, cylinder
samples, etc., and the inspection facilities shall meet the approval of the Department or its representatives and shall be in accordance with §501 Portland Cement Concrete - General. All precast concrete items shall be inspected as soon as they arrive at the construction site and shall be rejected if significant flaws or damage is detected. The precast concrete items shall be stored out of the way, so they do not incur damage. If damaged, precast concrete items will be rejected by the Engineer, and shall be removed from the site. For concrete poured in cold weather, it shall be in accordance with §555-3.08 Curing. 680-3.03 343 Section 600 STANDARD SPECIFICATIONS (USC) January 1, 2026 VOLUME 3
680-3.03thru 680-3.07 (Vacant)
680-3.08Contractor Responsibility with Utilities. All attachments to utility company poles shall be
made in accordance with the specifications and subject to the inspection of the utility companies owning the poles. The height of all proposed attachments above the ground and their locations on the poles shall be in accordance with the plans, standard sheets or as directed by the Engineer and shall meet the approval of the utility companies owning the poles. The Contractor shall protect all property and materials of the utility companies and shall be responsible for the repair or replacement of any damaged material or property. In the event that the point of attachment or location of the risers is such that the risers interfere with or do not provide proper clearance with existing utility company attachments, the Engineer, in consultation with the utility companies owning the poles, shall make the necessary adjustments in heights and location to eliminate such interference.
680-3.09(Vacant)
680-3.10Foundation Excavation and Concrete Foundation. All excavation shall be in accordance with
§206 Trench, Culvert and Structure Excavation . All excavation shall be backfilled as specified in §203-
3.13Select Structural Fill . All surplus excavation material shall be removed and disposed of by the
Contractor as specified in §203-3.02 Disposal of Surplus Excavated Material . The concrete foundations shall be as follows:
design computations, sealed, and signed by a Professional Engineer, for all traffic signal poles. The contractor shall confirm the size of the foundation needed is based off the design of the traffic signal pole needed. All foundation sizes shall be constructed as shown in the contract documents. The Engineer will have a minimum of twenty-one (21) calendar days for one (1) pole, and an additional two (2) days for each additional pole for review. The Contractor shall not start construction of the foundations for those traffic signal poles until the Engineer's review of the submittal is completed. If the Engineer’s review of a signal pole's design indicates a problem(s) exists, the Contractor will be notified within the time allotted for the review. In these cases, a meeting will be held between the Engineer and the Contractor to resolve the Engineer's concerns. Prior to excavating for pole placement and after locating all existing underground facilities, the Contractor shall dig a minimum 4 feet deep test pit at the proposed location of each pole. If obstructions are encountered the Contractor shall properly backfill the test pit and move to a new location as directed by the Engineer. All test pits shall be excavated and backfilled and paid in accordance with §206-3.05 Test Pits. The Contractor has the option to use cast-in-place or precast concrete foundations for the signal poles. If the Contractor elects to install a cast-in-place foundation, the signal pole may be installed on the foundation three (3) days after foundation placement. The span wire and signal heads shall not be installed until the concrete cylinder strength reaches at least 3000 psi. The Contractor shall assist the Engineer in making a requested number of test cylinders of the foundation concrete, store these cylinders at the location as directed by the Engineer, and transport these cylinders to a State testing facility. If the Contractor elects to use precast foundation, the contractor shall backfill the hole and be in accordance with §203-2.06 Select Granular Fill. For drilled shaft foundations under no circumstances shall temporary casing be left in place. All temporary casing shall be removed as the concrete is placed. 680-3.11 344 Section 600 STANDARD SPECIFICATIONS (USC) January 1, 2026 VOLUME 3 Holes shall contain no free water, nor any loose material at the time of concrete placement. Concrete shall meet the appropriate mix design requirements of Table 2 of MP 501-2. If unable to dewater the shaft and place concrete due to the presence of groun dwater and loose cohesionless soil at the base of the drilled shaft, proceed with the installation by not dewatering the shaft excavation and place tremie concrete meeting the requirements specified in Table 2 of MP 501 -2 and in accordance with §555-3.05 Depositing Structural Concrete Under Water. The bottom of the shaft excavation shall be cleaned of loose material to the satisfaction of the Engineer immediately prior to concreting
installed and constructed in accordance with the details specified in the contract documents.
accordance with the details specified in the contract documents.
680-3.11Traffic Signal Poles
signal pole locations shown on the contract documents shall be field checked for any condition that may affect their placement. Where changes are necessary, the exact location will be determined by the Engineer. Traffic signal poles shall be inspected for flaws or damage prior to being installed. If any flaws or damage is detected, poles shall be rejected, and replacements ordered. When field conditions require a change in traffic signal pole position from that shown in the contract documents, the traffic signal pole length requirements may vary. It shall be the Contractor’s responsibility to verify traffic signal pole length before ordering poles. Traffic signal pole installation shall include installation of horizontal shafts of monotube traffic signal pole structures, mast arms, and attachment of fittings as specified in the contract documents as follows:
installation, if mounted on a traffic signal pole.
span wire assembly.
poles and span wires to multi-sided poles.
Anchor Bolt Design and Torque Values and mast arm to pole connection bolts shall meet the tension requirements listed in accordance with §680-3.11 c – High Strength Bolt Tension Values. Each mast arm to pole connection bolt shall be furnished with a galvanized flat washer. In addition, the Engineer may require the contractor to submit, at any time, design computations for any or all of the traffic signal poles in the contract documents. The design computations must 680-3.11 345 Section 600 STANDARD SPECIFICATIONS (USC) January 1, 2026 VOLUME 3 be approved, stamped, and signed by a professional engineer licensed in New York State. The Engineer shall have twenty (20) working days to review the design computations for one traffic signal pole, and an additional two (2) days for each additional signal pole. If the Engineer’s review of a pole's design indicates a problem(s) exists, the Contractor will be notified within the time allotted for the review. In these cases, a meeting will be held between the Engineer and the Contractor to resolve the Engineer's concerns.
Anchor bolt and anchor plate size, length, and layout shall be designed by traffic signal fabricator. The connection of the pole to the foundation shall be a single-nut moment connection. Beeswax, or equivalent, shall be applied to the bearing face, the threads on the anchor bolt above the base plate and the threads inside the nut above the base plate. ASTM F1554 Grade 105 is allowed for Span Wire Poles, Pedestrian Poles and Monotubes. ASTM F1554 Grade 105 anchor bolts are not allowed for mast arm poles because they are subject to fatigue loading. Alternate methods of bolt tightening will be allowed as long as the Engineer can verify the torque values. The torque values in the table below are calculated as per Section 6.9 of FHWA Guidelines for the Installation, Inspection, Maintenance and Repair of Structural Supports for Highway Signs, Luminaires, and Traffic Signals, March 2005 Version. Anchor Bolt Torques Anchor Bolt Diameter
ASTM F1554 Grade 36 ¾ 80 1 190 1 ¼ 380 1 ½ 650 1 ¾ 1000 2 1550 2 ¼ 2300 2 ½ 3000 ASTM F1554 Grade 55 ¾ 120 1 290 1 ¼ 580 1 ½ 1000 1 ¾ 1600 680-3.12 346 Section 600 STANDARD SPECIFICATIONS (USC) January 1, 2026 VOLUME 3 2 2400 2 ¼ 3500 2 ½ 4800 ASTM F1554 Grade 105 (Not allowed for Mast Arm Poles) ¾ 200 1 490 1 ¼ 960 1 ½ 1700 1 ¾ 2650 2 4000 2 ¼ 5800 2 ½ 8000
High Strength ASTM F3125 Grade 325 bolts are used for mast arm to pole connections. The table below and its values are from Table 1003.1 in Section 10 of NYS Steel Construction Manual, 4th Edition. Minimum Bolt Tension (ASTM F3125 Grade 325) Bolt Diameter (inches) Minimum Bolt Tension* in Thousands of Pounds (kips) ½ 12 5/8 19 ¾ 28 7/8 39 1 51 1 1/8 64 1 1/4 81 1 3/8 97 1 ½ 118 * Equal to 70 percent of specified minimum tensile strengths of bolts, rounded off to the nearest kip.
