SECTION 202 — EXCAVATION AND EMBANKMENT — EXCAVATION AND EMBANKMENT
202.01 Description.
This work includes excavation and the satisfactory placement and compaction or disposal of all materials encountered within the limits of the work as necessary for the construction of the roadway, bridge, stormwater structures, etc. Earth Excavation. Earth excavation includes the removal of suitable and unsuitable soils not otherwise classified and the removal of boulders and rock fragments less than 1 cu yd in volume from the following areas: • Within the design excavation section • Beyond the design excavation section of the roadbed or side slopes where unsuitable materials are encountered • Beyond the design excavation section of shallow embankments when unsuitable materials are encountered Presplitting Bedrock. This work includes producing a plane of split rock before any drilling or blasting for roadway rock excavation. Ensure that the plane follows the design rock slope lines and extends from the top of the bedrock surface to the proposed rock shelf levels and either to the toe of finished rock slope or to the invert of side drains. Rock Excavation. Rock excavation includes the removal of intact bedrock and boulders or detached bedrock fragments that have a volume of 1 c u yd or more. Boulders and detached rock fragments that have a volume of less than 1 cu yd are considered Earth Excavation. Rock Excavation – Mechanical. Use this classification of rock excavation where blasting is prohibited. R emove rock excavated under this classification using hydraulic splitters, air rams, or paving breakers. Unsuitable Soils. Unsuitable soils include those soils other than muck that, due to their consolidation properties, degree of saturation, gradation, or other deleterious characteristics, will not provide: • A stable subgrade or side slopes • Cannot be used as or support embankment • Cannot be placed and compacted as backfill
Part 200 — Earthwork and Erosion Control August 2025
SECTION 202 — EXCAVATION AND EMBANKMENT 200-15 Muck Excavation. Muck excavation includes the removal and disposal of deposits of saturated or unsatu rated mixtures of soils and organic matter not suitable for foundation material regardless of moisture content. Stockpile the ex cavated muck at approved locations within the right -of-way and/or disposed of. Channel Excavation Earth. Channel Excavation Earth includes all materials other than water or Channel Excavation Rock, removed from existing, new, or temporary water courses. Channel Excavation Rock. Channel Excavation Rock includes intact bedrock and boulders 1 cu yd or more in volume removed from existing, new, or temporary water courses. Channel Excavation Rock – Mechanical. Use t his classification of rock excavation in channel construction areas where blasting is prohibited. Remove rock excavation under this classification using hydraulic splitters, air rams, or paving breakers. Unclassified Excavation. Unclassified Excavation includes the excavation, stockpiling, and/or removal and disposal of a composite mixture of various types of materials that are impractical to segregate into separate classifications as determined by the Engineer. Embankment Construction. Embankment Construction includes constructing roadway embankments, including the preparation of the areas: • Upon which they will be placed • The benching of embankments • The construction of side slopes and toe drainage ditches • The construction of dikes within or outside the right-of-way • The placing and compacting of approved material where unsuitable material has been removed • The placing and compacting of embankment material in holes, pits, and other depressions within the roadway area
Part 200 — Earthwork and Erosion Control August 2025
200-16 SECTION 202 — EXCAVATION AND EMBANKMENT Use only materials in the construction of embankments and backfills that meet the material requirements. Handling, Hauling, and Stockpile Management of Contaminated Soils and Unclassified Soils. This item of work includes the requirements for the RIDEM approved Remedial Action Work Plan (RAWP) and the Soil Management Plan (SMP), including: • Maintaining existing or proposed chain link fencing (as applicable) for excavation locations, temporary staging areas, and soil stockpile • Furnishing, installing, and removing temporary barrier fencing for excavation locations, temporary staging areas, and temporary soil stockpiles, as applicable • The special handling, hauling, unloading, and stockpile management