534.05 Basis of Payment.
The horizontal opening of a culvert will also be sho wn as a classification for payment. The horizontal opening of a culvert shall be the horizontal opening in a single barrel culvert or the sum of the horizontal openings in a multiple barrel culvert. Two classifications of horizontal opening will be given f or the purpose of measurement for payment. The first classification of horizontal opening shall be structures with an opening less than or equal to 48 inches. The second classification of horizontal opening shall be structures with an opening greater than 48 inches. If separate pay items are not shown on the plans for cleaning catch basins, manholes, and other appurtenances to the structures measured by linear feet (pipes and culverts), the cleaning of these appurtanancies will be measured for payment by i ncluding the length through the appurtenances in the total number of linear feet of the attached drainage structure. The length through an appurtenance will be added to the length of the largest structure connected to the appurtenance.
534.05 Basis of Pay ment.
a.Unit Price Coverage . The contract unit price for cleaning existing drainage structures shall be full compensation for all materials, tools and labor required for cleaning the structures, disposing of all materials that are removed from the struct ure and installing new rodent screens.
b.Payment will be made under Item No .: 534-A Cleaning Pipe Underdrain Outlets - per each 534-B Cleaning Existing Catch Basin - per each 534-C Cleaning Existing Manhole - per each 534-D Cleaning Existing Drop Inlet - per each 534-E Cleaning Existing * (Less Than Or Equal To 48" Horizontal Opening) - per linear foot 534-F Cleaning Existing * (Greater Than 48" Horizontal Opening) - per linear foot * Pipe, Culvert, etc. SIDE DRAIN PIPE
535.01 Description.
This Section shall cover the work of furnishing and installing side drain pipe in conformity with these specifications. The word "pipe" in this Section shall include both round and arch pipe. It shall cover only those pipes specifically designated on the plans as side drain; it shall not apply to other pipes laid parallel to the roadway. The kind, type, and size of each side drain pipe will be shown on the plans or in the proposal. The location of each will be shown on the plans or designated. This Section shall include furnishing and constructing such joints and necessary cutting to provide connections to other drainage facilities, and other incidentals necessary for completion of t he work.
535.02 Materials.
a.General Materials furnished for use shall conform to the appropriate requirements of Division 800, Materials, with specific reference made to Sections 831, 846 and 851.
b.Abbreviations: Side Drain SD Concrete PC for Plain Concrete Pipe RC for Reinforced Concrete Pipe Vitrified Clay VC Corrugated Metal CM for Plain Corrugated Metal CCM for Coated Corrugated Metal Corrugated Aluminum CA for Plain CCA for Coated Corrugated Steel CS for Plain CCS for Coated Plastic ABS for Acrylonitrile Butadiene Styrene
534.05 Basis of Payment.
HDPE for High Density Polyethylene PP for High Performance Polypropylene PVC for Polyvinyl Chloride
c.Optional Types of Pipes. Provided a specific type of pipe is not specified by the plans or proposal, the Contractor will be permitted to install any of the optional types of pipe herein. Substitutions will only be allowed with hydraulically equivalent pipes. The hydraulic equivalence of optional types of pipes will be shown on the plans. Optional types of p ipe shall meet the following criteria: • Diameters less than or equal to 24 inches {600 mm} – P.C.; V.C.; 16 gage {1.6 mm} C.M. with greater than or equal to 24 inches {600 mm} of cover, 14 gage {2.0 mm} CM with less than 24 inches {600 mm} cover; or P.V. C., A.B.S. or HDPE, or PP pipe (HDPE and PP up to 36 inches {900 mm} diameter) with minimum of 24 inches {600 mm} of cover, and maximum of 25 feet {7.5 m} fill height. • Diameters greater than 24 inches {600 mm} - Class 2 R.C.; V.C.; 14 gage {2.0 mm} C.M. ; P.V.C. or HDPE and PP(HDPE and PP up to 36 inch {900 mm} diameter) with a minimum of 24 inches {600 mm} of cover, and a maximum of 25 feet {7.5 m} fill height. Higher strength and/or coated finish CM pipe when required will be noted in the pay item. The Contractor may, at his option, substitute a higher grade pipe than specified or, with written approval, a cast iron or ductile iron pipe meeting the appropriate requirements of Section 854, provided no additional cost is incurred by the Department for such substitution. Any installation, once started, shall be completed using the same type of pipe unless specifically designated otherwise by plan details or requested and approved in writing.