680-3.12Traffic Signal Grounding System. The Contractor shall install copper-clad ground rods, #6 bare
ground wire, and fittings as shown in the contract documents. The traffic signal grounding system shall be a closed loop system to tie all ground rods together in the intersection and be electrically connected to the grounding lug on the pole or traffic signal cabinet. The traffic signal grounding system, when comple ted, shall be tested in accordance with §680-3.32 Signal Operation Tests. If the requirements of this test are not 680-3.13 347 Section 600 STANDARD SPECIFICATIONS (USC) January 1, 2026 VOLUME 3 met, the contractor shall repair or install additional ground rods, longer ground rods, electrical bonding of metallic conduit, or other grounding measures may be required.
680-3.13Conduit. Underground conduit installations shall have a minimum cover of 18 inches except
under roadways, where the minimum cover shall be 24 inches. Excavation for the installation shall be performed in accordance with §206 Trench, Culvert and Structure Excavation. The conduit shall be laid on a uniform grade to allow any condensation to drain to pullboxes or “T” drains. Conduit shall be backfilled in accordance with §203-3.06 Select Granular Fill. In rock excavations, the Contractor shall place and tamp a bedding of select backfill before laying the conduit. Conduit may be placed under pavement by trenchless installation methods in accordance with in §650 Trenchless Installation of Casing. Pavement shall not be disturbed without permission of the Engineer. In the event obstructions are encountered, small test pit may be cut in the pavement upon approval of the Engineer. Trenchless installation test pits shall be kept 2 feet from the edge of pavement and shoulder whenever possible provided that the conduit is not damaged in the process. All bends in conduit shall be made without kinking, flattening, or appreciably reducing the internal diameter of the conduit. A hydraulic or power pipe bender shall be employed for all bends in steel conduit. Any evidence of destruction of the protective coating will be cause for rejection. All connections in metallic conduit shall be tight. Ends of conduit shall be reamed to remove burrs and rough edges. Conduit ends in pullboxes, junction boxes, cabinet, etc. shall be equipped with insulating bushings. All couplings and bushings shall be mechanically threaded. Compression or slip type couplings or bushings shall not be allowed. All metallic conduits shall be bonded with a #6 bare stranded copper ground wire. All conduits installed shall be tested for clear bore and correct installation by the Contractor in the presence of the Engineer. After installation and testing, contractor shall furnish and install in each conduit run, a No. 10 AWG galvanized steel drag wire, nylon or polypropylene rope with a tensile strength at least 500 lb. with a minimum three feet of extra wire or rope left at each end. Empty conduit shall be temporarily sealed by the Contractor.
680-3.14Pullboxes. Pullboxes shall be constructed and installed in accordance with the contract
documents. Placement of pullboxes in drainage swales or other runoff areas shall be avoided and if located in a drainage swale in the contract drawings the contractor will notify the EIC of the issue so a more suitable location can be chosen. When a pullbox is required to be placed in sidewalk, the affected slab(s) shall be removed and replaced in kind and shall be set flush with the sidewalk. Pullboxes shall be precast concrete or cast-in-place concrete and shall be either round or rectangular as shown in the contract documents. Precast pullboxes shall be in accordance with §723-45 Precast Reinforced Concrete Foundations and Pullboxes . Cast-in-place concrete pullboxes shall be in accordance with §501 Portland Cement Concrete – General. Cast iron frames and covers shall be as shown in the contract documents and be installed on each pullbox. Cast iron frames and covers shall be set in mortar in accordance with §705 -21 Masonry Mortar, placed true to line and grade, and make full and even bearing on the underlying surface. Frames and covers that do not fit together properly, will be rejected by the Engineer, and shall be removed from the site.
680-3.15Signal Cable and Shielded Communication Cable. All terminal connections shall be made with
approved solderless plugs of the proper size using a crimping tool that is self -releasing when proper compression has been applied. The Contractor shall use connectors that provide continuity and physical contact around the circumference of the connector and conductor. Cable shall be installed to form a continuous circuit between the proper equipment terminals. During installation of the cable, the Contractor shall take care not to damage conductors, insulation, or outer covering. The length of cable installed shall not cause excessive stress on the conductors or any part of the cable. 680-3.16 348 Section 600 STANDARD SPECIFICATIONS (USC) January 1, 2026 VOLUME 3 An insert lubricant shall be used when placing cable in conduit. Cable shall be pulled through conduit by hand. The use of winches or other power actuated pulling equipment shall not be permitted. Between three and five feet of slack shall be left for each cable at each pullbox or junction box. Short bends of cable shall be avoided inside pullboxes. Cable in pullboxes or junction boxes shall not cross over any other cables already in place or block any conduit. All cable shall be identified as to function in each pullbox, junction box, or cabinet by aluminum, brass, or plastic cable markers. If a wire numbering system is used for identification, the key to the system shall be placed along with the wiring diagram in the traffic signal cabinet. Conductors in traffic signal cabinets shall be dressed neatly with tie wraps. Spare conductors shall be taped and coiled neatly in the bottom of the traffic signal cabinet. Ends of spare conductors shall be taped. Field wiring entering traffic signal cabinets shall be identified as to function. Splices in shielded communication cable will not be permitted between equipment terminals. Where cable is installed on span wire or messenger cable, the wire or cable shall be supported, at intervals not greater than 16 inches, by messenger rings or other non-corrosive metal lashing. Taping and plastic cable ties shall not be permitted. Integral messenger cable shall be installed in accordance with the contract documents. When integral messenger cable is installed on Utility poles, the Contractor shall make all arrangements with the Utility for the installation. The Contractor shall obser ve all Utility requirements for attachments to poles and clearances with Utility facilities. The Contractor shall notify the Utility prior to start of the work and observe the Utility requirements for accomplishment of the work. All necessary hardware used with integral messenger cable shall develop the full breaking strength of the integral messenger wire. Poles at each end and at each change of direction shall be guyed as specified in the contract documents. When installed on Ut ility poles, guy wires shall be installed as directed by the Utility. Fused wiring and cables shall always be separated from unfused wiring and cables.
680-3.16Cable Splices. Cable splices shall be permitted only in pullboxes, and utility manholes. All cable
runs between units of equipment shall be without splices. Conductors in traffic signal cabinets shall not be spliced. Splices in overhead cable for new signal installations or signal rebuilds shall not be allowed. Splices in overhead cable, when necessary, shall be made with the approval of the Engineer. All splices shall be capable of satisfactory operation under continuous submersion in water. Multi- conductor cables shall be spliced and insulated to provide a watertight joint and to prevent absorption of moisture by the cable. Moisture shall be excluded from the joint during the splicing operation and the work shall be done in dry weather or under shelter. All materials and tools involved in the splicing process shall be kept dry. One of the following methods shall be used for making a watertight and electrically insulated splice: Method No. 1. The outer covering and insulation of the conductor shall be removed from each conductor for a minimum length necessary for the use of a pressure release crimping tool. The conductor ends shall be bared and joined with a seamless, solderless-type sleeve connector of the same AWG size as the conductor being spliced, using a pressure-release crimping tool designed for the size connector being used. After crimping, the sleeve connector shall maintain proper contact with both conductors around the circumference of the splice and along the length of the sleeve. The portion of each conductor where insulation has been removed, and the sleeve connector, shall be reinsulated with a coat of fast-drying sealing agent of electrical grade, a tight wrap of overlapping layers of rubber tape, a second coat of fast-drying sealing agent of electrical grade, and then a tight wrap of overlapping layers of polyvinylchloride tape. The sealing agent and tape shall extend at least 1 inch onto the undisturbed insulation of each conductor. Layers of tape shall be applied on the splice to equal 1.5 times the thickness of the original insulation. 680-3.17 349 Section 600 STANDARD SPECIFICATIONS (USC) January 1, 2026 VOLUME 3 Rejacketing the cable shall be accomplished in a similar manner as described in Method No. 1 except that the sealing agent and tape shall extend at least 4 inches onto the undisturbed outer covering of each cable. Individual splices in each conductor shall be staggered to minimize the outside diameter of the spliced cable. Method No. 2. All the requirements for splicing specified in Method No. l shall apply except that the completed splice, including sleeve connector and the portion of each conductor where the insulation has been removed, shall be reinsulated and the cable rejacketed by using an acceptable mold poured full of a two-component, electrical-insulating resin. The resin shall produce satisfactory pouring consistency without applying external heat. The resin shall be mixed and applied per the manufacturer’s directions. Method No. 3. This method shall be accomplished by use of a weatherproof or waterproof splice connector/splice box. Splicing shall be accomplished by following the splice connector/splice box manufacturer’s instructions. This method shall be considered as the preferred method, as it requires less installation time and material, compared to the other two methods listed above.