of unclassified, contaminated, or hazardous soil from the excavation location to the approved stockpile/testing location(s) • Testing the soil for contamination • The management of site security/access • The setup, maintenance, and removal of the stockpile locations including above soils, polyethylene sheeting, hay bales, and temporary barrier fencing • Work and contingency plan supplies • Equipment • Site maintenance • Dust control • Returning the site to a condition acceptable to the Engineer Load, Haul, and Dispose of Contaminated Soil. This item of work includes soil management, special handling, loading and hauling of unclassified, contaminated or hazardous soil, and disposal at an off -Project Industrial/Commercial property, recycling or disposal facility accord ing to RIDEM regulations for recycling/disposal of these materials and as directed by the Engineer. Load, Haul, and Disposal of Other Waste. This item includes all testing for the presence of controlled/hazardous materials that may exist in and around existing bridge joints classified herein as other waste. Other waste includes solid debris and/or refuse materials such as: • Bridge joint material • Caulk • Concrete • Rubble
Part 200 — Earthwork and Erosion Control August 2025
SECTION 202 — EXCAVATION AND EMBANKMENT 200-17 • Pipe • Lumber and other building materials This item also includes any special handling, transporting, and disposing of the wastes to a proper and fully licensed off-site disposal or recycling facility. Manage contaminated and hazardous waste according to all applicable State, Federal, and local regulations including the EPA, OSHA, and RIDEM Remediation Regulations. Perform the work according to all applicable revisions and in compliance with all applicable permits.
202.02 Materials.
Common Borrow. Ensure that Common Borrow complies with Subsection M01.01 before final placement. Gravel Borrow. Ensure that the Gravel Borrow complies with Subsection M01.09, Table I, Column I before final placement. Contaminated Soils. Contaminated soil classifications are defined as follows: • Type 1. Excess excavated Project soil that cannot be reused in which levels of arsenic, lead, and other RCRA Eight Metals, TPH, VOCs, and PAHs are found to be below RIDEM Method 1 Residential Direct Exposure Criteria (RDEC) through testing. • Ty pe 2. Excavated or excess excavated Project soil that cannot be reused in which levels of arsenic, lead, and other RCRA Eight Metals, TPH, VOCs, and PAHs are found to be above RDEC but below I/C DEC through testing. Load, haul, and dispose of this soil at a licensed facility. Concentrations are within disposal parameter limits allowed in State landfills as landfill cover. • Ty pe 3. Excavated or excess excavated Project soil in which levels of arsenic, lead, and other RCRA Eight Metals, TPH, VOCs, and PAHs are found to be above I/C DEC through testing but are within acceptable criteria parameters such that the material can be disposed in out-of-state landfills for landfill cover or landfilling without pretreatment. Load, haul, and dispose this soil at a licensed facility. • Ty pe 4. Excavated Project soil in which levels of arsenic, lead, and other RCRA Eight Metals, TPH, VOCs, and PAHs are found to be above I/C DEC through testing but are within acceptable criteria parameters such that the material can be disposed of in out-of- state landfills for landfilling without pretreatment or the material is suitable for asphalt batching. Load, haul, and dispose this soil at a licensed facility. • Ty pe 5. Excavated Project soil in which contamination levels exceed EPA and/or RIDEM hazardous waste characteristics necessitating disposal as hazardous waste.
Part 200 — Earthwork and Erosion Control August 2025
200-18 SECTION 202 — EXCAVATION AND EMBANKMENT Handling, Hauling, and Stockpile Management of Contaminated Soils and Unclassified Soils. Use all materials and equipment required to adequately provide and maintain excavation location security/access, minimize the effects of erosion and surface run -off, and complete the unclassified, contaminated, or hazardous soil excavation, and the handling, hauling, unloading, and stockpiling. Load, Haul, and Disposal of Other Waste. Use all required materials to adequately remove, contain, haul, and dispose of contaminated other waste, debris, or surplus materials resulting from the Project as described in the Contract. Use personal protective equipment as specified in the Contractor’s Project specific Health and Safety Plan (HASP).
