1403.1GENERAL

The following notification requirements apply to all potential Contract revisions including those defined in 1402, “Contract Revisions.” The Engineer will consider requests for Contract revisions only if the notification procedures in this section are followed. Failure to follow the notification procedures in this section is deemed to be a waiver of the claim. The specified time limits may only be extended through a written, jointly-signed agreement between the Contractor and the Engineer. The Engineer will address the underlying issue prompting the notification in a timely manner.

1403.2FIRST NOTICE, BY CONTRACTOR

The Contractor shall notify the Engineer as soon as a Contract revision appears necessary . The Contractor shall not start or continue with an Activity or Contract Item for which a Contract revision may be necessary without authorization from the Engineer.

1403.3WRITTEN NOTICE, BY CONTRACTOR

If the Contractor disagrees with the Engineer’s response or the Engineer does not respond to the first notice, the Contractor shall provide a written notice. Provide this written notice within 5 Business Days of first notice if Engineer has not responded or within 5 Business Days of receiving the Engineer’s response to the first notice. The written notice shall include the following:

(1)A description of the situation
(2)The time and date the situation was first identified
(3)The location of the situation, if appropriate
(4)A clear explanation of why the situation represents a Contract revision, including

appropriate references to the pertinent portions of the Contract or law

(5)A statement of the revisions deemed necessary in the Contract Unit Price(s), delivery

schedule(s), phasing, time, etc. Because of the preliminary nature of this notice, the Department recognizes that this information may rely on estimates

(6)An estimate of the time by which the Engineer must respond to minimize cost or delay
(7)Anything else that will help achieve timely resolution

1403.4WRITTEN ACKNOWLEDGEMENT, BY ENGINEER

The Engineer will provide a written acknowledgment of receipt of the Contractor’s written notice.

1403.5FINAL WRITTEN RESPONSE, BY ENGINEER

Within 10 Business Days of receiving the Contractor’s written notice, the Engineer will provide a written response that includes one of the following:

(1)Confirmation of the need for a Contract revision. The Contractor shall pursue time

extensions in accordance with 1806, “Determination and Extension of Contract Time,” and compensation in accordance with 1904, “Compensation for Contract Revisions”

(2)Denial of the request for a Contract revision, in which case the Engineer will make clear,

by reference to the Contract, why the issue does not represent a revision to the Contract

(3)A request for additional information, in which case the Engineer will state clearly what is

needed and by when; the Engineer will respond within 10 Business Days of receiving the additional requested information

1403.6CONTRACTOR’S RECOURSE

If the Contractor disagrees with the Engineer’s final written response or the Engineer’s response is untimely, the Contractor may pursue a claim in accordance with 1517, “Claims for Compensation Adjustment.” The Contractor shall give the Engineer written notice of the intent to pursue a claim within 5 Business Days of receiving the Engineer’s final written response.

Get an email when 1403 changes

Minnesota revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Minnesota Standard Specifications for Construction, 2025 Edition. Pages 50–0 of 1,081. View official source ↗

Ask about this section

Scoped to Minnesota 2025 Standard Specifications for Construction, Section 1403 — Notification for Contract Revisions. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.