680-3.17Span Wire Assembly. Span wire assemblies, including necessary hardware, shall be installed in
accordance with the contract documents. Span wire assemblies shall be single span wire, dual span wire with upper tether, or dual span wire with lower tether. The Contractor shall determine the span and tether wire diameter based upon traffic signal pole design load using the table on standard sheet 680 -07. All necessary hardware for attaching span and tether wires to the poles shall develop the full breaking st rength of the span or tether wire. Breakaway links for lower tether wires shall develop the strength specified on the standard sheets. The span wire shall be looped around each traffic signal pole and secured by clamps as shown in the standard sheets. Sag shall be at least 5 percent of the span when the traffic signal system installation, including overhead signs, is complete. The Contractor shall ensure that proper clearance is maintained between the installed span wire and any nearby Utility facilities in accordance with the contract documents. If proper clearance cannot be maintained, the Contractor shall work with the local Utility to ensure the Utility facility is properly insulated and protected. Contractor shall notify the Engineer in this situation.
680-3.18Messenger Assembly. The messenger assembly shall be installed in accordance with the contract
documents. When a messenger assembly is installed on Utility poles, the Contractor shall make all arrangements with the Utility for the installation. All necessary hardware used with the messenger assembly shall develop the full breaking strength of the messenger cable. Traffic signal poles at each end, and poles at each change of direction along the run of messenger, shall have guy wires installed as s pecified in the contract documents. When installed on Utility poles, guy wires shall be installed where required by the Utility. The signal control cable shall be fastened to the messenger cable at intervals of 16 inches or less by messenger rings, stain less steel cable straps, or other non-corrosive metal. Taping and plastic cable bands shall not be permitted.
680-3.19Guy Assembly. Guy wire shall be installed in accordance with the contract documents. Guy
assemblies on Utility poles shall meet the Utility requirements. Excavation for the guy wire anchor shall be of the minimum width possible to accept the unexpanded anchor. Backfill shall be compacted as specified in the contract documents. 680-3.20 350 Section 600 STANDARD SPECIFICATIONS (USC) January 1, 2026 VOLUME 3
680-3.20Riser Assembly. Riser assemblies and weatherheads shall be installed and constructed in
accordance with the contract documents. Riser assemblies on Utility poles shall meet the Utility requirements.
680-3.21Vehicular and Pedestrian Traffic Signal Bracket and Mounting Assembly. Traffic signal
heads shall be installed as specified in the contract documents. Each traffic signal head shall be assembled from the signal sections and brackets in the configuration specified in the contract documents. Traffic signal heads shall be properly aligned. All mounting hardware shall be securely tightened to prevent loosening by the wind. Polycarbonate traffic signal heads shall have steel reinforcing plates installed inside the top of the top section for span wire installations or on the inside bottom of lowest section of post top mounted signals. All traffic signal head assemblies are to be directly wired to the traffic signal cabinet. Until traffic signal heads are placed in operation, they shall be bagged with opaque material and shall be adequately secured in a neat and orderly manner. The existing signal heads cannot be blocked by the new signal heads at any point during construction. Traffic signal heads with optically programmed indications shall be installed, directed, and veiled in accordance with the manufacturer's instructions and the contract documents. LED traffic or pedestrian signal modules that are supplied by the State shall be installed in traffic or pedestrian signal heads as shown in the contract documents. When the Contractor is required to furnish the LED modules, unless otherwise waived, the Contractor shall provide LED modules that are in accordance with §724-05 Traffic Signal LED Indications . Backplates for traffic signal heads shall be installed as specified in the contract documents.
680-3.22Wiring Color Code. The following wire color code system, unless otherwise shown on the
plans, shall be used for wiring signal heads. Signal cable conductor colors shall be as defined in IMSA specification number 20-1 and as shown below. CONDUCTOR COLORS AND SEQUENCE FOR CABLES Conductor No. Base Color Tracer Color 1 Black 2 White 3 Red 4 Green 5 Orange 6 Blue 7 White Black 8 Red Black 9 Green Black 10 Orange Black 11 Blue Black 12 Black White 13 Red White 14 Green White 15 Blue White 680-3.22 351 Section 600 STANDARD SPECIFICATIONS (USC) January 1, 2026 VOLUME 3 16 Black Red 17 White Red 18 Orange Red 19 Blue Red 20 Red Green 21 Orange Green
Coded Wire for Signal Heads: PRIORITY FUNCTION PRIORITY FUNCTION 1 Phase 2 8 Phase 3 2 Phase 6 9 Overlap No. 1 3 Phase 5 10 Overlap No. 2 4 Phase 1 11 Overlap No. 3 5 Phase 4 12 Overlap No. 4 6 Phase 8 13 Double Clearance No. 1 7 Phase 7 14 Double Clearance No. 2
cable sizes and simple signal indications. See contract plans for switch pack table assignment of wire colors for all faces and functions. COLOR-CODED WIRE GROUPINGS Cable Size Indication Priority 1 Function Priority 2 Function Priority 3 Function Priority 4 Function 5C R 14/5C-X-R* - - - Y 14/5C-X-O - - - G 14/5C-X-G - - - Ground 14/5C-X-W - - - 10C R 14/10C-X-R 14/10C-X-R/B - - Y 14/10C-X-O 14/10C-X-O/B - - G 14/10C-X-G 14/10C-X-G/B - - Ground 14/10C-X-W 14/10C-X-W/B - - 15C R 14/15C-X-R 14/15C-X-R/B 14/15C-X-R/W - Y 14/15C-X-O 14/15C-X-O/B 14/15C-X-BL/W - G 14/15C-X-G 14/15C-X-G/B 14/15C-X-G/W - Ground 14/15C-X-W 14/15C-X-W/B 14/15C-X-B/W - 680-3.22 352 Section 600 STANDARD SPECIFICATIONS (USC) January 1, 2026 VOLUME 3 19C R 14/19C-X-R 14/19C-X-R/B 14/19C-X-R/W 14/19C-X-B/R Y 14/19C-X-O 14/19C-X-O/B 14/19C-X-BL/W 14/19C-X-O/R G 14/19C-X-G 14/19C-X-G/B 14/19C-X-G/W 14/19C-X-BL/R Ground 14/19C-X-W 14/19C-X-W/B 14/19C-X-B/W 14/19C-X-W/R
WIRE COLOR CODE* INDICATION 14/2C-1-B Blue Light 14/2C-1-W Ground Wire
PED NUMBER WIRE COLOR CODE* INDICATION PED NUMBER WIRE COLOR CODE* INDICATION 14/7C-1P-R DONT WALK 14/7C-3P-R DONT WALK 14/7C-1P-G WALK 14/7C-3P-G WALK 14/7C-1P-B Switch Wire 14/7C-3P-B Switch Wire 14/7C-1P-O Switch Wire 14/7C-3P-O Switch Wire 14/7C-1P-W Ground Wire 14/7C-3P-W Ground Wire 14/7C-1P-BL Spare Wire 14/7C-3P-BL Spare Wire 14/7C-1P-W/B Spare Wire 14/7C-3P-W/B Spare Wire 14/7C-2P-R DONT WALK 14/7C-4P-R DONT WALK 14/7C-2P-G WALK 14/7C-4P-G WALK 14/7C-2P-B Switch Wire 14/7C-4P-B Switch Wire 14/7C-2P-O Switch Wire 14/7C-4P-O Switch Wire 14/7C-2P-W Ground Wire 14/7C-4P-W Ground Wire 14/7C-2P-BL Spare Wire 14/7C-4P-BL Spare Wire 14/7C-2P-W/B Spare Wire 14/7C-4P-W/B Spare Wire * Key for Wire Color Code: XX / XXC - X - X / X AWG No. of Cable No. Color Tracer Conductors For the Given of Wire Color Conductor Size Colors: R-Red, O-Orange, G-Green, BL-Blue, W-White, B-Black.
