4-46 Sectio N 407 – Bonde D Wearin G Course
407.0 1 DESCRIPTION . This work shall consist of applying a bonded wearing course pavement. This work shall be performed in conformance with the lines, grades, thicknesses, and typical cross -sections shown on the Plans or established by the Engineer. 407.0 2 MATERIALS . Materials shall meet the requirements of the following subsections: Performance -Graded Asphalt Binder ................................ ................................ ......... 702.01 Polymer -Modified Emulsified Asphalt ................................ ................................ ......702.02(c) Anti-Strip Additives ................................ ................................ ................................ ...702.04 Aggregate for Bituminous Concrete Mixtures ................................ ........................... 704.10 General Bituminous Concrete Mixture Design Requirements ................................ ..716.02(a) Bonded Wearing Course Mixtures ................................ ................................ ............. 716.02(c) Bituminous Mixing Plant and Laboratory ................................ ................................ .716.03 Prepari ng and Mixing Bituminous Concrete Mixtures ................................ .............. 716.04 407.0 3 AGENC Y MATERIA L EVALUATION . Bonded wearing course will be sampled and tested on a statistically random basis for both quality control and acceptance in accordance with the specified requirements, and the material quality will be evaluated based on the results of these tests. The act ual mixture produced shall not vary from the job mix formula target values by more than production tolerances specified in Table 407.03A . For the purposes of verification sampling, the tolerances given in Table 407.03A will be considered the specification limits for an individual sample. Continued production outside these ranges will be grounds to halt production and rescind the mix design. TABLE 407.03A – MIXTURE PRODUCTION TOLERANCES Material Property Lower Mixture Tolerance Upper Mixture Tolerance Aggregate, percent passing the 3/8 inch (9.50 mm) or larger sieves (dry sieve) JMF – 4% JMF + 4% Aggregate, percent passing the No. 4 (4.75 mm) sieve through the No. 16 (1.18 mm) sieves (dry sieve) JMF – 3% JMF + 3% Aggregate, percent passing the No. 30 (0.600 mm) sieve through the No. 100 (0.150 mm) sieves (dry sieve) JMF – 2% JMF + 2% Fines, percent passing the No. 200 (0.075 mm) sieve (dry sieve) JMF – 1.5% JMF + 1.5% Mixture temperature 1 JMF – 20°F JMF + 20°F Asphalt binder content JMF – 0.4% JMF + 0.4% 1 The m ixture temperatures shall not exceed 355°F.
4-47 Material may be sampled at either the production facility or on the project site and may be tested at either
the production facility ’s qualified lab, or at the Agency’s Materials Testing and Certification Section Central Laboratory .
4-48 The plant sh all be operated so that no intentional deviations are made from the approved job mix
formula. T he continual production of non -conforming work at a reduced price, in lieu of making adjustments to bring work into conformance, will not be allowed. The Contractor shall provide process control adequate to produce work of acceptable quality. At a minimum, the Contractor shall perform sampling and testing at the frequencies specified in Table 407.04A as applicable for the mixture type, and shall calculate the cumulative weighted PWL using the equation specified in Subsection 407.06(a)(1) after each quality control sublot . The Engineer will not sample or test for process control or assist in controlling t he Contractor’s production operations. TABLE 407.04A – QUALITY CONTROL TESTING AND SAMPLING CRITERIA Parameter Test Method Minimum Frequency (Select the Least Frequent) Mixture gradation AASHTO T 30, AASHTO T 308 1 per 500 tons Mixture temperature Verified thermometer 1 per 250 tons at plant (truck) Asphalt binder content AASHTO T 308 1 per 500 tons Cold feed gradation AASHTO T 27 1 per day Cold feed percentage fractured face 1 AASHTO T 335 1st day of paving, 1 per week or 5,000 tons Cold feed flat and elongated particles 2 ASTM D4791 1 per month Fine and coarse aggregate moisture content 3 AASHTO T 255 2 per day Stripping 4 ASTM D3625 1 per week 1 Fractured faces for crushed gravel sources only. 2 Flat and elongated percentage for all material retained on or above the No. 4 (4.75 mm) sieve. 3 For drum -mix and continuous mixing plants only. 4 Stripping testing for stripping prone aggregates only. Testing will be witnessed by Agency staff. Control over production shall follow the control limits established for the mix design for quality control samples. A single result outside the control limit will necessitate the Contractor take action to return production to in control. Production shall be suspended if two out of three values in row exceed the control limits , or if the quality control cumulative weighted PWL falls below 60%.
4-49 After suspens ion, a passing quality control test from a trial drop shall be used to show the mix has
been returned to in control, and production may resume. Following a PWL suspension, three tests will be conducted before reevaluating for suspension of production based on the total project PWL, however, production shall be suspended if two out of those three tests exceed the control limits. Failure or inaction by the Contractor to maintain control over the mix production will result in mix design suspension.
