If the Department pays for the Work of a Contract Item on an actual quantity basis and the accepted quantities of Work vary from the quantities in the Contract but do not meet the requirements established for significant changes in 1402.3, “Significant Changes to the Character of Work,” the Department will pay for the Work of the Contract Item as follows:
quantities of Work performed by the Contractor and accepted by the Engineer.
or loss of anticipated profits or overhead suffered or claimed by the Contractor due to differences between the actual quantities of Work and the quantities in the Cont ract.
allocation of costs among the Contract Items due to differences between the actual quantities of Work and the quantities in the Contract.