SECTION 621: MOBILIZATION
621.1 Description
This Work consists of mobilization, remobilization and demobil ization to and from a Project.
621.2 Materials
The Contractor shall provide personnel, Equipment, Materials, and operating supplies to the Project site.
621.3 CONSTRUCTION REQUIREMENTS Mobilization and demobilization s hall consist of obtaining all required insurance, bonds
and permits; preparatory Work and operations necessary for the movement of personnel, Equipment, supplies, and Incidentals to and from the Project si te; this item shall also include the establishment of offices, buildings, and other facilities n ecessary for the Project, before beginning Work on the Project. I t does not include mobilizatio n and demobilization for specific items of Work for which payment is provided elsewhere in the Co ntract.
621.4 Method of Measurement
The Accepted quantities complete in place will be considered f or compensation as directed by the Project Manager.
621.5 Basis of Payment
Pay Item Pay Unit Mobilization Lump Sum
621.5.1 Work Included in Payment
The Department will pay the Cont ractor partial payments using the following procedure: 1. When five percent (5%) or more of the Total Original Contrac t Amount less mobilization is earned, 25 percent of the amount Bid for mobili zation will be paid. 2. When ten percent (10%) or more of the Total Original Contrac t Amount less mobilization is earned, up to 50 percent, less previous amounts paid, of the amount Bid for mobilization will be paid. 3. When 25 percent or more of the Total Original Contract Amoun t less mobilization is earned, up to 75 percent, less previous amounts paid, of the am ount Bid for mobilization will be paid. 4. When 50 percent or more of the Total Original Contract Amoun t less mobilization is earned, up to 100 percent, less previous amounts paid, of the a mount Bid for mobilization will be paid. The total sum of all Mobilization payments shall not exceed th e Original Contract Amount Bid for the item. The Department will not make additional payments for demobiliz ation and remobilization due to shutdowns, whole or partial suspensions of the Work or f or other mobilization activities required for satisfactory completion of the Contract. Section 622: Field Laboratories and Field Offices Page 693