The following steps should be used to determine the appropriate color-coded wiring for a given signal installation:
680-3.23 353 Section 600 STANDARD SPECIFICATIONS (USC) January 1, 2026 VOLUME 3
to the function.
680-3.23Pedestrian Push Button and Sign. The ADA pedestrian push button and pedestrian information
sign shall be installed and constructed in accordance as shown in the contract documents. Pedestrian push button and sign shall be installed on either an existing pole, a newly installed signal pole , or its own post and footing. A pedestrian push button station (assembly of mounting bracket, pedestrian information sign, and ADA push button) may be substituted for a pedestrian push button and sign. The pedestrian push button shall be mounted between 3.5 to 4 ft. above an accessible surface and within 10 in of an adjacent accessible surface as shown in the contract documents. The indication shall be controlled by the push button at the marked or obvious crosswalk. The orientation of the pedestrian information sign and ADA pedestrian push button shall be parallel to the line of pedestrian travel.
680-3.24Fire Pre -emption Tell -Tale Light. The fire pre -emption tell -tale light shall be installed in
accordance with the contract documents. The fire pre-emption tell-tale light shall be wired to display a blue light during the emergency pre- emption interval and to remain unlit at all other times. The fire pre-emption tell-tale light shall be oriented on the traffic signal pole in the position that provides the best view for emergency vehicles as they approach the traffic signal location.
680-3.25Flashing Beacon Sign Assembly. The flashing beacon sign assembly shall be constructed as
shown in the contract documents. The pole shall be galvanized steel and installed as specified in the contract documents. The pole may be constructed from a bracket mount traffic signal pole. The sign panel shall be constructed in accordance with §645 – Signs. The flashing beacon signal indications, solid state flasher, and flasher cabinet shall be installed as shown in the contract documents. When not installed behind a guiderail, the pole shall be equipped with an approved breakaway base (or transformer base) fabricated in accordance with §723-15 Breakaway Transformer Base (Aluminum). The breakaway base shall be mounted on pavement or concrete as specified in the contract documents. Details of the school zone flashing beacon shall be in accordance with the contract documents. The school zone flashing beacon shall meet the operational requirements of individual school districts as well.
680-3.26Inductance Loop Installation. Inductance loops shall be installed in accordance with the contract
documents. Loop dimensions shall be as specified in the contract documents. Pullboxes, conduits, and curb cuts shall be completed before beginning the inductance loop installation. The inductance loop shall be outlined on the pavement to conform to the specified configuration. Immediately after sawing by either wet or dry methods, the sawcut and pavement shall be flushed with pressurized clean water to remove the saw slurry, dust, or other cutting debris. Compressed air shall be used to remove all dust and water from the sawcut. If the sawcut is damp, do not proceed with the installation until it is dry. Hot air may be used to dry the sawcut. At the edge of pavement or curb, a 1 -inch (minimum) diameter Steel Conduit, Zinc Coated Flexible Liquid-Tight Conduit, or Rigid Plastic Conduit shall be installed between the pavement and pullbox in accordance with the contract documents. The curb or pavement shall be cut or scored to leave a permanent mark to show where the conduit runs under the curb or pavement. The inductance loop wire shall be installed starting at the roadside pullbox, passed around the loop for the specified number of turns, and brought back to the pullbox. Splices shall not be permitted outside the pullbox. The wire shall be depressed in the sawcut without the use of sharp objects that might damage the wire insulation. The inductance loop shall be held in place at 2 feet intervals with 1 inch (approximate) strips of rubber, neoprene, flexible tubing, or foam backer rod. These hold down strips shall be left in place when the sawcut 680-3.27 354 Section 600 STANDARD SPECIFICATIONS (USC) January 1, 2026 VOLUME 3 is filled with Roadway Loop Embedding Sealer and shall be in compliance with §724 -22 Roadway Loop Embedding Sealer. The pair of inductance loop wires between the edge of pavement and the splice to the shielded lead-in cable in the pullbox shall be twisted together with two to five twists per foot. The splice between the inductance loop wires (twisted pair) and the shielded lead -in cable shall be moisture proof and shall have a dielectric strength at least equal to that of the original insulation. The bared conductor ends shall be joined with an appr opriate crimping tool using an un -insulated, size coded, solderless type connector of the correct size, or be twisted and soldered. The splice shall be reinsulated in accordance with Method No. 1 of §680-3.16 Cable Splices except that heat shrinkage polyolefin tubing may be used as an alternate to the rubber tape, and the first layer of PVC tape and sealing agent shall be extended as needed to cover 1 inch (minimum) of the inductance loop wire tube. The polyolefin tubing shall be at least as thick as the o riginal insulation. Upon completion of the re -insulating, a final waterproof coating shall be applied over the entire splice. As an alternative to the above, the Contractor should consider using Method No. 3 of §680-3.16 Cable Splices. The inductance loop wires (twisted pair) and the splice to the shielded lead-in cable within the pullbox shall be supported by wire hangers as near as possible to the top of the pullbox to prevent their immersion in water. The shielded lead-in cable shall be continuous (no splices) from the pullbox to the traffic signal cabinet terminals. The ground wire in the shielded cable shall be grounded at the traffic signal cabinet terminals only. The completed inductance loop installation, including the shielded lead -in cable to the traffic signal cabinet, shall have a minimum of 50 meg-ohms leakage resistance to ground. This resistance shall be tested in accordance with §680-3.32 Signal Operation Tests prior to sealing the loop. When it is determined that the resistance to ground requirements are met, the sawcut shall be filled with roadway loop embedding sealer. All work involving the sealer shall be done in compliance with the manufacturer's specifications. If the Roadway Loop E mbedding Sealer has set sufficiently to open the inductance loop to traffic, but its surface remains tacky, the inductance loop may be dusted with cement dust to facilitate opening the loop to traffic.
680-3.27Solar Power System. The Contractor shall furnish and install the Solar Power System unit at
the locations specified in the contract documents or other designated locations as specified by the Engineer. The Contractor shall submit to the Engineer for approval complete shop drawings, detailed specifications, catalog cuts, parts lists, instruction sheets, and wiring diagrams for the equipment to be installed. Solar Power System unit assembly shall be built in accordance with the details shown on the plans/Standard Specifications/standard construction sheets and as directed by the engineer. The Contractor shall install the Solar Power System, in accordance with the manufacturer’s recommendations, mount the solar assembly as shown in the contract documents. The Contractor shall adjust the position of the solar panel array in a manner that maximizes solar exposure. The solar array shall be oriented so that the maximum amount of energy is captured over the entire year. Documentation specifying the correct TILT angle and ORIENTATION (bearing) shall be given to the Engineer for inspection and verification prior to any installation. The solar panel array shall be positioned in a location that results in no shadows being cast on the solar panels at any time of the year. The Contractor shall consider the effects of leaves on trees, regardless of whether or not there are any leaves on trees at the time of installation. Any natural vegetation such as trees, bushes, or brush that may block the solar array shall be cleared and paid for under the appropriate contract items. The Contractor shall also have the appropriate tools, such as a compass and protractor, to verify that the panels have been correctly installed per manufactures recommendation for a given location. The details of physical installation of the Solar Power System unit and their cables, cabinet placement and solar panel details in relation to the field conditions shall be submitted and be accepted by the Engineer. 680-3.28 355 Section 600 STANDARD SPECIFICATIONS (USC) January 1, 2026 VOLUME 3 The Contractor shall maintain all furnished equipment and wirings/ cables in good working condition until system acceptance by NYSDOT and shall provide replacement, at no additional cost to the state, due to breakdown, damage, or theft within ten (10) working days.
