B
HomeLibrariesCopilotSearchProjectsBookmarks
FeedbackHelp Desk
Libraries
Building Codes
Code LibraryIBC — BuildingIRC — ResidentialIFC — FireIPC — PlumbingIMC — MechanicalIFGC — Fuel GasIECC — EnergyNEC — ElectricalModel Codes
Specifications
CSI SpecificationsDOT SpecsTransit SpecsUSACE
Standards
TransportationRailroadFire SafetyAccessibilityStructural
Tools & References
DiagramsAssembliesProductsCalculatorsChecklistsPermits
PricingLog in
General Provisions (00100-00999)

536RELAID PIPE

AL · 2022 Standard SpecificationsBook pages 419419View official source ↗

536.01 Description.

The deformation is unacceptably excessive if the mandrel cannot be pulled through the pipe by hand without damaging the pipe. If the deformation is unacceptably excessive, the pipe shall be replaced without extra compensation. There will be no direct payment f or testing.

535.04 Method of Measurement.

Side drain pipe will be measured in the same manner as specified in Article 530.04. Excavation and foundation backfill for side drain pipe will not be measured separately for payment, but the cost thereof shall b e included in the contract unit price bid for the side drain pipe.

535.05 Basis of Payment.

a.Unit Price Coverage. Accepted side drain pipe, measured as specified above, will be paid for at the contract unit price per foot {meter} for the respective item s, which shall be payment in full for furnishing pipe, excavating trenches, placing pipe, backfilling trenches, and for all tools, equipment, labor, and incidentals necessary to complete the work.
b.Payment Will Be Made Under Item No.: 535-A ___ inch {mm} Side Drain Pipe ( * ) - per linear foot {meter} 535-B ___ inch {mm} Span, ___ inch {mm} Rise Side Drain Pipe ( * ) - per linear foot {meter} * Show specific type, class, or wall thickness, if required. Example: V.C., or P.C., or Class ___ _ R.C., or ___ gage {mm} C.A., or ___ gage {mm} C.S., or ___ gage {mm} C.C.S., or ___ gage {mm} C.C.A. RELAID PIPE

536.01 Description.

This Section shall cover the work of relaying pipe, regardless of size, in accordance with the requirements of these specifications, at the locations shown on the plans or designated and in accordance with established lines and grades. The item shall inclu de furnishing and construction of such joints, necessary cutting and connections to other pipes, the removal and preservation of that portion of pipe culverts, in place, which are to be replaced by new or relaid pipe; it shall also include furnishing and construction of such joints, necessary cutting and connections to other pipes, catch basins, endwalls, etc., as may be required to complete the work shown on the plans or directed.

536.02 Materials.

a.Salvaged Pipe . Pipe to be relaid shall be selected sal vaged pipe which is approved for relaying.
b.Joint Material . An applicable type of joint sealer required by Article 530.02 shall be used.

536.03 Construction Requirements.

a.Removing Pipe in Place . Removal of pipe shall be in accordance with the provis ions of Article 206.03.
b.Laying Pipe . Pipe shall be handled so that there will be no loss or damage, before relaying. Pieces or sections of pipe found satisfactory by the Engineer shall be relaid in accordance with the requirements of the appropriate sections governing culvert pipe. Special reference is made to construction details of Section 530 which are applicable to side drain pipe relaid.

536.04 Method of Measurement.

Relaid pipe will be measured in the same manner as specified in Article 530.04. Ex cavation and foundation backfill for relaid pipe will not be measured separately for payment, but the cost thereof shall be included in the contract unit price bid for the relaid pipe.

538.03 Construction Requirements.

536.05 Basis of Payment.

a.Unit Price Coverage .
1.The accepted length of relaid culvert pipe, measured as noted above, will be paid for at the contract unit price bid for either roadway pipe relaid or side drain pipe relaid, regardless of size or type of pipe. Said unit costs shall be full compensation fo r the salvaging of the pipe in conditions for reuse and the re -installation of the pipe in accordance with the provision for roadway pipe as covered by Section 530 and Section 535 for side drain pipe including all equipment, tools, labor, and incidentals necessary to complete the work.
2.No payment will be made for the removal of existing pipe lines replaced by new or relaid pipe, except for that portion of the old pipe removed outside the limits of excavation provided by Subarticle 214.04(a).
b.Payment will be made under Item No .: 536-A Roadway Pipe Relaid - per linear foot {meter} 536-B Side Drain Pipe Relaid - per linear foot {meter} SECTION 538 ROADWAY PIPE REHABILITATION

538.01 Description.

This Section shall cover the work of rehabilitating roadway pipe using a cured -in-place liner, polyethylene (PE) liner pipe, or a liner shown on the plans, at the locations shown on the plans or directed by the Engineer.

538.02 Materials.

a.Cured -in-Place Liner. Cured -in-Place Liner material shall be a lining system selected from List II -32 of the Department’s MSDSAR . All cured -in-place lining products shall comply with ASTM F -1216, "Rehabilitation of Existing Pipelines and Conduits by the Inversion and Curing of a R esin-Impregnated Tube", ASTM F -1743, "Rehabilitation of Existing Pipelines and conduits by Pulled -in-Place Installation of Cured -in-Place Thermosetting Resin Pipe (CIPP)", or ASTM F -2019 “Rehabilitation of Existing Pipelines and Conduits by the Pulled in P lace Installation of Glass Reinforced Plastic (GRP) Cured -in-Place Thermosetting Resin Pipe (CIPP), including appendices. The liner shall be a flexible tube fabricated to a size that, when installed, shall fit the internal circumference of the existing ro adway pipe. Allowance shall be made for circumferential stretching during insertion so that the final cured product is snug against the wall of the host pipe. The material shall be able to stretch to fit irregular pipe sections and negotiate bends. Any com pounds, process water or condensate used during the installation or curing operation shall be contained, removed from the site and disposed of in a manner approved by the Engineer.
b.PE or HDPE Liner Pipe. Polyethylene or high density polyethylene liner pipe shall be selected from List II -32 of the Department’s MSDSAR .
c.Liner Shown on the Plans. Any liner shown on the plans may be used as an alternate to cured -in-place liner or PE liner pipe. The material requirements for alternate liners will be show n on the plans.
d.Minimum Length of Liner. The minimum length of liner material shall span the distance from the inlet to the outlet of the pipe, unless required otherwise by the Engineer or shown otherwise on the plans.

538.03 Construction Requirements .

a.Submittals. The Contractor shall submit eight copies of the product data and installation procedures of the cured -in-place liner, or PE liner pipe for review and distribution. The product data for PE liner pipe shall include actual certified test reports meeting AASHTO M 326. The submittal of the product data
Source: Alabama Standard Specifications for Highway Construction, 2022 Edition. Pages 419419 of 934.