202.03 Construction Methods.
Excavation – General. Remove all soil, rock, and other material, and use or dispose of the materials as required. Finish the excavation for the roadway, intersections, and entrances to reasonably smooth and uniform surfaces. Clean and scale all rock cuts for all loose fragments. Do not dispose of any excess materials on the Project site. Conduct excavation operations so that material outside of the slope limits will not be disturbed. Before beginning excavation operations, ensure that all work has been performed according to SECTION 201, and install all erosion and pollution controls according to SECTIONS 206 through 211. Maintain slopes, crowns, berms, and ditches on all excavations to ensure satisfactory drainage at all times to protect the work and to maintain safe working conditions. When the excavation operations encounter remains or artifacts of potential historical or archaeological significance, temporarily halt operations. Immediately contact the Engineer, who will determine the disposition of the discovery. When directed by the Engineer, excavate the site to preserve the artifacts encountered, and remove them for delivery to the custody of the proper State authorities. The excavation will be paid for as Extra Work according to Subsection 104.05.
Part 200 — Earthwork and Erosion Control August 2025
SECTION 202 — EXCAVATION AND EMBANKMENT 200-19 Submit a Blasting Plan before the performance of any drilling or blasting. Ensure that the Plan includes as a minimum the full details of drilling and blasting patterns and techniques proposed for controlled and production blasting. Department review of the Blasting Plan does not relieve the Contractor of the responsibility to use current drilling and blasting technology and for obtaining the desired results. Furnish a technical representative from the manufacturer of the explosive materials. Provide an individual experienced in the use of explosives commensurate with the circumstances encountered in the Project. Ensure that the manufacturer's representative is available before starting and during blasting operations to determine the proper equipment, devices, materials, methods, and procedures used for the work. For all operations involving explosives and/or blasting agents, ensure that the work is performed according to the “NFPA 495: Explosives Materials Code,” as amended. If the Code conflicts with the RIDOT Standard Specifications, the Code will apply. For blasted excavation work, develop the means and methods necessary to attain rock slopes consistent with the most conservative safety requirements. Excavate material classified as rock to a minimum depth of 12 in. below subgrade within the limits of the roadbed, and backfill the excavation as required.
Part 200 — Earthwork and Erosion Control August 2025
200-20 SECTION 202 — EXCAVATION AND EMBANKMENT Revise and resubmit rejected plans accordingly. C omply with this program at all times during the prosecution of the work. Not later than two calendar weeks before initiating blasting, present permits to the Engineer before any blasting will be allowed. Do not initiate blasting until the Engineer has given approval in writing. If the Engineer determines at any time that the use of explosives is unsafe or dangerous to persons, property, utilities, or the work, the Engineer may direct the Contractor to use other means that do not require the use of explosives at no additional cost to the Department.
Part 200 — Earthwork and Erosion Control August 2025
SECTION 202 — EXCAVATION AND EMBANKMENT 200-21 Use presplitting where the intended exposed rock slope exceeds 10 ft in vertical height. Rock cuts more than 25 ft in vertical height may be presplit in stages (lifts), provided that no stage is less than 10 ft in depth. Offset presplitting holes in successive stages not more than 2 ft inside of the previously presplit stage face. When drilling and blasting behind existing previously drilled and blasted rock faces to widen the rock cut, presplit along the new rock face alignment to prevent over blasting of the new rock face. If after excavating the blasted rock, it is not possible to hold a true and neat face-of-rock, excavate all loose and unstable, fractured, or seamed rock to a stable face of rock behind the neat lines. Ensure that the drilled presplitting holes follow the required rock slope lines and inclinations. Provide a maximum spacing of 3 ft between presplitting holes, center -to- center, and a diameter not greater than 3 in. Extend presplitting holes from the top of solid bedrock surface to 2 ft below the toe of finished bedrock slope. Maintain the proper angle of drilling so that all presplit holes lie essentially in the same plane and are parallel to each other. Do not allow any hole to deviate more than ½ ft at any location in the plane of the specified slope line nor in its vertical alignment.
