DESCRIPTION
628.01.01 General. This work consists of preparatory work and operations necessary for the movement of
personnel, equipment, supplies, and incidentals to the project site before beginning work. This work also consists of furnishing potable water and electricity to Department furnished field laboratories used on the project. Supply the amount of water and electricity necessary to satisfy the requirements of the Department on a 24 hour basis. Make all necessary connections to the laboratories. Qualified personnel who currently hold a Nevada State Contractors Board C2 License Classification shall make electrical connections. Provide a suitable location for the field laboratories, in a secured area, and on level pads. Satisfactorily construct, maintain, and cleanup a settling pond or holding tank for the laboratory drain. METHOD OF MEASUREMENT
628.04.01 Measurement. Mobilization will be measur ed by the lump sum.
BASIS OF PAYMENT
628.05.01 Payment. The accepted quantity, measured as provided above, will be paid at the contract price per
unit of measurement for the pay item listed below that is shown in the proposal. Payment will be full compensation for the work prescribed in this Section. When mobilization does not appear as an item in the proposal, the cost of such work shall be considered included in the contract unit price bid for other items of work and no additional compensation shall be allowed therefore. Payment will be made under: Pay Item Pay Unit Mobilization ................................ .............................................................................................................................................. Lump Sum SECTION 629 TIME RELATED OVERHEAD DESCRIPTION
629.01.01 General. This work consists of time related overhead incurred by the Contractor and by any joint
venture partner, subcontractor, supplier , or other party associated with the Contractor. Time related overhead costs include field and home office overhead that are in proportion to the time required to complete the work. Time related overhead does not include costs that are not related to time, including but not limited to; mobilization, licenses, permits, and any other charges incurred only once during the contract. CONSTRUCTION
629.03.01 General. Field office overhead expenses include time related costs associated with the normal an d
recurring operations of the construction project, and shall not include costs directly attributable to any of the work of the contract. Such time related costs include, but are not limited to; the salaries and benefits of project managers, general superi ntendents, field office managers and other field office staff assigned to the project, and rent, utilities, maintenance, security, supplies and equipment cos ts of the project field office. Home office overhead or general and administrative expenses refer to the fixed costs of operating the Contractor's business. Such costs include, but are not limited to, general administration, insurance, personnel and subcontract administration, purchasing, accounting, and project engineering and estimating. Home office overhead shall exclude expenses specifically related to other contracts or other businesses of the Contractor, equipment coordination, material deliveries, and consultant and legal fees. METHOD OF MEASUREMENT
629.04.01 Measurement. Time related overhead will be measured by the day for each eligible working day
assessed to the contract, however, not to exceed the number of working days specified in Subsection 108.02, plus or minus authorized changes. Time related overhead will not be measured for payment during suspensions of work ordered in conformance with the provisions in Subsection 108.04 or 108.06, or any suspensions mutually agreed upon between the Engineer and the Contractor. In the event of early completion of the contract, the number of days measured for payment will be the number of working days specified in Subsection 108.02, plus or minus authorized changes. In the event a Value Engineering Proposal is submitted, and is subsequently approved, which provides for a reduction in the number of contract working days, the net savings in the cost of time related overhead due to the decreased working days will be eligible for the provisions of Subsection 105.19 . The provisions in Subsection 104.02 shall not apply to time related overhead. BASIS O F PAYMENT
629.05.01 Payment. The accepted quantity, measured as provided above, will be paid for at the contract price
per unit of measurement for the pay item listed below that is shown in the proposal. Payment will be full compensation for the work pres cribed in this Section. The dollar amount paid per eligible working day will be the contract bid price or 20% of the original contract amount divided by the number of working days specified in Subsection 108.02, whichever is less. Upon completion of all w ork on the project, payment for any amount due the Contractor will be made. Payment will be made under: Pay Item Pay Unit Time Related Overhead ................................ ................................ ..................................................................................................... Day If the quantity of time related overhead, measured as provided above, exceeds 125% of the original contract quantity and the Department provides a written request, submit an audit examination and report of actual overhead