Division 800 — Incidental Construction

801Mobilization

KS · 2015 Standard Specifications✓ Full text on BuildSpecBook pages 492–492 Save this section

Ask about Section 801

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

801 - MOBILIZATION 800-1

801.1 Description

Move required personnel, equipment, materials, supplies and incidentals to the project site prior to beginning work. Include other work and costs incurred before the project starts. B I D I T E M S U N I T S M o b i l i z a t i o n L u m p S u m M o b i l i z a t i o n ( D B E ) L u m p S u m The bid item "Mobilization (DBE)" is only used on Federal Aid Projects having a DBE Goal set by KDOT. This bid item gives the Contractor the option to provide funds for mobilization to DBE subcontractors. If the Contractor elects not to utilize the bid item "Mobilization (DBE)", a unit price of $0.00 is an acceptable bid for this item.

801.2 MATERIALS - None specified.

801.3 CONSTRUCTION REQUIREMENTS - None specified.

801.4 Measurement and Payment

a. Mobilization. The Engineer will make partial payments according to TABLE 801-1. TABLE 801-1: MOBILIZATION PARTIAL PAYMENTS Percent of Original Contract Amount Completed Pay Lesser of the Two % of Mobilization % of Original Contract Amount 5 25 2.5 10 50 5 25 60 7.5 50 100 10 Accepted 100 NA The Percent of Original Contract Amount Completed = the amount earned by the Contractor* divided by the total dollar value of the original contract (all bid items). *Do not include monies earned for "Mobilization", "Traffic Control (Lump Sum)", "Contractor Construction Staking" and "Stored Materials". b. Mobilization (DBE). On behalf of the DBE subcontractor(s), submit to the Engineer a written request for partial payment of this item. Requests may be made 30 days in advance of the DBE subcontractor beginning work or mobilizing. Limit the amount requested to the amount of mobilization necessary for the work that will begin within 45 days of the request. Make additional requests at appropriate times until 100% of this item is paid. The lump sum amount bid for "Mobilization (DBE)" shall not exceed 10% of the total amount identified by the Contractor for each DBE. The total lump sum amount bid must equal the sum of the DBE mobilization amounts designated on 07-19-80, latest revision. Amounts recorded on 07-19-80, latest revision, must be actual amounts to be paid to the DBE’s. Do not include any markups. The Contractor is required to pay the DBE subcontract or the requested amount of partial payment for this item, no later than 5 days after the DBE begins mobilizing or work. Payment for "Mobilization" and "Mobilization (DBE)" at the contract unit is full compensation for the specified work.

Get an email when 801 changes

Kansas revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Standard Specifications for State Road and Bridge Construction, 2015 Edition. Pages 492–492 of 978. View official source ↗

Ask about this section

Scoped to Kansas KDOT Standard Specifications for Road & Bridge Construction, Section 801 — Mobilization. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.