535.03 Construction Requirements.
a.General. Construction details for installing side drain pipe shall be as specified in Section 530, except as modified in this Section. The requirements of Subarticle 530.03(b) for partial construction of fills in advance of trenching will not apply. Trenches shall be excavated as specified in Section 214. No separate measurement or direct payment will be made for excavation and backfill of trenches for side drain pipes. Special bedding will not be required; however, the pipe shall be bedded with ordinary care in the lo osened soil foundation of the trench. Should the material at the elevation of the bottom of the pipe be ledge rock or other unsuitable bedding, it shall be excavated without additional compensation. The pipe shall be installed so that it will not vary at a ny point more than 1 inch {25 mm} from established line and grade. The pipe shall be backfilled in thoroughly compacted layers not more than 6 inches {150 mm} in thickness, using pneumatic tamps unless otherwise directed, but there will be no specific dens ity requirements. Backfill shall be ordinary excavation material.
b.Testing for Excessive Deformation in PVC, HDPE, and PP Pipe. PVC, HDPE, and PP pipe shall be tested for excessive deformation. The test shall be performed by the Contractor in the presen ce of the Engineer. Testing shall be conducted no fewer than 30 days after the completion of the compaction of all fill over the pipe. The Contractor shall conduct the test by pulling a nine point mandrel through the entire length of the pipe by hand. The mandrel shall meet the following requirements: • It shall be made of steel or aluminum; • It shall have an effective diameter of 95 % of the nominal inside diameter of the pipe; • It shall be at least as long as the diameter of the pipe; • It shall be fitted with pulling rings at each end; • It shall be stamped or engraved on some segment other than a runner with the pipe size and mandrel outside diameter. Prior to testing, the Contractor shall provide the Engineer with a proving ring to verify the mandrel size.
536.01 Description.
The deformation is unacceptably excessive if the mandrel cannot be pulled through the pipe by hand without damaging the pipe. If the deformation is unacceptably excessive, the pipe shall be replaced without extra compensation. There will be no direct payment f or testing.
535.04 Method of Measurement.
Side drain pipe will be measured in the same manner as specified in Article 530.04. Excavation and foundation backfill for side drain pipe will not be measured separately for payment, but the cost thereof shall b e included in the contract unit price bid for the side drain pipe.
535.05 Basis of Payment.
a.Unit Price Coverage. Accepted side drain pipe, measured as specified above, will be paid for at the contract unit price per foot {meter} for the respective item s, which shall be payment in full for furnishing pipe, excavating trenches, placing pipe, backfilling trenches, and for all tools, equipment, labor, and incidentals necessary to complete the work.
b.Payment Will Be Made Under Item No.: 535-A ___ inch {mm} Side Drain Pipe ( * ) - per linear foot {meter} 535-B ___ inch {mm} Span, ___ inch {mm} Rise Side Drain Pipe ( * ) - per linear foot {meter} * Show specific type, class, or wall thickness, if required. Example: V.C., or P.C., or Class ___ _ R.C., or ___ gage {mm} C.A., or ___ gage {mm} C.S., or ___ gage {mm} C.C.S., or ___ gage {mm} C.C.A. SECTION 536 RELAID PIPE
536.01 Description.
This Section shall cover the work of relaying pipe, regardless of size, in accordance with the requirements of these specifications, at the locations shown on the plans or designated and in accordance with established lines and grades. The item shall inclu de furnishing and construction of such joints, necessary cutting and connections to other pipes, the removal and preservation of that portion of pipe culverts, in place, which are to be replaced by new or relaid pipe; it shall also include furnishing and construction of such joints, necessary cutting and connections to other pipes, catch basins, endwalls, etc., as may be required to complete the work shown on the plans or directed.
536.02 Materials.
a.Salvaged Pipe . Pipe to be relaid shall be selected sal vaged pipe which is approved for relaying.
b.Joint Material . An applicable type of joint sealer required by Article 530.02 shall be used.
536.03 Construction Requirements.
a.Removing Pipe in Place . Removal of pipe shall be in accordance with the provis ions of Article 206.03.
b.Laying Pipe . Pipe shall be handled so that there will be no loss or damage, before relaying. Pieces or sections of pipe found satisfactory by the Engineer shall be relaid in accordance with the requirements of the appropriate sections governing culvert pipe. Special reference is made to construction details of Section 530 which are applicable to side drain pipe relaid.
536.04 Method of Measurement.
Relaid pipe will be measured in the same manner as specified in Article 530.04. Ex cavation and foundation backfill for relaid pipe will not be measured separately for payment, but the cost thereof shall be included in the contract unit price bid for the relaid pipe.
Source: Alabama Standard Specifications for Highway Construction, 2022 Edition. Pages 417–418 of 934.