680-3.28Meter Pan. The Contractor shall install a power meter pan as shown on the contract documents
The power meter will be furnished by the Utility. All power meter pan fittings shall be weather tight and waterproof with the use of duct seal or other means approved by the Engineer. The power cable for the traffic signal cabinet shall be pulled through the cabinet wall from the generator transfer switch with 6 feet of power cable slack neatly coiled in the traffic signal cabinet. The power meter pan and generator transfer switch shall be connected by a separate length of power cable. The Contractor shall be responsible for furnishing and installing suitable support hardware, channels, struts, rods, nuts and bolts as required for pole or pedestal mounting of the power meter pan as specified in the contract documents.
680-3.29Traffic Signs. All traffic sign panels shall comply with the MUTCD and §645—Signs. Traffic
signs shall be installed as specified in the contract documents. Each traffic sign shall be assembled with mounting brackets in the configuration specified in the contract documents. Traffic signs shall be aligned for proper visibility for the traveling motorist . All mounting hardware shall be securely tightened to prevent loosening by the wind. All electronic traffic signs shall be installed in accordance with manufacturer instruction and contract documents. The existing overhead signs cannot be blocked by the new overhead signs at any point during construction. New overhead signs shall remain covered until the day the new signal is to be turned on.
680-3.30Field Galvanizing. All abrasions of galvanized steel due to handling equipment, erection, etc.,
and all points of attachment, shall be field repaired as specified in §719-01 Galvanized Coatings and Repair Methods. Field galvanizing shall be done after all welding, drilling, etc., of the installed steel traffic signal poles, etc. has been completed.
680-3.31Rectangular Rapid Flashing Beacon (RRFB). Each RRFB shall conform to all provisions
of the §645 – Signs and §680 – Standard Sheets shall apply. Prior to any fabrication or installation of any of the components of the Flashing Beacon, the Contractor shall submit detailed specifications, parts lists, manufacturer’s cut sheets, instruction sheets, and wiring diagrams to the Engineer for approval at least 14 calendar days before installation. The Contractor shall install and position the beacon assembly in such a manner as to optimize visibility for roadway traffic, and optimize incident light for the solar assembly, using the manufacturer’s recommendations and instructions for installation. If the Engineer determines that the unit is not functioning properly, the Contractor shall secure the services of the manufacturer’s representative for installation and testing.
680-3.32Signal Operation Tests. Prior to placing a signal in operation, the Contractor shall perform all
tests described herein in the presence of the Engineer as well as a representative from the Regional Traffic Safety and Mobility Group. Signal operation tests shall be performed during off-peak traffic hours and all standard precautions shall be in place to protect the traveling public. The equipment required for each test shall be supplied by the Contractor along with the equipment manufacturer's written instructions describing how to perform the test. The following tests shall be performed by the Contractor at the time directed by the Engineer and prior to acceptance of the work:
680-3.33 356 Section 600 STANDARD SPECIFICATIONS (USC) January 1, 2026 VOLUME 3
to ground of not more than that shown in the table below as determined in the following manner:
signal cabinet fuse and the ground system.
Controller Voltmeter Equivalent Installed Reading (Volts) Resistance (Ohms) Model 2070 or 170 Series 20 2.0 All others 10 1.0 If the voltmeter reading is higher than the appropriate voltage shown in the above table using the above procedure, the grounding system has an unacceptable resistance to ground. In accordance with NFPA NEC 250.56 the system shall have an impedance of less than 25 ohms. If the requirements are not met the Contractor shall repair or install additional grounding, including electrical bonding of underground metallic conduit, to meet the test requirements.
circuit between the circuit and ground. The insulation resistance shall not be less than 10 megohms on each circuit except that inductive loop detector circuits shall have an insulation resistance of not less than 50 megohms. This test shall be performed with a megohmmeter.
days of continuous operation of the traffic signal control equipment, shall be performed to demonstrate that every part of the traffic signal system operates in accordance with the contract documents and specifications. If unsatisfactory performance of a system component is discovered during this time, the condition shall be corrected, and the test repeated until 10 days of continuous satisfactory operation is obtained Functional tests shall not begin on a Friday or on the day before a legal holiday. On the day the functional test begins, initial turn-on shall be made between the hours of 9:00 am and 2:00 pm. Prior to turn-on, all traffic signal control equipment required for traffic signal system operation shall be installed and ready for operation, including pedestrian signal indications, pedestrian signs and push buttons, and vehicle detectors. All louvers, visors, and traffic signal heads shall be directed to provide maximum visibility. Clearance height of traffic signal heads shall be as specified in the contract documents. Temporary shutdowns caused by power interruption (e.g., local power outage) or traffic accidents will not constitute discontinuity of the functional test. The functional testing shall be periodically monitored by the Engineer and the Regional Traffic Safety and Mobility Group or their designated representative (representative shall have knowledge of traffic signal operations). Removal of existing signal equipment shall not begin until the new signal has been placed into operation and verified by NYSDOT Signals unless prior permission has been given by NYSDOT Traffic Signal Maintenance.
680-3.33Accessible Pedestrian Signal (APS). This work shall consist of furnishing and installing an
APS in accordance as shown in the contract documents and manufacturer’s instructions for a complete working APS. The Control Unit shall be mounted in the pedestrian head and powered from the pedestrian head lamp indications. The APS shall be mounted on a pole near the start of the crosswalk. The pedestrian push button shall be mounted between 3.5 and 4 feet above an accessible surface and shall face an accessible approach (orientated parallel to the line of pedestrian travel) and within 10 inches of adjacent 680-3.34 357 Section 600 STANDARD SPECIFICATIONS (USC) January 1, 2026 VOLUME 3 accessible surface, in accordance with contract documents. If there is an adjacent push button within 10 feet, the APS controller shall be programmed with the crossing street name which shall be audibly announced to eliminate any confusion for the pedestrian.
680-3.34Traffic Signal Battery Backup System. The Traffic Signal Battery Backup System shall be
installed in accordance with the contract documents and manufacturer instructions. Contractor shall follow all applicable Utility requirements as well. All battery backup system equipment shall be installed prior to turning on a new traffic signal. Battery backup system shall be successfully tested in the presence of the Regional Traffic Safety and Mobility Group prior to final acceptance.
680-3.35thru 680-3.36 (Vacant)
680-3.37Vehicular and Pedestrian Traffic Signal LED Module. Vehicular and Pedestrian Traffic
Signal LED Module shall be installed in Type I vehicular or Type I pedestrian signal section according to the requirements of §680-3.21 Vehicular and Pedestrian Traffic Signal Bracket and Mounting Assembly.
680-3.38Watertight Disconnect Box. A watertight disconnect box shall be installed near the meter pan
on the traffic signal pole as shown in the contract documents.
680-3.39Generator Transfer Switch. A generator transfer switch shall be installed at all traffic signal
locations. The generator transfer switch will enable auxiliary power (e.g., portable generator or BBS) to be supplied to the traffic signal in the event there is loss of power from the Utility. The generator transfer switch shall be installed in accordance with the contract documents and manufacturer instructions. Contractor shall follow all applicable Utility requirements as well.