Part 200 — Earthwork and Erosion Control August 2025
200-22 SECTION 202 — EXCAVATION AND EMBANKMENT
Part 200 — Earthwork and Erosion Control August 2025
SECTION 202 — EXCAVATION AND EMBANKMENT 200-23 Reduce all particles to a maximum size of 6 in. and produce a uniform material. Compact the roadway surface according to Subsection 202.03.3.
Part 200 — Earthwork and Erosion Control August 2025
200-24 SECTION 202 — EXCAVATION AND EMBANKMENT that the balance of the embankment is composed of suitable material compacted as specified.
Part 200 — Earthwork and Erosion Control August 2025
SECTION 202 — EXCAVATION AND EMBANKMENT 200-25 place common borrow. Do not exceed a thickness of 8 in. for each fill layer, measured after compaction. ● The bedding material will extend to the height specified in Subsection 701.03.3. Compaction – General. Uniformly compact each lift to the specified density before the next lift is placed. Keep dumping and rolling areas separate from one another, and do no t cover a lift by another until the compaction requirements have been met. Route and distribute hauling and leveling equipment over each lift of the fill to make the best use of the compaction effort.
Part 200 — Earthwork and Erosion Control August 2025
200-26 SECTION 202 — EXCAVATION AND EMBANKMENT
Part 200 — Earthwork and Erosion Control August 2025
SECTION 202 — EXCAVATION AND EMBANKMENT 200-27 Methods. The Contractor may implement any effective and lawful method for handling, hauling, unloading, and/or stockpiling unclassified and contaminated soil encountered in the work area, if the required excavation has the approval of the Engineer. Assume all responsibility for the adequacy of the methods, materials, documentation, and equipment employed. Test all stockpiled soil before disposing at an industrial/commercial site. Security Fencing. Provide fencing with ingress/egress gates around all areas of construction, including all excavations, staging areas, and stockpiles to limit access by unauthorized persons and to protect the public. Include the use of existing or proposed chain link fencing or temporary barrier fencing. Use temporary barrier fencing where sufficient chain link fencing has not yet been placed or will not be placed to enclose an area to limit access. Install temporary barrier fence according to the manufacturer's recommendations. Maintain fencing until the appropriate pavement or a 2 -ft soil cover has been placed or a permanent fencing has been installed. Dust and Erosion. During excavation of unclassified and contaminated soil, use acceptable methods to control dust and sedimentation erosion. Install fencing and staked hay bales around excavations to minimize the effects of erosion and surface run-off as directed by the Engineer. Unclassified Excavated Soil. Ensure that all unclassified excavated soil within utility easements for installation of storm drain lines and associated structures is visually screened for environmental issues at point of excavation origin before placement in trucks and hauling to a tem porary stockpile for ultimate reuse as backfill at point of excavation origin. While engaged in unclassified, contaminated, or hazardous materials removal, the Engineer will provide an on- Project inspection. If the work violates the requirements of the Contract, the Engineer will issue a stop work order effective immediately and unt il the violation is resolved. Standby time and expenses required to resolve the violation will be at no additional cost to the Department. Stockpiles. Maintain and protect designated stockpiles from exiting damage with chain link fencing. At all temporary stockpile locations, maintain and protect from exiting damage with proposed chain link fencing (as applicable), or provide temporary barrier fencing before initiating the development of soil stockpiles. Before initiating the development of all soil stockpiles, furnish and install erosion control hay bales along the interior perimeter of the fencing. Use all required equipment to adequately place and maintain the stockpiles in a neat and orderly fashion within approved stockpile areas, volume, and buffer limitations. Place all stockpiled
Part 200 — Earthwork and Erosion Control August 2025
200-28 SECTION 202 — EXCAVATION AND EMBANKMENT unclassified and contaminated soil entirely on two layers of 12-mil polyethylene, and ensure that the soil is entirely covered with a 12- mil layer of polyethylene at the completion of each day. Overlap the polyethylene sheets with adjacent sheets by 4 ft minimum. If additional stockpile locations are required, the materials and setup required will be at no additional cost to the Department. Ensure that each stockpile location has been placed on and covered by the required polyethylene and that the fencing and erosion control hay bales are in place. Maintain site security/access, fencing, erosion control hay bales, and dust control as required by the Contract and Soil Management Plan at the stockpile locations and at all areas traveled for the stockpiling operation leading to and from the stockpile areas. Maintain the unclassified soil stockpile until the soil has been reused to backfill the excavation at the point of origin. Test, classify, and approve the excess unclassified stockpile