621.02 Materials.
620.04 Method of Measurement.
The volume of accepted concrete within the neat lines of the structure as shown on the plans or revised at the written direction of the Engineer will be computed in cubic yards {cubic meters}. The method of average end areas will not be used where results obtained differ from those obtained by more accurate mathematical computation. No deduction will be made for the volume of concrete displaced by steel reinforcement, weep holes, conduits, anchor bolts, or for chamfers of less than 3 inch {75 mm} leg measurements. Attention is directed to Section 502 for Reinforcing Steel, and Sections 210 and 214 for Excavation and Foundation Backfill.
620.05 Basis of Payment.
621.01 Description.
This Section shall cover the work of furnishing and installing miscellaneous drainage structures including necessary metal frames, grates, covers, etc. in accordance with the plan details and these specifications at the locations and to the grades shown on the plans or directed by the Engineer. The various units will be further designated by type to distinguish shape, size, etc. by plan details. Certain units or portions of units may be constructed of cast -in-place concrete, precast concrete, and/or masonry as specified by plan details. This Section shall also include the furnishing and installing of grates on new or existing structures when the Item of 621 -G is provided on the plans, otherwise, inlet grates are classified as an integral part of the inlet or catch basin. This Section shall also include the furnishing and installing of stilling basins when the Item of 621 -I is provided on the plans.
621.02 Materials.
621.03 Construction Requirements.
621.03 Construction Requirements.
621.04 Method of Measurement.
621.04 Method of Measurement.
621.05 Basis of Payment.
621.05 Basis of Payment.
622.01 Description.
This Section shall cover the work of raising or lowering the covers or gratings of existing inlets, catch basins, or manholes, all in accordance with plan details and these specifications at the locations shown on the plans or directed.
622.02 Materials.
All new materials used shall be in accordance with the requirements of Section 621, plan details, and Division 800, Materials.
622.03 Construction Requirements.
Heads, covers, and/or gratings of existing manholes, inlets, or catch basins that are raised, lowered, or moved in elevation without moving the structure proper will be considered reset. All work shall be done in a workmanlike manner by competent workmen and the unit re -established in proper working order at its new elevation. Any manhole, inlet, or catch basin heads, covers, gratings, or other material broken, destroyed, lost, or rendered unfit fo r reuse through carelessness, negligence, or improper handling of the work, shall be replaced by the Contractor without extra compensation. Concrete and brick masonry work shall conform to requirements of Sections 620 and 613, respectively. When adjustment s to manholes, inlets, or catch basins require the removal of a portion of the existing facility, the Engineer will designate that portion of the structure to be removed. The removal of