4-50 407.0 5 Constructio N Requirements
4-51 (c) Preparation of Surfaces . The existing bituminous concrete pavement surface shall be prepared as
shown on the Plans and as directed by the Engineer prior to applying the polymer -modified emulsified asphalt. This shall include patching, pothole repairs, raveling repairs, crack seali ng, and other repairs directed by the Engineer and performed in accordance with Subsection 406.08 and Subsection 417.05(c) . Surface preparation material shall be a bituminous material or mixture approved by the Engineer or as otherwise specified. The sur face of the area to be overlaid shall be thoroughly cleaned and free of dirt, oil, debris, other foreign materials, and standing water. All utility structures within the area to be paved shall be covered with material approved by the Engineer and referenc ed for location and adjustment, if necessary, after paving.
4-52 407.0 6 MIXTUR E PROPERTIE S PAY ADJUSTMENT . The Mixture Properties Pay Adjustment will
be based on the Mixture Properties Pay Factor calculated using the equations specified below.
4-53 (2) Mixture Properties Pay Factor . Once the weighted PWL for gradation has been determined,
the Mixture Properties Pay Factor will be calculated using the formulas below. For 85% ≤ PWL W ≤ 100% 𝑃𝐹𝑀𝑃=0.00067 𝑃𝑊𝐿 𝑊−0.05700 For 50% ≤ PWL W < 85% 𝑃𝐹𝑀𝑃=0.00286 𝑃𝑊𝐿 𝑊−0.24310 For PWL W < 50% 𝑃𝐹𝑀𝑃=0.00800 𝑃𝑊𝐿 𝑊−0.50000 where: PWL W = Weighted percent within specification limits PFMP = Mixture Properties Pay Factor
4-54 407.0 7 METHO D OF MEASUREMENT . The quantity of Bonded Wearing Course of the type specified
to be measured for payment will be the number of square yards of mixture complete in -place in the accepted work. The quantit y of all applicable Pay Adjustments will be calculated according to the appropriate subsection. 407.0 8 BASIS OF PAYMENT . The accepted quantity of Bonded Wearing Course of the type specified will be paid for at the Contract unit price per square yard. Payment will be full compensation for furnishing, mixing, hauling, and placing the material specified, and for furnishing all labor, materials, and equipment necessary to complete the work. The costs of furnishing testing facilities and supplies at the plant will be considered included in the Contract unit price for Bonded Wearing Course. Surface preparation, patching, and crack sealing will be paid for separately in accordance with Section 406 and Section 417 . The quantity of all Pay Adjustments will be debited or credited against the Contract dollar amounts for those items. Payment will be made under: Pay Item Pay Unit 407.0100 Bonded Wearing Course, Type A ................................ ............................. Square Yard 407.0200 Bonded Wearing Course, Type B ................................ ............................. Square Yard 407.0300 Bonded Wearing Course, Type C ................................ ............................. Square Yard 407.9100 Pay Adjustment, BWC, Mixture Properties (N.A.B.I.) ............................ Dollar
4-55 Sectio N 410 – Materia L Transfe R Vehicle
410.0 1 DESCRIPTION . This work shall consist of furnishing and using an approved material transfer vehicle (MTV) in bituminous concrete paving operations. 410.0 2 CONSTRUCTIO N REQUIREMENTS . An approved MTV shall be used to transfer the bituminous material from the hauling equipment to the paver . The MTV shall operate independently from the paver and shall be a commercially manufactured unit specifically designed for the transfer of mix from the hauling equipment to the paver without depositing the mix on the roadway surface . The MTV or separate hopper shall be designed such that the deposited mix is remixed prior to placement on the roadway . The minimum storage capacity of the MTV, not including any separate hopper, shall be 12 tons. The MTV shall be capable of swing ing or offsetting the material transfer delivery system to side discharge into the paver. If the MTV and associated actions do not effectively eliminate mat segregation as determined by the Engineer, the Engineer may require a hopper insert with remixing c apabilities or other measures . When the MTV traverses a bridge that is not a buried structure, it shall be as near to empty as possible and shall not exceed 5 mph while on any structure . 410.0 3 METHO D OF MEASUREMENT . The quantit y of Material Transfer Vehicle to be measured for payment will be the number of tons of bituminous pavement transferred by the MTV to the paver in the completed and accepted work , as determined by the weigh slips. 410.0 4 BASIS OF PAYMENT . The accepted quan tity of Material Transfer Vehicle will be paid for at the Contract unit price per ton . Payment will be full compensation for the equipment as specified and for furnishing all labor, tools, equipment , and incidentals necessary to complete the work . Payment will be made under: Pay Item Pay Unit 410.10 00 Material Transfer Vehicle ................................ ................................ ......... Ton