680-4METHOD OF MEASUREMENT
680-4.01General. Each Unit. The following items will be measured for payment as the number of each
unit furnished and installed in accordance with the contract documents: Concrete Base for Controller Cabinet Traffic Signal Pole Concrete Work Pad Traffic Signal Cabinet Span Wire Assembly Traffic Signal Section Guy Assembly Type I Traffic Signal Section Riser Assembly Pedestrian Signal Section Traffic Signal Bracket Assembly Type I Pedestrian Signal Section Controller Assembly LED Traffic Signal Module Pedestrian Push Button Assembly LED Pedestrian Signal Module Fire Pre-Emption Tell Tale Light Meter Pan Overhead Traffic Signal Sign Assembly Ground Rod Flashing Beacon Sign Assembly Pullbox Rectangular Rapid Flashing Beacon (RRFB) Assembly Linear Foot Measurement. The following items will be measured for payment as the number of feet installed in accordance with the contract documents: Inductance Loop Wire Shielded Communication Cable Shielded Lead-in Cable Signal Cable with Integral Messenger Inductance Loop Installation Shielded Communication Cable w/ Integral Messenger Messenger Assembly Conduit 680-4.02 358 Section 600 STANDARD SPECIFICATIONS (USC) January 1, 2026 VOLUME 3 Signal Cable Ground wire
680-4.02Concrete. The payment quantity of concrete will be measured as the number of cubic yards or
the number of each unit furnished and installed, in accordance with individual pay items. See §680-4.01 Each Unit and §680-4.10 Foundation Excavation and Concrete Foundation.
680-4.03thru 680-4.07 (Vacant)
680-4.08Contractor Responsibility with Utilities. (None Specified)
680-4.09(Vacant)
680-4.10Foundation Excavation and Concrete Foundation
excavation for cast-in-place and precast concrete foundation will be the number of cubic yards of concrete shown in the table on the contract documents for Traffic Signal Pole Foundations for the specified foundation size.
foundation will be in accordance with §680-4.01 Each Unit or as computed from the payment limits specified in the contract documents.
foundations will be in accordance with §680-4.01 Each Unit or as computed from the payment limits specified in the contract documents.
680-4.11Traffic Signal Poles. The payment quantity of traffic signal poles will be in accordance with
§680-4.01 Each Unit.
680-4.12Traffic Signal Grounding System. The payment quantity of ground wire and conduit will be in
accordance with §680-4.01 Linear Foot Measurements and the payment quantity of ground rod will be in accordance with §680-4.01 Each Unit.
680-4.13Conduit. The payment quantity of conduit trenchless installation method will be the number of
linear feet completed as computed from the payment limits specified in the contract documents.
680-4.14Pullboxes. The payment quantity of pullboxes will be in accordance with §680-4.01 Each Unit
680-4.15Signal Control Cable and Shielded Communication Cable. The payment quantity of traffic
signal control cable and shielded communication cable will be in accordance with §680-4.01 Linear Foot Measurements
680-4.16Cable Splices. The payment quantity of cable splices will be as computed from the payment limits
specified in the contract documents.
680-4.17Span Wire Assembly. The quantity to be measured for payment will be in feet to the
nearest whole foot of span wire assembly installed and will be in accordance with §680-4.01 Each Unit. 680-4.18 359 Section 600 STANDARD SPECIFICATIONS (USC) January 1, 2026 VOLUME 3
680-4.18Messenger Assembly. The quantity to be measured for payment will be in feet to the
nearest whole foot of messenger assembly installed and will be in accordance with §680-4.01 Each Unit.
680-4.19Guy Assembly. The quantity to be measured for payment will be in feet to the nearest
whole foot of guy assembly installed and will be in accordance with §680-4.01 Each Unit.
680-4.20Riser Assembly. The quantity to be measured for payment will be in feet to the nearest
whole foot of riser assembly installed and will be in accordance with §680-4.01 Each Unit.
680-4.21Vehicular and Pedestrian Traffic Signal Bracket and Mounting Assembly. The quantity to
be measured for payment will be the number of bracket/mount assemblies installed and will be i n accordance with §680-4.01 Each Unit.
680-4.22Wiring Color Code. (None specified)
680-4.23Pedestrian Push Button and Sign. The quantity to be measured for payment will be number
of pedestrian push button and sign installed and will be in accordance with §680-4.01 Each Unit.
680-4.24Fire Pre-Emption Tell Tale Light. The quantity to be measured for payment will be the
number of individual fire preemption tell-tale lights installed and will be in accordance with §680-
4.01Each Unit.
680-4.25Flashing Beacon Sign Assembly. The quantity to be measured for flashing beacon sign
assembly installed will be in accordance with §680-4.01 Each Unit.
680-4.26Inductance Loop Installation. The quantity to be measured for payment of inductance loops
installed will be the number of linear feet as computed from the payment limits specified in the contract documents.
680-4.27Solar Power System. The quantity to be measured for payment will be computed from the
payment limits specified in the contract documents.
680-4.28Meter Pan. The quantity to be measured for payment of power meter pan installed will be in
accordance with §680-4.01 Each Unit.
680-4.29Traffic Signs. The quantity to be measured for payment of traffic signs installed will be in square
feet, rounded to the nearest whole square foot, as computed from the payment limits specified in the contract documents.
680-4.30Field Galvanizing. The quantity to be measured for payment of field galvanizing will be as
computed from the payment limits specified in the contract documents.
680-4.31Rectangular Rapid Flashing Beacon (RRFB). This work will be measured as the number of
RRFB furnished and installed in accordance with the Contract Documents, or as directed by the Engineer.
680-4.32Signal Operation Tests. No separate payment will be made for this work thus measuring
unit is not applicable.
680-4.33Accessible Pedestrian Signal (APS). The quantity to be measured for payment of APS furnished
and installed will be in accordance with §680-4.01 Each Unit. 680-4.34 360 Section 600 STANDARD SPECIFICATIONS (USC) January 1, 2026 VOLUME 3
680-4.34Traffic Signal Battery Backup System. The quantity to be measured for payment of Traffic
Signal Battery Backup System furnished and installed will be in accordance with §680-4.01 Each Unit.
680-4.35thru 680-4.36 (Vacant)
680-4.37Vehicular and Pedestrian Traffic Signal LED Module. The quantity to be measured for
payment of traffic signal LED modules furnished and installed will be in accordance with §680-4.01 Each Unit.
680-4.38Watertight Disconnect Box. The quantity to be measured for payment of watertight disconnect
box furnished and installed will be in accordance with §680-4.01 Each Unit.
680-4.39Generator Transfer Switch. The quantity to be measured for payment of generator transfer
switch furnished and installed will be in accordance with §680-4.01 Each Unit.
680-5BASIS OF PAYMENT
680-5.01General. The unit price bid for individual items shall include the cost of all labor, materials, and
equipment necessary to satisfactorily complete the work. No direct payment will be made for the installation of the power service connection, but the cost shall be covered in the various traffic signal items. Items with additional provisions are as follows:
680-5.02Concrete. The unit price bid for cubic foot or cubic yard of concrete shall include the cost of all
labor, materials, and equipment necessary to satisfactorily complete the work. The Performance Concrete Quality Units will be calculated in accordance with §501-5, Determination of Quality Adjustment.
680-5.03thru 680-5.07 (Vacant)
680-5.08Contractor Responsibility with Utilities. (None Specified)
680-5.09(Vacant)
680-5.10Foundation Excavation and Concrete Foundation
shall include the excavation, any protective system(s) required to ensure the safety of the workers and the public, backfill (select granular backfill or concrete), concrete form work, concrete mixing/delivery, QC testing of concrete, bar reinforcement for concrete, placement of precast foundation by use of a crane, conduit bends and fittings, anchor bolt placement, restoration of surfaces in kind, and saw cutting as required in the contract documents. Progress payments will be made at the unit price bid for 80 percent of the quantity for each foundation properly installed except for the restoration. The remaining 20 percent will be paid for upon satisfactory completion of each foundation.
shall include the cost of all sawcutting, excavation, backfill, concrete form work, restoration of surfaces, concrete, placement of precast foundation by use of a crane, conduit bends and fittings. 680-5.11 361 Section 600 STANDARD SPECIFICATIONS (USC) January 1, 2026 VOLUME 3
all sawcutting, excavation, backfill, form work, restoration of surfaces, concrete, placement of precast foundation by use of a crane, and conduit bends and fittings.