soil for proper disposal off-site. See Subsection 202.02.3 for testing criteria. Maintain the contaminated soil stockpile until the soil has been tested and approved for proper disposal off-site. See Subsection 202.02.3 for testing criteria. Maintain an inventory of supplies and equipment required to execute the required work that includes the supplies to be used to implement a contingency plan for unexpected conditions. After removal of stockpiled soils and upon completion of the use of the stockpile area(s), remove and dispose of the polyethylene sheeting, hay bales, and temporary barrier fencing, and restore the stockpile area(s) to a condition acceptable to the Engineer. Load, Haul, and Dispose of Contaminated Soils. If unclassified, contaminated, or hazardous soil will be stockpiled, place the soil on and cover with polyethylene sheeting, as described in the RAWP and SMP. Minimize odors during excavation, handling, loading, hauling, and/or disposal. For unclassified and contaminated soil excavation and handling, the Contractor may choose and implement any effective and lawful method for handling, loading, hauling, and/or disposal of unclassified, contaminated, or hazardous soil encountered in the work area, provided that the Contractor performs the required excavation subject to the approval of the Engineer. Control access, dust, and sedimentation erosion during excavation of unclassified, contaminated, or hazardous soil. Install fencing and staked hay bales around excavations to protect the public, limit site access, and minimize the effects of erosion and surface run-off. While engaged in unclassified, contamination, or hazardous materials removal, the Engineer may conduct an on-site inspection. If the work violates the requirements of the Contract, RIDOT will issue a stop work order effective immediately and until the violation is resolved. Standby time and expenses required to resolve the violation will be at no additional cost to the Department. For all excavated Type 1 or Type 2 soils proposed for reuse as common borrow, perform geotechnical, arsenic, and lead testing at the point of excavation origin before placing in trucks.
Part 200 — Earthwork and Erosion Control August 2025
SECTION 202 — EXCAVATION AND EMBANKMENT 200-29 Place soils that meet common borrow requirements into trucks, and haul to the project specific designated temporary stockpile location for reuse within the limits of the Project. For all excavated Type 1 and Type 2 soils that do not meet common borrow requirements, place the soils into trucks and haul to the project specific designated area for further characterization (before off Project disposal). Cover the soils with a 12-mil layer of polyethylene at the completion of each workday. For excavated Type 1 or Type 2 soils proposed for reuse as common borrow, perform geotechnical, arsenic, and lead testing at the point of excavation origin before placing in trucks. For soils meeting common borrow requirements, place the soils into trucks , and haul to an approved temporary stockpile location for reuse within the Project limits. For excavated Type 1 and Type 2 soils not meeting common borrow requirements, place the soils into trucks and, as applicable, haul to the project specific designated stockpile area for further characterization (before off Project disposal). Cover with a 12 -mil layer of polyethylene at the completion of each work day. For excavated Type 1 or Type 2 soils not proposed for reuse and Type 3, Type 4, or Type 5 soils, immediately place the soils into trucks, and haul directly to an off -Project recycling/disposal site, or haul to the project specific designated stockpile area for further characterization (before off Project disposal). Cover the soils with a 12- mil layer of polyethylene at the completion of each workday. Surround all temporary stockpile locations with fencing and erosion control. If necessary, select additional, temporary stockpile areas subject to the approval of the Engineer. Inspect the covers, fencing, and erosion control on a daily basis. If necessary, restore as needed to control dust and erosion. Reuse contaminated soil within the Project limits, or dispose the soil at an off -Project facility according to RIDEM regulations for recycling/disposal of the materials. Perform the on- project confirmatory testing and characterization testing of Types 2, 3, 4, or 5 soils for disposal. Do not dispose the material at any facility that currently maintains a listing as a State or Federal waste site. Perform imported soil testing. Conform to the applicable RIDEM requirements for handling, storage, transporting, and disposal of contaminated/hazardous waste material when handling and disposing of the materials. Submit the material testing data and any additional data to the receiving facility, to the Engineer, and to RIDEM before the removal and final disposal of contaminated material from the Project limits or an interim stockpile area. Where specifications, requirements, and reference documents vary, the more stringent requirements shall apply. Load, Haul, and Disposal of Other Waste. Separation of Contaminated Materials. Segregate the hazardous materials from non-hazardous materials to prevent contaminating larger quantities of material.
