B
HomeLibrariesCode AISearchProjectsBookmarksAddress
FeedbackHelp Desk
Libraries
Estimate & calculate
CalculatorsChecklists
PricingLog in
Incidental Construction (600-699)

621Mobilization

NM · 2019 Standard Specifications✓ Full text on BuildSpec Save this section

Ask about Section 621

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

SECTION 621: MOBILIZATION

621.1 Description

This Work consists of mobilization, remobilization and demobil ization to and from a Project.

621.2 Materials

The Contractor shall provide personnel, Equipment, Materials, and operating supplies to the Project site.

621.3 CONSTRUCTION REQUIREMENTS Mobilization and demobilization s hall consist of obtaining all required insurance, bonds

and permits; preparatory Work and operations necessary for the movement of personnel, Equipment, supplies, and Incidentals to and from the Project si te; this item shall also include the establishment of offices, buildings, and other facilities n ecessary for the Project, before beginning Work on the Project. I t does not include mobilizatio n and demobilization for specific items of Work for which payment is provided elsewhere in the Co ntract.

621.4 Method of Measurement

The Accepted quantities complete in place will be considered f or compensation as directed by the Project Manager.

621.5 Basis of Payment

Pay Item Pay Unit Mobilization Lump Sum

621.5.1 Work Included in Payment

The Department will pay the Cont ractor partial payments using the following procedure: 1. When five percent (5%) or more of the Total Original Contrac t Amount less mobilization is earned, 25 percent of the amount Bid for mobili zation will be paid. 2. When ten percent (10%) or more of the Total Original Contrac t Amount less mobilization is earned, up to 50 percent, less previous amounts paid, of the amount Bid for mobilization will be paid. 3. When 25 percent or more of the Total Original Contract Amoun t less mobilization is earned, up to 75 percent, less previous amounts paid, of the am ount Bid for mobilization will be paid. 4. When 50 percent or more of the Total Original Contract Amoun t less mobilization is earned, up to 100 percent, less previous amounts paid, of the a mount Bid for mobilization will be paid. The total sum of all Mobilization payments shall not exceed th e Original Contract Amount Bid for the item. The Department will not make additional payments for demobiliz ation and remobilization due to shutdowns, whole or partial suspensions of the Work or f or other mobilization activities required for satisfactory completion of the Contract. Section 622: Field Laboratories and Field Offices Page 693

Get an email when 621 changes

New Mexico revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: New Mexico Standard Specifications for Highway and Bridge Construction, 2019 Edition. View official source ↗

Ask about this section

Scoped to New Mexico 2019 NMDOT Standard Specifications for Highway & Bridge Construction, Section 621 — Mobilization. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.