Tee or wye branch connections will be measured per each along the centerline of the barrel. An additional allowance of 5 lft of the smaller diameter pipe will be made for making such connections. Elbow connections will be measured along the centerline of such connection. An additional allowance of 2 lft of pipe of the same diameter as that of the elbow will be 90 made for each such connection.
Increaser and reducer connections will be measured by the linear foot as the larger diameter pipe over the length of the connection. 719.08 Basis of Payment The accepted quantities of drain tile and replacement pipe will be paid for in accordance with 715.14. Terminating pipe sections will be paid for at the contract unit price per linear foot for pipe, drain tile terminal section, of the size specified, complete in place. Structure backfill will be paid for in accordance with 211.10. Flowable 100 backfill will be paid for in accordance with 213.09. Riprap will be paid for in accordance with 616.13. Tee and wye connections will be paid for by means of the allowance of an additional 5 lft of the smaller pipe at the connection. Elbow connections will be paid for by means of the allowance of an additional 2 lft of the pipe at the connection. If increaser or reducer connections are made, payment will be made on the basis of the larger diameter of the connection for the full length of the section forming such connections. 110 Payment will be made under: Pay Item Pay Unit Symbol
Pipe, Drain Tile Terminal Section, ______ in. .......................... LFT diameter The cost of excavating, backfilling with suitable excavated material, disposal, planking, removal of existing tile, and neces sary incidentals shall be included in the 120 cost of this work. 719.08 765