The Department will pay for Materials ordered for the Work, but not used, if the Engineer cancels a portion of the Work or the Contract, orders the termination of the Work before completion of the entire unit, or orders a quantity greater than the quantity needed for the Work, in accordance with the following:
will pay for purchased surplus Materials shipped or delivered in accordance with the Contract at the Contract Unit Price
Department will perform any of the following:
accordance with the Contract, and pay the actual purchase price and transportation cost plus 15 percent
the Contractor 1) the difference between the purchase price and the credit received for the returned Material; 2) transportation costs; and 3) 10 percent of the total of items 1) and 2) for administrative costs
15 percent, upon delivery, for Materials that required special manufacture, fabrication, or processing, making the Materials unsuitable for general use, only if the supplier refuses to cancel or modify the order for Materials The foregoing items (1) to (3) will not apply and the Department will not pay for Materials ordered for the Work, but not used, if the Contractor or supplier takes possession of the surplus Material at no additional cost to the Department. The Department will pay an amount for surplus Materials not greater than the Contract Unit Price for the same quantity of Materials complete in place. The Contractor shall provide receipted invoices or an affidavit showing the purchase price and transportation charges for surplus Materials that will become the property of the Department. The Contractor shall deliver surplus Materials that the Department purchases to the storage sites designated by the Engineer.
The Department will only pay for Materials incorporated in the Work, except as otherwise specified in this section. The Department will only pay for surplus Materials inspected, tested, or accepted for use and for Material properly preserved, stored, and maintained in accordance with 1606, “Storage of Materials,” and 1607, “Handling Materials,” until delivered to the Department.