Part 200 — Earthwork and Erosion Control August 2025
200-30 SECTION 202 — EXCAVATION AND EMBANKMENT Regulatory Requirements. Perform all work to comply with RIDEM or other State, Federal, or local agency regulations pertaining to the proper testing, removal, containment, transporting, and disposal of known or suspected other waste, debris, or surplus materials resulting from the Project. The following documents are commonly required in the Contract for RIDOT Projects: • Rhode Island Rules and Regulations for the Investigation and Remediation of Hazardous Materials (the Remediation Regulations) (250-RICR-140-30-1) • Rhode Island Rules and Regulations for Hazardous Waste Management • Rhode Island Solid Waste Regulations • Rhode Island Oil Pollution Control Regulations • “Hazardous Waste Operations and Emergency Response,” Federal Occupational Safety and Health Act (OSHA), 29 CFR 1910.120 • “General Regulations for Hazardous Waste Management,” USEPA, 40 CFR 260 • “Regulations for Identifying Hazardous Waste, Hazardous Waste Generators and Hazardous Waste Transporters,” EPA, 40 CFR 261, 262 and 263 • US Department of Transportation (USDOT) Title 49 Code of Federal Regulations (CFR) • Safety and Health Regulations Promulgated by the US Department of Labor, OSHA, 29 CFR 1910 – Occupational Safety and Health Standards and 29 CFR 1926 – Safety and Health Regulations for Construction • USEPA Standard Operating Safety Guidelines – Office of Emergency and Remedial Response, Emergency Response Division • USEPA Medical Monitoring Program Guidelines Health and Safety. Health and safety measures must comply with SECTION 826. Conformance. While engaged in contaminated waste material transportation and disposal, the Engineer will provide on-site inspection. If the work violates any requirements of this or any other specification or violates any State, local, or Federal regulation, the Engineer may issue a stop work order effective immediately and until the violation is resolved. Standby time and expenses required to resolve the violation will be at no additional cost to the Department. The disposal of waste or other material that becomes contaminated as a result of careless handling or use of unauthorized procedures by the Contractor or its employees/subcontractors will be at no additional cost to the Department.
Part 200 — Earthwork and Erosion Control August 2025
SECTION 202 — EXCAVATION AND EMBANKMENT 200-31 Contaminated Waste Transportation and Disposal. Obtain all necessary permits, manifests, shipping papers, bills of lading, and acceptance approvals in conjunction with contaminated hazardous material/waste and/or solid waste removal, hauling, transportation, and disposal. Provide timely notification of the actions as required by applicable Federal, State, and/or local authorities. Transport all contaminated waste to an off-site recycling or disposal facility according to applicable local, State, and Federal regulations governing the transportation, recycling, and disposal of the waste.
202.04 Method of Measurement.
Excavation – General. The quantities of all types of excavation will be measured in the cubic yards as surveyed or calculated. Two sets of cross sections will be taken over the area to be excavated ― one for the area in its original position and one after completion of the excavation. Intermediate sets of cross sections may be taken for progress payments. The cross sections will be taken at intervals by field survey techniques. If the final set of cross sections demonstrate unauthorized excavation below the specified subgrade, the excess excavation will not be measured for payment. Replace and compact the excess excavation by suitable excavation or borrow material, at no additional cost to the Department. The final set of cross sections may include an amount for overbreakage or slides that, in the judgment of the Engineer, were not caused by the Contractor’s carelessness. The cross sections will be plotted and the volume determined by either the average end- area method or other equivalent method.
