Utilities & Misc (700-799)

747Pipe Extension, Deformed, Min. Area ____ sq ft, ________ .... LFT

IN · 2024 Standard SpecificationsBook pages 759761View official source ↗

Area ____ sq ft, ________ .... LFT material Pipe, Bridge Deck Drain System ............................................... LS Pipe, Drainage through Concrete Masonry ............................... LS 610 Pipe, End Bent Drain, ________ in. .......................................... LFT diameter Pipe, Relaid, ____ in. x ____ in. ............................................... LFT span rise Pipe, Relaid, ________ in . ........................................................ LFT diameter Pipe, Roadway Drain Casting Extension ................................... EACH Pipe, Sanitary Sewer, ________ in. ........................................... LFT diameter Pipe, Slotted Drain, ________ in., ________ in. ....................... LFT 620 diameter thickness Pipe, Slotted Vane Drain, ________ in. .................................... LFT diameter Pipe, Type ____, Ci rcular, ______ __ in. ................................... LFT diameter Pipe, Type ____, Deformed, Min. Area ____ sq ft ................... LFT Pipe, Underdrain Ou tlet, ________ in. ...................................... LFT diameter Safety Metal End Secti on, ____, _____ ___ in. ......................... EACH slope diameter 630 Safety Metal End Section, ____, Min. Area ____ sq ft ............. EACH slope Soil Pipe, Cast Iron, _______ in. ............................................... LBS diameter Video Inspection for Pipe .......................................................... LFT The cost of reinforcing bars, straps, and hook bolts used in anchors shall be included in the cost of the concrete anchor. The cost of the toe plate anchor and galvanized bolts required for pipe end sections 640 and safety metal end sections shall be included in the cost of the pay items. The cost of pipe support brackets and all hardware used to attach the roadway drain casting extension pipe to the drain casting and the pipe support bracket to the structural member and to the drain extension pipe shall be included in the cost of the pay items. The cost of the pipe, all necessary fittings, all mounting hardware, design costs, and all other costs to provide the bridge deck drain system shown on the plans shall be included in the lump sum cost of the bridge deck drain system. 650 715.14 748 The cost of concrete backfill for slotted drain pipe and slotted vane drain pipe shall be included in the cost of the pay items.

B borrow obtained from planned excavation may be used to backfill culverts. No deduction will be made from the excavation or borrow quantities. If existing concrete building foundations , concrete walls, concrete columns, or concrete steps not visible and not shown on the plans are encountered within the limits of the trench, the removal of such items, as required, will be paid for in accordance 660 with 203.28. The cost of sawing of pavement, excavation above the trench bottom elevation shown on plans, backfilling with material other than structure backfill or flowable backfill, dewatering, shoring, timber mats, class A concrete required for collar construction or sealing existing pipe, joint materials, replacing pipe which is damaged during installation or re-laying operations, sanitary sewer testing required by the local utility, and all other necessary incidentals shall be included in the cost of the pay items in this section. 670 The cost of removal of pavement, existing pipe, end sections, anchors, or headwalls, concrete collars, encasements, and the disposal of surplus materials shall be included in the cost of the pay items. The cost of concrete, grating, pipe tu bing, reinforcing bars, aggregate leveling bed, hardware cloth, and necessary incidentals, for construction of grated box end sections will be included in the cost of the grated box end section. Geotextile required to be placed on top of the structure backfill material will not be paid for separately. The cost of the geotextile shall be included in the cost of the 680 structure backfill. The cost of providing video inspection equipment, technician, and a copy of the video inspection shall be included in the cost of video inspection for pipe. No additional payment will be made for repair, remediation, or replacement of pipes, backfill, video inspection of the repaired, remediated, or replaced pipe, and all other work associated with the repair, remediation, or replacement of unacceptable pipes. 690 The cost of mandrel testing shall be included in the cost of the pipe. 715.14 749

Source: Indiana Standard Specifications, 2024 Edition. Pages 759761 of 1,248.