4-5 SECTIO N 404 – BITUMINOU S SURFAC E TREATMEN TS
404.01 DESCRIPTION . This work shall consist of furnishing and applying a bituminous treatment on an
approved surface.
404.02 MATERIALS . Materials shall meet the requirements of the following subsections:
Anionic Emulsified Asphalt ................................ ................................ ....................... 702.02(a) Cationic Emulsified Asphalt ................................ ................................ ...................... 702.0 2(b) Polymer -Modified Emulsified Asphalt ................................ ................................ ......702.02(c) Sand Cover ................................ ................................ ................................ ................. 704.11(a)
404.03 WEATHER LIMITATIONS . Bituminous material shall only be applied when the following
conditions prevail.
404.05 PREPARATION OF SURFACES . All surfaces to be treated shall be dry, patched, and free of
irregularities in order to provide a reasonably smooth and uniform surface. Any necessary surface preparation, patching, or crack sealing shall be performed in accordance with Section 406 and Section 417. The Contractor shall clean the surfaces prior to treatment and remove all loose or objectionable material, dust, and debris. All drop inlets, catch basins, and manholes shall be covered prior to application of the treatment and uncovered after application. 4-7 404.06 APPLICATION OF BITUMINOUS MATERIALS .
702.02 It shall be applied by distributors in a uniform, continuous spread over the area to be treated
at the temperature recommended by the manufacturer. The application rate shall be as specified in Table 404.06D , or as directed by the Engineer. 4-9 TABLE 404.06D – EMULSIFIED ASPHALT SEAL COAT APPLICATION RATE Surface Type Application Rate (gal/SY) All 0.100 – 0.140 Sand cover material, meeting the requirements of Subsection 704.11(a) or as approved by the Engineer, shall be applied immediately after the emulsified asphalt, prior to the emulsion breaking or curing, using an aggregate spreader attached to the distributor. The application rate for sand cover material shall be as specifie d in Table 404.06E , or as directed by the Engineer. The Contractor shall be required to apply additional sand cover material above the prescribed rate in the event excessive emulsified asphalt is applied. TABLE 404.06E – SAND COVER APPLICATION RATE Surface Type Application Rate (lbs/SY) All 0.350 – 0.650 Following application of the sand cover material, the Contractor shall perform pavement friction testing in accordance with AASHTO T 242 . The surface shall exhibit a minimum skid resistance value of 35. One test shall be performed each day of production. T ests shall be conducted using the standard ribbed tire as specified by AASHTO M 261 . Testing equipment shall have been calibrated no more than 3 years before the start of testing. Calibration documents shall be provided to the Engineer prior to testing. The Contractor shall maintain the treated surfaces until the Contract is complete and the work accepted. Holes or irregularities shall be repaired by filling them with material acceptable to the Engineer.
404.07 TRAFFIC CONTROL . Equipment or traffic will not be allowed on the emulsion treated surface
until the emulsion has fully cured and the treatment will not “pick up” under traffic, or as directed by the Engineer.
404.08 PROTECTION OF STRUCTURES , VEHICLES, AND TREES . The Contractor shall use care in
applying bituminous material and protecting surfaces of adjacent structures, vehicles, and trees from being spattered with the material. The use of skirting or end panels may be required to control application widths and limit overspray. 4-10 404.09 METHOD OF MEASUREMENT . The quantity of Tack Coat, Emulsified Asphalt; Tack Coat, Polymer -Modified Emulsified Asphalt; Fog Seal, Emulsified Asphalt; and Seal Coat, Emulsified Asphalt to be measured for payment will be the number of hundredweight used in the complete and accepted work. The quantity of Cover Material, Sand to be measured for payment will be the number of pounds used in the complete and accepted work.
404.10 BASIS OF PAYME NT. The accepted quantity of Tack Coat, Emulsified Asphalt; Tack Coat,
Polymer -Modified Emulsified Asphalt; Fog Seal, Emulsified Asphalt; and Seal Coat, Emulsified Asphalt will be paid for at the Contract unit price per hundredweight. Payment will be full compensation for cleaning the roadway surface; furnishing, transporting, and placing the emulsified asphalt; and for furnishing all materials, labor, tools, equipment, and incidentals necessary to complete the work. The quantity of Cover Material, Sand wil l be paid for at the Contract unit price per pound. Payment will be full compensation for furnishing, hauling, and placing the material specified; performing friction testing and supplying test reports; and for furnishing all labor, tools, testing apparatu ses, equipment, and incidentals necessary to complete the work. Surface preparation, patching, and crack sealing will be paid for separately in accordance with Section 406 and Section 417 . Payment will be made under: Pay Item Pay Unit 404.1100 Tack Coat, Emulsified Asphalt ................................ ................................ .Hundredweight 404.1200 Tack Coat, Polymer -Modified Emulsified Asphalt ................................ ..Hundredweight 404.3100 Fog Seal, Emulsified Asphalt ................................ ................................ ...Hundredweight 404.5100 Seal Coat, Emulsified Asph alt ................................ ................................ ..Hundredweight 404.8100 Cover Material, Sand ................................ ................................ ................ Pound 4-11 SECTIO N 406 – BITUMINOU S CONCRET E PAVEMENT 406.0 1 DESCRIPTION . This work shall consist of constructing one or more courses of Superpave bituminous concrete pavement on a prepared foundation in accordance with these specifications and in conformance with the lines, grades, thicknesses, and typical cross -sections shown on the Plans or established by the Engineer. The Agency will accept this work under quality assurance provisions, in accordance with these specifications and the provisions of AASHTO M 323 except where otherwise noted in Section 702 , Section 704, Section 716 , and the Agency’s Bitumi nous Concrete Policy Manual . 406.0 2 MATERIALS . Materials shall meet the requirements of the following subsections: Performance -Graded Asphalt Binder ................................ ................................ ......... 702.01 Emulsified Asphalt ................................ ................................ ................................ .....702.02 Warm -Mix Asphalt Technologies ................................ ................................ .............. 702.03 Anti-Strip Additives ................................ ................................ ................................ ...702.04 Aggregate for Bituminous Concrete Mixtures ................................ ........................... 704.10 Recycled Asphalt Materials ................................ ................................ ....................... 704.2 2 General Bituminous Concrete Mixture Design Requirements ................................ ..716.02(a) Superpave Mixtures ................................ ................................ ................................ ...716.02(b) Bituminous Mixing Plant and Laboratory ................................ ................................ .716.03 Preparing and Mixing Bituminous Concrete Mixtures ................................ .............. 716.04 406.0 3 AGENC Y MATERIA L EVALUATION . Material evaluation and acceptance by the Agency will follow the procedures outlined in this subsection for the applicable quality assurance tier and Contract item. Acceptance sampling of bituminous materials by the Agency will be on a statistically random basis in accordance with the specified requirements, and the material will be evaluated for acceptance based on the results of these tests. Contractor quality control samples will not be used to evaluate, accept, reject, or determine pay factors for any material. Material may be sampled at either the production facility or on the project site and may be tested at either the production facility ’s qualified laboratory or at the Agency’s Mate rials Testing and Certification Section Central Laboratory .