GENERAL PROVISIONS

109MEASUREMENT OF QUANTITIES

PA · 2026 Standard Specifications✓ Full text on BuildSpecBook pages 96–0 Save this section

Ask about Section 109

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

109.01MEASUREMENT—

(a)Units of Measure. Work performed under this contract will be measured in the following units shown

in the Measurement and Payment sections of the Specifications and in the Design Items in the proposal, unless otherwise specified:

• Lump Sum. Not measured. Indicates complete construction of the item of work, as specified.

• Each. Measured by the number of individual items of work completed.

• Linear Foot. Measured parallel to the longitudinal base or foundation upon which items are placed, or along the longitudinal surface of the item.

• (M. Linear Feet. 1,000 Linear Feet, to the nearest 0.01 M. feet.)

• Vertical Foot. Measured vertically to the nearest 0.1 foot, with a minimum vertical measurement of 1 foot, at each unit.

• Square Foot, Square Yard. Measured by a two-dimensional area method on the surface of the item.

• Cubic Yard. Measured by a three-dimensional volume method.

• Acre. Measured by a two-dimensional area method on the surface to the nearest 0.1 acre.

• Pound. Measured by actual item net weight (avoirdupois).

• Ton. Measured by actual item net weight in short tons consisting of 2,000 pounds, avoirdupois.

• Gallon. Measured by actual item liquid volume.

• M. Gallon. Measured by actual item liquid volume consisting of 1,000 gallons, to the nearest 0.1 M. gallon.

• (Foot Board Measure. Measurement by a three-dimensional method of the actual item lumber board foot.)

• (M. Feet Board Measure. 1,000 feet board, to the nearest 0.01 M. feet board.)

• Set. Measured as an item unit set, consisting of two or more parts together, as specified.

• Bag. Measured as an item unit bag.

• (Bushel. Measured by actual item dry measure consisting of 32 quarts.)

(b)General. Measurement will be according to the system of weights and measures recognized by the

United States Bureau of Standards. Method of measurement and computation of quantities will conform to generally recognized engineering and construction practice. Computer generated or electronic digital measuring and computing devices are acceptable methods. A station, when used as a definition or term of measurement, will be 100 linear feet, horizontal measurement. When required, weigh material on accurate, acceptable scales, using competent, qualified personnel at locations designated. When material is shipped by rail, the car weight may be accepted, if only the actual weight of material is measured. However, car we ights will not be acceptable, for material passed through mixing plants. Weigh empty trucks used to haul material measured by weight daily, as directed. Mark each

truck with a distinct, legible identification. Trucks may be selected at random and weighed, as directed, to verify the weight of material by weighing the truck empty and loaded on other acceptable scales. Use acceptable vehicles to haul material to be measured by volume at the delivery point. Use acceptable vehicles of any size or type, provided the actual body contents can be readily and accurately determined. Load vehicles to at least their water level capacity. Level the loads at the delivery point. If requested, material measured by the cubic yard may be weighed and converted to tons, if approved in writing by the District Executive. Factors to be used for conversion from weight measurement to volume measurement or weight measurement to area measurement will be determined by the Representative and agreed to by the Contractor before using this method of measurement. Measure asphalt material by the gallon or ton, as indicated. Measure volumes at 60F or correct to volume at 60F, using ASTM D1250 for asphalts or ASTM D633 for tars. Net certified scale weights, or weights based on certified volumes for rail shipments, will be used as a measurement basis. Weights will be subject to correction when asphalt material has been lost from the car or by the distributor, wasted, or otherwise not incorporated in the work. If asphalt materials are shipped by truck, the net certified weight or volume, subject to correction for loss or foaming, may be used for computing quantities.

MEASUREMENT OF QUANTITIES in other states

Get an email when 109 changes

Pennsylvania revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Publication 408 Highway Construction Specifications, 2026 Edition. Pages 96–0 of 1,522. View official source ↗