680-5.11Traffic Signal Poles. The unit price bid for traffic signal poles shall include the cost of all labor,
materials, and equipment necessary to satisfactorily complete the work, including the grounding system, anchor bolts, mast arms, horizontal member of monotube traffic signal pole structure, and breakaway transformer bases.
680-5.12Traffic Signal Grounding System. (None specified)
680-5.13Conduit. The unit price bid for conduit shall include all handling, cutting, bending, fitting,
installation, capping, painting, testing, furnishing, and placing of pull lines and conduits, concrete inserts, and expansion and incidental fittings as required. Conduit bends and fittings in concrete footings will be paid for under their respective footing item. Conduit Excavation and Backfill will be paid for under the pay item for Conduit Excavation and Backfill including Surface Restoration in §206 Trench, Culvert, and Structure Excavation. The trenchless alternative method of installation will be paid for under the pay item for Trenchless Installation Method for Conduit and the unit price bid per foot shall include excavation, backfilling for entrance and exit pits; test pits; and restoration of surfaces in kind.
680-5.14Pullboxes. The unit price bid for each pullbox shall include all concrete, reinforcing steel,
crushed stone or gravel, extensions, saw cutting, excavation, backfill, frames, covers, installation, restoration of surfaces, grounding system and incidentals.
680-5.15Signal Control Cable and Shielded Communication Cable. The unit price bid per foot of signal
control cable and shielded communication cable shall include the installation, connectors, lashing or messenger rings, splices when permitted, testing, cable markers, and incidental fittings for the cable connected in place.
680-5.16Cable Splices. The unit price bid shall include all material and labor for cable splices where
needed.
680-5.17Span Wire Assembly. The unit price bid shall include all labor and materials for span wire
assemblies and all fittings to attach the span wire assemblies to the traffic signal poles.
680-5.18Messenger Assembly. The unit price bid shall include all labor and materials for messenger
assemblies and all fittings to attach the messenger assemblies to the traffic signal poles.
680-5.19Guy Assembly. The unit price bid shall include all labor and materials for guy assemblies and all
fittings to attach the guy assemblies to the traffic signal poles.
680-5.20Riser Assembly. The unit price bid shall include all labor and materials for riser assemblies and
all fittings to attach the riser assemblies to the traffic signal poles.
680-5.21Vehicular and Pedestrian Traffic Signal Bracket and Mounting Assembly. The unit price bid
shall include all brackets, elbows, tees, arms, and fittings to attach the signal head to span wire, pole, or mast arm. The unit price shall also include labor and materials to assemble the individual signal sections and brackets to form a complete signal head including internal wiring.
680-5.22Wiring Color Code. (None specified)
680-5.23 362 Section 600 STANDARD SPECIFICATIONS (USC) January 1, 2026 VOLUME 3
680-5.23Pedestrian Push Button and Sign. The unit price bid shall include the installation, ADA push
button, pedestrian information sign, mounting hardware, pole drilling, and necessary fittings as required. When the pedestrian push button and sign is installed on its own post, the unit price sh all also include the cost of the post.
680-5.24Fire Pre-Emption Tell-Tale Light. The unit price bid shall include the installation, light
fixture, bulb, nipple, guard, and all attachments, hardware, and fittings as required.
680-5.25Flashing Beacon Sign Assembly. The unit price bid shall include installation, the flashing beacon
signal head, two-circuit flasher, cabinet, sign panel, mounting brackets, and all necessary hardware. The unit price bid for school zone flashing beacon shall include installation, controller unit and programming, as well as equipment listed above. The cost of the pole, pole excavation, concrete foundation, and breakaway transformer base will be paid for under their respective items.
680-5.26Inductance Loop Installation. The unit price bid per linear foot (to nearest whole foot) shall
include the cost of all pavement sawcutting and drilling, loop embedding sealer, pavement cut -outs, and installation. Inductance loop wire, pullboxes, shielded lead -in cable, vehicle detector inductance loop, conduit, and conduit excavation and backfill shall be paid under their respective items.
680-5.27Solar Power System. The unit price bid shall include all labor and materials for installing and
furnishing the solar power system, including solar panel(s), rechargeable batteries, cabinet, electrical wiring and cables, and all attachments, hardware, and fittings as required.
680-5.28Meter Pan. The unit price bid shall include all labor and materials for installing and furnishing
the power meter pan including the mounting brackets for attaching the power meter pan to the pole, incidental hardware, fittings, and electrical wiring.
680-5.29Traffic Signs. The unit price bid shall include all labor and materials for installing and furnishing
the traffic signs, including the mounting brackets for attaching the traffic signs to span wire, pole, or mast arm, as well as sign panel incidental hardware, fittings, and electrical wiring (if needed).
680-5.30Field Galvanizing. The unit price bid shall include all labor and materials required for field
galvanizing as needed.
680-5.31Rectangular Rapid Flashing Beacon (RRFB). The unit price bid for each RRFB shall include
the cost of furnishing all labor, materials, and equipment necessary to satisfactorily complete the work, including the signs shown in the associated details. The cost of the pole, pole excavation, concrete foundation and breakaway transformer base will be paid for under their respective items.
680-5.32Signal Operation Tests. The unit bid price is not applicable for testing
680-5.33Accessible Pedestrian Signal. The unit price bid for each Accessible Pedestrian Signal installed
shall include the cost of all labor, materials, equipment, system programming and testing necessary to complete the work.
680-5.34Traffic Signal Battery Backup System. The unit price bid shall include all labor and materials
required for installing the complete traffic signal battery backup system.
680-5.35thru 680-5.36 (Vacant)
680-5.37 363 Section 600 STANDARD SPECIFICATIONS (USC) January 1, 2026 VOLUME 3
680-5.37Vehicular and Pedestrian Traffic Signal LED Module. The unit price bid shall include all labor
and materials required for installing the LED modules.
680-5.38Watertight Disconnect Box. The unit price bid shall include all labor and materials required for
installing the watertight disconnect box.