Part 200 — Earthwork and Erosion Control August 2025
200-32 SECTION 202 — EXCAVATION AND EMBANKMENT Overbreakage from blasting will not be measured for payment. Remove as directed at no additional cost to the Department.
Part 200 — Earthwork and Erosion Control August 2025
SECTION 202 — EXCAVATION AND EMBANKMENT 200-33 construction will not be measured or paid for separately and will be considered incidental to the various classifications of excavation. However, when embankment is constructed from excavation material and there is required borrow material to complete the embankment, this borrow material will be measured for payment. Appurtenances, structures, pipes, and drainage structures less than 50 cu yd in volume will not be deducted from embankment volumes for measurement of embankment or measurement of borrow for embankment. If the Contractor places more borrow than is required and thereby causes a waste of excavation, the waste will be deducted from the borrow volume as measured. Borrow. Common Borrow, Gravel Borrow, or other borrow approved for use to replace unsuitable materials removed by excavation or to construct embankment will be measured by the cubic yard as in- place and compacted. This volume will be determined by the difference in areas using cross sections as described in Subsection 202.04.1. Handling, Hauling, and Stockpile Management of Contaminated Soils and Unclassified Soils. This item will be measured for payment by the ton. The number of tons will be determined from weight slips generated by a certified scale at the receiving facility or at a location approved by the Engineer. Load, Haul, and Dispose Soil, Type 1. This item will be measured for payment by the tons of soil loaded, hauled, and disposed. The number of tons will be determined from weight slips generated by a certified scale at the receiving facility or at a location approved by the Engineer. Load and Haul Contaminated Soil, Type 2. This item will be measured for payment by the tons of soil loaded and hauled. The number of tons will be determined from weight slips generated by a certified scale at the receiving facility or at a location approved by the Engineer. Disposal of Contaminated Soil, Type 2. This item will be measured for payment by the tons of soil disposed. The number of tons will be determined from weight slips generated by a certified scale at the receiving facility or at a location approved by the Engineer.
Part 200 — Earthwork and Erosion Control August 2025
200-34 SECTION 202 — EXCAVATION AND EMBANKMENT Load and Haul Contaminated Soil, Type 3. This item will be measured for payment by the tons of soil loaded and hauled. The number of tons will be determined from weight slips generated by a certified scale at the receiving facility or at a location approved by the Engineer. Disposal of Contaminated Soil, Type 3. This item will be measured for payment by the tons of soil disposed. The number of tons will be determined from weight slips generated by a certified scale at the receiving facility or at a location approved by the Engineer. Load and Haul Contaminated Soil, Type 4. This item will be measured for payment by the tons of soil loaded and hauled. The number of tons will be determined from weight slips generated by a certified scale at the receiving facility or at a location approved by the Engineer. Disposal of Contaminated Soil, Type 4. This item will be measured for payment by the tons of soil disposed. The number of tons will be determined from weight slips generated by a certified scale at the receiving facility or at a location approved by the Engineer. Load, Haul, and Dispose Of Contaminated Soil, Type 5. This item will be measured for payment by the actual cost, verified by the Force Account records, for the facility profiling, loading, transporting, and disposing, and by Invoices from the disposal facility per soil type. Load, Haul, and Disposal of Other Waste. Load, Haul, and Disposal of Other Waste will be measured for payment by the tons of the removed, handled, and disposed waste. The number of tons will be determined from weight slips generated by a certified scale at the receiving facility or at a location approved by the Engineer.
202.05 Basis of Payment.
The Department will pay for the completed and accepted quantities at the Contract unit prices as follows.