680-5.39Generator Transfer Switch. The unit price bid shall include all labor and materials required
for installing the generator transfer switch. Payment will be made under: Item No. Item Pay Unit
680.5001 Pole Excavation and Concrete Foundation Cubic Yard
02 Concrete Base for Controller Cabinet Each
03 Concrete Work Pad (5 feet x 5 feet x 4 inches) Each
680.5ZXXYY Pullbox (w/ Cast Iron Cover) Each XX= Size YY = Type Z = Base 01 – 15-inch 01 – Reinforced Concrete 0 - without concrete base 02 – 18-inch 02 – Optional Reinforced 1 - with concrete base 03 - 24-inch Concrete/Bituminous 04 - 30-inch Fiber 05 - Rectangular, 26-inch x 18 inch 06 - Rectangular, 26-inch x 18 inch or 24-inch Diameter 07 - Rectangular, 26-inch x 18 inch or 30-inch Diameter
680.52XXYY Conduit Foot
XX = Type YY = Nominal Diameter (in inches) 01 – Metal Steel, Zinc Coated 01 – ½” 02 – Flexible Liquid Tight Seal 02 – ¾” 04 – PVC Coated Galvanized Steel 03 – 1” 05 – Rigid Plastic, Class 1 (Heavy Wall) 04 – 1 ¼” 06 – Rigid Plastic, Class 2 (HDPE) 05 – 1 ½” 07 – Rigid Plastic, Class 1 or 2 06 – 2” 08 – Flexible, Liquid Tight PVC 07 – 2 ½” 09 – PVC Schedule 80, 4 Ducts 08 – 3” 10 – Fiberglass – Multi-Cell-4 Duct 09 – 3 ½” 80 – PVC Schedule 80 10 – 4” 12 – 5” 13 – 6”
680.5301 Trenchless Installation Method for Conduit Foot
680.54Inductance Loop Installation Foot
680.56Emergency Pre-emption System Each
680.58XXYY Standardized Span Wire Traffic Signal Pole Each
680.59XXYY Traffic Signal Pole, Fluted - Span Wire Each
680.60XXYY Traffic Signal Pole - Span Wire Each
XX = Load in kips (01, 02, 03, 04, ...) YY = Length in whole feet *
680.62XXYY Traffic Signal Pole - Mast Arm Each
680.63XXYY Traffic Signal Pole--Dual Mast Arm** Each
680.66XXYY Traffic Signal Pole, Fluted Each
XX=Mast arm mounting height in feet* YY=Mast arm length in whole feet
680.67XXYY Pedestrian Signal Pole - Post Top Mount Each
680-5.39 364 Section 600 STANDARD SPECIFICATIONS (USC) January 1, 2026 VOLUME 3
680.68XXYY Pedestrian Signal Pole - Bracket Mount Each
XX = Overall Pole Height in Whole Feet YY = 01 – Steel, YY = 02 – Aluminum
680.7001 Single Span Wire Assembly Each
02 Dual Span Wire Assembly with Upper Tether Wire Each
03 Dual Span Wire Assembly with Lower Tether Wire Each
04 Messenger Assembly Each
05 Guy Wire Assembly Each
0602 Riser Assembly, 1/ 2-inch Diameter Each
0603 Riser Assembly, 1-inch Diameter Each
0604 Riser Assembly, 1-1/ 2-inch Diameter Each
0606 Riser Assembly, 2-inch Diameter Each
0607 Riser Assembly, 2 ½-inch Diameter Each
0608 Riser Assembly, 3-inch Diameter Each
0609 Riser Assembly, 3½-inch Diameter Each
0610 Riser Assembly, 4-inch Diameter Each
0612 Riser Assembly, 5-inch Diameter Each
0613 Riser Assembly, 6-inch Diameter Each
680.71Shielded Lead-in Cable Foot
680.72Inductance Loop Wire Foot
680.73XXYY Signal Cable Foot
680.74XXYY Signal Cable with Integral Messenger Foot
XX = Number of Conductors YY = Wire Gauge
680.75XXYY Shielded Communication Cable Foot
680.76XXYY Shielded Communication Cable with Integral Messenger Foot
XX = Number of Pairs YY = Wire Gauge
680.78XXYY Traffic Signal Pole, Fluted, with Mast Arm Each
680.79XXYY Traffic Signal Pole, Fluted, with Dual Mast Arm Each
XX=Mast arm mounting height in feet* YY=Mast arm length in whole feet
680.80Battery Backup System Each
680.81Solar Power System Each
0101 Traffic Signal Module - 12-inch, Red Ball, LED Each
0102 Traffic Signal Module - 12-inch, Red Arrow, LED Each
0103 Traffic Signal Module - 12-inch, Yellow Ball, LED Each
0104 Traffic Signal Module - 12-inch, Yellow Arrow, LED Each
0105 Traffic Signal Module - 12-inch, Green Ball, LED Each
0106 Traffic Signal Module - 12-inch, Green Arrow, LED Each
0107 Traffic Signal Section - Aluminum Type I, 12-inch Each
0108 Traffic Signal Module - 12-inch, Each
Bi-Modal Yellow/Green Arrows, LED
02 Traffic Signal Section - Optically Programmed - 12-inch Each
0301 Traffic Signal Module - 8-inch, Red Ball, LED Each
0302 Traffic Signal Module - 8-inch, Red Arrow, LED Each
0303 Traffic Signal Module - 8-inch, Yellow Ball, LED Each
0304 Traffic Signal Module - 8-inch, Yellow Arrow, LED Each
0305 Traffic Signal Module - 8-inch, Green Ball, LED Each
0306 Traffic Signal Module - 8-inch, Green Arrow, LED Each
0307 Traffic Signal Section - Aluminum Type I, 8-inch Each
680-5.39 365 Section 600 STANDARD SPECIFICATIONS (USC) January 1, 2026 VOLUME 3
0308 Install Ball/Arrow LED Traffic Signal Module Each
0601 Traffic Signal Section - Polycarbonate, Type I, 12-inch Each
0701 Traffic Signal Section - Polycarbonate, Type I, 8-inch Each
11 Traffic Signal Bracket Assembly - 1 Way Each
12 Traffic Signal Bracket Assembly - 2 Way Each
13 Traffic Signal Bracket Assembly - 3 Way Each
14 Traffic Signal Bracket Assembly - 4 Way Each
15 Traffic Signal Bracket Assembly - 5 Way Each
3103 Pedestrian Signal Section - Aluminum Type I, 12 inch Each
3104 Install Pedestrian Signal Module Each
3105 Pedestrian Signal Module - 12-inch,
Bi-Modal Hand/Man Symbols, LED Each
3106 Pedestrian Signal Section - Polycarbonate, Type I, 12-inch Each
3107 Pedestrian Signal Module - 16-inch by 18-inch,
Bi-Modal HAND/MAN LED Each
3108 Pedestrian Signal Section, Aluminum,
Type I, for 16 inches by 18 inches LED module Each
3109 Pedestrian Signal Section - Polycarbonate, Type I,
for 16-inch by 18-inch LED module Each
41 Pedestrian Signal Bracket Mount Assembly Each
42 Pedestrian Signal Post Top Mount Assembly Each
5001 Pedestrian Signal Module - 12-inch Countdown Timer, LED Each
5002 Pedestrian Signal Module - 16-inch x 18-inch, Bi-Modal
Hand/Man Symbols with Countdown Timer, LED Each
XX Accessible Pedestrian Signal (APS) Each
XX = 51 W/O Post, XX = 52 W/ Post
99 Backplates for Traffic Signal Heads Each
680.82XX Overhead Sign Assembly Each
XX = Type (see Standard Sheets) 01 = A 04 = D 07 = G 10 = J 02 = B 05 = E 08 = H 03 = C 06 = F 09 = I
20 Flashing Beacon Sign Assembly Each
21 School Flashing Beacon Sign Assembly Each
22 Install Flashing Beacon Sign Assembly Each
23 Breakaway Transformer Base Each
24 Rectangular Rapid Flashing Beacon (RRFB) Each
25 Pedestrian Push Button and Sign - without Post Each
26 Pedestrian Push Button and Sign - with Post Each
30 Fire Pre-Emption Tell Tale Light Each
680.84XX Pedestrian Pushbutton Station Each
XX = 51 W/O Post, XX = 52 W/ Post 680.9XXYYY Monotube Traffic Signal Structure Each XX = mounting height in feet YYY = span length in feet
680.9401 Watertight Disconnect Box Each
02 Meter Pan Each
03 Ground Wire Foot
99 Install Electrical Disconnect/Generator Transfer Switch Each
680.95XXYY Electrical Service Cable Foot
XX = Number of Conductors 685-3.01 366 Section 600 STANDARD SPECIFICATIONS (USC) January 1, 2026 VOLUME 3 YY = Wire Gauge
680.99Performance Concrete Quality Adjustment Quality Unit
NOTE: SEE PAY ITEM CATALOG FOR ITEM NUMBERS CONTAINING VARIABLES. * Mast arm mounting heights, and span wire pole length and load, are as defined on the `Standard Traffic Signal Poles' standard sheets and in §724-03 Traffic Signal Poles. ** The mast arm length and mounting height indicated by the item number is for only one of the mast arms. The other mast arm length and mounting height shall be as indicated in the contract documents. SECTION 681 AND 682 (VACANT)
Traffic Signals in other states
Get an email when 680 changes
New York revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.