Part 200 — Earthwork and Erosion Control August 2025
SECTION 202 — EXCAVATION AND EMBANKMENT 200-35 Pay Item Pay Unit Earth Excavation CY Rock Excavation CY Rock Excavation – Mechanical CY Muck Excavation CY Channel Excavation – Earth CY Channel Excavation – Rock CY Channel Excavation – Rock Mechanical CY Loam Excavation CY Unclassified Excavation CY Presplitting Bedrock SY Common Borrow CY Gravel Borrow CY Handling, Hauling, and Stockpile Management of Contaminated Soils and Unclassified Soils TON Load, Haul, and Dispose Soil, Type 1 TON Load and Haul Contaminated Soil, Type 2 TON Disposal of Contaminated Soil, Type 2 TON Load and Haul Contaminated Soil, Type 3 TON Disposal of Contaminated Soil, Type 3 TON Load and Haul Contaminated Soil, Type 4 TON Disposal of Contaminated Soil, Type 4 TON Load, Haul, and Disposal of Contaminated Soil, Type 5 Force Account Load, Haul, and Disposal of Other Waste TON Payment at the Contract unit prices is full compensation for all resources, labor, materials, equipment, and incidentals required to finish the work according to the Contract, complete and accepted. Excavation. Grading, compaction, and disposal of surplus material is incidental to this work and no separate payment will be made. Rock removal in excess of 12 in. below subgrade will not be paid for but will be measured to determine excess backfill volume. The volume will be deducted from that backfill measured for
Part 200 — Earthwork and Erosion Control August 2025
200-36 SECTION 202 — EXCAVATION AND EMBANKMENT payment. Perform all backfilling in excess of the 12 -in. depth at no additional cost to the Department. No payment will be made for additional excavation quantities caused by the offsetting of presplitting holes beyond the specified face in the top or successive stages. Compensation for haul ing earthwork materials within the Project limits will not be paid for separately but will be included in the Contract unit prices for the items. Borrow. Common Borrow and/or Gravel Borrow will be paid for at their Contract unit prices per cubic yard, if in the Contract for embankment construction or if approved for replacement of unsuitable soils in excavation or under shallow embankment. Handling, Hauling, and Stockpile Management of Contaminated Soils and Unclassified Soils. The accepted quantities of Handling, Hauling, and Stockpile Management of Contaminated Soils and Unclassified Soils will be paid for at the Contract unit price per ton. Load, Haul, and Dispose Soil, Type 1. This item will be paid for at the Contract unit price per ton. Load and Haul Contaminated Soil, Type 2. This item will be measured for payment by the tons of soil loaded and hauled. Disposal of Contaminated Soil, Type 2. This item will be paid for at the Contract unit price per ton. If the actual cost paid to the disposal facility for disposing this material is different than the only acceptable bid price, the price paid per ton for this item will be adjusted (higher or lower) by that difference in Dollars/Ton. Load and Haul Contaminated Soil, Type 3. This item will be paid for at the Contract unit price per ton. Disposal of Contaminated Soil, Type 3. This item will be paid for at the Contract unit price per ton. If the actual cost paid to the disposal facility for disposing this material is different than the only acceptable bid price, the price paid per ton for this item will be adjusted (higher or lower) by that difference in Dollars/Ton. Load and Haul Contaminated Soil, Type 4. This item will be paid for at the Contract unit price per ton.
Part 200 — Earthwork and Erosion Control August 2025
SECTION 202 — EXCAVATION AND EMBANKMENT 200-37 Disposal of Contaminated Soil, Type 4. This item will be paid for at the Contract unit price per ton. If the actual cost paid to the disposal facility for disposing this material is different than the only acceptable bid price, the price paid per ton for this item will be adjusted (higher or lower) by that difference in Dollars/Ton. Load, Haul, and Dispose of Contaminated Soil, Type 5. This item will be measured for payment by the actual cost, verified by the force account records for the facility profiling, loading, transporting, and disposing, and the Invoices from the disposal facility per soil type referenced herein. Load, Haul, and Dispose of Other Waste. This item will be paid for at the Contract unit price per ton. If the actual cost paid to the disposal facility for disposing this material is different than the only acceptable bid price, the price paid per ton for this item will be adjusted (higher or lower) by that difference in Dollars/Ton.